Linac Coherent Light Source Project Update Incident Budget Schedule Project activities- Highlights Charge 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 11 October 2004-Worker Severely Injured Sector 20 Equipment Alcove Electrician employed by “Bay Span” Working “hot” on a breaker panel – 480V Short-to-ground, arc/explosion Worker’s shirt caught fire Burned over ~50% - upper body, hands Discharged from hospital 16 December 2004 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Safety Management Mike Scharfenstein, LCLS ES&H Coordinator SLAC corrective actions defining path forward for LCLS Policies/procedures for management of contractor safety are important to LCLS 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Conventional Construction Safety Richard Hislop ( ANL Advanced Photon Source) working with LCLS through 9/2005 APS Project Construction ES&H Line Construction Management APS Lab Office Modules APS Utilities expansion Center for Nanoscale Materials 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu LCLS - Estimated Cost, Schedule (My Standard LowResolution Slide $315M Total Estimated Cost $379M Total Project Cost FY2005 Long-lead purchases for injector, undulator FY2006 Construction begins FY2008 FEL Commissioning begins March 2009 Construction complete – operations begins CD-0 CD-1 CD-2a Title I Design CD-2b Complete XFEL Commissioning CD-3b CD-3a FY2001 FY2002 FY2003 2002 2003 FY2004 Project Engineering Design 2004 FY2005 Long-Lead Procurement 2005 FY2006 2006 FY2007 FY2008 Operation Construction CD-3a 7 April 2005 LCLS Facility Advisory Committee FY2009 CD-4 John N. Galayda galayda@slac.stanford.edu FY2005 – Start Long-Lead Procurements Linac Coherent Light Source BCWS Profile (AYM$) WBS System FY02 FY03 September 2004 FY04 FY05 FY06 1.1 Project Mgmt., Admin. & Integration 0.00 1.43 2.50 6.61 1.2 Injector System 0.00 0.64 1.60 1.3 Linac System 0.00 0.18 1.17 1.4 Undulator System 0.00 0.57 1.5 X-Ray Transport & Diagnostics 0.00 0.70 1.6 X-Ray Endstations 0.00 1.9 Conventional Facilities 0.00 Estimated Base Cost Contingency % Contingency FY07 FY08 FY09 Total 5.82 4.70 4.03 1.92 27.02 9.34 4.86 0.93 0.26 0.05 17.67 3.37 11.25 8.43 2.16 0.43 27.01 1.90 6.88 23.61 13.78 1.45 0.09 48.28 0.75 2.81 6.59 6.87 7.59 0.62 25.93 0.00 0.46 0.39 1.61 6.59 6.45 0.50 15.99 0.11 1.44 6.17 23.54 34.19 8.74 0.40 74.59 0.00 3.64 9.82 35.57 77.27 75.50 30.68 4.01 236.49 0.00 0.00 0.01 14.51 8.27 30.00 19.82 6.00 78.52 0.0% 0.0% 0.0% 40.8% 10.7% 39.7% 64.6% 149.7% 35.2% Total Estimated Cost (Base + Contingency) 0.00 3.64 9.83 50.08 85.54 105.50 50.50 10.00 315.00 2.1 Project Mgmt., Admin. & Integration 1.50 0.00 0.67 1.86 1.35 4.71 9.46 19.33 38.88 2.2 Injector System 0.00 0.00 0.44 0.70 0.24 3.63 0.65 0.34 5.99 2.3 Linac System 0.00 0.00 0.00 1.10 1.11 0.34 2.54 2.4 Undulator System 0.00 0.29 0.45 5.40 0.38 0.34 6.87 0.97 5.97 0.12 3.52 0.00 0.00 Authorized 0.00 0.02 0.00 0.00 0.78 FY2005 2.6 X-Ray Endstations 0.00 0.00 0.00 President’s 0.95 0.40 0.75 2.12 FY2006 0.00 Budget 1.09 0.51 1.81 2.9 Conventional Facilities 2.5 X-Ray Transport & Diagnostics 0.00 0.00 0.00 0.21 0.00 0.00 0.00 0.00 0.21 Other Project Costs 1.50 0.00 1.91 4.00 3.53 16.09 15.52 21.41 63.97 Total Project Costs (Base + Cont. + OPC) 1.50 3.64 11.74 54.08 89.08 121.59 66.02 31.41 378.97 Linac Coherent Light Source Funding Profile (AYM$) FY02 TEC Funding OPC Funding Total Funding 7 April 2005 LCLS Facility Advisory Committee FY03 0.00 1.50 1.50 FY04 5.93 0.00 5.93 7.46 2.00 9.46 FY05 FY06 FY07 FY08 FY09 Total 50.08 85.54 105.50 50.50 10.00 315.00 4.00 3.50 16.00 15.50 21.50 64.00 54.08 89.04 121.50 66.00 31.50 379.00 John N. Galayda galayda@slac.stanford.edu EIR Thanks to Mark Reichanadter for his tireless efforts to close out the 5/10/2004-3/31/2005 External Independent Review It is possible that it will be over soon (famous last words) ESAAB for CD-2B (approval of the baseline for the entire project) Scheduled for 8 April 2005 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Ultrafast Science and LCLS Experiments – 120 Attendees, all prospective users Organizers: Jerry Hastings and Keith Hodgson Monday-Tuesday, October 25-26 For program information see: http://www-conf.slac.stanford.edu/ssrl/2004/lcls_workshop.htm A Workshop in Ultrafast Science and LCLS Experiments at