Meeting of the LCLS Facilities Advisory Committee LCLS Organization & Execution M. Reichanadter / SLAC Oct12-13, 2004 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu Outline Progress in the past six months Status of the Project (work in progress) Cost, Schedule (CP) and Resources TPC, TEC and Contingency LCLS Organization & WBS Project Management Execution & Control Plans for the next six months Oct12-13, 2004 LCLS FAC Meeting 2 Mark Reichanadter reich@slac.stanford.edu LCLS Progress in the Last Six Months Title I Design for LCLS CF Submitted. Scope of the LCLS is defined in LCLS Technical Specifications SLAC establishes the LCLS Division for the construction phase John Galayda named Associate Director, reporting to the SLAC Lab Director Division creates functional groups (Laser, Controls, Engineering, etc.) to support cross-functional systems (Injector, Linac, Undulator, etc.) LCLS to create construction/technical procurement “cell” LCLS continues to add staff (both matrixed and direct) EIR - Burns & Roe submitted report to OECM Cost, schedule & contingency found to be “reasonable” 72 findings …. covering 14 areas of project management as per DOE O413.3 CAP Submitted to DOE-OECM. Project validation letter expected soon DOE “Lehman” Review LCLS is working responding to recommendations on cost, schedule, contingency and organization Assume a Continuing Resolution of 3-months in FY05 funding (Jan05). Current estimates: TPC from $315m to ~$350M, CD-4 from 30Sep08 to 31Mar09, Constr Start from 10/1/05 to 3/31/06 On schedule to submit a revised cost and schedule estimate to DOE on 15Oct04 Oct12-13, 2004 LCLS FAC Meeting 3 Mark Reichanadter reich@slac.stanford.edu LCLS Project Cost/Schedule (Jun04) Linac Coherent Light Source BCWS Profile (AYM$) WBS System FY02 FY03 June 2004 FY04 FY05 FY06 FY07 FY08 Total 1.1 Project Mgmt., Admin. & Integration 1.2 Injector System 1.3 Linac System 1.4 Undulator System 1.5 X-Ray Transport & Diagnostics 1.6 X-Ray Endstations 1.9 Conventional Facilities Estimated Base Cost Contingency Total Estimated Cost (Base + Contingency) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.43 0.64 0.18 0.57 0.70 0.00 0.11 3.64 0.00 3.64 2.50 1.60 1.17 1.90 0.75 0.46 1.44 9.82 0.00 9.83 3.74 12.67 5.51 9.80 3.82 0.55 5.69 41.79 8.08 49.87 3.98 3.66 12.75 14.17 9.52 4.11 29.15 77.34 7.84 85.18 4.05 0.71 5.27 18.65 7.58 10.04 18.94 65.24 22.42 87.67 3.30 0.35 1.00 0.44 1.50 1.43 7.34 15.37 21.45 36.82 19.01 19.63 25.89 45.53 23.88 16.59 62.68 213.20 59.80 273.00 2.1 Project Mgmt., Admin. & Integration 2.2 Injector System 2.3 Linac System 2.4 Undulator System 2.5 X-Ray Transport & Diagnostics 2.6 X-Ray Endstations 2.9 Conventional Facilities Other Project Costs 1.50 0.00 0.00 0.00 0.00 0.00 0.00 1.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.67 0.44 0.00 0.02 0.78 0.00 0.00 1.91 1.83 0.97 0.00 0.30 0.89 0.23 0.00 4.21 1.63 0.81 0.00 0.47 0.00 0.96 0.00 3.87 5.22 4.16 1.22 4.98 1.94 0.81 0.00 18.33 9.55 0.10 0.77 0.08 1.17 0.51 0.00 12.18 20.40 6.48 1.99 5.84 4.78 2.50 0.00 42.00 Total Project Costs (Base + Cont. + OPC) 1.50 3.64 11.74 54.08 89.04 106.00 49.00 315.00 Linac Coherent Light Source Funding Profile (AYM$) TEC Funding OPC Funding Total Funding Oct12-13, 2004 LCLS FAC Meeting $90 FY02 FY03 FY04 FY05 FY06 FY07 FY08 Total 0.00 5.93 7.46 50.08 85.54 90.00 34.00 273.00 1.50 0.00 2.00 4.00 3.50 16.00 15.00 42.00 1.50 5.93 9.46 