CF Overview & Status Design Status CMGC Status Latest VE Decisions CF Total Estimated Cost Beneficial Occupancy Dates CF Organization Summary Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Design Status √ Title I - completed May 04 √ Interim services by JE between Title I/Title II – completed at the start of Title II √ Final Tunneling Memorandum and Geotechnical Investigation Report completed Jan 05 √ Geotechnical Baseline Report (GBR) awarded April 05 to HatchMott MacDonald Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Design Status – cont’d √ Title II AE Design Kickoff March 29-30 √ 30% design review was performed in Aug-Sept 05 Meeting was held at JE Cypress facility to review sum total of <1,000 comments from the various disciplines 100% civil design delivered Oct 26, 05 Road-work for North Access Road/Survey Tower Road Open excavation at EBD/FEE/NEH Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Design Status – cont’d 60% design review scheduled for Oct 28 (will likely be delayed ~ 3 weeks as a result of recent VE decisions) 100% design review Jan 18, 05 Progress drawings for design reviews are available at http://www-ssrl.slac.stanford.edu/lcls/cf/ When performing design reviews… A commitment for a timely review and response back to JE is necessary system mgrs citizen committees various groups and departments, i.e. CEF, ES&H, SU Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Design Status – cont’d 30% construction cost estimate delivered by JE Oct 4, 05 ($74.3M) Title I Estimate $50.2M DCN process was followed for all design changes to include estimated hard cost Valued at ~$3.5M 30% independent cost estimate delivered by WDWC Oct 7, 05 ($66.4M) Title I Estimate $72M Reconciliation report needs to be completed Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CMGC Status Approved! SO DOE Chicago DOE Washington DOE Awarded to Turner Construction (TC) Oct 17, 05 Phase I - $.6M Phase II - $12M Incentive Fee - $.55M Safety Schedule Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CM/GC Phase 1 Effort Phase 1 – preconstruction activities to include: Provide effective overlap period and oversight of effort during Title II Estimates during Title II CPM Schedule Identify lead-time for critical items Design coordination Constructability reviews Value Engineering reviews Site investigation Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CM/GC Phase 1 Effort – cont’d Develop construction bid packages Develop list and contact potential bidders Develop prequalification criteria Solicit bids Recommend award to SLAC for approval of subcontractor Award contract to subcontractors Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CM/GC Phase 1 Effort – cont’d Develop Project Management Plan (PMP) Construction Management Plan – outlines project scope, organization, and specific approach to accomplish project Project Safety Plan – project specific identifying job hazards, safety performance and individuals responsible for project safety Procurement Plan – identifies systems, methods and procedures for solicitation to subcontractors Quality Control and Assurance Plan – method of controlling time, cost and quality of various management tasks specific to the project Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CM/GC Phase 2 Effort Phase 2 – CM/GC shall provide all materials, labor, and services required to construct the Project All general conditions including field personnel, office staff, temporary offices, temporary construction, safety implementation, construction equipment, coordination of all subs, project administration, construction waste management, commissioning Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CMGC Status – cont’d Held Kick-off meeting Oct 19, 05 Delivered cost estimates from both JE and WDWC AE Design schedule Other data was relayed i.e. weekly Owner/Architect/Contractor (OAC) meetings, etc Critical message Safety First! Cost estimate for CLOC Construction sequencing, particularly the demolition of FFTB Civil work North Access Road Open cut Schedule of preparation of procurement packages for construction Remaining Phase II work Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Cost Estimates Largest variance! JE Est WDWC Est Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Title II JE Cost Summary by CSI Title II Est $74.4M Title I Est $50M Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity Variance $24.1M↑ David Saenz saenzd@slac.stanford.edu Title II JE Cost Summary by CSI Site-work $4.2M (TI) vs $7.4 (TII) delta of $3.2M↑ Mechanical $8M (TI) vs $13.4M (TII) delta of $5.4M↑ Electrical $5.8M (TI) vs $12.8 (TII) delta of $7M↑ Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Title II JE Cost Summary by Area Areas with most significant increase: •UH $4.3M →$10.9M •NEH $6.4M →$9.6M •CUP $395K →$2.8M •XRT $3.8M →$5.7M •FEH $6M →$10.7M •CLOC $12.9M →$21.3M Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Title II Breakdown by Structure (with Area) Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Cost Estimate Delta results in reduction in scope of various items To date $11M worth of scope has been reduced Total value of items continue to fall short of remaining in the box by ~$3.6M Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu VE Scope Reductions - Tunneling Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu •T2 – shorten xrt 60’ and access tunnel 40’ •T3a – enlarge access tunnel to 19’ •T5a/b – square off transition tunnel, shift FEH 60’ to the west (T2) •T6 – cut/cover FEH (not approved) XRT/FEH Tunnel Floor Plan Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Architectural, Site, Finishes Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Architectural, Site, Finishes – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu A01 – Delete masonry veneer NEH – Service Yard Entrance Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu A15 – Reduce glazing Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu A07 – 3rd floor shell only, no interior build out CLOC Floor Plan 3rd Floor Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu A12 – Eliminate Conf Ctr Conf Center Floor Plan Conf Center Elevation Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Architectural, Site, Finishes – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu G08 – use pan form concrete NEH Cross Section Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu G10 – reduce size of basement level shaft NEH Floor Plan – Basement Level Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Architectural, Site, Finishes – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu S06 – replace screen wall at CUP service yard w/ 8’ mesh fence Site Plan Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu S04 – reduce retaining walls S03 – reduce excavated bowl Site Plan - CLOC Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Mechanical Scope Reductions Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Mechanical Scope Reductions – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Mechanical Scope Reductions – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu M13 – place baseline UH design with alt plan Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Mechanical Scope Reductions – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Electrical Scope Reductions Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Electrical Scope Reductions – cont’d Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Summary of Scope Reductions Tunneling - $.847M Architectural, Structural, General - $4.484M Mechanical - $3.782M Electrical - $1.762M Running Total = ~$11M All cost reductions have been approved by Systems Managers and Project Office. Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu At grade in RSY LCLS CF Rendering Cut & Cover Location of Pep Ring Rd BTH UNDULATOR HALL ELECTRON BEAM DUMP & FEE NEAR EXPERIMENTAL HALL AND CENTRAL LABS & OFFICE X-RAY TRANSPORT & DIAGNOSTICS TUNNEL FAR EXPERIMENTAL HALL (redesign) Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CF Cost Estimate – Aug 05 19% 4% 1.9.1 System Management & Integration 77% 1.9.2 Title 1 & Title 2 Conventional Facilities 1.9.3 Construction-T3 Conventional Facilities Total CF Cost = $80.6M Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Beneficial Occupancy Dates (L3 and L4) Sector 20 3/31/06 MMF 4/3/06 Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu CF Staff FY 06-08 Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Summary Open Issues… Prepare for upcoming Lehman visit on Nov 17, 05 Demonstrate readiness for CD-3 Review (7-9 February 2006) Title II 60% design review coming shortly (?) Geotechnical Baseline Report (GBR) in process, due in parallel with design by outside separate consultant Independent Seismic Peer Reviewer on-board and working with JE (Forell/Elsesser Engineers, Inc.) S20 and MMF to complete construction in the next 120 calendar days by XL Construction Changes will delay BO date Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu Summary – cont’d Turner Construction (TC) to begin full steam ahead Conduct cost estimate and major planning, conduct VE and constructability reviews, project schedule and develop bid packages Possible advancement Phase II effort RSY North Access Road [1] Memo was sent SSO requesting approval to commence this activity Open-cut of NEH area [1] ? Utility investigation? Title III Construction for RSY – CLOC by TC (03/06) MEP Technical Review will be required within the next 4 weeks Resolution to additional near future de-scope items Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu End of presentation Oct 27, 2005 FAC Review CF Design, Cost and Schedule Maturity David Saenz saenzd@slac.stanford.edu