SSRL will be organized on October 25-26, 2004. There will also be a pre-registration reception on Sunday evening, October 24th from 5-7 pm. The tentative schedule for the workshop is a joint session on Monday morning, October 25th. On Monday afternoon and Tuesday morning, there will be breakout sessions for each of the five thrust areas of the LCLS: (1) Atomic, molecular and optical physics (2) High energy density states of matter (3) Optical pump-x-ray probe studies in chemistry, biology and materials science (4) Diffraction imaging of single objects approaching atomic scale resolution and (5) Coherent x-ray scattering for the study of dynamics (X-ray photon correlation spectroscopy) The workshop will end with a joint session on Tuesday afternoon, October 26th. The workshop and breakout sessions will focus on the scientific goals and technical needs of the LCLS experimental end-stations, as well as experimental specifications. This workshop provides an opportunity to all users, including potential future users to participate in building ultrafast science at LCLS by providing input and sharing their scientific ideas. For atomic, molecular and optical physics breakout session at the meeting please contact Lou DiMauro (dimauro@bnl.gov) Phil Bucksbaum (phb@umich.edu) Nora Berrah (berrah@wmich.edu) Jerry Hastings (jbh@slac.stanford.edu) For the other breakout thrust areas please contact John Arthur (jarthur@SLAC.Stanford.EDU). 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Scientific Advisory Committee Meeting 27-28 October Start of CD-1 activity Presentations by each Team Leader Near- and Long-term goals Performance requirements, near- and long-term Intensity, repetition rate Wavelength Commissioning likely to progress from 1.5 to 0.15 nm Time scale for production of conceptual design (CD-1) 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu PIXEL Initiative to build out LCLS Experiments Thrust areas: SSRL/LCLS Contact (1) Coherent scattering at the nanoscale G.B. Stephenson* K. Ludwig S. Brennan (2) Pump/probe diffraction dynamics K. Gaffney* D. Reis J. Larsson A. Lindenberg (3) High energy density (HED) physics R. Lee* P. Heimann J. B. Hastings (4) Nano-particle/single molecule(non-periodic) imaging J. Hajdu* J. Miao H. Chapman J. Arthur (5) Atomic, molecular, L. DiMauro* J. B. Hastings and optical science N. Berrah * Team leader 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Detector Review 28 February 2005 Detector Subcommittee formed, recommendations received Y. Amemiya, U. of Tokyo Gareth Derbyshire, RAL (Chair) Eric Eikenberry, SLS Lothar Strueder, Max Planck Inst. Albert Walenta, Univ. Siegen 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu LCLS Injector 10/2005 Shutdown LINAC HOUSING SIDEWALL RF Gun TR UM EN T CH A MB VA CU EA TM PU MP S 1 F YA C 1, G SP SE O OL AL S FR 1 1 Transverse RF Cavity 2 EO SC 2 QU 7 AD QU AD Pb 2 10' HIGH CONCRETE A , B , C ARE THE DETECTOR LOCATIONS INSIDE THE LCLS INJECTOR VAULT VA LV E Fe 2 Fe 3 BEAM LINAC HOUSING SIDEW ALL 7 April 2005 LCLS Facility Advisory Committee QUAD QUAD CM4 EO3 BPM 19 SC11 B02 AD QU 04 SC10 D 04 WS OTR 6 Q UA SC9 B01 AD 03 BPM 16 B PM 15 9.4 ACCELERATOR SECTION 21-1B DUMP 02 3" TUBE 6 B PM 18 Q S01 BP M 20 SC13 LE 01 3 5 17 PEP-2 HE/LE BYPASS QU VALVE HE 4 Pb 1 BP M SECTION 20-8C 2 B0 SECTION 20-8B 2" TUBE BPM VA 14 LV E 4 SC 12 YA G 4 SECTION 20-8A 1 10' ACCEL QE-901 10' ACCEL ACCEL BEAM STOPPER 10' LINAC HOUSING SIDEW ALL P E N . 21 -1 PIC PIC PEN. 20-17 OT R5 Fe 1 PEN. 20-16 PEN. 20-15 SC 8 LINAC HOUSING SIDEW ALL 3 BP M OT R4 BP M 12 Pb 3 13 0 1 , 0 2 ... ETC. ARE POINT-SOURCE LOCATIONS ALONG THE HE BYPASS LINE BP M 11 B DL1 Bend OP PE R C ST SC 6 KE R RF BSOIC A RA D LI NA C OT VA R3 LV E 2 ... ETC. ARE SIX SOURCE AREAS ALONG THE DRIFT REGION KIC UN DU LA TO R TO 9 N 10 D IF IC AT IO OT R M O OT R 6 U RC E BP M 1 , 2 SO Laser Heater OR BP M KEY: 10 'A CC EL ER AT BP YA G M 7 3 QU AD 1/22/2004 LI G HT SI D EW AL L QU BP M AD 8 H ER EN T SC 5 C O HO US IN G L0-1 & L0-2 3-m SLAC Sections 3 Gun Diagnostics YA BP G 2 M 5 LI NA C RF Cav . BP M LINAC HOUSING SIDEW ALL ER AT OR SC 4 SC X-Y 2 4 LI N AC SC 3 BP M QU AD FC Y A 3, G C M2 QU AD 3 10 'A CC EL BP M FC YA 2, G CM 2 10' HIGH S2 M1 BP M DE QU A QU D AD C HO BP M AT U HV GA AL TE L VA ME LV TA ES L PO HO RC LD UPIN ER EC