Linac Coherent Light Source Project Update Recent progress Enhancements of capability Conventional facilities cost 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Linac Coherent Light Source 1.1 Management, Global Controls 1.2 Injector 1.3 Linac 1.3 e-Beam Transport Far Experiment Hall (underground) 1.4 Undulator Near Experiment Hall 1.5 X-Ray Transport/Optics/Diagnostics 1.6 Endstation Systems 1.9 Conventional Facilities 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu LCLS Cost/Schedule Status Report - Work Breakdown Structure 31-Aug-05 Cumulative to Date ($K) WBS Budgeted Cost Work Scheduled Variance Actual Cost Work Performed Work Performed Cost 8,880 8,375 8,648 -505 1.2 Injector 7,113 6,163 6,096 1.3 Linac 3,122 3,049 2,520 1.4 Undulator 8,912 6,244 1.5 X-ray Transport 4,356 1.9 Conventional Facilities 1 LCLS Total Base Cost Performance Indices SPI CPI Variance -273 0.94 0.97 28,970 28,970 0 -951 67 0.87 1.01 19,297 19,297 0 -73 529 0.98 1.21 26,431 26,431 0 6,206 -2,668 39 0.70 1.01 50,724 50,724 0 4,225 4,102 -131 123 0.97 1.03 27,127 27,127 0 721 721 680 0 41 1.00 1.06 14,779 14,779 0 4,813 4,828 5,394 15 -567 1.00 0.89 80,649 80,649 0 37,917 33,604 33,646 -4,313 -42 0.89 1.00 247,976 247,976 0 315,000 315,000 Avail. Contingency 67,024 67,024 % Contingency / Rem. Work 31.3% 31.3% % Complete LCLS Base Cost 13.6% 13.6% LCLS Total Estimated Cost 2.1 LCLS Project Mgmt, Planning & Admn (OPC) Latest Revised Estimate Budgeted Schedule 1.1 Project Management 1.6 X-ray Endstations At Completion ($K) 4,437 4,538 4,345 101 193 1.02 1.04 33,021 33,021 0 699 757 578 58 179 1.08 1.31 6,107 6,107 0 1 1 1 0 0 1.05 1.00 2,545 2,545 0 2.4 Undulator (OPC) 742 689 776 -53 -86 0.93 0.89 5,873 5,873 0 2.5 X-ray Transport (OPC) 480 412 339 -68 73 0.86 1.22 4,015 4,015 0 2.6 X-ray Endstations (OPC) 0.83 1.39 5,200 5,200 0 0 0 0 56,761 56,761 0 64,000 64,000 2.2 Injector (OPC) 2.3 Linac (OPC) 165 137 98 -28 39 2.9 Conventional Facilities (OPC) 0 0 0 0 0 2 LCLS Total Other Project Cost 6,524 6,534 6,136 10 397 1.00 1.06 LCLS Other Project Cost LCLS Total Obligations to Date 58,430 LCLS Total Project Cost 44,441 Avail. Management Reserve 7,239 7,239 % Contingency / Rem. Work 14.4% 14.4% % Comp LCLS Other Project Cost 40,137 39,782 -4,303 355 0.90 1.01 11.5% 11.5% 379,000 379,000 13.2% 13.2% % Complete LCLS TPC 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.2 Injector 10/2005 Shutdown -Laser transport tubes -RF waveguide to injector Gun fabrication in process RF Gun LINAC HOUSING SIDEWALL TR UM PU MP S 1 F YA C 1, G SP SE O OL AL S FR 1 Transverse RF Cavity 1 OT R QU AD EO SC 2 QU 7 AD Pb 2 10' HIGH CONCRETE A , B , C ARE THE DETECTOR LOCATIONS INSIDE THE LCLS INJECTOR VAULT VA LV E Fe 2 Fe 3 BEAM LINAC HOUSING SIDEW ALL LCLS Facility Advisory Committee QUAD CM4 SC11 B02 QUAD EO3 B PM 18 SECTION 21-1B Q S01 BP M 20 Q S02 DRIFT SECTION LINAC HOUSING SIDEW ALL Straight Ahead Spectrometer 27 October 2005 BPM 19 DUMP 04 SC10 D 04 WS OTR 6 Q UA SC9 B01 SC 8 AD 03 BPM 16 B PM 15 9.4 ACCELERATOR 17 02 3" TUBE 6 SC13 LE 01 3 5 B0 PEP-2 HE/LE BYPASS QU VALVE HE 4 Pb 1 BPM VA 14 LV E 4 SC 12 YA G 4 SECTION 20-8C 2 BP M SECTION 20-8B 2" TUBE QE-901 SECTION 20-8A 1 10' ACCEL BEAM STOPPER 10' ACCEL ACCEL AD PIC PEN. 20-17 10' LINAC HOUSING SIDEW ALL P E N . 21 -1 PIC QU Fe 1 PEN. 20-16 PEN. 20-15 OT R5 LINAC HOUSING SIDEW ALL 3 BP M OT R4 BP M 12 Pb 3 13 0 1 , 0 2 ... ETC. ARE POINT-SOURCE LOCATIONS ALONG THE HE BYPASS LINE BP M 11 B DL1 Bend OP PE R C ST SC 6 KE R RF BSOIC A 9 LI NA C RA D ... ETC. ARE SIX SOURCE AREAS ALONG THE DRIFT REGION KIC UN DU LA TO R TO 10 N BP M D IF IC AT IO BP M M O 2 U RC E Laser Heater OT R SO OR BP YA G M 7 3 QU AD 10 'A CC EL ER AT SC 5 LI G HT SI D EW AL L QU BP M AD 8 HO US IN G 3 H ER EN T 1/22/2004 1 , 2 6 YA BP G 2 M 5 C O SC 4 Gun Diagnostics RF Cav . SC 3 LI NA C ER AT OR QU AD 4 LINAC HOUSING SIDEW ALL LI N AC QU AD BP M BP M SC X-Y 2 BP M 10 'A CC EL 3 FC Y A 3, G C M2 CM 2 FC YA 2, G KEY: L0-1 & L0-2 3-m SLAC Sections 10' HIGH S2 M1 BP M DE QU A QU D AD C HO BP M AT U HV GA AL TE L VA ME LV TA ES L PO HO RC LD UPIN ER EC VA LV E MA SC G Sp N E QU 1 X ec TIC A D -Y, tro . YA G OM CA T RF H OD GU E N E0 1 1 ER VA LV E S1 OT VA R3 LV E 2 EN T CH A MB VA CU EA TM LO AS NG SE BE MB LL L OW Y S