Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M. Reichanadter / SLAC Oct 27-28, 2005 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu Outline Status of the LCLS Progress in the past six months Project Management Cost and Schedule Performance Contingency Allocation Organization and Integration Plans for the next six months Risks/challenges ahead Oct 27-28, 2005 LCLS FAC Meeting 2 Mark Reichanadter reich@slac.stanford.edu LCLS Project Status LCLS Critical Decision Status; CD-0 Approve Mission Need – Complete (Jun01) CD-1 Approve Preliminary Baseline Range – Complete (Oct02) CD-2A Approve Long-Lead Procurement Budget – Complete (Jul04) CD-3A Approve Start of Long-Lead Procurements – Complete (Dec04) CD-2B Approve Performance Baseline – April 11, 2005 OECM validated baseline June 7, 2005 CD-3B Approve Start of Construction – Scheduled (Mar06) CD-4 Approve Start of Operations – Scheduled (Mar09) LCLS Major Upcoming Start/Completion Dates; Start of LCLS Construction Start– Mar06 Injector Laser Commissioning Start– Jun06 Injector E-Beam Commissioning Start– Apr07 Linac-to-Undulator Commissioning Start – Mar08 “First Light” (E-Beam through Undulator) Start – May08 LCLS Major Upcoming Project Reviews DOE Status Meeting – Nov17, 2005 CD-3B DOE “Lehman” Review – Feb06 Assess readiness for start of construction Oct 27-28, 2005 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu LCLS Project Status (last six months) SLAC has reorganized its divisions and upper management. ISMS, construction/contractor management procedures have undergone extensive revision. Additional training for all personnel and higher visibility on safe working practices at SLAC.\ More visibility into SLAC Operations and Photon Science. LCLS is in the Design/Procure/Construct (execution) phase. Safety First! Then think about schedule, technical and cost. Performance and progress based on “earning-value” against its resource-schedule. With CD-2b, changes are handled via LCLS Change Control Board (working well) LCLS Staffing at ANL, LLNL and SLAC nearing full project team (on schedule). Strengthened Procurement and Conventional Facilities A few positions are still open (Controls Mgr, Undulator ME’s @ SLAC, CF UTR’s) LCLS Procurements are going well with the dedicated cell. Procurement team is co-located with technical team and working reasonably well. All Injector, Linac, Undulator & CF LLP’s are well-advanced CM/GC procurement (LCLS largest and most complex now awarded (Turner Construction). LCLS Technical Specifications improving. Technical Specifications continue to mature most are now complete or nearing completion. Photon System (XTOD and XES) are the least mature (input from Users and final CF design System Integration strengthened with R. Boyce, D. Marsh and A. Chan. LCLS Title 2 Design is key concern. Schedule delays (30% submission late) Cost high (working to get back in the box) Oct 27-28, 2005 LCLS FAC Meeting Mark Reichanadter reich@slac.stanford.edu LCLS Activities @ SLAC You are here B750 LCLS temporary staging/storage, permanent lab, testing and machine shop space. Share with other users, LSS?, EXO? Remove Mark II Detector? B280 LCLS Central Design Team 2 floors, 84 offices ~13,000sf MMF-4,000sf facility used to tune, measure and store undulator magnets S20-2,160sf facility Laser & Control Rm S24 Stairway FFTB/BSY Vertical Wall Project • LCLS upgrades to the SLAC site are underway. (LLP funding) • Shutdown allows the installation of key injector components in the injector vault. Oct 27-28, 2005 LCLS FAC Meeting 5 Mark