VA LV E MA SC G Sp N E QU 1 X ec TIC A D -Y, tro . YA G OM CA T RF H OD GU E N E0 1 1 ER LO AS NG SE BE MB LL L OW Y S Load Lock VA LV E S1 Q S02 DRIFT SECTION LINAC HOUSING SIDEW ALL Straight Ahead Spectrometer John N. Galayda galayda@slac.stanford.edu QS0 3 O TR FC 4 Injector Building out for bid Laser bids, ranked Gun in fabrication at SLAC Preparations for October shutdown Elev -35’-0” Elev 0’-0” Sector 20 Laser Facility vacuum connection to linac 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Long-Lead Procurements, FY2005 - Linac Selected Linac Systems X-band RF system – underway Klystron construction >50% Chicane Magnets vendor survey 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Long-Lead Procurements, FY2005 Undulator Systems Undulator Hardware Magnet Blocks Magnet Poles Awarded Strongback Awardees chosen final negotiations near complete Undulator Measurement Lab design complete, bid package in preparation for room On track for complete delivery of undulators by June 2007 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Undulator Magnet Measurement – Bldg 81 CMM Out to Bid See LCLS-TN-05-04 Test stand lay-out is driven by requirement to match Earth Magnetic Field (to ~0.1G) conditions in lab to Undulator Hall, i.e. azimuth and gap orientation need to be identical 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.5 X-ray Transport, Optics, and Diagnostics Finally we can give some funds TTF damage tests Gas cell design Help with gun laser pulse shaping 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Undulator Hall (175m) Linac-to-Undulator (227m) Beam Dump (40M) Front End (29m) X-ray Near Transport Expt. (250m) Far Expt. Hall Hall 1.9 Conventional Facilities Title-II Kickoff 29-30 March 2005 We must finalize (!) Title – II specifications by 8 April Award of CM/GC is slipping later than ideal Complete Title-II by 30 November 2005 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Alternate Far Hall Layout 14.6m 10-meter hutch length 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Charge to Committee Breakouts: • • • • • • • Accelerator systems design and construction Undulator systems design and construction X-ray transport, optics and diagnostics design and construction Experiment station systems design and construction Conventional facilities design and construction Controls Planning and execution of commissioning and early operations Title II Conventional Facilities Design begins Monday – Consequence of building design change goes up rapidly •Mirrors upstream of Near Hall •Far Hall layout Changed PEP schedule has forced change to shut-down schedule SLAC Radiation Physics has done some outstanding work on collimation and dose to undulators – Committee may wish to hear about this Friday Morning Diagnostics talk- may be repeated to Electron Beam Group Thank you for giving your time to this review process. We value your advice 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu End of Presentation 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu X-Ray Subgroup- Paul Fuoss presenting Issues: Details of designs are sparse, User workshops should be aimed at collecting more detail. There is not enough effort going into the shot-by-shot beam diagnostics (?) There is not enough effort going into optics stability Consider making the center hutch in the far hall longer Recommendations Concentrate on LCLS-specific problems such as shot-by-shot diagnostics, data flow, feedback control, preservation and measurement of coherence The detector advisory committee should coordinate the effort of LCLS and MIE Identification and communication of critical issues to LCLS experimenters should be a priority Do not fund detector efforts unless resources are sufficient to produce a useful end result 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Controls Global standards are required - push for this (vacuum? where is the interface?) You desperately need a central database for all project data (not just controls) SLC-aware IOC good progress prototyping, still lack functional requirements and top level design decisions on Applications and which should be EPICs vs SLC. X-ray beam line controls requirements must be defined BPMs - are electrons and positrons on a single pulse still needed? Is it OK to simply keep the "old" original