Undulator Commissioning Heinz-Dieter Nuhn – LCLS Undulator Group Leader June 8, 2009 Undulator Plans June 2009 FAC 1 1 Heinz-Dieter Nuhn nuhn@slac.stanford.edu 29 Undulators Installed Undulator Plans June 2009 FAC 2 2 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Segment Installation Schedule Undulator Segments are being installed in the tunnel as they finish tuning 1/25/2009 – 3/2/2009 (U25 (SN16) Test installation) 3/3-24/2009 U13 – U33 4/22/2009 U09 – U12 5/13/2009 U06 – U08 6/3/2009 U04 and U05 6/3/2009 Removed U33 for damage check. 6/17/2009 U02, U03, and U33 installation planned. Three plus one more undulators are to be installed Regular Undulator Rotation Program will start after temperature calibration procedure Undulator Plans June 2009 FAC 3 3 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Undulator Beam Operation Highlights December 13, 2008 First electron beam through undulator vacuum chamber. No extra steering corrections necessary to get 100% transmission to main dump. Pre-beam girder alignment was sufficient. April 10, 2009 First electron beam through undulator segments. Detected FEL beam after 105 minutes, CCD saturation 20 minutes later. Undulator Plans June 2009 FAC 4 4 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Preset Girder Positions for First Beam • The girders were moved in x and y direction before the first beam was sent through the undulator, mostly to align the beam pipes and the quadrupoles as close to a straight line as possible but also to use the off-axis quadrupole fields to compensate for the earth magnetic field. Both corrections were based on measurements provided by the Metrology group. • The first beam shot did not need any alignment correction to pass through the undulator beam pipe (remember a 130-mlong soda straw) to the main dump. The maximum orbit error was only about 1 mm. The plot is from J. Welch's girderPositionPlotGui and shows schematically the position by which each of the girders was displaced. Undulator Plans June 2009 FAC 5 5 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Checking Undulator K Using YAG Luminescence* 3rd hamrmonic of Spontaneous Undulator Radiation on YAG Crystal Expected Kund = 3.4926±0.0005 Ee = 11.1 GeV Yttrium K Edge at 17.038 keV equals 3rd harmonic of undulator radiation at 11.286 GeV Kmin =3.3532 Kavg =3.4616 Ee = 11.3 GeV Spontaneous Radiation from Dump Bend Kmax =3.4256 Ee = 11.5 GeV Ee = 11.7 GeV Ee = 11.9 GeV More precise bracketing gave Kavg =3.4932±0.0045 (1.7 ×10-4 from expected value) 10 or 11 undulators IN, Ipk = 500 A, LH = 200 uJ First and third harmonic of spontaneous radiation as background Undulator Plans June 2009 FAC 6 6 *by J. Welch and J. Frisch Heinz-Dieter Nuhn nuhn@slac.stanford.edu YAG Screen Image of First Lasing FIRST LCLS FEL LIGHT 10 or 11 undulators IN, Ipk = 500 A, LH = 200 uJ First and third harmonic of spontaneous radiation as background Undulator Plans June 2009 FAC 7 7 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Undulator Characterization: 1st Field Integral U09 Horizontal (I1X) and vertical (I1Y) first field integrals measured by fitting a kick to the difference trajectory as function of undulator displacement Reference Point Beam Based Measurements MMF Measurement Undulator Plans June 2009 FAC 8 8 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Measurement of 1st Field Integral U11 Reference Point Beam Based Measurements MMF Measurement The beam-based measurement relies on the RF cavity BPMS to achieve a 20 nrad measurement resolution of the kick angle inside the undulator Undulator Plans June 2009 FAC 9 9 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Alignment Tolerance Verification Random misalignment with flat distribution of widh ±a => rms distribution a/sqrt(3) Undulator Plans June 2009 FAC 10 10 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Simulated: Horizontal Module Offset Simulation and fit results of Horizontal Module Offset analysis. The larger amplitude data occur at the 130-m-point, the smaller amplitude data at the 90-m-point. 