Reichanadter reich@slac.stanford.edu LCLS Performance – Aug05 LCLS Cost/Schedule Status Report - Work Breakdown Structure 31-Aug-05 Cumulative to Date ($K) WBS Budgeted Cost Work Scheduled Work Performed At Completion ($K) Variance Actual Cost Work Performed Performance Indices Latest Revised Estimate Budgeted Schedule Cost SPI CPI Variance 1.1 Project Management 8,880 8,375 8,648 -505 -273 0.94 0.97 28,970 28,970 0 1.2 Injector 7,113 6,163 6,096 -951 67 0.87 1.01 19,297 19,297 0 1.3 Linac 3,122 3,049 2,520 -73 529 0.98 1.21 26,431 26,431 0 1.4 Undulator 8,912 6,244 6,206 -2,668 39 0.70 1.01 50,724 50,724 0 1.5 X-ray Transport 4,356 4,225 4,102 -131 123 0.97 1.03 27,127 27,127 0 721 721 680 0 41 1.00 1.06 14,779 14,779 0 1.9 Conventional Facilities 4,813 4,828 5,394 15 -567 1.00 0.89 80,649 80,649 0 1 LCLS Total Base Cost 37,917 33,604 33,646 -4,313 -42 0.89 1.00 247,976 247,976 0 1.6 X-ray Endstations LCLS Total Estimated Cost 2.1 LCLS Project Mgmt, Planning & Admn (OPC) 315,000 315,000 Avail. Contingency 67,024 67,024 % Contingency / Rem. Work 31.3% 31.3% % Complete LCLS Base Cost 13.6% 13.6% 4,437 4,538 4,345 101 193 1.02 1.04 33,021 33,021 0 699 757 578 58 179 1.08 1.31 6,107 6,107 0 1 1 1 0 0 1.05 1.00 2,545 2,545 0 2.4 Undulator (OPC) 742 689 776 -53 -86 0.93 0.89 5,873 5,873 0 2.5 X-ray Transport (OPC) 480 412 339 -68 73 0.86 1.22 4,015 4,015 0 2.6 X-ray Endstations (OPC) 165 137 98 -28 39 0.83 1.39 5,200 5,200 0 2.9 Conventional Facilities (OPC) 0 0 0 0 0 0 0 0 2 LCLS Total Other Project Cost 6,524 6,534 6,136 10 397 56,761 56,761 0 64,000 64,000 2.2 Injector (OPC) 2.3 Linac (OPC) 1.00 1.06 LCLS Other Project Cost LCLS Total Obligations to Date 58,430 LCLS Total Project Cost 44,441 Avail. Management Reserve 7,239 7,239 % Contingency / Rem. Work 14.4% 14.4% % Comp LCLS Other Project Cost 40,137 39,782 -4,303 355 % Complete LCLS TPC Oct 27-28, 2005 LCLS FAC Meeting 6 0.90 1.01 11.5% 11.5% 379,000 379,000 13.2% 13.2% Mark Reichanadter reich@slac.stanford.edu • LCLS in the “green” LCLS TEC Planned Spending / Month LCLS PROJECT - PED & CONSTRUCTION 80,000,000 70,000,000 • Variances caused by inaccurate plan rather than real schedule delay. 60,000,000 50,000,000 40,000,000 30,000,000 20,000,000 10,000,000 0 Prior Mo's MAR_05 APR_05 MAY_05 JUN_05 JUL_05 AUG_05 SEP_05 OCT_05 NOV_05 DEC_05 JAN_06 FEB_06 Mo S 17,613,41 1,663,846 2,281,115 2,968,973 3,286,115 4,140,441 5,962,705 5,517,648 7,741,969 6,294,452 6,155,789 5,380,789 5,463,736 Mo P 17,613,41 1,663,846 2,281,115 2,625,520 2,915,361 2,976,891 3,527,565 Mo A 17,613,41 1,663,846 2,281,115 2,876,780 2,729,733 3,335,870 3,144,993 Cum S 17,613,41 19,277,25 21,558,37 24,527,34 27,813,46 31,953,90 37,916,60 43,434,25 51,176,22 57,470,67 63,626,46 69,007,25 74,470,99 Cum P 17,613,41 19,277,25 21,558,37 24,183,89 27,099,25 30,076,14 33,603,71 Cum A 17,613,41 19,277,25 21,558,37 24,435,15 27,164,88 30,500,75 33,645,75 Oct 27-28, 2005 LCLS FAC Meeting 7 Mark Reichanadter reich@slac.stanford.edu LCLS TEC Planned Spending / Month UNDULATOR SYSTEM (TEC)- SPA 18,000,000 16,000,000 14,000,000 • Largest variance due to plan called for full earned-value on Und materials rather than progress payment. 