HYDRAULIC ANALYSIS OF THE UPPER NORTHWEST INTERCEPTOR SECTIONS 5 AND 6 Deana Lynn Donohue, P.E. B.S., California State University, San Jose, 1996 PROJECT Submitted in partial satisfaction of the requirements for the degree of MASTER OF SCIENCE in CIVIL ENGINEERING (Water Resources) at CALIFORNIA STATE UNIVERSITY, SACRAMENTO FALL 2009 © 2009 Deana Lynn Donohue, P.E. ALL RIGHTS RESERVED ii HYDRAULIC ANALYSIS OF THE UPPERNORTHWEST INTERCEPTOR SECTIONS 5 AND 6 A Project by Deana Lynn Donohue, P.E. Approved by: __________________________________, Committee Chair Ralph Hwang, Ph.D., P.E.,F ASCE __________________________________, Second Reader Dave Ocenosak, P.E. Principal Civil Engineer ______________________ Date iii Student: Deana Lynn Donohue, P.E. I certify that this student has met the requirements for format contained in the University format manual, and that this project is suitable for shelving in the Library and credit is to be awarded for the project. __________________________, Graduate Coordinator Cyrus Aryani, Ph.D, P.E., G.E. Department of Civil Engineering iv ___________________ Date Abstract of HYDRAULIC ANALYSIS OF THE UPPERNORTHWEST INTERCEPTOR SECTIONS 5 AND 6 by Deana Lynn Donohue, P.E. Project Overview The Upper Northwest Interceptor Sections 5 and 6 (UNWI 5/6) are part of a regional gravity sewer system designed and constructed to relieve the capacity deficiencies in the north eastern portion of Sacramento County. Sacramento Regional County Sanitation District (SRCSD) defines an interceptor as any pipe that conveys greater than 10 million gallons per day (mgd) of sewage. The UNWI system conveys flows to the regional wastewater treatment plant in Elk Grove, located in the southwestern portion of Sacramento County. UNWI 5/6 is a 5.5-mile gravity interceptor located along Elkhorn Boulevard starting at Don Julio Boulevard and terminating at Cherry Lane to the west. The interceptor diameter is 48 and 66-inch to convey an ultimate flow of 80.6 mgd. Currently, the interceptor conveys much less flow than 80.6 mgd and interim flows were considered during design. This project also includes the design of two hydraulic control structures to v channelize and direct flow during low flow periods in the near-term and redirect flow during periods of maintenance or high flow. This paper will describe the hydraulic design criteria and process for design of UNWI 5/6 project components including the interceptor and hydraulic control structures. This interceptor project has been constructed and is currently in operation. Information Source The information included in this report is the actual design criteria and calculations. Brown and Caldwell was the engineering consultant and contracted to design this project for SRCSD. I was the project engineer for the design team and participated during both design and construction. Final Design Summary Construction of the UNWI 5/6 project was completed in 2006 and is currently operational. The hydraulic analysis for this interceptor project was comprehensive and included considerations for several flow scenarios, hydraulic jumps, sedimentation, and odor control. The hydraulic design was completed to address near and long-term flow requirements to operate under a varied range of flows. The final design addresses the upstream capacity deficiencies and allows for relief of the northern Sacramento area while the remaining downstream sections under construction. Flow monitoring data is not available, however, details on the current operation of the project was related during vi discussions with the SRCSD Principal Engineer. Section 4. ______________________, Committee Chair Ralph Hwang, Ph.D., P.E., F ASCE ______________________ Date vii These results are summarized in ACKNOWLEDGMENTS I would like to thank my sons, Conrad and Clinton, for their patience and understanding during the long hours of studying, reading, and lecture time. I hope that they are inspired by my dedication to education. I would also like to acknowledge and thank the Civil Engineering Department faculty and staff at the California State University, Sacramento. I appreciate the dedication and patience of the staff including Neysa Bush, Professor Ramzi Mahmood, and Ed Dammel. Finally, I want to express my sincere appreciation and gratitude to Professor Ralph Hwang for his knowledge, his dedication to me as a student, and his guidance as I completed the graduate program. viii TABLE OF CONTENTS Page Abstract ...................................................................................................................................... v Acknowledgments...................................................................................................................... viii List of Tables ............................................................................................................................. xi List of Figures ............................................................................................................................ xii Chapter 1. INTRODUCTION ............................................................................................................... 1 1.1 Project Background ................................................................................................. 4 1.2 Upper Northwest Project Description ..................................................................... 5 1.2.1 Dry Creek Interceptor .................................................................................... 6 1.2.2 Hydraulic Transitions..................................................................................... 8 1.2.3 Interim Dry Creek Interceptor Connection Alternative Comparison ............. 10 2. INTERCEPTOR OPERATIONAL DESIGN CRITERIA................................................... 14 2.1 Hydraulic Flow Path ............................................................................................... 14 2.2 Pipe and Structure Lining ....................................................................................... 16 2.3 Pipe Slope ............................................................................................................... 16 2.4 Maximum Operational Flexibility .......................................................................... 18 2.5 Safe Maintenance Access ....................................................................................... 18 3. INTERCEPTOR FLOW EVALUATION ........................................................................... 20 3.1 Basis of Wastewater Flow ...................................................................................... 20 3.2 Wastewater Flow .................................................................................................... 22 4. INTERCEPTOR DESIGN EVALUATION ........................................................................ 