electronics in place and disconnected, so the new electronics are limited to LCLS requirements? BPM location and anchoring must be decided Undulator BPM performance requirements should be articulated including max working range The engineering process seems to be proceeding without explicit requirements and reviews. An example of this is the PNET module Where is global controls on the org chart? Can we get x-band klystrons and waveguides from the NLCTA? Injector laser controls interface needs close communication between vendor, controls group and laser experts/operators Follow new code requirements for low-smoke fireproof cables It is unclear how to design feedback to control X-band phase- explore "dithering". 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Electron Systems Do gun tests as early as possible, at vendor maybe consider creation of a gun test facility Order 2 guns They recommend continued testing of laser pulse shaping at DUVFEL Consider doing electron beam tests at DUVFEL Consider collaboration with LLNL on gun laser development Recommend a hot spare laser Recommend the formation of a laser group Consider doing tests of "lock-in" detection of low gain at DUVFEL Consider x-band waveform modulation as the input modulation for lock-in detection Show analysis and simulations of collimator performance at the next review, including shower computations Continue work on ESASE Recommend x-y scanners for wire monitor, rather than diagonal Consider the design of a feedback loop that adjusts the laser based on electron beam measurements Consider options for the ULTIMATE LCLS Master Oscillator Continue tests of THz measurement techniques at SPPS (WHEN?) Consider schemes to modulate X-band phase for optimal set-up Place appropriate emphasis on challenging phase/amplitude control of X-band system By 1/2005, force a decision on undulator design changes for AC wake field 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Undulator Systems Cradle system needs attention Trade-offs must be considered to decide whether longer girders can improve tolerance to ground motion They recommend that, if the gap/period is changed, a new prototype is not necessary Consider feed-forward from temperature measurement to undulator horizontal position to control K Decision has been made to NOT to hire a general contractor responsible for delivering complete undulators. The consequences of this decision (plans for control of final assembly) should be presented 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Conventional Facilities Prepare a prediction of floor performance in terms of settlement and vibration, based on SLAC experience, calculation, etc. that covers "DC-to_daylight" bandwidth Give serious consideration to "active" alignment techniques to compensate for performance limitations of floor and supports Give further consideration to where cut/cover is better than tunneling Consider heating the tunnel walls Report the earthquake design criteria for LCLS construction CLO- 300 people in 90,000 square feet seems tight- revisit space allocation Committee is skeptical of 27 month construction schedule We need a construction procurement expert We need a construction safety expert W need a construction QA function/program We need a review by a fire safety engineer Confirm that the standards chosen (UBC1997 was an example quoted at the review) are the latest, and that no changes in requirements and standards are imminent. (?) Consider an excavated tunnel cross-section that is not circular Go through a cost-optimization exercise. it may be possible to save money on construction cost Consider having your procurement group set up bulk purchasing agreements for commodities. 