Load Lock John N. Galayda galayda@slac.stanford.edu QS0 3 O TR FC 4 LCLS RF Gun Fab. In SLAC Klystron Dept. Dual Feed Suppresses the time dependent dipole kick Matching phase for 2 feeds by holding mechanical tolerances on both arms Z-coupling (instead of -coupling) Pulsed heating reduced + easier machining Racetrack shape compensates for stronger quadrupole mode Overcoupling =2 15 MHz mode separation adopted Push-Pull deformable tuners Replace plungers Shaping of RF pulse for reducing average power 4kW -> 1.8 kW ; cooling channels designed for handling 4kW Reduce reflected power from gun Gun fabricated at SLAC Courtesy L.Xiao RF design complete Mechanical model in progress 120Hz heat calculations under way LCLS-TN-05-3.pdf L. Xiao, et al., “Dual feed RF gun for the LCLS”, SLAC-PUB-11213, May 2005, http://www.slac.stanford.edu/pubs/slacpubs/11000/slac-pub-11213.html ; to be published in the proceedings of the 2005 Particle Accelerator Conference, 16-20 May 2005, Knoxville, TN; also to be published at the Joint Accelerator Conference Website ( http://www.JACOW.org ) 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Injector Laser Chosen - Thales Delivery expected in May LLNL (Brent Stuart, et al.) Studying temporal pulse shaping ANL ( Yuelin Lee) Studying transverse pulse shaping Bill White, LCLS Laser Group Leader Group will support facility lasers 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Architecture Thales Laser System 119MHz 400mW Femtolasers Oscillator Femtosource Scientific 20s (chirped mirrors) 150ps 80mW 119MHz Stretcher 5W, 119MHZ Spectra Physics MILLENIA Vs 1.5mx3.75m footprint (~4.5’x11.5’) DAZZLER 20 mJ, 120 Hz RGA Regen Amp JEDI #1 100 mJ,120 Hz 1mJ, 120Hz Amplifiers are not cryo-cooled IR stability <1%rms (short term) Pre-Amp 4-pass Bowtie 80 mJ, 120 Hz >20mJ, 120Hz To cathode >2.5mJ, 120Hz THG Compressor >25mJ, 120Hz 27 October 2005 LCLS Facility Advisory Committee Amplifier 2-pass Bowtie >40mJ, 120Hz JEDI #2 100 mJ,120 Hz 100 mJ, 120 Hz John N. Galayda galayda@slac.stanford.edu 1.3 Linac LCLS Klystron Fab Complete Injector Quad first article measured 27 October 2005 LCLS Facility Advisory Committee BC-1 Dipoles ordered John N. Galayda galayda@slac.stanford.edu 1.4 Undulator Systems Progress, Changes Magnet Blocks Awarded Magnet Poles Awarded Strongback Awarded Assembly, first articles Awarded Undulator Measurement Lab designed RFP issued for room On track for complete delivery of undulators by June 2007 Design Changes Electromagnet quadrupoles Aluminum surface in undulator vacuum chamber Fixed supports in ANL scope Planning production prototype tests Shim incorporated in undulator design – permits K reduction (significant shutdown required) 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.4 Baby Pictures (cont’d) Magnetized blocks 27 October 2005 LCLS Facility Advisory Committee Magnet Poles John N. Galayda galayda@slac.stanford.edu 1.9 Conventional Facilities Sector 20 Injector Magnet Meas. 2/28/06 Completion 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu FFTB Shielding 27 October 2005 LCLS Facility Advisory Committee Sector 24 Stairs John N. Galayda galayda@slac.stanford.edu Next Steps Construction manager Cost estimate Construct road? Construct tunneling portal? Plan FFTB decommissioning Date will be between April and June 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.5 New layout of FEE Incorporates Offset Mirrors 7 ft Fe STOP 3 ft concrete Offset Mirrors GAS ATTEN SOLID ATTEN COLLIM ~30m 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 4 ft Fe STOP 1.6 XES instrumentation effort Old Plan: XES to build a generic set of instrument components (infrastructure PPS, MPS, network) New Plan: XES builds one instrument for soft x-ray Atomic Physics studies Experiment infrastructure, laser, chambers, PPS Pixel array detector spec’ed for cluster imaging 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.6 - Since the Last Review Scope modifications Soft X-Ray Atomic Physics Experiment Deletion of generic optics Re-program to functional near hall station Pixel Array Detector Specs address single molecule imaging 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 1.9 New FEH design in baseline Entrance 14ft tunnel Fire door Fire door 46ft tunnel passage below beam pipe 