24 ix TABLE OF CONTENTS Page 4.1 Hydraulic Criteria ................................................................................................... 24 4.2 Hydraulic Analysis ................................................................................................. 25 4.2.1 Shearing Stress ............................................................................................... 25 4.2.2 Slope Evaluation ............................................................................................ 26 4.3 Hydraulic Control Structures .................................................................................. 34 4.3.1 UNWI 4/5 Junction Structure ........................................................................ 37 4.3.2 28th Street Junction Structure ......................................................................... 52 5. PROJECT CONCLUSIONS ................................................................................................ 54 Appendices................................................................................................................................. 56 Appendix A. UNWI 4/5 Junction Structure Drawings ............................................................ 57 Appendix B. 28th Street Junction Structure Drawings ............................................................. 65 Appendix C. County Design Criteria ....................................................................................... 67 References .................................................................................................................................. 69 x LIST OF TABLES Page 1. Table 1 Comparison of Alternatives for Crossing Dry Creek............................................. 13 2. Table 2 UNWI 5/6 Projected Wastewater Flows ................................................................ 22 3. Table 3 Slope Analysis- 28th Street to Don Julio ................................................................ 31 4. Table 4 Slope Analysis- Cherry Lane to 28th Street............................................................ 32 5. Table 5 Summary of Design Slopes by Reach .................................................................... 33 6. Table 6 Hydraulic Characteristics of 27 and 30-inch Pipes ................................................ 44 7. Table 7 Weir Calculation Results ....................................................................................... 47 8. Table 8 HGL and Water Depths in the UNWI 4/5 Structure and Pump Wet Well ............ 50 xi LIST OF FIGURES Page 1. Figure 1 Project Location Map – Northeastern Sacramento County .................................. 2 2. Figure 2 Upper Northwest Interceptor Sections 5 and 6 ..................................................... 3 3. Figure 3 Local Interceptor Layout ...................................................................................... 7 4. Figure 4 Interceptor and Trunk Sewer Flow Insertion Points ............................................. 23 5. Figure 5 Open Channel Flow in Pipe Flowing Less than Full ............................................ 28 6. Figure 6 Visual Basic Program for Calculating Flow Depth .............................................. 29 7. Figure 7 Sample Calculation Spreadsheet .......................................................................... 30 8. Figure 8 28th Street Junction Structure to Existing Elkhorn Structure ................................ 36 9. Figure 9 Schematic of Interim Design Flow HGL along Segment A ................................. 40 10. Figure 10 Weir Elevation at the UNWI 4/5 Junction Structure .......................................... 46 11. Figure 11 Schematic of Interim Design Flow HGL along Segment A ............................... 52 12. Figure A-1 UNWI 4/5 Junction Structure Plan................................................................... 58 13. Figure A-2 UNWI 4/5 Junction Structure Top Plan ........................................................... 59 14. Figure A-3 UNWI 4/5 Junction Structure Section 1 ........................................................... 60 15. Figure A-4 UNWI 4/5 Junction Structure Section 2 ........................................................... 61 16. Figure A-5 UNWI 4/5 Junction Structure Section 3 ........................................................... 62 17. Figure A-6 UNWI 4/5 Junction Structure Section 4 ........................................................... 63 18. Figure A-7 Existing Elkhorn Blvd Junction Structure Modifications Sta. 1+00 ................ 64 19. Figure B-1 Dry Creek Relief Interceptor Junction Structure Plans and Section ................. 66 20. Figure C-1 Design Flow Criteria ........................................................................................ 68 xii 1 Chapter 1 INTRODUCTION The hydraulic analysis for Sacramento Regional County Sanitation District (SRCSD) Upper Northwest Interceptor Sections 5 and 6 (UNWI 5/6) design project is systematically presented in this report. The purpose for this paper is to discuss the hydraulic design and evaluate the project hydraulic design to the operation of the completed project. This UNWI system serves to convey wastewater from northern portion of Sacramento County to the regional wastewater treatment plant in the southwestern portion of Sacramento County. The UNWI system is one of the largest interceptor projects undertaken by the County of Sacramento and cost over $300 million to design, build, and construct. I was the project engineer for UNWI Sections 5 and 6; I assisted with the design and provided technical assistance during the construction process. The UNWI 5/6 Project is located in the northeastern portion of Sacramento County. A general area map is depicted on Figure 1. 2 UNWI 5/6 Location Figure 1 Project Location Map- Northeastern Sacramento County The interceptor alignment is highlighted in the vicinity and location map shown on Figure 2. UNWI Section 6 is located along Elkhorn Boulevard from Don Julio Boulevard to the 28th Street Structure and UNWI 5 continues along Elkhorn Boulevard from the 28th Street Structure to the UNWI 4/5 Junction Structure. The interceptor is 48inch diameter along UNWI Section 6 and changes diameter to 66-inch at the 28th Street Junction Structure where a large amount of flow (12 mgd) enters the system. 3 UNWI 4/5 Junction Structure 28th Street Junction Structure UNWI 7 Transition Structure Figure 2. Upper Northwest Interceptor Section 5 and 6 UNWI Sections 5/6 involved many aspects of hydraulic aspects during design including: wastewater flow projection, slope analysis, hydraulic jump analysis, gravity flow, pump station design, and weir design. This report emphasizes the assumptions made and design criteria established for UNWI 5/6 and presents the hydraulic analysis process completed for the design of this project. The following information is provided in this report: Interceptor Design Criteria, Hydraulic analysis of the alignment and projected flows, and Hydraulic analysis of the junction structures. 