Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule Cost Estimate Organizational Chart Summary Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu SLAC Site Plan SLAC Main Gate Pep Ring Road Bldg #081 - MMF Sector 25 Sector 20 Upstream LCLS General Work Boundary Research Yard Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu LCLS CF Systems Description Extends SLAC LINAC ~ 1/2 mile (814 meters) Includes a composition of renovations to existing SLAC infrastructure and new facilities Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Systems Description Sector 20 Injector Facility Magnetic Measurement Facility Linac Improvements Beam Transport Hall Undulator Hall Front End Enclosure Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Systems Description – cont’d Electron Beam Dump Near Experimental Hall X-Ray Transport & Diagnostics Tunnel Far Experimental Hall Central Lab Office Complex Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Construction Projects in Progress S20 Injector Facility (CF PM: Bob Law) √ Title I/II complete Title III has been awarded and in process ($2.2M) Pre-construction Kickoff August 2005 Onsite Mobilization September 2005 Beneficial Occupancy date March 31, 2006 (L3) Scope includes: 2,000sf Injector Facility RF Hut K10B Substation ($.3M) Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu S20 Injector Facility – cont’d Construction Hazards do exist Managed by SLAC trained UTR Pre-work Hazard Analysis and Job Hazard Analysis and Mitigation (JHAM) will be performed by contractors Proper PPE is required to visit the jobsite. If you don’t have it, don’t go out to the job site Risks, Challenges and ESH Issues will be addressed by the WBS Manager in breakout Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu S20 Construction Photos Existing Building From I280 Demolition of Steel Oct 26, 2005 FAC CF Overview Partial Demo of Metal Siding Demolition of Steel Partial Demo of Metal Siding New K10B Substation David Saenz saenzd@slac.stanford.edu Construction Projects in Progress Magnetic Measurement Facility (CF PM: Javier Sevilla) Title I/II complete Title III has been awarded and in process ($2.5M) Pre-construction Kickoff August 2005 Onsite Mobilization September 2005 BO date April 3, 2006 (L3) Scope includes: 4,000sf lab Building 12KV feeder (funding split 50-50 w/lab) Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Magnetic Measurement Facility – cont’d Construction Hazards will do exist Managed by SLAC trained UTR Pre-work Hazard Analysis and Job Hazard Analysis and Mitigation (JHAM) will be performed by contractors Proper PPE is required to visit the jobsite. If you don’t have it, don’t go out to the job site Risks, Challenges and ESH Issues will be addressed by the WBS Manager in breakout Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu MMF Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Construction Projects in Progress FFTB/BSY Shielding (CF PM: Jesse Saldivar) Design complete by in-house CEF engineer Title III has been awarded and in process ($160K) Award October 10, 2005 BO date October 25, 2005 Scope includes: Removal of (12) 9’x9’x3’ concrete shielding blocks weighing ~18 tons each x 12 = 437,400 #’s Form and pour of 60y^3 of concrete = 243,000 #’s Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu FFTB/RSY Shielding – cont’d Construction Hazards will do exist Managed by SLAC trained UTR Pre-work Hazard Analysis and Job Hazard Analysis and Mitigation (JHAM) will be performed by contractors Proper PPE is required to visit the jobsite. If you don’t have it, don’t go out to the job site Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu FFTB/BSY Shielding Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Construction Projects in Progress Sector 24 Equipment Enclosure (CF PM: Jesse Saldivar) Design complete by outside consultant Title III has been awarded and in process Award October 2005 at $51K BO date October 25, 2005 Scope includes: Installation of new 6 flight steel stairs Installation of steel enclosure Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu S24 Equipment Enclosure – cont’d Construction Hazards will do exist Managed by SLAC trained UTR Pre-work Hazard Analysis and Job Hazard Analysis and Mitigation (JHAM) will be performed by contractors Proper PPE is required to visit the jobsite. If you don’t have it, don’t go out to the job site Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Sector 24 Equipment Enclosure Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Research Yard •RSY Work Boundaries •Plan was presented to the lab in July to begin clearing the areas for upcoming construction activities…. Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Research Yard – cont’d •RSY Work Boundaries •and they’ve responded positively! Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Potential Upcoming Activities •Survey Tower Road •North Access Road •Utility Location Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Beam Transport Hall RSY Oct 26, 2005 FAC CF Overview Plan At Grade UH SB (E) Pep Ring Rd CUP (E) CEH CLOC David Saenz saenzd@slac.stanford.edu Below Grade Plan FEE Undulator Hall Oct 26, 2005 FAC CF Overview EBD NEH FEH XRT David Saenz saenzd@slac.stanford.edu New Facilities (below grade) Beam Transport Hall – 227m long above grade facility to transport the electron beam through the existing RSY Electron Beam Dump – 40m long underground facility used to separate the electron and x-ray beams Undulator Hall – 175m long underground tunnel housing undulators and ancillary equipment Central Lab Office Complex – office facility to house ~ 300 LCLS