6ft 28x33ft hutch 15x25ft control cabin Sliding hutch door 10ft 10ft 29x33ft hutch 36x33ft hutch 10ft 30ft transition Toilets 20ft tunnel Future tunnel to other stations 212ft 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Recent Events SSRL User Meeting, 17 October 2005 Pat Dehmer presentation, 2007 Budget LCLS has high priority, high visibility, high likelihood of full funding BES must get funding above its “line” to do LCLS without shutting down some facilities BES is prepared to do this for LCLS IF we are ready 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Wouldn’t Be a Project Without Some Challenges… Conventional Facilities High bids Sector 20, Magnet Measurement Facility, Construction Management Jacobs Title-II (30%) estimate for future work is 50% above Title-I Electrical, Mechanical disciplines are 100% above Title-I Jacobs expects increased escalation 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu De-Scopes Undulator Hall A/C redesign ~$3.5M savings Other CF Economies - $ 7.5M Still looking for $5M further CF reductions might yield $1M-$2M Flipping Mirrors - $2M More to go, emphasis on: Reversible No impact on commissioning and early operation 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu 3rd Undulator Line Near Expt. Hall XR tunnel shortened from 250m to 230m 2nd Undulator Line Entrance 14ft tunnel 15x25ft control cabin 46ft tunnel 28x33ft hutch 1 20ft tunnel 27 October 2005 LCLS Facility Advisory Committee 29x33ft hutch 2 212ft John N. Galayda galayda@slac.stanford.edu 36x33ft hutch 3 Central Lab Office Complex (CLOC) Capacity >260 78,000 GSF Total 150-Seat Conference Room Leave 3rd floor unfinished Delete 3rd floor? 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Continuing Resolution No slowdown unless CR extends past December CF, undulator assembly must go forward to stay on schedule Will ask for help. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Response to Comments/Recommendations Members of the FAC had minor concerns about the organization chart as having a baroque appearance in that on the surface, lines of authority don’t appear to be that clear. However, throughout the course of the FAC meeting clear lines of responsibility and authority were in evidence and only a few issues on communication (notably between the physics requirements on the conventional facilities and the operations configurations and approaches) were apparent. Response: The LCLS organization chart has been revised to clarify roles and responsibilities. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu LCLS Project Organization (Sep05) 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu The project should incorporate those risk or trade-off items identified in this and previous FAC meetings into the Project Risk Registry to ensure adequate tracking and resolution. The project may wish to also incorporate any such risk items cited in official DOE reviews as well. Response: The LCLS organization continues to use the Risk Registry on a monthly basis as a key management tool to proactively address its known risks. The undulator floor stability risk has now been retired as it has now been shown that expected stability issues can be addressed with the alignment systems and BBA at acceptable intervals. https://www-lclsinternal.slac.stanford.edu/projectspace_L2/Project_Office/Risk_Registry_Document s/LCLS_risk_registry_September_05.pdf 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu The project is entering into its boost phase where it is undergoing its maximum gradient: staffing, effort and procurement. During this phase, the timeliness of decisions often becomes critical and delays can quickly accumulate that can impact the overall progress of the project without specific attention. This is a concern to the FAC as the decision making process is not transparent and may need to accelerate to ensure avoiding unnecessary delays. Response: The decision making process has been made more transparent with the Change Control Board (CCB). With the CD-2b (Approve Performance Baseline), LCLS has enacted the CCB to deal with technical, cost and schedule issues on a timely basis. The CCB forum ensures that decisions are communicated uniformly across the project and formally documented in a manner consistent with good configuration control. Since CD-2b (April 2005), LCLS has approved 77 changes to the project and allocated ~$7M of contingency to the baseline cost of the LCLS. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu The critical path of the project, likewise, may be extremely fluid during this phase and near critical paths can quickly become critical paths, and so those efforts which at present are not on the critical path, must understand that they can quickly become the pacing activities. Response: The LCLS has significantly increased its staffing since April 2005 and with that some time for assimilation of new staff into the project is required. The LCLS is now nearly complete on its staffing plan so the inefficiencies due to assimilation can be expected to drop off. Critical path is monitored regularly and has not shown any appreciable degradation since established at 215 days. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu …However, an insightful planning exercise is to evaluate all activities for early starts up to the point where all of the budget authorization (BA) in each fiscal year would be used. In addition, exceeding this optimistic BA plan by 5 to 10% would also be helpful in evaluating potential resource demands. This planning assures that there are “swing items” identified in order to accomplish other work if planned activities are delayed. If the project doesn’t have swing items identified to work in the available time and with the available BA, the CD-4 milestone may be at greater risk than necessary. “Swing procurements” are procurements that can be advanced should budget become available due to delays in other areas. This is of primary importance between FY06 and FY07. Since civil construction sets the critical path, LCLS will plan to use its budget flexibility in this area to best advantage, based on advice from the Construction Manager. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu A useful plot that can illustrate this phenomenon, and serve as both a leading and lagging indicator, is the contingency as a percent of the estimate to complete (ETC) budget as a function of the percent of the project complete. Generally, this should be roughly a horizontal line above 20%. Early in the project life it would likely start out at a higher number and depending upon the remaining risks within a project, the percentage can also be less than 20%. Response: Currently, the LCLS holds ~32% contingency on work remaining. This number may fall lower as the conventional facilities estimates become more mature and LCLS approaches the start of construction. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu There is a need for a central database containing and controlling the complete configuration of the LCLS project. Work has begun on defining the detailed needs of the central database effort for the LCLS project. An IT Manager (Andrea Chan from the SLAC SCS group) has been hired into the LCLS Division and bringing significant experience in setting up databases in a project environment. At the same time Sergei Chevtsov in the LCLS Controls Group has been looking at the relational database needs for the control system, in particular the RDB requirements for online modeling for the accelerator. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu The LCLS Project should consider giving the FAC access to the LCLS internal website. This would allow the FAC to view other reviews and important work that can have an impact on the scope and details of FAC meetings. It will also allow the LCLS Project to exploit the full potential of the FAC. LCLS is in the process of exploring a different data management system, which would make access control but the system is not likely to become operational in this calendar year. At present, LCLS is working with Kem Robinson to do it the hard way now or wait until the simpler solution is in place. 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu Charge to Committee Consider responses to last review Consider planned/proposed scope changes to accommodate conventional facilities costs 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu End of Presentation 27 October 2005 LCLS Facility Advisory Committee John N. Galayda galayda@slac.stanford.edu