130 m Horizontal Model Offset (Gauss Fit) 90 m Location Fit rms Unit 090 m 0782 µm 130 m 1121 µm Average 0952 µm Budget Tolerance Undulator Plans June 2009 FAC 11 11 Heinz-Dieter Nuhn S. Reiche Simulations 2006 nuhn@slac.stanford.edu LCLS Tolerance Budget 1 fi 2 P e 2 P0 Tolerance Budget Components si fi Units 0.452 0.32 z < 1.1 0.64<b/b0<1.56 30 0.176 3.7 µm Module Detuning DK/K 0.060 0.400 0.024 % Module Offset in x 1121 0.125 140 µm Module Offset in y 268 0.298 80 µm Quadrupole Gradient Error 8.8 0.029 0.25 % Transverse Quadrupole Offset 4.7 0.214 1.0 µm Break Length Error 20.3 0.049 1.0 mm Error Source Hor/Ver Optics Mismatch (z-1)0.5 Hor/Ver Transverse Beam Offset Undulator Plans June 2009 FAC si fi @ 130 m (24.2% red.) 0.71 12 12 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Girder Stability : Position / Temperature Temperature fluctuations, girder deformation, and ground motion cause changes in Undulator strength, which depends on Temperature Beam trajectory Quadrupole position instability, which causes Changes to the electron beam trajectory (phase errors) Good News: Observed stability of girder positions and temperatures is better than expected. Undulator Plans June 2009 FAC 13 13 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Girder Stability During 2008 Winter Break Measurements show how much the girder posiiton deviatation from a straight line changed over the period of one week during lab closure. RMS Position Change < 1 µm Alignment Diagnostics System (ADS) Undulator Plans June 2009 FAC 14 14 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Girder 13 Stability During 19h Operation 200 nm Alignment Diagnostics System (ADS) Undulator Plans June 2009 FAC 15 15 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Girder 15 Movement (18 h) During ROD (11 h) Mechanical Hysteresis >1 µm Alignment Diagnostics System (ADS) Undulator Plans June 2009 FAC 16 16 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Temperature Recording of Girder 16 SHUT DOWN (UND INSTALLATION) REPAIR OPPORTUNITY DAY (ROD) HVAC SETPOINT ADJUSTMENT 50 mK Undulator Plans June 2009 FAC 17 17 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Temperature at all Girders Upstream U23 Center U23 Downstream U23 On Girder Undulator Plans June 2009 FAC Mounted to Undulator 18 18 Heinz-Dieter Nuhn nuhn@slac.stanford.edu K is Adjusted for Temperature Deviations Undulator Plans June 2009 FAC 19 19 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Use of (T-)Corrected K Values TEMPERATURE CORRECTED K K ADJUSTMENT RANGE TAPER REQUIREMENT Undulator Plans June 2009 FAC 20 20 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Radiation Control and Monitoring Undulator radiation damage is greatly reduced through Machine Protection System (MPS) hardware interlocks that inhibit beam to the undulator hall when PEP/ANL type BLM signals are above threshold Beam loss fiber signals are above threshold Horizontal and/or vertical trajectory is outside ±1mm Comparator toroids indicate beam loss. Any of the upstream profile monitors is inserted More than 1 BFW is inserted or a BFW is moving A regular TLD monitoring program is in place (s. below) A regular undulator circulation program will start soon (s. below) Undulator Plans June 2009 FAC 21 21 Heinz-Dieter Nuhn nuhn@slac.stanford.edu TLD Replacement Program Thermo Luminescent Dosimeters (TLDs) are mounted inside the Undulator Hall and are regularly replaced and evaluated Baseline 10/3/2008 – 12/9/2008 (10 TLDs) Startup 12/12/2008 – 12/17/2008 (12 TLDs) 1st Undulator 1/28/2009 – 2/4/2009 (15 TLDs) 1st Undulator 2/4/2009 – 2/11/2009 (14 TLDs) 1st Undulator 2/11/2009 – 2/18/2009 (18 TLDs) 1st Undulator 2/18/2009 – 3/2/2009 (48 TLDs) FEL Operation 3/24/2009 – 4/22/2009 (68 TLDs) FEL Operation 4/22/2009 – 5/6/2009 (125 TLDs) FEL Operation 5/6/2009 – 5/27/2009 (128 TLDs) FEL Operation 5/27/2009 – … (128 TLDs) FEL Operation … Latest TLD placements include detection of neutrons and high energy gamma through use of moderators and W and Pb absorbers. TLD volume is expected to taper down after initial observation period. Undulator Plans June 2009 FAC 22 22 Heinz-Dieter Nuhn nuhn@slac.stanford.edu TLD Readings at First Undulator LOCATION WEEK 1 PHOTON [rad] WEEK 2 PHOTON [rad] WEEK 3 PHOTON [rad] U25:ANL-BLM 0.081 0.106 0.051 U25: PEP-BLM 0.042 0.048 0.030 U25: Back +X 0.065 0.008 0.033 U25: Back +Y 0.012 0.071 0.064 U25: Back -X 0.039 0.026 0.029 U25: Back +Y 0.013 0.042 0.014 U25: Front +X 0.112 0.093 0.072 U25: Front +Y 0.217 0.105 0.110 U25: Front -X 0.046 0.055 0.025 U25: Front -Y 0.141 0.123 0.093 Recorder Photon Doses about 0.1 rad per week Undulator Plans June 2009 FAC 23 23 Heinz-Dieter Nuhn nuhn@slac.stanford.edu SN16 Radiation Damage Test HAS BEEN INSTALLED ON GIRDER 25 DURING BEAM OPERATION Undulator Plans June 2009 FAC 24 24 Heinz-Dieter Nuhn nuhn@slac.stanford.edu [rad] Dose During Initial X-Ray Operation e-folding length 8.7 m Increased TLD Readings are expected to be predominantly low energy synchrotron radiation, not to cause significant magnet damage Undulator Plans June 2009 FAC 25 25 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Dose During Recent X-Ray Operation e-folding length 8.7 m neutron dose at end of undulator line about 100 mrad/week or less Increased TLD Readings are expected to be predominantly low energy synchrotron radiation, not to cause significant magnet damage Undulator Plans June 2009 FAC 26 26 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Electronics Shielded TLD Readings at End of Undulator Line Undulator Plans June 2009 FAC LOCATION Photon Dose over 3 weeks [rad] Downstream U32 without / with 1.6 mm Pb wrap 0.52 / 1.84 Downstream U33 without / with 1.6 mm Pb wrap 1.38 / 6.37 Downstream (about 2.5 m) U33 without / with W 0.62 / 0.05 Downstream (about 2.5 m) U33 without / with Al 0.59 / 0.31 U33 Cam Motors CM2 / CM5 0.00 / 0.02 U33 Horizontal Slide Motor SL1 0.08 On top of RFBPM Chassis U31 / U32 0.04 / 0.31 Girder Motion Electronics Racks U25 / U29 / U33 0.03 / 0.01 / 0.01 WPM Electronics Racks U25 / U31 2.08 / .08 North Side of Tunnel opposite of U33 0.08 27 27 Heinz-Dieter Nuhn nuhn@slac.stanford.edu SN20 Radiation Damage Test HAS BEEN INSTALLED ON GIRDER 33 DURING FEL OPERATION Undulator Plans June 2009 FAC 28 28 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Undulator Circulation Program Undulators will be periodically removed from the Undulator Hall to be re-measured at the MMF to check for radiation damage A “test”-undulator was re-measured after several weeks of beam operation. No damage was found. First undulator that participated in FEL run was removed on June 3 and MMF testing has found it to be undamaged Depending on MMF availability, up to 2 undulators per month will be removed from the Undulator Hall for checking After the undulators have been found undamaged they will be reinstalled onto the original girder Undulator Plans June 2009 FAC 29 29 Heinz-Dieter Nuhn nuhn@slac.stanford.edu Summary Undulator tuning and installation close to completion Initial beam operation went extremely smoothly: no tweaking required Temperature and girder stability are well within tolerance Beam loss control and radiation monitoring is in place High radiation levels at initial FEL operation are expected to be predominantly low energy photons that should not generate demagnetization Very low dose levels measured at electronics components Undulator circulation program has started Undulator Plans June 2009 FAC 30 30 Heinz-Dieter Nuhn nuhn@slac.stanford.edu End of Presentation Undulator Plans June 2009 FAC 31 31 Heinz-Dieter Nuhn nuhn@slac.stanford.edu