 OMCS Status Report Psoft- Portal & FMCS Upgrade

advertisement
Psoft- Portal & FMCS Upgrade
OMCS Status Report
Current Project
Status

Green
Yellow
Reporting Period
22 Ju1 2014
Service
Peoplesoft@Customer
ULKY- Project Manager
OMCS - SDM
Transition Manager
Linda Krauth
John Schumacher
Meera Vijayan
Red
Current Lifecycle Phase
/ Milestone
Planned Go Live Date
Project Start Date
Project End Date
Initialization
Portal : 13-March 2014
FMCS: 10-Oct-2014
02-Dec-2013
07-Nov-2014
Meeting Coordinates
Dial in: US Toll free 1.866.682.4770 Conference Code:0544277 Pin:2345
Time: Tues at 8.30 am EST
This week’s Report (07/22/2014)
FSCM -Activities Completed
 Showstopper Bug # 1421 resolved
 Bug # 1470 – Refresh FIUPG from FI92P iscompleted and released to continue Second Pass testing
 Bug # 1471 – Refresh of FI92P is completed and FI92P is released for Chapter 2 tasks update, as part of the
Third pass
 Initial Pass on FITYPE is completed, 83% of testing was done and 77% of bugs were resolved. Going forward,
FITYPE will be used as a resource
FSCM – Action Items / Activities in Progress
1. Bugs are resolved on priority basis
2. Testing continues on FIUPG
3. 31% of testing is completed in Second Pass, 66 bugs were raised and 22 resolved as of 07/21
4. Complete testing on FIUPG for second pass and sign off second pass
5. Complete third pass on FI92P and release for testing third pass
6. Capture and Analyze Third pass timings to prepare for Dry Run & Cut Over plans
Next Update: 07/29/2014
Page 1
Last week’s update (07/15/2014)
FSCM – Action Items / Activities in Progress
1. Bugs are resolved on priority basis
2. Testing continues on FITYPE & FI92P; FITYPE should be signed off ASAP
3. As of 07/15, 74% testing is completed on FITYPE & 20% testing is completed on FI92P
4. FIUPG will be refreshed from FI92P starting 07/18 and delivered on 07/21, so the users can continue with the
testing on second pass until FI92P is delivered
5. Third pass activites on FI92P will happen next week and the tentative delivery date as per the project plan is
08/06. But we are planning to deliver a week ahead depending on the progress of the update next week.
Page 2