4 1.1 Project Background The northern and northeastern portions of the Sacramento County have experienced extensive growth and the regional interceptor system requires increased capacity to accommodate the increased sewer flows. UNWI 5/6 is part of the larger Upper Northwest Interceptor regional sewer system that was identified in the 1993 Sacramento Sewerage Expansion Study [1]1 to provide relief capacity to existing collection systems that are served by the SRCSD interceptor system. SRCSD is the agency that provides the major infrastructure that conveys all the sewage in Sacramento County to be treated at the regional wastewater treatment plant located in Elk Grove. The Upper Northwest Interceptor alignment and flow requirements were evaluated in the Upper Northwest Interceptor Design Report [2]. The UNWI system was divided into 9 sections for final design to allow multiple design efforts to occur simultaneously. 1 Denotes reference stated in the References, all references will be called out using this format. 5 1.2 Upper Northwest Project Description The Upper Northwest Interceptor Sections 5/6 are part of a regional gravity sewer system designed and constructed to relieve the capacity deficiencies in the northern portion of Sacramento County. The UNWI system conveys flows to the regional wastewater treatment plant in Elk Grove, located in the southwestern portion of Sacramento County. UNWI 5/6 is a 5.5-mile gravity interceptor is the most upstream gravity section of this regional system and begins at a transition structure located at the intersection of Elkhorn Boulevard and Don Julio Boulevard. The interceptor continues along Elkhorn Boulevard to the intersection of Cherry Lane and Elkhorn Boulevard. The interceptor diameter is 48 and 66-inch to convey an ultimate flow of 80.6 mgd. The UNWI 5/6 accepts flows from several trunk sewers and a smaller interceptor, Dry Creek Interceptor. 6 1.2.1 Dry Creek Interceptor The Dry Creek Interceptor extends along the south fork of Dry Creek turning south across Elkhorn Blvd near Cherry Lane. The Dry Creek interceptor is currently at capacity and the UNWI 5/6 is designed and constructed, in part, to relief flows in this interceptor. Since Upper Northwest Interceptor Sections 1 through 4, which are downstream from UNWI Sections 5/6, will not be completed until approximately the year 2010, interim flows will be directed through the existing southern portions of the Dry Creek Interceptor by the existing Elkhorn junction structure. The Dry Creek Interceptor extends along the south fork of Dry Creek turning south across Elkhorn Blvd near Cherry Lane. The Dry Creek interceptor is currently at capacity and the UNWI 5/6 is designed and constructed, in part, to relief flows in this interceptor. Since Upper Northwest Interceptor Sections 1 through 4, which are downstream from UNWI Sections 5/6, will not be completed until approximately the year 2010, interim flows will be directed through the existing southern portions of the Dry Creek Interceptor by the existing Elkhorn 7 junction structure. A schematic of the interceptors in this area are presented in Figure 32. Figure 3 Local Interceptor Layout The existing Elkhorn Junction Structure is located on the north side of Elkhorn Blvd at the north fork of Dry Creek and combines flow from the Rio Linda Collector with Dry Creek Interceptor. This structure was constructed with a 30inch RCP pipe stub on the east side to collect additional future flows. The 30- 2 Map provided by SRCSD 8 inch pipe stub was used for the interim connection between UNWI 5 and Dry Creek Interceptor. Once UNWI 1 through 4 are operational, UNWI 5 will be connected to UNWI 4. The Upper Dry Creek Interceptor (upstream of Elkhorn Blvd.) will then flow into UNWI 4 and continues to the Natomas Pumping Station. The existing Elkhorn Junction Structure is located on the north side of Elkhorn Blvd at the north fork of Dry Creek and combines flow from the Rio Linda Collector with Dry Creek Interceptor. This structure was constructed with a 30inch RCP pipe stub on the east side to collect additional future flows. The 30inch pipe stub was used for the interim connection between UNWI 5 and Dry Creek Interceptor. Once UNWI 1 through 4 are operational, UNWI 5 will be connected to UNWI 4. The Upper Dry Creek Interceptor (upstream of Elkhorn Blvd.) will then flow into UNWI 4 and continues to the Natomas Pumping Station. 1.2.2 Hydraulic Transitions There are 2 hydraulic control structures required for UNWI 5/6 including: Upper Northwest 4/5 Junction Structure 28th Street Junction Structure 9 These hydraulic control structures will divert and channelize flow for a smooth transition of flow. These junction structures are summarized below. UNWI 4/5 Junction Structure An interim junction structure is required to divert UNWI flow into the Lower Dry Creek Interceptor at Dry Creek and Cherry Lane. This structure is needed in the interim until UNWI 1 through 4 are constructed and flow can continue directly to the Natomas Pumping Station. The structure must collect flow from Upper Dry Creek Interceptor as well as UNWI 5. In the interim it must be able to divert both interceptor flow streams to the Lower Dry Creek Interceptor and ultimately be able to divert flow down the future UNWI 4. The final design configuration of this structure is shown on Figures A-1 through A-6 and provided in Appendix A. The plan views are shown on Figures A-1 and A-2 and the Sections view of the structure are shown on Figures A-3 through Figure A-3. This design configuration incorporated the existing 30-inch stub on the existing Elkhorn Junction Structure by extending that pipe to the new interim structure and also utilizes the existing 27-inch pipe on the Upper Dry Creek Interceptor. The existing Elkhorn Junction Structure plan view is shown in Figure A-7. Under ultimate PWWF the 27-inch pipe and the 30-inch pipe will flow under a surcharged condition. 10 28th Street Junction Structure This structure will combine flow from the Dry Creek Relief Interceptor into UNWI 5 at the intersection of 28th Street and Elkhorn Boulevard. The future relief interceptor will be a 24-inch gravity pipeline and will enter the junction structure with matched hydraulic grade lines with UNWI 5 under PWWF. Under initial conditions with lower flows, there will be a fall into the structure. This structure layout is shown on Figure B-1 provided in Appendix B and was designed as part of this project, however, due to delays during construction of the UNWI Sections 5 and 6 this structure will be constructed as part of the Upper Dry Creek Relief Project. 