LCLS NEH ARR Welcome Status of ARR Elements IRR Process John Arthur LCLS Experimental Facilities Division August 11, 2009 LCLS Transition to Science DOE Status Review of the LUSI MIE Project Welcome to the NEH ARR NEH ARR Status August 11, 2009 2 2 J. Arthur jarthur@slac.stanford.edu ARR agenda NEH ARR Status August 11, 2009 3 3 J. Arthur jarthur@slac.stanford.edu ARR Strategy LCLS will argue that: Processes and people are in place to operate NEH safely The processes have been used, people trained, and all hardware installed for the first instrument (AMO) LCLS will use the same processes for additional instruments SAD, ASE, operational procedures, IRR, User safety processes apply to all instruments ARR committee is asked to: •Agree that LCLS is ready to start commissioning in Hutch 1 •Approve use of LCLS processes to authorize commissioning of other NEH Hutches NEH ARR Status August 11, 2009 4 4 J. Arthur jarthur@slac.stanford.edu LCLS layout and management Undulator Hall (operational) Accelerator group manages XFD manages NEH Front End Enclosure (operational) Tunnel and Far Experimental Hall (under construction) NEH NEH ARR Status August 11, 2009 5 5 J. Arthur jarthur@slac.stanford.edu Hutch 1 will be used first NEH lower level X-ray hutches and control rooms AMO instrument Hutch 1 Hutch 2 Hutch 3 10m hard x-ray line NEH ARR Status August 11, 2009 6 6 J. Arthur jarthur@slac.stanford.edu LCLS within SLAC Use existing SLAC structures where it make sense SLAC Accelerator organization operates the linac Standard safety training handled through SLAC ES&H courses Radiation Protection group handles radiation safety PPS group in Controls Dept. handles PPS SLAC Citizen Safety Committees perform safety reviews SSRL User Administration group expanded to included LCLS Create new structures where necessary LCLS Experimental Facilities Division (XFD) XFD-specific procedures Floor Coordinators Instrument Readiness Review (IRR) process LCLS User work planning and control NEH ARR Status August 11, 2009 7 7 J. Arthur jarthur@slac.stanford.edu Administrative Controls Beam Authorization Sheet Central authorization document for operating accelerator Beam Line Authorization Central authorization document for bringing X-rays into hutch Note: BAS and BLA concern radiation safety only X-ray Phase Safety Checklist Central authorization document for starting a User experiment NEH ARR Status August 11, 2009 8 8 J. Arthur jarthur@slac.stanford.edu Documentation of Processes 13 documents required for first beam to NEH SAD ASE Hutch 1 BLA Rad Survey Plan for AMO Hutch 1 IAT (PPS) HPS Stopper test Hutch 1 Search FC Incident Response Hutch 1 online/offline FC Alarm & Warning Response NEH AHA NEH Bldg Emergency Plan FC Qualification Workbook SLAC-I-010-30100-016 SLAC-I-010-30100-000 CD-SS-PPS-06-12-13 CD-SS-PPS-06-12-03 SLAC-I-030-30200-002 SLAC-I-030-30300-002 SLAC-I-030-30700-002 SLAC-I-030-30300-001 SLAC-I-030-30500-001 SLAC-I-030-30400-001 SLAC-I-030-50200-001 signed signed draft draft signed signed signed signed signed signed signed draft signed Process for controlling records is in place NEH ARR Status August 11, 2009 9 9 J. Arthur jarthur@slac.stanford.edu Commissioning plan Materials describing pre-beam tests and commissioning with beam uploaded to LCLS commissioning site <http://ssrl.slac.stanford.edu/lcls/commissioning/> Includes checkout and commissioning of Hutch 1 safety systems Also includes checkout and commissioning of AMO instrument NEH ARR Status August 11, 2009 10 10 J. Arthur jarthur@slac.stanford.edu Post-start items from last ARR closed Post-start findings from the LCLS Undulator Complex ARR closeout, Dec 4, ‘08 1) An appropriate USI process has been developed. Observations: The SLAC USI process was evaluated during the August 2008 ISM Effectiveness Review, which found that the SLAC USI process is not properly documented. SLAC has developed a Corrective Action in response to the finding. The Committee has evaluated the Corrective Action, and determined that when completed the USI process will be improved. Post-Start Findings: a) Complete the Corrective Action as scheduled. b) Present the USI process documentation at the next Accelerator Readiness Review. The USI procedure has been written as Chapter 23 of the SLAC Guidelines for Operations, and the corrective action is closed. 2) Procedures necessary for the safe operation of the activity have been developed, reviewed, and approved, and an appropriate process for the development, review and approval of new and revised procedures is in place. Observations: Procedures and qualification systems are in place, using pre-existing systems. The procedure management systems are embedded in the host organization. Post-Start Findings: a) Open post-start document revisions listed in Appendix C of the Commissioning document should be completed prior to the next ARR. b) Existing Accelerator Operations documents should be reviewed and updated as applicable. The open document revisions listed in Appendix C of the Commissioning document have been completed. They were Accelerator Operations documents which have been be updated, and continue to be reviewed and updated as applicable. NEH ARR