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Robinson Summation Risk registry should show AC conductivity Prepare a tunnel/undulator stability/error budget!! The Project mgmt has not yet demonstrated global systems integration Go through a value engineering cycle Improve integration between conventional facilities and laser systems 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu I am happy to announce that Paul Emma has agreed to take over leadership of the LCLS accelerator system physicists' group. Paul's ability, cooperative spirit and dedication have earned him the respect of his peers and the LCLS WBS managers alike. I should add my expression of gratitude to the system physicist team for their advice to me and their efforts to make the LCLS a success. I ask that you all give your support to Paul and the Accelerator Systems Physicist team as we turn the LCLS from a dream, nearly 14 years in the making, into a groundbreaking scientific facility and a running facility. The photon systems physicists, John Arthur for X-Ray Transport/Optics/Diagnostics and Jerry Hastings for X-Ray End Station Systems, will continue to report to me in this capacity at present, in addition to their responsibilities to SSRL and the PIXEL initiative (which will complete the suite of experiment stations for the LCLS). --- John Galayda 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu by 2012 Near Experimental Hall Soft X-ray Station AMO Physics Magnetic imaging Hard X-ray Imaging Station Coherent imaging Hard X-ray Diffraction Station Pump-probe dynamics Hard X-ray Diffraction Station XPCS Hard X-ray Station Extreme states of matter (assumes funding found) Far Experimental Hall 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 2008-9 Near Experimental Hall Soft X-ray Station AMO Physics (funded by LCLS) Hard X-ray Imaging Station Coherent imaging (funded by PIXEL) Extreme states of matter (funding?) Hard X-ray Diffraction Station Pump-probe dynamics (funded by PIXEL) XPCS (funded by PIXEL) Green applications do not have full capability, but can do preliminary experiments Far Experimental Hall 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Where Are We Now About to transit from administrative/design activities to construction activities Training profiles must change accordingly About to heavily exercise LCLS-SLAC synapses Citizens’ committees Matrix support from Technical Division, CEF SLAC oversight Oversight of LCLS activities at ANL, LLNL 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu How Will We Get There Write Safety Assessment Document Identify certain generic design features to control hazards Busbar covers? “Power ON” warning lights? Pinch hazard covers? Local crash buttons for motors? Enclosed laser paths? laser interlocks? Confirm it is all there in the Readiness Review 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu LCLS Project Management PMD LCLS Sector 20 Document # 1.9-001 Conventional Facility Construction Project Approval Form Revision 0 PART B – CITIZEN COMMITTEE REVIEW/APPROVAL PROCESS INSTRUCTIONS Jo Beth Folger (Author) Signature Date David Saenz (System Manager) Signature Date Michael Scharfenstein (Project ES&H) Signature Date Richard Hislop (Construction ES&H) Signature Date Part B shall be completed by the LCLS Conventional Facilities Manager or the Facilities Cost Account Manager for the particular project/activity. Check the first column if review by a particular committee, based on professional judgment, and/or direction from the SOC Chairperson, is required. At a minimum, the SOC Chairperson signature is required. Eric Bong (Injector-Linac System Mgr) Signature Date James Welch (Physics Liaison) Signature Date Darren Marsh (LCLS Quality Assurance Mgr) Signature Date Richard M. Boyce (LCLS Integration Mgr) Signature Date Mark Reichanadter (Chief Engineer) Signature Date John Galayda (Division Director) Signature Date Committee Chairperson Safety Overview Committee (SOC) Earthquake Safety Electrical Safety Environment al Safety Fire Protection Hazardous Exp. Equip. Hoisting and Rigging Safety Non-Ionizing Radiation Safety Radiation Safety Operating Safety Architectural Review Ken Moffeit Phone Notification Approval Signature Date Scott DeBarger Marjorie Widmeyer William Kroutil Frank O’Neill John Weisend Dave Ernst Roland Koontz Bill Wisniewski Janice Dabney Steve Williams The LCLS Construction Project Approval Form provides timely notification of a proposed construction project or work activity at SLAC, and serves as a checklist to identify hazards or other aspects of the work activity which are controlled by practices specific to SLAC. The Construction Project Approval Form also documents the authorization to commence work. It lists applicable permits, site specific training requirements, and organizations to be notified prior to the commencement of on-site work activities. (Note that this form will document an authorization to commence construction, not an approval to operate a particular facility or piece of experimental equipment.) 