54.08 89.04 106.00 49.00 315.00 4 Mark Reichanadter reich@slac.stanford.edu LCLS Cost / Schedule Estimate ~29.5% contingency on work remaining LCLS is ~30% complete on PED Current revised estimates; • TPC ~$350M •CD-4 ~31Mar09 •Increase overall float + 3-mo CR •Slight increase in contingency •Most cost growth is in PM & CF LCLS Integrated Budget/Work Schedule (WIP) LCLS Project Project Expenditures (SPA Chart) Oct 2004 350 •LCLS is limited by funding. BCWP 300 ACWP •In FY04, we spent FY04 funds + FY03 carry-over planning for a rampup in staff and procurements. BCWS $M, Escalated 250 CR Funding 200 150 •FY05 funds allow for full deployment of PED effort ($20M) and LLP ($30M). 100 •FY06 construction start. 50 0 D J F MAM J J A SON D J F MAM J J A S ON D J F MAM J J A S ON D J F MAM J J A S OND J F MAM J J A S FY04 Oct12-13, 2004 LCLS FAC Meeting FY05 FY06 FY07 5 •FY09 operations start FY08 Mark Reichanadter reich@slac.stanford.edu LCLS Integrated Budget/Work Schedule (FY04-FY05) LCLS Project FY04-05 Expenditures (SPA Chart) Oct 2004 •1Q-05 rampup “softened” but still show a shortfall 80 70 BCWP $M, Escalated •LLP start Jan05 more in Mar05 ACWP 60 BCWS CR Funding 50 Sched Funding •Working with ANL, LLNL and SLAC to further reduce LCLS costs in 1Q05. 40 30 20 10 0 D J F M A M J J A S O N D J F FY04 Oct12-13, 2004 LCLS FAC Meeting M A FY05 6 M J J A S •Title II effort deferred for 3 months (CP) Mark Reichanadter reich@slac.stanford.edu LCLS Peoplepower / Lab / Year LCLS FTE's Projections/Lab/Year Stanford Linear Accelerator Center Lawrence Livermore National Lab Argonne National Lab 160.0 140.0 •Latest FTE projections reflecting CR and extended schedule 120.0 FTE's 100.0 80.0 60.0 •SLAC FTE’s include T&M 40.0 •FY05 staff ~doubles 20.0 0.0 FY04(act) LCLS Estimated FTE's Argonne National Lab Lawrence Livermore National Lab Stanford Linear Accelerator Center Oct12-13, 2004 LCLS FAC Meeting FY05 FY06 FY07 FY08 FY09 FY04(act) FY05 FY06 FY07 FY08 FY09 Total 11.0 15.5 20.4 15.1 2.7 0.0 53.7 5.3 9.3 8.9 12.7 11.7 2.9 45.5 36.3 87.4 107.2 101.0 89.4 19.1 404.1 Total 52.6 112.2 136.5 128.8 103.8 22.0 503.3 7 Mark Reichanadter reich@slac.stanford.edu •FY09 still needs more start-up LCLS Peoplepower Rampup Estimate (all Labs) Admin/Exped Support Controls Engineering Controls Programming Controls Tech/Install/Fab Power Supply Engineering Computing/Database Support Electrical/RF Engineering Mechanical Design/Drafting Mech/Vac Engineering Mechanical Fab/Assembly Metrology Engr/Survey Optics/Laser Engineering Physics/Post-Doc Project Management/Support T&M Crafts Site Engineering/UTR Total FY04 (actuals) 2.6 2.5 3.3 0.4 0.3 0.0 1.5 7.4 8.2 0.2 0.6 1.0 15.5 7.2 0.1 1.8 52.6 FY05 FY06 3.6 11.9 12.2 0.8 1.9 1.9 6.8 14.5 14.4 6.6 2.4 2.1 19.3 9.2 0.4 4.2 112.2 5.9 13.4 10.5 4.3 2.3 2.3 8.8 7.9 14.3 14.7 6.6 2.2 22.6 10.6 2.6 7.5 136.5 Significant ramp-up in FY05 staff (Controls E/P, E/RF Engr & ME/MD are most critical) Oct12-13, 2004 LCLS FAC Meeting 8 FY07 FY08 5.9 11.3 6.3 5.3 1.5 2.3 7.3 5.4 13.0 16.0 5.7 1.8 20.3 10.7 8.9 7.1 128.8 FY09 4.5 6.7 10.9 4.2 1.2 2.0 8.5 0.6 6.8 10.4 4.1 5.2 24.3 6.7 3.0 4.7 103.8 2.0 1.3 2.6 0.1 0.0 0.6 1.5 0.0 1.8 0.7 0.2 0.6 6.6 2.3 0.0 1.7 22.0 TOTAL 24.5 47.1 45.8 15.1 7.2 9.1 34.4 35.8 58.5 48.6 19.6 12.9 108.6 46.7 15.0 27.0 555.9 Need smoother FY09 transition to operations Mark Reichanadter reich@slac.stanford.edu LCLS Procured Materials and