researchers, engineers, technicians, administrative staff and visiting experimentalists Far Experimental Hall – underground cavern/tunnels to house 3 experimental hutches, prep and shop space Front End Enclosure – 30m long underground facility to house various diagnostic equipment in support of the photon beam Near Experimental Hall – underground facility whose primary function is to house 3 experimental hutches, prep and shops X-Ray Transport & Diagnostics Tunnel – 250m long underground tunnel used to transport photon beams from NEH to FEH Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CLOC Floor Plans • Headcount of CLOC Personnel = 284 • Capacity of Conf Center = 150 • Gross square footage of CLOC (offices and labs) = 78,622sf Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CLOC Exterior Elevations Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu LCLS Site Plan Spear Future Office Space Undulator Hall Research Yard Pep Ring Road SLC Office Complex Survey Tower NEH Beam Transport Hall SLC Tunnel Future Beam Lines Beam Dump Front End Enclosure X-Ray Transport Pep Tunnel Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Design Status √ Title I - completed May 04 √ Interim services by JE between Title I/Title II – completed at the start of Title II √ Final Tunneling Memorandum and Geotechnical Investigation Report completed Jan 05 √ Geotechnical Baseline Report (GBR) awarded April 05 to HatchMott MacDonald Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Design Status – cont’d √ Title II AE Design Kickoff March 29-30 √ Title II 30% design review was performed in Aug-Sept 05 On-site internal review Summary of the design review was held at JE Cypress facility to review sum total of <1,000 comments from the various disciplines √ 100% civil design complete delivered Oct 25, 05 (still under review) Road-work for North Access Road/Survey Tower Road Open excavation at EBD/FEE/NEH Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Design Status – cont’d Latest schedule reflects 60% design review scheduled for Oct 28 100% design review Jan 18, 05 Drawings for design reviews are available at http://www-ssrl.slac.stanford.edu/lcls/cf/ When performing design reviews… A commitment for a timely review and response back to JE is necessary system mgrs citizen committees various groups and departments, i.e. CEF, ES&H, SU Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Design Status – cont’d Deliverable from JE 30% construction cost estimate Oct 4, 05 ($74.3M) Deliverable from Independent Cost Estimator (WDWC) 30% independent cost estimate Oct 7, 05 ($66.4M) More on cost issues in breakout session Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Cost Estimates Largest variance! JE Est WDWC Est Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CMGC Status Approved! SO DOE Chicago DOE Washington DOE Awarded to Turner Construction (TC) Oct 17, 05 Phase I - $.6M Phase II - $12M Incentive Fee - $.55M Safety Schedule Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CMGC Status – cont’d Held Kick-off meeting Oct 19, 05 Critical message Safety First! Cost estimate for CLOC Construction sequencing, particularly the demolition of FFTB Civil work North Access Road Open cut Schedule of preparation of procurement packages for construction Remaining Phase II work Held first weekly OAC meeting Oct 26, 05 Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CMGC Status – cont’d 30% construction cost estimate delivered by JE Oct 4, 05 ($74.3M) 30% independent cost estimate delivered by WDWC Oct 7, 05 ($66.4M) however, the non-tunneling scope was not well defined Formal reconciliation is not yet complete. TC will provide “reality-check” estimate in ~ 1 week. TC will provide a “bottoms-up” estimate from the 60% design drawings/specifications Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu LCLS CF Construction Schedule •Major construction phase FY 06 at 30 months duration •Beneficial Occupancy dates are key to technical system interfaces •Site-work at NEH is key! Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CF BCWS 1.09 Conventional Facilities TEC Total $80.6M (fully burdened & escalated) 40000 35000 30000 25000 20000 15000 10000 5000 0 37.65 26.11 8.98 5.56 1.72 Prior Oct 26, 2005 FAC CF Overview .58 FY05 FY06 FY07 FY08 David Saenz saenzd@slac.stanford.edu FY09 CF Cost Estimate – Aug 05 19% 4% 1.9.1 System Management & Integration 77% 1.9.2 Title 1 & Title 2 Conventional Facilities 1.9.3 Construction-T3 Conventional Facilities Total CF Cost = $80.6M Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu CF Staff FY 06-08 Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Summary Design Status Title II Kickoff March 29, 2005 Interactive Planning session scheduled April 13, 2005 - complete 30% design review - complete 60% design review is imminent 90%/100% design submittal is scheduled As-Built program - complete Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Summary Construction Status to Date S20 on schedule and progressing well with XL Construction MMF on schedule and progressing well with XL Construction Downtime Projects Going Well FFTB/RSY Shielding Sector 24 Equipment Enclosure Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu Summary – cont’d CMGC Status Award of contract to Turner Construction Lots to do during Phase I Geotechnical Baseline Report (GBR) has been awarded Independent Seismic Peer Reviewer on board RSY work plan to prepare for upcoming construction agreed to by lab and progressing very well Complete environmental sampling & waste disposal analysis - continues to progress Oct 26, 2005 FAC CF Overview David Saenz saenzd@slac.stanford.edu