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Date How We Will Get There Schedule our safety design reviews like other project activities – by subsystem Flowcharts for Safety Approval processes with branches to address, e.g. Design Review Authorization Work planning/execution JHAM AHA Electrical Work Hoisting Excavation Work Authorization 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu A Concern- Can We Live With This? Proposed Schedule for Accelerator Operations 2005 - 2008 Seeman/Erickson/Dungan 3/9/05 2006 December Run Run Run Year 2007 2007 2007 2007 2007 2007 2007 2007 2007 2007 2007 2007 January Run February Run March Run April Run May Run June Run July Run August Run SeptemberDown October Down November Down December Run Run Run Run Run Run Run Run Run Down Down Down Run Run Run Run Run Run Run Run Down Down Run/Startup Run Run 2008 2008 2008 2008 2008 2008 2008 2008 2008 2008 2008 January Run February Run March Run April Run May Run June Run July Run August Run September Run October Down November Down Run Run Run Run Run Run Run Run Run Down Down Run Run Run Run Run Run Run Down Down Run/Startup Run Month Linac PEP-II FFTB SPEAR 3 2005 2005 2005 2005 2005 2005 2005 2005 2005 2005 March April May June July August September October November December Run Run Run Run Run Run Run Down Run Run Run Run Run Run Run Run Run Down Run Run Down Tune up E166? SPPS? E167? Run Run Run Run Run Down Down Run/Startup Run Run - exc. few days 2006 2006 2006 2006 2006 2006 2006 2006 2006 2006 2006 January Run February Run March Run April Run May Run June Run July Run August Down SeptemberDown October Down November Down Run Run Run Run Run Run Run Down Down Down Down E166? SPPS? E167? E166? SPPS? E167? SPPS? SPPS? Dismantled Run Run Run Run Run Run Run Down Down Run/Startup Run A lot of people are waiting to “hear” from us on this 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu LCLS Facility Advisory Committee Membership Kem Robinson, Harry Carter, John Cleary, John Corlett, Roger Falcone, Josef Feldhaus, Paul Fouss, Thomas Himel, Vim Leemans, Pat O'Shea, Joachim Pflueger, Thomas Rabedeau, Jörg Rossbach, Keith Schuh, Peter Siddons, Thomas Tschentscher, Karen White, Lawrence Berkeley National Laboratory (LBNL), Chair Fermi National Accelerator Laboratory (FNAL) Stanford University (SU) Lawrence Berkeley National Laboratory (LBNL) UC Berkeley Deutsches Elektronen-Synchrotron (DESY) Argonne National Laboratory (ANL) Stanford Linear Accelerator Center (SLAC) Lawrence Berkeley National Laboratory (LBNL) University of Maryland (UMD) Deutsches Elektronen-Synchrotron (DESY) Stanford Linear Accelerator Center (SLAC) Deutsches Elektronen-Synchrotron (DESY) Fermi National Accelerator Laboratory (FNAL) Brookhaven National Laboratory (BNL) Deutsches Elektronen-Synchrotron (DESY) Thomas Jefferson National Accelerator Facility (TJNAF) Meetings 29-30 April 2004 12-13 October 2004 7-8 April 2005 DOE (Lehman) Review 10-12 May will cover PIXEL 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu FFTB/SPPS Schedule Must preserve funds for FY boundary BUT Acceleration of 2006 procurements considered Conventional construction – SPPS/FFTB schedule LCLS schedule shows May 2006 Shutdown Some evidence that delay past March 2006 will delay LCLS commissioning start- Linac Complete by end of 2007 shutdown Startup planning should exploit this! 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu What’s Next Review Calendar FAC 7-8 April 2005 SAC 5-6 May 2005 Lehman 10-12 May 2005 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu PIXEL Initiative Experiment Stations (instruments?) for LCLS CD-0 Draft under review Warm Dense Matter looking for funding outside BES 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Start of LCLS Project 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.9 Conventional Facilities Construction Manager Out for Bids Undulator Hall (175m) Beam Dump (40M) Front End (29m) Linac-to-Undulator (227m) X-ray Near Transport Expt. (250m) Far Expt. Hall Hall Central Lab Office Complex (CLOC) Capacity ~300 72,000 GSF Total 150-Seat Conference Room 7 April 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu