Status of the Proposed PIXEL Project John Arthur SSRL/SLAC Photon

advertisement
Status of the Proposed PIXEL Project
Photon
Instrumentation
for
John Arthur
SSRL/SLAC
X-ray Experiments
at
LCLS
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
Boundary conditions that define the PIXEL project
LCLS construction schedule
DOE funding profile
LCLS science thrusts endorsed by SAC
Organization of the PIXEL project
Org chart
Phased approach
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
LCLS Construction Schedule
NEH beneficial occupancy
June 2007
FEH beneficial occupancy
September 2007
First electrons through undulator
May 2008
Begin LCLS operations phase
April 2009
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
PIXEL possible funding profile
Asking for a total of $50-60M extending over FY06-FY12.
About $18-22M would arrive in FY06-08. The funding profile
is still being worked out with BES; nothing is certain yet.
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
The LCLS Science
Thrust Areas
Coherent scattering at the nanoscale (XPCS)
Atomic, Molecular, and Optical Science
Pump/probe diffraction dynamics
Pump/probe high-energy-density (HED) science
Nano-particle and single-molecule (non-periodic) imaging
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
BES approach to the
Thrust Areas
AMO science will be included in LCLS construction project
HED science deemed to be outside the mission of BES
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
Proposed PIXEL Scope
Build instruments that address the 3 remaining Thrust Areas
within BES mission
Include one additional instrument, for soft-x-ray coherent
imaging of magnetic domains (also endorsed by SAC)
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
DOE BES project
requirements
PIXEL will be a major item of equipment (MIE) procurement project
Not a line-item in the DOE budget
Can include construction funding and R&D funding
Must build distinct instruments, separate from what LCLS builds
Assume all new rules for BES project management apply
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
PIXEL
organization
Keith Hodgson
SSRL Director
Jerry Hastings
SSRL Asst. Dir for LCLS Science
LCLS Science Teams
John Arthur
PIXEL Project Director
TBD
PIXEL Project
Chief Engineer
Engineering
&
Development
4-5 Engineers
2-3 Designers
Budget
ES&H
PMCS
Database
Purchasing
Administration
Inst #1
Instrument Scientist
Inst #2
Instrument Scientist
Inst #3
Instrument Scientist
Inst #4
Instrument Scientist
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
Why a phased approach is needed
Each instrument costs $12M-$15M
Funding profile provides ~$22M maximum by end of FY08
So at most two instruments can be funded through FY08
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
What will $12M-$15M buy?
Typical PIXEL
“instrument”
+
PEOPLE
April 7, 2005
PIXEL Project status
Controls (including laser timing)+Computers
Slits
Flight path
Valves/windows/pumps
KB focusing system (1 µm and sub-µm options)
X-ray pulse split+delay with table
Crystal monochromator with table
Diffractometer with table
Optical table for laser
Laser PPS
Laser system (10 mJ Ti:sapphire plus OPA)
Laser diagnostics
X-ray diagnostics
2d detector
John Arthur
jarthur@slac.stanford.edu
The phased approach
Build two instruments in Phase 1, plus a prototype 2d detector
Have Phase 1 instruments able to use first light (summer 2008)
Start to roll Phase 1 science resources onto LCLS ops in 2009
End Phase 1 in 2009-2010 time frame
Begin Phase 2 in 2009, hire additional scientists
Phase 2 includes two instruments plus additional detectors
Finish Phase 2 in 2012
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
Proposed Project Milestones
CD0 (Statement of mission need, beginning of project) mid 2005
CD1 (Completion of conceptual design)
mid 2006
CD2a (Baseline costs of Phase 1)
late 2006
CD3a (Begin construction of Phase 1
mid 2007
CD4a (Finish Phase 1)
2009-2010
CD2b (Baseline Phase 2)
2008-2010
CD3b (Construction Phase 2)
2009-2010
CD4b (Finish Phase 2)
April 7, 2005
PIXEL Project status
2012
John Arthur
jarthur@slac.stanford.edu
Phased Scheme
Presented to LCLS
Science Team
Leaders
Not yet approved
by SAC, for
discussion only
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
2008-9
Near Experimental
Hall
Soft X-ray Station
AMO Physics (funded by LCLS)
Hard X-ray Imaging Station
Coherent imaging (funded by PIXEL)
Extreme states of matter (funding?)
Hard X-ray Diffraction Station
Pump-probe dynamics (funded by PIXEL)
XPCS (funded by PIXEL)
Green applications do not
have full capability, but can
do preliminary experiments
Far Experimental
Hall
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
by 2012
Near Experimental
Hall
Soft X-ray Station
AMO Physics
Magnetic imaging
Hard X-ray Imaging Station
Coherent imaging
Hard X-ray Diffraction Station
Pump-probe dynamics
Hard X-ray Diffraction Station
XPCS
Hard X-ray Station
Extreme states of matter
(assumes funding found)
Far Experimental
Hall
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
Summary
The funding profile constraints on the PIXEL project,
along with the LCLS schedule, indicate that a phased
approach is needed
Two instruments in Phase1, two in Phase2, along with a
detector development program
Funding for this project is lean, especially in the first
years
Strong support from the Science Teams will be needed
April 7, 2005
PIXEL Project status
John Arthur
jarthur@slac.stanford.edu
Download