1.2.3 Interim Dry Creek Interceptor Connection Alternative Comparison Three alternatives for the design of the interim connection of UNWI 5 with the Dry Creek Interceptor were evaluated and are described below. Each option includes using an interim hydraulic junction structure on the Upper Dry Creek Interceptor. Alternative 1 -- Match Hydraulic Grade Line Alternative 1 will consist of the 66-inch UNWI 5 constructed such that its HGL at the ultimate PWWF is the same as that of the existing 27-inch Dry Creek Interceptor. The 30-inch stub in the existing Elkhorn Junction Structure would be 11 extended along Dry Creek Interceptor and, together with the existing 27-inch pipe, would send all UNWI 5 flow into the Lower Dry Creek Interceptor. By matching inverts, the 66-inch UNWI 5 would cross beneath the south fork of Dry Creek approximately 1000 feet upstream of the interim junction structure with approximately 8 feet of cover. This alternative provides the greatest amount of ground cover of all of the identified alternatives; however, the invert of UNWI 5 would be lower than Dry Creek Interceptor by 3.5 feet and ponding of sewage would occur for approximately 2,700 feet upstream of the structure requiring maintenance efforts to prevent odors. Alternative 2 -- Match Pipe Inverts The configuration for Alternative 2 will consist of the same interim junction structure as Alternative 1 except the invert of UNWI 5 would match that of Dry Creek Interceptor. UNWI 5 would cross beneath the south fork of Dry Creek with approximately 6.5 feet of cover which is less than required 10 feet by the Department of Fish and Game for environmental protection. This option was not chosen since an adequate amount of depth below Dry Creek was not achieved. Alternative 3 -- UNWI over Dry Creek Interceptor 12 Under Alternative 3, the 66-inch UNWI 5 would be constructed over the existing Dry Creek Interceptor. The interim junction structure would house the crossing and the interim UNWI sewer flows would be sent to the Lower Dry Creek Interceptor via the existing 27-inch pipe and an extension of the 30-inch stub. Alternative 3 was not chosen since this option did not allow flexibility of diverting flows through the existing Lower Dry Creek Interceptor since the structure would not be connected to the existing infrastructure. Additionally, where the UNWI 5 pipe crossed Dry Creek, the pipe was in the scour zone of the creek since the ground cover was not sufficient. The advantages and disadvantages for each alternative are summarized in Table 1. Alternative 1 was selected for final design to maximize the hydraulic design options for diverting flows to the existing infrastructure during interim flow conditions. 13 Table 1 Comparison of Alternatives for Crossing Dry Creek Alternative 1 Advantages 2 Greatest amount of cover over 66 inch pipe Flexibility of diverting flows to existing infrastructure Smooth hydraulic flow line 3 Constructed over existing interceptor Disadvantages Ponding of wastewater requiring odor control Creek Crossing Less cover over 66 inch pipe Less flexibility for diverting flows to existing infrastructure Creek Crossing Depth of pipe cover was not sufficient More expensive structure Flatter slope No flexibility for diverting flows to existing infrastructure Comment Selected Option to ensure greatest hydraulic flexibility for design of structure and piping 14 Chapter 2 INTERCEPTOR OPERATIONAL DESIGN CRITERIA A summary of the design criteria for the Upper Northwest Interceptor Sections 5/6 and the evaluations conducted that provided the basis of design is presented in this section. The design criteria adopted for this project are a compilation of the Sacramento Regional County Sanitation District (SRCSD) design standards, along with the project team’s experience in designing and constructing major sewer interceptors. The operational design criteria are established to ensure that the SRCSD operational requirements are met during design for all flow scenarios considered. The design for UNWI 5/6 is based on several criteria that focus on the ability to construct the project and to provide a long-term facility requiring infrequent maintenance. Criteria that were considered include hydraulic flow path, operational flexibility, and safe maintenance access. 2.1 Hydraulic Flow Path A smooth hydraulic flow path along the interceptor will minimize turbulence and offgassing that reduces flow capacity and overall odors in the interceptor. Additionally, the hydraulic flow path is impacted by many design factors including lining, slopes, curves, and existing utilities. 15 Sedimentation Sedimentation of gravel or other objects along the interceptor would reduce flow capacity over time and require maintenance for removal. An analysis of the shearing stress required to prevent sedimentation was completed during design of the interceptor. The interceptor slopes were designed to establish a minimum velocity of 2 fps during periods of flow and to provide the minimum shearing stress to prevent sedimentation as discussed in Section 3.4.1. Odor Control Air movement in large pipelines is sometimes a poorly handled phenomenon and is often overlooked. Improper air handling can create concentrated odors and adverse hydraulic effects when the entrapped air is eventually vented. For this reason, proper air passage was assured throughout the length of the pipeline. Specific areas of concern are air connections across drop structures and siphons and areas of hydraulic jumps where the tail water may inundate the pipe impeding the flow of air. The design of this interceptor provided for adequate air flow along the pipeline and provided continuity of air flow at structures. UNWI Section 6 connects to UNWI 7 at a transition structure located approximately 300 feet west of the intersection of Elkhorn and Don Julio Boulevards. UNWI 7 is a force 16 main that passes through the site of the SRCSD Corporation Yard for the northern collection/conveyance system at the northeast corner of Don Julio Blvd and Elkhorn Blvd. Upstream of UNWI 7 is the Van Maren Pump Station. At that location, an odor control dosing station was constructed which suppresses sulfide development in UNWI 5/6 to reduce odors. That odor control system was designed as part of the Van Maren Pump Station so there is no odor control system included in the UNWI 5/6 design. 2.2 Pipe and Structure Lining The installed RCP interceptor and hydraulic control structures were lined with PVC for protection against hydrogen sulfide corrosion. The PVC liner covers the full inner circumference inside the interceptor. The liner was not be welded along the flow line to allow for dissipation of groundwater from behind the PVC liner. All structures were lined with PVC and portions of the structures that could not be effectively lined by T-lock PVC liners manufactured by Ameron were lined with a differently anchored PVC lining product such as those manufactured by Arrow-Lock. 2.3 Pipe Slope The pipe slope for each reach between manholes is designed to maintain a minimum velocity of 2 feet per second (fps) during low flow periods to maximize shear stress for prevention of debris sedimentation along the interceptor. 17 Horizontal and Vertical Curves Horizontal and vertical curves impact velocities and flow transitions along the interceptor to avoid turbulence and off-gassing. The allowable radius of curvature was specified to maintain a constant velocity and smooth transition of flow to minimize sedimentation and odor production. Horizontal and vertical curves were limited to a maximum of 45 degrees. Existing Utilities Minimum horizontal clearance of 10 feet is recommended for parallel utilities to minimize the potential of damage along the alignment. In select locations, the horizontal clearance is less than 10 ft. Adjustments to the alignment were made during design based on the information provided on the utility maps and field confirmation by potholing of facilities near the interceptor alignment. Minimum vertical clearance was 12 inches to provide increased constructability of the interceptor and to provide the required clearance beneath potable waterlines. In the event that the pipe slope was impacted adversely and the design slope could not be maintained, the existing utility was realigned. 18 2.4 Maximum Operational Flexibility A wide range of flows are accommodated with the final interceptor design. Current wastewater flows in the interceptor are very low, under certain operational scenarios zero, since the upstream portions of this project are not connected. The projected minimum design flow of 3-mgd for the initial operation scenario provides a minimum flow velocity of approximately 2.5-fps. The projected maximum design flow of 80.6 mgd will provide a minimum flow velocity of approximately 8 fps. The interceptor design slope was analyzed for average dry weather (minimum flow), peak dry weather flow, and peak wet weather flow (maximum flow) to ensure operational requirements were realized under all conditions. 2.5 Safe Maintenance Access A critical aspect of locating the interceptor and the maintenance holes along the selected alignment is to provide a safe working area for maintenance crews. Maintenance Holes Access to the gravity portion of the interceptor will be through maintenance holes. SRCSD standard interceptor maintenance holes will be used throughout the project. The maintenance hole structures were 60-inch diameter chimney style with flat top, frame and cover mounted to a cast-in-place encasement surrounding the pipeline. The structures 19 have an interior, sealed cover that allows direct access to the interceptor pipe. The encasement encapsulated the entire pipe segment between joints. At maintenance holes, “short” segments of pipe were used to allow the entire pipe joint to be encapsulated in concrete. Venting of specific maintenance holes was considered for odor control; however, this was not necessary. SRCSD bolts and gaskets all manholes to force air to travel to a downstream control structure for treatment. For this project, the air travels to the Arden or Natomas Pump Station for odor control. Covers for the maintenance holes were designed to be 36-inch cast iron covers in accordance with SRCSD standards. During final design, placement of the interceptor manholes was optimized to allow for maintenance access safety. Access to the maintenance holes may be accomplished by temporarily closing the outside traveled lane and the bike lane. Lane closures typically provide 20-feet of working area for the maintenance crew to operate with traffic on only one side of the work area. . 20 Chapter 3 INTERCEPTOR FLOW EVALUATION This section provides a summary of the Upper Northwest Interceptor Sections 5 and 6 service area flow evaluation. The overall project flow and pipe capacity were evaluated during the preliminary design on a regional basis. The flow and pipe capacity were also evaluated for project specific flows and capacity. 3.1 Basis of Wastewater Flow The design flows for the UNWI Sections 5 and 6 were determined using information found in the County Sanitation District No. 1 (CSD-1) Trunk Sewer Master Plan. The flows were obtained from the District in a spreadsheet format that presented both Average Dry Weather (ADWF) and Peak Wet weather (PWWF) flows for future projection years including 2010, 2020, and Build out. The flow data included flow projections from the proposed “trunk sheds” for a 48-hour time period in 15-minute increments. Trunk sheds are small tributary sewer areas that were identified for conveyance of sewer flows to a particular location (manhole). The trunk shed flow insertion points were based on location of the proposed future trunks and existing trunks identified during the master planning efforts. The minimum, average, and maximum flows were identified for each of the flow insertion points from available data 21 provided by DSRSD. The design flows for the UNWI 5/6 were determined by totaling the insertion point flows. The 19 flow insertion points identified in the CSD-1 Master Plan were grouped into several aggregate flow points that represented estimated manhole locations. These insertion points and the associated flows are shown in Figure 4. It was important to identify these manhole locations and the approximate location for flow entering the system to understand the required depth of the interceptor since the trunk sewers typically require greater depth due to slope requirements and distance to the interceptor. The grouped insertion points were reviewed and approved by SRCSD and CSD-1. The design flows calculated in the CSD-1 Trunk Sewer Master Plan were determined by an Equivalent Single family dwelling unit (ESD) accounting system. An ESD is defined as the average base wastewater flow contribution from a single-family dwelling. The tributary area for the UNWI Sections 5 and 6 was divided into “trunk sheds” as part of that analysis. The Average Dry Weather flow (ADWF) was generated by using the area of the “trunk sheds” tributary to the UNWI Sections 5/6 and the land use data. The base wastewater and inflow/infiltration (I/I) flow rates were calculated by assigning ESD’s per acre for each of the “trunk sheds” based on the land use data. The ESD’s were converted to an ADWF by using the land use and County design flow criteria is shown on Figure 22 C-1 provided in Appendix C for gallons per day per acre per ESD (gpd/acre/ESD). The design flow or Peak Wet Weather flow (PWWF) was generated using the ADWF and applying a peaking factor determined by County standards. The UNWI Sections 5/6 Tributary Area design flow was determined to be 84.8 mgd. 3.2 Wastewater Flow Wastewater flows for the UNWI Sections 5/6 alignments are summarized in Table 2. The pipe was sized for open channel flow using the ultimate wastewater flows projected for the overall area served by the interceptor. Table 2 UNWI 5/6 Projected Wastewater Flows Flow Condition Average Dry Weather Flow, (mgd) Peak Dry Weather Flow, (mgd) Peak Wet Weather Flow, (mgd) 2010 2020 Build Out 6.1 6.2 17.4 9.1 9.2 26.2 32.6 42.9 84.8 During the wastewater flow analysis, it was determined that the flows anticipated to enter the system near the termination point (UNWI 4/5 Structure) would likely enter the system downstream of this project. (3.99+0.14+0.017) to 80.6 mgd. Therefore, the design flow was reduced by 4.2 mgd 23 Figure 4 Interceptor and Trunk Sewer Flow Insertion Points 24 Chapter 4 INTERCEPTOR DESIGN EVALUATION This section presents the interceptor design evaluation including: hydraulic design criteria and the hydraulic analysis for all project components. 