12,000,000 10,000,000 8,000,000 6,000,000 4,000,000 2,000,000 0 Prior Mo's MAR_05 APR_05 MAY_05 JUN_05 JUL_05 AUG_05 SEP_05 OCT_05 NOV_05 DEC_05 JAN_06 FEB_06 Mo S 2,965,465 281,380 402,133 257,358 958,576 1,162,423 2,884,622 1,223,069 1,423,281 1,151,226 1,596,843 1,034,532 1,288,822 Mo P 2,965,465 281,380 402,133 267,959 876,646 843,105 607,519 Mo A 2,965,465 281,380 402,133 679,807 531,300 878,825 466,762 Cum S 2,965,465 3,246,846 3,648,978 3,906,336 4,864,912 6,027,335 8,911,957 10,135,02 11,558,30 12,709,53 14,306,37 15,340,90 16,629,73 Cum P 2,965,465 3,246,846 3,648,978 3,916,938 4,793,584 5,636,689 6,244,208 Cum A 2,965,465 3,246,846 3,648,978 4,328,786 4,860,086 5,738,910 6,205,673 Oct 27-28, 2005 LCLS FAC Meeting 8 Mark Reichanadter reich@slac.stanford.edu • We are correcting the plan. LCLS Cost and Schedule Performance LCLS Cost and Schedule Indices (TEC Only) 1.100 BCWP/BCWS (SPI) 1.050 BCWP/ACWP (CPI) 1.000 • Biggest SV (In, UN) appear to be due to an inaccurate plan not a schedule delay. • Call for managers to utilize a 6-mo look-ahead 0.950 0.900 0.850 0.800 05 gAu 9 5 l-0 Ju 05 nJu 5 -0 ay M 5 r- 0 Ap 5 -0 ar M 05 bFe 05 nJa LCLS FAC Meeting 04 cDe 04 vNo 4 -0 ct O Oct 27-28, 2005 Mark Reichanadter reich@slac.stanford.edu LCLS Summary Schedule – Aug05 FY 2004 OCT JAN FY 2005 APR DOE Milestones JUL OCT JAN APR FY 2006 JUL CD2b CD3a OCT JAN Sector 20 Injector Facility Linac Facility Main Control Center Magnetic Measurement Facility Undulator Hall Construction Title 1 APR S20/Alcove B.O. FY 2008 JUL Injector JAN Title 2 T1 Title 2 Construction Construction OCT JAN APR LCLS ARR LCLS Start Operation (XRay to Far Hall) BD B.O. Construction FEE B.O. CLOC B.O. BTH B.O. Construction Drive Laser Award •Maintained full schedule float on critical path UV Beam to Cathode Injector ARR C/O Design/Procure RF Gun • Schedule Float •Mar05 213 days •CP - Und B.O. - Und Inst to 1st Light XTOD B.O. UND B.O. Title 2 Drive Laser Highlights JUL 1st Light Linac ARR FEH B.O. Drive Laser RFP JUL MCC B.O. MMF Title 2 Title 1 FY 2009 APR Linac B.O. NEH B.O. Other Facilities (Undulator,BD, RY, NEH, FEH,FEE, BTH,CLOC & X-Ray Xport) OCT Construction Title 2 MMF Title 1 JAN Injector Accelerator ARR Start Injector FFTB Shutdown Comm (Drive Laser) Title 2 Title 1 OCT CD4 Start Proc for T3 Constr T1 JUL CD3b Major LCLS Milestones Conventional Facilities FY 2007 APR Commission Design/Procure Wall Region Install Heater Region Install • Starting construction on schedule is key Laser Heater Install Accelerator Region Install Gun Region Install Linac X-Band Klystron Cableplant Inject RF Install Commission Spectrometer Install Design/Procurement L1, BC1, L2, BC2, L3, & LTU, E-Dump • CP - Und B.O. – Inst to 1st Light E-Dump Install Installation L2,BC2,L3 L1, BC1 LTU Install Commission Undulator Ti Strongback • FY05 Shutdown •~1 month • FY06 shutdown •~ 4 months Magnet Blocks Magnet Poles Design Design Procure Rcv 1st Arts Testing at MMF 33 Prod Unds Received Del of 1st Arts to MMF F/MM Install Commission X-Ray Transport & Diagnostics Design/Procure Solid Attenuator Install Commissioning Diagnostics X-Ray End Stations Gas Attenuator Install Tunnel Mech/Vac Install Award Initial Funding Laser Design/Procure/Assy Design/Procure 2-D X-Ray Detector Operations Oct 27-28, 2005 LCLS FAC Meeting Commission Install Install Commission 10 Operations • FFTB Shutdown •Jul06 •LCLS may request advancing this date Mark Reichanadter reich@slac.stanford.edu LCLS L1 – L2 Milestone Performance LCLS showing good milestone performance @ L2 in FY05 Oct 27-28, 2005 LCLS FAC Meeting 11 Mark Reichanadter reich@slac.stanford.edu LCLS L3 Milestone Performance – FY05 LCLS showing good milestone performance @ L3 in FY05 Oct 27-28, 2005 LCLS FAC Meeting 12 Mark Reichanadter reich@slac.stanford.edu LCLS L3 Milestone Performance – FY06 FY06 will be a key year for LCLS. Boost Phase Oct 27-28, 2005 LCLS FAC Meeting 13 Mark Reichanadter