Services-Lab LCLS Procurement & Subcontract Commitments ANL/LLNL/SLAC Procurement efforts are decentralized $90,000 $80,000 $70,000 $60,000 AYK$ T3 Constr $50,000 SLAC $40,000 LLNL ANL $30,000 $20,000 SLAC ~$15M/yr w/o Construction ANL FY06-FY07 SC Undulators $10,000 $0 FY04 AYK$ ANL LLNL SLAC T3 Constr Total FY05 FY04 Oct12-13, 2004 LCLS FAC Meeting $20 $353 $1,801 $0 $2,174 FY06 FY07 FY08 FY05 FY06 FY07 FY08 Total $4,710 $8,059 $18,974 $0 $31,763 $1,404 $4,734 $2,908 $0 $9,400 $17,164 $20,023 $10,289 $637 $49,914 $0 $48,009 $0 $0 $48,009 $23,278 $80,825 $32,171 $637 $139,086 9 LLNL modest procurements of mostly commercial items Mark Reichanadter reich@slac.stanford.edu LCLS Long-Lead Procurements LCLS PROJECT Long Lead Procurements (LLP) BCWS, AYM$ WBS 1.02 Description Injection System * Drive Laser ($1,090k) * Streak Camera ($350k) 1.03 Total 12.7 1.3 14.0 - - LINAC System 0.1 0.2 1.2 0.7 0.9 1.1 - 0.2 0.3 1.5 •Laser and Conv Fac are most critical to maintaining schedule. 1.2 1.9 0.9 1.2 •Sufficient time is built into the LCLS schedule to provide for the procurement process. 1.5 1.4 - 0.1 Conventional Facilities S20 Injector Facility Magnetic Measurement Facility Total LLP BA Contingency Oct12-13, 2004 LCLS FAC Meeting 19.8 10 •Laser system includes a large number of small procurements + system integration. 0.1 0.1 0.3 Undulator System Ti Strongback Magnet Blocks Magnet Poles 1.09 FY06 - BC1 Magnets BC2 Magnets RF Xband 1.04 FY05 •All LLP’s have been reviewed during LCLS TDR’s. 1.5 1.4 3.1 22.9 30.0 31% •APP’s start the procurement process. •Contingency on LLP ~31% Mark Reichanadter reich@slac.stanford.edu LCLS Summary Schedule (WIP) FY 2004 OCT JAN APR DOE Milestones FY 2005 JUL OCT CD2b JAN APR FY 2006 JUL OCT CD3a Major LCLS Milestones Sector 20 Injector Facility Linac Facility Main Control Center Magnetic Measurement Facility T2 T1 OCT JAN FY 2008 APR Injector JAN Title 2 JUL OCT JAN APR Construction LCLS Start Operation (XRay to Far Hall) Title 2 •LCLS Schedule •Systems are ~decoupled during PED, construction, & I&C. B.O. Construction B. BD B.O. XTOD B.O. FEH B.O. BTH B.O. Title 2 CLOC B.O. Construction OAL UV Beam to Cathode OSC/Pre-Amp Drive Laser Avail for LH Comm DL1 Install Comp Integ & C/O Design/Procure 1st RF Power Des/Proc Install & C/O Install WG & LTDL1 •Critical Path RF Cond RF Gun Ops w/Beam L1, L2, L0, SAB & DL1 & LH Linac Design/Procure Install & C/O X-Band Klystron Design/Procurement Commission •Linac (~140 days) Cableplant L1, BC1, L2, BC2, L3, & LTU, E-Dump •Undulator (~170 days) E-Dump Install Installation L1, BC1 L2,BC2,L3 LTU Install •T3-BO-LTU-Dump Commission Undulator Design Ti Strongback Magnet Poles JUL B.O Construction T1 Title 1 FY 2009 APR Alcove B.O. Title 1 Drive Laser RF Gun OCT 1st Beam on Linac Axis NEH B.O. UND B.O. FEE B.O. Other Facilities (Undulator,BD, RY, NEH, FEH,FEE, BTH,CLOC & X-Ray Xport) JUL 1st Beam on Undulator Construction Title 2 JUL CD4 MMF Title 1 FY 2007 APR MMF Qual Complete FFTB Shutdown Start Proc for T3 Constr Conventional Facilities JAN CD3b Granite Beams Magnet Blocks •1st Beam in Undulator Vendor A-Prod Units Design Vendor B-Prod Units Procure Testing at MMF Last Prod Unds Received Rcv 1st Arts •Increased float with new extended schedule Test Del of 1st Arts to MMF F/MM Install Comm X-Ray Transport & Diagnostics Commissioning Diagnostics Design/Procure Install Comm X-Ray End Stations Laser Detector