Status August 11, 2009 11 11 J. Arthur jarthur@slac.stanford.edu Post-start items from last ARR closed 3) Records important for operational and post-operational activities are controlled. Observations: A number of SLAC and LCLS document control systems exist. Records are maintained in compliance with DOE requirements, but some discrepancies were noted in the use of terminology. Post-Start Findings: a) The discrepancies in the use of the term “Guidance” document needs to be addressed. b) Usage of technical procedures as recommended/non-mandatory should be addressed. c) The records management retention process should be reviewed by the PPS group to assure records are being maintained in accordance to DOE requirements. d) The LCLS document control system currently being revamped should include all LCLS divisions. a, b) Discrepancies in the use of the term “Guidance” in SLAC documentation have been eliminated. At issue was the title of the SLAC Guidelines for Operations. The Guidelines for Operations is consistent in its requirements. c) PPS group records management has been reviewed and improved. d) The LCLS document control system was adopted by the divisions of the LCLS Directorate. NEH ARR Status August 11, 2009 12 12 J. Arthur jarthur@slac.stanford.edu Post-start items from last ARR closed 4) Equipment and systems having safety importance meet criteria established in the SAD and have been appropriately tested. Observations: Equipment and systems required are specified in the Beam Authorization Sheets. The BAS for this commissioning activity has been drafted; the systems required are properly specified. Post-Start Findings: a) Complete and check the BAS. The BAS was completed and signed off once the ARR pre-start action items had been completed and authorization to operate the beam had been given from SLAC management. 5) Training and qualification programs relevant to safe operation in compliance with the ASO and ISM have been established. Observations: The training and qualification programs were reviewed and found to be appropriate. Post-Start Findings: a) Evaluate staff training requirements and ensure that required training is current. Training for staff is evaluated annually and is kept current through the ES&H Staff Training program. Specific training for MCC Operators is evaluated performed and tracked by the Operations staff supervisors. NEH ARR Status August 11, 2009 13 13 J. Arthur jarthur@slac.stanford.edu Safety equipment PPS Final Design Review held April 2009 Initial Acceptance Test Review held July 2009 IAT performed last week Radiation shielding Analysis of NEH, concentrating on Hutch 1, prepared by SLAC Radiation Physics: RP-09-14 Shielding installed exceeds requirements NEH ARR Status August 11, 2009 14 14 J. Arthur jarthur@slac.stanford.edu People Staffing is complete for commissioning and early AMO operations Includes 5 Floor Coordinators Training is sufficient to begin commissioning NEH ARR Status August 11, 2009 15 15 J. Arthur jarthur@slac.stanford.edu Open safety items 1 open XFD RSWCF Mechanical problem with hutch door Problem was fixed Awaiting final re-check of door interlock by Floor Coordinator NEH ARR Status August 11, 2009 16 16 J. Arthur jarthur@slac.stanford.edu ARR element summary Documentation Readiness Safety Assessment Document (SAD) has been Accelerator Safety Envelope (ASE) has been Commissioning plan has been SLAC USI process has been Operating procedures have been developed and Emergency procedures have been developed and Process for controlling records approved approved developed approved approved approved in place Hardware Readiness Shielding in place as specified by SLAC Radiation Protection Interlock/Access Control Systems are operational and tested (pending RSWCF closeout) Radiation monitoring equipment calibrated and in place Personnel Readiness Training and Qualification of operating personnel sufficient Staffing requirements are met NEH ARR Status August 11, 2009 17 17 J. Arthur jarthur@slac.stanford.edu IRR Process Final exam for a new LCLS instrument before commissioning with X-rays Includes screening for potential USI’s What is reviewed Ability of instrument to perform Safety Qualifications of staff Product of review Documentation of review proceedings Pre-start and post-start findings Leads to authorization to commission from XFD director NEH ARR Status August 11, 2009 18 18 J. Arthur jarthur@slac.stanford.edu IRR Documentation Instrument Readiness Review IRR Committee Charter IRR Checklist Formal handoff from construction group to operations Functional certification by lead engineers Safety certification by XFDSO, based on documentation from SLAC Committees and safety officers NEH ARR Status August 11, 2009 19 19 J. Arthur jarthur@slac.stanford.edu AMO IRR status Committee established Chair: Tom Rabedeau (SSRL) Includes representation from SSRL, LCLS, Accelerator, Controls, Rad Physics Includes XFD Safety Officer, NEH Area Manager First presentations to committee August 6 Final review August 12 NEH ARR Status August 11, 2009 20 20 J. Arthur jarthur@slac.stanford.edu End of Presentation NEH ARR Status August 11, 2009 21 21 J. Arthur jarthur@slac.stanford.edu