reich@slac.stanford.edu Contingency Allocation to Date Contingency Allocation (Oct04 - Present) Total $11.97M (~$1.1M/mo) # of BCR's since April 2005 Total: 77BCR's 7,000 6,000 20 5,000 AYK$ 77 BCR’s is high 5 months after baseline 4,000 15 3,000 10 2,000 5 1,000 0 0 PM IN LN UN XT XE PM CF -1,000 INJ LN UN XTOD ES CF •CF: Interim work on CF + T2 increase, MMF and S20. CM/GC and 30% estimate overruns will require significant additional contingency. •UN: Undulator materials •Apr05 rebaseline covered schedule variances in Injector-Linac. Oct 27-28, 2005 LCLS FAC Meeting 14 Mark Reichanadter reich@slac.stanford.edu CT LCLS Contingency Performance LCLS Contingency Trend 40.0% 35.0% 30.0% 25.0% % Complete BCWP/BAC 20.0% Cont/(BAC-BCWP) 15.0% 10.0% 5.0% 0.0% 05 gAu 5 l-0 Ju 5 -0 ay 05 nJu M 5 -0 ar 5 r- 0 Ap M 05 bFe 05 nJa 04 cDe 04 vNo 4 -0 ct O Contingency allocation has been reasonable to date. CM/GC + 30% CF estimate will make large draws on contingency in Oct05. Need to hold the line on contingency until Mar06 (CF construction bids). Oct 27-28, 2005 LCLS FAC Meeting 15 Mark Reichanadter reich@slac.stanford.edu LCLS Long-Lead Procurements •All major LLP’s are under contract. LCLS Procurements and Subcontracts •Drive Laser •Streak Camera $70,000 •BC1/BC2 Magnets CM-2 $60,000 •RF X-band (SLAC) AYK$ $50,000 T3 Constr •RF Gun (SLAC) $40,000 SLAC •Ti Strongbacks $30,000 CM-1 LLNL •Magnet Poles ANL •Magnet Blocks $20,000 •1st Und Article $10,000 •S20 Facility $0 FY05 FY06 FY07 FY08 •MMF Facility FY09 AYK$ FY05 FY06 FY07 FY08 FY09 Total ANL $2,219 $15,646 $13,244 $62 $2,104 $33,274 LLNL $30 $2,863 $2,615 $4,502 $1 $10,011 SLAC $12,425 $14,310 $16,617 $15,514 $4,565 $63,430 T3 Constr $2,541 $20,246 $29,993 $5,701 $0 $58,481 Total $17,215 $53,064 $62,468 $25,779 $6,670 $165,196 Oct 27-28, 2005 LCLS FAC Meeting 16 •Some smaller (less critical) items yet to be procured. •Laser and Conv Fac are most critical to maintaining schedule. Mark Reichanadter reich@slac.stanford.edu LCLS Technical Specifications •Technical baseline specifications are defined via; •GRD •PRD’s •ESD’s •ICD’s •RDS’s •Technical specs under configuration mgmt Oct 27-28, 2005 LCLS FAC Meeting 17 Mark Reichanadter reich@slac.stanford.edu LCLS Technical Specifications Status Requirements Document Total No. Documents Number Approved Number in Sign-Off % Complete Global Requirements Document (GRD) 1 1 0 100 Complete Physics Requirements Documents (PRDs) 57 43 1 75 PRDs decreased from 64 to 57 Engineering Specification Documents (ESDs) 104 53 0 51 Management Physics Liaison Support Controls Injector Linac Undulator X-R Endstations Conventional Facilities 2 8 4 40 19 8 15 8 2 3 3 31 7 0 0 7 0 0 0 0 0 1 0 0 100 37 75 77 37 0 0 87 Room Data Sheets (RDSs) 58 49 0 84 Interface Control Documents (ICDs) 11 9 0 82 Injector Linac Undulator X-R TOD XES 3 4 1 2 1 3 4 1 1 0 0 0 0 0 0 100 100 100 50 0 231 155 2 ~67 Total Oct 27-28, 2005 LCLS FAC Meeting 18 Comments LCLS Specs • Jul05 • PRD’s @ 37% • ICD’s @ 5% • 67% is a big improvement but still more to go RDSs reduced from 59 to 58 Linac ICDs reduced from 32 to 4. Undulator ICD reduced from 2 to 1. • ESD’s particularly IN, LN, and UN need more effort. • Physics support being added to Photon System Mark Reichanadter reich@slac.stanford.edu LCLS Project Organization (Sep05) Oct 27-28, 2005 LCLS FAC Meeting 19 Mark Reichanadter reich@slac.stanford.edu LCLS Staffing FY2004 (actuals) 11.2 5.4 40.2 56.8 LCLS Estimated FTE's ANL LLNL SLAC Total FY2005 15.59 8.7 88.48 112.77 FY2006 20.76 10.43 107.79 138.98 FY2007 13.01 11.77 106.5 131.28 Actual Reported LCLS FTE's @ SLAC 120 100 60 FY2009* 0.33 5.72 51.69 57.74 TOTAL 63.71 52.48 469.25 585.44 • • • • 112.0 FTE’s (Sep05) Staffing nearly complete Still a few more to go Does not include additional staff under contract – Jacobs – PMCS – AIM – Consultants – CM/GC (Oct05) • Good News: LCLS has staffed up at planned rate. Are they all working on the right things? FY05 funding @ SLAC 80 FTE's FY2008 2.82 10.46 74.59 87.87 Award Title I 40 Treading water. CR or full-funding? 