4.1 Hydraulic Criteria The design of this project was based on accepted design criteria for open channel, gravity pipe flow under all flow scenarios and establishing a smooth flow path along the interceptor. The design criteria used for the hydraulic analysis are summarized below. Design criteria associated with the hydraulic analysis included the following: Gravity pipe shall flow in an open channel condition for all flow conditions. Minimum Depth to Diameter (d/D) ratio of 0.75 Minimum dry weather flow velocity of 2 fps Minimum peak dry weather flow velocity of 3 fps. Minimum shearing stress of 0.07 pounds per square foot (discussed in Section 3.4) Manning’s “n” factor of 0.013. Maximum design velocity of 10 fps or less, unless unusual topography prevents lower velocities in the pipe. 25 These criteria were based on the consideration of re-suspending solids and limiting the generation and release of odors. 4.2 Hydraulic Analysis The hydraulic analysis for this project consisted of determining the shearing stress to maintain solids suspension and identifying slope based on established flow scenarios. The diameter size was established during the pre-design completed by others and was verified during the slope analysis for this project. 4.2.1 Shearing Stress Determining the required flow to re-suspend solids in a pipeline is based on the shearing stresses available along the pipe wall that interface with the flow. The 1993 Sacramento Sewerage Expansion Study [1] provided criteria for evaluating shearing forces at the pipe/water interface for gravity pipes. This criterion is in accordance with the ASCE Manuals and Reports on Engineering Practice No. 60, “Sulfide in Wastewater Collection and Treatment Systems.” Shearing stress is calculated using the following relation: T0 = wRS Where: T0 = shearing stress in pounds per square foot (lbs/sq ft) 26 w= specific weight (lbs/cubic foot) R= hydraulic radius (ft) S= pipe invert slope The result is an average shearing stress and is considered adequate near the bottom of the pipe when the flow in the pipe is one-third full. For most practical purposes, the value obtained from this relation is considered valid for situations where flow depths are less than one-third of the full pipe flow and the velocity is a minimum of 2 feet per second (fps). The recommended range for shearing stress is 0.03 to 0.08 lbs/sq ft. The lower end of the range is recommended for grit particles (approximately 1 mm). Historically, SRCSD has used a minimum shearing stress equal to 0.07 lbs/sq ft for larger interceptor pipelines such as UNWI Sections 5 /6. 4.2.2 Slope Evaluation The hydraulic analysis for the UNWI 5/6 project was completed using two spreadsheet models. Both hydraulic spreadsheet models were developed using Microsoft Excel and completed to determine slopes, velocities, and depth of flow for each of the projected flows listed in Table 2. 27 A slope analysis was performed to determine the minimum slope that could be used for the pipe design to maintain minimum shear stress of 0.07 and the maximum slope to remain at or below critical flow. Maintaining pipe flow at or below critical flow is important to minimizing turbulence and odor generation. Additionally, the flow depth was limited to a minimum d/D ratio to 0.75 to allow air flow along the pipe and prevent an anaerobic condition. Therefore, evaluating the range of acceptable pipe slopes for both minimum and maximum flow was performed. Manning’s Equation was used for the slope analysis. Since the pipe is flowing less than full, the hydraulic radius (R) needed to be determined for a cross section that is a fraction of a circle. The cross section of the less than full pipe flow is presented on Figure 5. 28 E D A C O D (ft) d (ft) B Figure 5 Open Channel Flow in Pipe Flowing Less than Full The line ADC represents the flow line and d is the depth of flow equal to 0.75D. The pipe diameter is denoted by D (ft). Point O represents the center of the circle. The equation for R is: R= A/P [3] Where: R= Hydraulic Radius of a Circle A= Area of Flow = Area of the Circle – (Area of Sector AOCE – Area of Triangle AOCD) P = Wetted Perimeter = Arc ABC 29 Angle = cos-1 (0.25D/0.5D) Area of Sector AOCE = [(2*)Deg.]*(1/4 D2) Length of Arc ABC = D – [(2*)Deg.]*(D) Area of Triangle AOCD = 2*1/2*(0.25D)*(0.25D tan ) This equation was entered into Microsoft Excel using a visual basic program so that the d/D value, slope, and friction coefficient could be entered. The visual basic program is presented in Figure 6. FLDEPTH =RESULT(1) =ARGUMENT("Q",1) =ARGUMENT("D",1) =ARGUMENT("S",1) =SET.NAME("DEPTH",0) =SET.NAME("STEP",0.0005) =0.0135*Q/S^0.5 =SET.NAME("DEPTH",DEPTH+0.1) =ROUND(2*ACOS(1-2*DEPTH/(D/12)),4) =(D/12)^2.6667*(C10-SIN(C10))^(5/3)/(20.16*C10^(2/3)) =IF((C11)<C8,GOTO(C9)) =SET.NAME("DEPTH",DEPTH-0.1) =SET.NAME("DEPTH",DEPTH+STEP) =ROUND(2*ACOS(1-2*DEPTH/(D/12)),4) =(D/12)^2.6667*(C15-SIN(C15))^(5/3)/(20.16*C15^(2/3)) =IF(C16<C8,GOTO(C14)) =IF(12*DEPTH>D,GOTO(C21)) =SET.NAME("DEPTH",12*DEPTH) =RETURN(DEPTH) =RETURN(D) Figure 6 Visual Basic Program for Calculating Flow Depth 30 The spreadsheet calculated full pipe flow, flow depth, hydraulic radius, and Froude number based on these design criteria entered. Critical slope was determined by entering slope values until a Froude number of 1 was obtained as a result. A sample of the spreadsheet is presented in Figure 7. Figure 7 Sample Calculation Spreadsheet The results of the analysis for minimum slope are presented in Table 3 and Table 4. Since a large inflow will occur into the UNWI Sections 5 and 6 at 28th Street from the Upper Dry Creek Relief and the McClellan Air Force Base, the slope 31 criteria are presented from both 28th Street to Don Julio Boulevard and Cherry Lane to 28th Street, the location of a hydraulic control structure. Initial wastewater flows in the interceptor will be very low and, under certain