Design/Procure/Assy Design/Procure 2-D X-RAY Detector Operations Oct12-13, 2004 LCLS FAC Meeting Install & Commission Demo Operations 11 Mark Reichanadter reich@slac.stanford.edu LCLS WBS Organization 1.3 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6 1.3.7 •LCLS is organized into fully integrated (design through commissioning) decoupled systems. •Decoupling allows each system to go as fast as technically possible. •Allows phased commissioning 2.3 1.4 1.4.1 1.4.2 1.4.3 1.4.4 1.4.5 1.4.6 Management & Integration Product-based Components I&A – Components into subsystems Physics Commissioning 2.4 1.6 1.6.1 1.6.2 1.6.3 1.6.4 1.6.5 1.6.6 •Controls is embedded in technical systems. •Improves controls / hardware interface. •Configuration management is easier. •Needs good coordination between Controls Manager and System Manager. • Dual signature authority Oct12-13, 2004 LCLS FAC Meeting 2.6 12 LINAC SYSTEM System Management & Integration Linac Controls & Power Conversion Subsystem Linac Magnets & Supports Linac Vacuum Subsystem Linac Electron Diagnostics Linac RF Subsystem Linac Installation & Alignment Linac Commssioning (OPC) UNDULATOR SYSTEM Undulator System Management & Integration Controls Undulator Magnet & Support Vacuum System Diagnostics Undulator System Installation and Alignment Undulator Commssioning (OPC) X-RAY END STATION SYSTEMS System Management & Integration Controls Subsystem Mechanical/Vacuum Subsystem Laser Subsystem X-Ray Detectors System Installation & Alignment X-Ray Endstation Systems Commissioning (OPC) Mark Reichanadter reich@slac.stanford.edu LCLS Project Organization thru L3 •LCLS Continues to add staff in key areas •With FY05 funding; •Chief Scientist •QA/QC •Database Mgr •Constr Safety •Undulator ME’s •Deputy CF Mgr •LCLS Division provides functional support below L3 •Reorg in process to exploit Injector-Linac common systems Oct12-13, 2004 LCLS FAC Meeting 13 Mark Reichanadter reich@slac.stanford.edu LCLS Technical Specifications •Technical baseline specifications are defined. •Additional documents are added as the design evolves. •Technical specs under configuration mgmt Oct12-13, 2004 LCLS FAC Meeting 14 Mark Reichanadter reich@slac.stanford.edu LCLS is under Configuration Management Management Control LCLS Project Management Plan with Appendices LCLS Advance Procurement Plan w/ Critical Procurements Appendix LCLS Quality Implementation Plan LCLS Risk Management Plan with Risk Registry Appendix Technical Control Technical Specifications Documents With GRD, PRDs, ESDs, ICDs WBS Dictionary Cost/Schedule/Resource Control LCLS P3 Cost & Schedule Database With Baseline Change Requests LCLS L1-L2-L3 Milestones Oct12-13, 2004 LCLS FAC Meeting 15 Mark Reichanadter reich@slac.stanford.edu LCLS Project Coordination •ILCC meets quarterly to address issues affecting resource allocation and coordination to the LCLS project at the partner laboratories. •Federal Project Director is invited to ILCC meetings. •FAC meets semiannually and provides advice on the construction and technical capabilities of the LCLS. •SAC meets semiannually and provides advice on the scientific program of the LCLS. Oct12-13, 2004 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu LCLS Monthly Report (14 months reporting, 6 on Integrated project) •Technical Highlights •Issues and Assessments •Earned-Value Performance •Milestone Performance •Change Control Log LCLS Cost Performance Report - Work Breakdown Structure Current Period ($K) Actual Budgeted Cost Variance Cost Work Work Work Schedule Cost Scheduled Performed Performe WBS Budgeted Cost Work Work Scheduled Performe 30-Jun-04 Cumulative to Date ($K) Actual Variance Cost Work Schedule Cost Performe At Completion ($K) Performance Indices Budgeted SPI CPI 1.1 Project Management 162 140 115 -21 25 3,380 3,355 3,622 -25 -268 0.99 0.93 19,015 1.2 Injector 124 80 227 -45 -148 1,796 1,637 2,098 -160 -461 0.91 0.78 19,629 1.3 Linac 150 85 129 -65 -44 999 934 1,031 -64 -96 0.94 0.91 25,882 1.4 Undulator 112 152 211 40 -58 1,837 1,894 2,074 57 -181 1.03 0.91 45,526 1.5 X-ray Transport 30 55 68 25 -13 1,365 1,412 1,447 46 -36 1.03 0.98 23,877 1.6 X-ray Endstations 67 67 21 0 46 267 267 148 0 118 1.00 1.80 1.9 Conventional Facilities 1 LCLS Total Base Cost 19 311 -68 -292 1,280 1,184 1,323 -97 -140 0.92 0.89 62,679 598 1,082 -134 -484 10,924 10,681 11,744 -243 -1,063 0.978 0.909 213,201 LCLS Total Estimated Cost 273,000 Avail. Contingency 59,799 % Contingency / Rem. Work 29.5% % Complete LCLS Base Cost 2.1 LCLS Project Mgmt, Planning & Admn (OPC) 2.2 Injector (OPC) 116 106 218 -10 -112 1,836 1,825 1,752 -11 73 0.99 0.70 44 46 0 1 46 214 149 0 -65 149 2.3 Linac (OPC) 0 0 0 0 0 0 0 0 0 0 2.4 Undulator (OPC) 0 0 0 0 0 6 2 0 -4 2 0.27 160 44 39 -116 6 526 84 39 -442 46 0.16 2.5 X-ray Transport (OPC) 2.6 X-ray Endstations (OPC) 2 LCLS Total Other Project Cost LCLS Total Project Cost LCLS FAC Meeting 17 5.5% 1.04 20,404 6,481 1,992 5,844 4,781 0 0 0 0 0 0 0 0 0 0 320 196 257 -124 -61 2,582 2,059 1,790 -522 269 0.798 1.150 42,000 1,053 794 1,339 -259 -545 13,506 12,741 13,535 -765 -794 0.943 0.941 315,000 2,498 % Complete LCLS TPC Oct12-13, 2004 16,593 87 732 Mark Reichanadter reich@slac.stanford.edu 4.0% Latest Revised Estimate Variance How do we keep control of the project? What are we doing? Single source of cost/schedule baseline data: LCLS WBS (P3) Technical Specifications (GRD, PRDs, ESDs, ICDs, (see LCLS QIP) (Single Source) Signature authority on Procurements Regular Design Reviews (reduce risk) Plan the work … Work the plan … Need to change the plan? → BCR → work new plan How are we doing? Earned-Value Performance Management Monthly Status on % Complete Actual cost tracking versus budgets Cost / Schedule Variances (PARS) – Emphasize meeting schedules, costs track closely. L1, L2, L3 Milestone Reporting Monitor Critical Path and Float Contingency Usage / Risk Management Who is doing what? Communication & Coordination Weekly / Monthly LCLS Management and Physics Meetings Weekly/Monthly/Quarterly LCLS/DOE Meetings LCLS Monthly Report ANL-LLNL-SLAC MOU Inter-Laboratory Coordinating Council (ILCC) LCLS Website (for all official documentation) Need Help? $$ - Contingency solves alot, though not all problems Resources @ ANL/LLNL/SLAC via the ILCC Oct12-13, 2004 LCLS FAC Meeting 18 Mark Reichanadter reich@slac.stanford.edu Plans for the Next Six Months CD-2b (Approve Performance Baseline) CD-3a (Authorize Long-Lead Procurements) Make plans for full FY05 funding (~$54M) Get funds out to partner labs Staff up particularly in Controls, PM, and Engineering Establish colocated procurement cell & staff Award Long-Lead Procurements Laser, Undulator, MMF, S20 Authorize Title II (Jacobs) Put out SOW for CF Constr Mgmt Oct12-13, 2004 LCLS FAC Meeting 19 Mark Reichanadter reich@slac.stanford.edu