20 • Oct 27-28, 2005 LCLS FAC Meeting 20 Ju l-0 5 05 A pr - 5 Ja n0 ct -0 4 O Ju l-0 4 04 A pr - 4 Ja n0 O ct -0 3 0 Mark Reichanadter reich@slac.stanford.edu Davis – Bacon Approval Thanks to Richard M for working this issue! Oct 27-28, 2005 LCLS FAC Meeting 21 Mark Reichanadter reich@slac.stanford.edu Plans for the Next Six Months (Apr05) CD-2b (Approve Performance Baseline) done CD-3a (Authorize Long-Lead Procurements) done Make plans for full FY05 funding (~$54M) done Get funds out to partner labs done Staff up particularly in Ctrls, PM, and Engr done Establish colocated procurement cell & staff done Award Long-Lead Procurements done Laser, Undulator, MMF, S20 Authorize Title II (Jacobs) done Put out SOW for CF Constr Mgmt done Oct 27-28, 2005 LCLS FAC Meeting 22 Mark Reichanadter reich@slac.stanford.edu Plans for the Next Six Months (Oct05) Make plans for full FY06 funding (~90$M). Phase-fund construction sub-contracts Complete T2 (Jacobs) Design (on schedule, within cost estimate) Prepare for start of construction (Turner) Prepare independent cost estimate to validate Jacobs Develop construction sequence to minimize impact on SLAC ops Prepare procurement subcontract packages Prepare project for CD-3b PSAD, PEP, FHA, etc. Independent “Lehman” Review on Readiness Strengthen System Integration Design Reviews and Technical Specifications Risk Registry Continue good performance on cost, schedule, milestones and procurements Oct 27-28, 2005 LCLS FAC Meeting 23 Mark Reichanadter reich@slac.stanford.edu Near-term LCLS challenges LCLS is the execution phase of the project. Plans are planned, costs estimated, project approved … now it’s time to execute. FY05-FY06 critical time (boost phase) of the project. Performance (solve problems, make decisions) is key. Follow P3. Watch staffing levels via variances. (Use the 6-month look ahead as a roadmap) Use the Risk Registry pro-actively to manage work (not just a DOE requirement) FY06 Continuing Resolution Planning estimates show enough carryover (due to the FY05 CR) to cover one quarter. Beyond a one-quarter CR, LCLS will need to defer procurements to retain core staff. Prepare for start of LCLS Construction (CD-3b) T2 CF is critical path for construction start CM/GC on-board (Good news!) PSAD will require effort from all of LCLS System Engineering and Integration Continue documenting PRD’s, ICD’s, etc.. Mature design reduces risk. RMB and DM will help to provide uniformity and high-quality across the LCLS Sustained effort on design reviews will help to validate progress and identify integration issues early on. Oct 27-28, 2005 LCLS FAC Meeting 24 Mark Reichanadter reich@slac.stanford.edu Summary Good performance thus far (15% comp) SLAC is organized to support the LCLS LCLS is ~fully staffed up at all Labs MMF/S20/S24/FFTB under construction Undulators under fabrication Overall milestone performance is good Shutdown going reasonably well so far T2 >30%, CM/GC on-board LCLS ISMS is the priority. Oct 27-28, 2005 LCLS FAC Meeting 25 Mark Reichanadter reich@slac.stanford.edu