operational scenarios, zero. A minimum flow of 3 mgd was used for the hydraulic analysis. Table 3 Slope Analysis – 28th Street to Don Julio Pipe Diameter (in) Slope 48 0.0022 48 0.00373 48 0.0022 48 0.00434 3 4 Flow (Qmin) (mgd) 3 3 Critical Slope based on minimum flow Critical Slope based on minimum flow Flow (Qmax) (mgd) 42.8 42.8 d/D 0.18 0.16 0.80 0.61 Shear Velocity Stress (t) (fps) 3.1 0.06 3.7 0.09 6.1 0.28 8.2 0.30 Comment Minimum Initial Flow Ultimate PWWF 32 Table 4 Slope Analysis- Cherry Lane to 28th Street Slope 0.0014 66 66 0.00375 3 0.0012 80.8 0.90 5.6 0.13 66 6 80.8 0.57 9.1 0.34 Pipe Diameter 66 0.0037 Flow (Qmax) (mgd) Shear Velocity Stress (t) (fps) Comment 2.5 0.04 Minimum 3.6 0.08 Initial Flow Flow (Qmin) (mgd) 3 d/D 0.13 0.10 Ultimate PWWF As shown in Table 3, critical slope for the 48-inch diameter pipe 0.0037 for a flow of 3 mgd and 0.0043 for a flow of 42.5 mgd. The selected slope for this section was 0.0037 to achieve the maximum velocity at minimum flow and to remain close to critical slope and maximum velocity at maximum flow. The second spreadsheet was established to identify manhole to manhole slope requirements based on utility conflicts, connection points, and depth of pipe cover. The slope was adjusted between manholes as necessary and the hydraulic capacity was compared again to the design criteria. The slope for the 66-inch diameter pipe section was selected based on the shear stress, velocity, and d/D values along with additional criteria of depth of the pipe. The pipe depth for this 5 6 Critical Slope based on minimum flow Critical Slope based on minimum flow 33 section was critical since construction of pipe depths greater than 25 feet become difficult and cost preventive. In an effort to keep the pipe depth less than 25 feet and to meet the required inverts at both junction structures, the flattest slope possible was selected. A summary of slopes based on this evaluation is presented in Table 5. Table 5 Summary of Design Slopes by Reach Velocity at Maximum Q Start Station End Station (fps) Comment Section 6- Maximum Flow, 42.8 mgd 264+23 285+00 5.67 260+69 264+23 Supercritical Utility Conflict Pipe Diameter Slope 48 48 0.0037 0.0176 48 0.0037 239+73 260+69 48 0.2580 239+45 239+73 Supercritical Utility Conflict 48 48 0.0037 0.0136 205+86 200+81 239+45 205+86 5.67 Supercritical Grade Change 48 0.0037 66 0.0011 69+00 140+00 5.07 66 0.0030 19+77 69+00 8.38 66 0.0021 2+36 19+77 7.23 5.67 140+00 200+81 5.67 Section 5- Maximum Flow, 80.6 mgd Lowered for Upper Dry Creek Relief UNWI Section 6 has several locations where it was required to increase the pipe depth to avoid existing utilities which could not be moved or the grade changed and the minimum pipe cover could not be met. The minimum pipe cover required 34 to minimize pipe loading was 10 feet. At all these locations, the flow is supercritical and a hydraulic jump will occur. Hydraulic jumps will damage the pipe by scouring. To prevent damage to the pipe from scour, the pipe was lined for the entire circumference of the pipe. In addition, the potential for air venting was analyzed at these locations. The slopes for UNWI Section 5 were maintained generally within the slope range evaluated. However, the reach between Station 69+00 and Station 140+00 is just under the minimum slope of 0.0012 due the need to lower the 28th Street Structure to accommodate the Upper Dry Creek Relief. An economical analysis was performed to determine whether it would cost more to lower this structure or pump the Upper Dry Relief Interceptor flows. It was determined that the least costly solution was to increase the depth of the UNWI Section 5 pipe. However, due to the distance available to the UNWI 4/5 structure, the slope was reduced slightly to meet the required invert at that structure. 4.3 Hydraulic Control Structures Hydraulic control structures are designed to divert and channelize flow for a smooth transition at pipe diameter changes or flow convergence points. For this project, two junction structures were required. The UNWI 4/5 Junction Structure was designed to 35 channelize incoming flow and outgoing flow, accommodate a pipe change, and provide interim flow control. The 28th Street Junction Structure was designed for both a pipe diameter change and a point for flow convergence from 2 pipes. Both structures are located along UNWI Section 5. A schematic of the layout from the 28th Street Junction Structure to the existing Elkhorn Junction Structure is shown in Figure 8. The schematic shows UNWI Section 5 divided into two segments for the purpose of discussion. 36 Figure 8 28th Street Junction Structure to Existing Elkhorn Structure The segment of UNWI Section 5 between the UNWI 4/5 Junction Structure and the existing Elkhorn Junction Structure has been labeled Segment A and the project portion between the 28th Street Junction Structure and the UNWI 4/5 Junction Structure has been labeled as Segment B. 37 4.3.1 UNWI 4/5 Junction Structure The UNWI 4/5 Junction Structure will collect flow from Upper Dry Creek Interceptor as well as from UNWI Sections 5 and 6. Sewer flow from the UNWI Sections 5 and 6 enters the UNWI 4/5 Junction Structure from a 66 inch pipe that originates at an upstream junction structure, the 28th Street Junction Structure discussed in Section 4.3.2. The UNWI 4/5 junction structure was designed to perform as a diversion of sewer flow from the UNWI 4/5 Junction Structure to the UNWI Sections 1 through 4 and flow will continue directly to the Natomas Pumping Station. In the interim, flow from the Dry Creek Interceptor, Rio Linda Interceptor, and UNWI Sections 5/6 will initially be sent down the existing Lower Dry Creek Interceptor. The hydraulic criteria used for the design of UNWI 4/5 Junction Structure included: Maintain subcritical flow in the 66-inch diameter pipe, Interim flow equal to 26 mgd, Build out flow equal to 80.6 mgd, Mannings’ “n” equal to 0.013, and 38 Entrance loss coefficient into the structure of 0.1 The UNWI 4/5 Junction Structure was constructed with a weir and a pump station to convey flow through the existing downstream sections of the Lower Dry Creek Interceptor. A three mgd pump station was designed as part of this structure to discharge sewage to a bay located on the south side of the structure. The weir was designed to allow sewage to spill during periods of maintenance or in the event that the pump either failed or the flow reached 26 mgd. The existing Elkhorn Junction Structure was modified to allow sewage to flow to the Lower Dry Creek Interceptor from the UNWI 4/5 Junction Structure until the remaining sections of the UNWI system are constructed. The existing junction structure has a 27-inch diameter opening and a 30-inch diameter opening that has a plug to prevent infiltration of groundwater into the structure since a connection had not been constructed. In an effort to use the existing Elkhorn Structure pipe openings at, the invert elevations for the 27 and 30-inch diameter pipes at the UNWI 4/5 Junction Structure that connected to the existing Elkhorn Structure needed to be determined to allow for conveyance of the interim flow of 26 mgd. Additionally, the weir length and the pump station hydraulics needed to be calculated based on the hydraulics required to convey the interim flow. 39 The hydraulic design for the 66 inch pipe discharging into the UNWI 4/5 Structure, the Elkhorn Structure connection, the UNWI 4/5 Structure weir and pump station are presented in the following sections. Hydraulic Grade Line for the 66-inch Diameter Pipe The 66-inch diameter pipe into the UWNI 4/5 Junction Structure is the section of pipe between the 28th Street Structure and this structure. This pipe will carry a build out flow of 80.6 mgd and the required freeboard between the hydraulic grade line and the invert of the 27 and 30-inch diameter pipes in this pipe was designed to be a minimum of 6-inches. This design will allow wastewater to be stored in the 66-inch diameter pipe in the event of a failure downstream or maintenance in the structure. Based on the pipeline profile and slope analysis performed, the invert of the 66-inch diameter pipe was set at 20.42 feet at the UNWI 4/5 Junction Structure to allow for an adequate slope and the minimum freeboard required. The crown elevation in the 66 inch pipe is at 25.92 feet. The flow depth in the pipe at build out flow of 80.6 mgd is 3.37 feet and the HGL is 23.79 feet. 40 Connection to the Existing Elkhorn Junction Structure The hydraulic calculation for the flow available through the 27 and 30-inch diameter pipes assumed that the headloss through both pipes were equal, the pipes were flowing full, and the required total flow through the pipes was 26 mgd. A schematic of the design including HGL at the interim flow of 26 mgd is shown in Figure 9. Ground Elevation 47 ft Ground Elevation 47 ft Figure 9. Schematic of Interim Design flow HGL along Segment A The invert elevation at the existing Elkhorn Junction Structure was set at 24.49 feet. The invert elevation at the UNWI 4/5 Junction Structure discharge bay was set based on the slope required to provide 26 mgd of flow, the hydraulic grade 41 line of the existing 27 inch Dry Creek Interceptor, and the hydraulic grade line of the 66 inch diameter pipe. The total flow in each pipe was calculated by determining the headloss using the following equation for each pipe diameter and setting these equations equal to each other: hL= n2Q2*L/2.21*R4/3*A2 (ft) [4] Where: n = Manning’s friction coefficient Q= pipe flow (cfs) L= length of pipe section (ft) R= hydraulic radius (ft) A= area of the pipe (ft2) Since the Manning’s friction coefficient was assumed to be equal for both pipes this term and the constant (2.21) cancel each other when setting the equations for these pipes equal to each other. The hydraulic radius was determined for both the pipe diameters. The hydraulic radius (R) was calculated using the following equation: R=A/W (ft) [4] 42 Where: R= hydraulic radius of the pipe (ft) A= area of the pipe (ft) W= the wetted perimeter (ft) The equation has two unknowns, Q27 and Q30 and was solved for one of the unknowns in terms of the other unknown. The total flow is equal to the sum of the flow in each pipe, therefore, the flow for one was solved by adding the two flows and subtracting from the total flow of 26 mgd. The second flow was determined from subtracting the calculated flow and subtracting from the total flow of 26 mgd. The pipe flow units used were mgd since the units cancel for all other components of the calculation. Based on the calculation, the flow was determined to be 11.2 mgd and 14.8 mgd in the 27-inch and 30-inch diameter pipes, respectively. The velocity in each pipe was determined based on Q= VA and calculated to be 4.4 and 4.6 fps for the 27 and 30-inch pipes, respectively. The velocity was calculated to determine the minor headloss in each pipe using the equation HL= kV2/2g [4]. Where: HL= headloss (ft) 43 k = headloss coefficient V = velocity (fps) g = 32.2 ft/s2 The minor headloss due to entrance or pipe bends in each pipe was less than 0.1 and determined to be negligible. The pipe friction losses were determined using the Hazen Williams headloss equation for submerged pipes. The pipe friction loss equation used was: hf = 3.022 * V1.85 * L/ C1.85 * D1.165 [4] Where: hf = pipe friction loss (ft) V = velocity (fps) L = pipe length (ft) C= Hazen Williams pipe friction coefficient D = pipe diameter (ft) The headloss was originally assumed to be equal and as would be expected the headloss was calculated to be 0.57 feet for both pipes for lengths of 253 feet for the 27-inch pipe and 263 feet for the 30-inch diameter pipe. The discharge bay invert was set 1 foot above the build out flow HGL for the 66 inch pipe at 24.81 feet and slightly below the existing 27 inch Dry Creek Interceptor calculated 44 invert of 24.85 feet. The slope for the 27 and 30 inch pipe was then calculated to be .0018 based on the inverts at each structure. The pipe flow for these pipes was not dependant on the slope since the pipes are submerged and under pressure. The hydraulic characteristics for the 27 and 30-inch pipes are summarized in Table 6. Table 6 Hydraulic Characteristics of 27 and 30-inch Pipes Pipe Diameter (inch) 27 30 Slope 0.0018 0.0018 Flow Q (mgd) 14.8 11.2 Velocity (fps) 4.4 4.6 Headloss (feet) 0.57 0.57 Weir The weir was designed to allow 26 mgd to spill into the discharge bay during interim operations. The height and length of the weir were calculated using a side weir calculation along with elevations determined by the pump station design. The pump station is discussed in more detail in the following section. The weir height was set to allow the discharge bay to fill to approximately 1 foot over the 30 inch pipe crown plus up to 6 inches of freeboard between the water level and the top of the weir. To determine the weir height, the hydraulic grade line in the pump station needed to be determined. The HGL in the discharge bay 45 was determined to be 27.88 feet based on the invert elevation of 24.81 feet and adding the 30 inch diameter pipe and the head loss of 0.57 feet (24.81+30/12+0.57 = 27.88 feet). The target freeboard between the top of the weir and the hydraulic grade line within the discharge bay was 6 inches. However, the head over the 27 and 30 –inch pipes required to ensure the design flow of 26 mgd, allowed for a 0.25 feet freeboard above this HGL to the top of weir elevation of 28.1 feet. The height of the water over the weir was chosen to be 0.96 feet, to keep the height of the water over the weir below 1 foot. A schematic view of the UNWI 4/5 Junction Structure weir elevation and HGL’s is shown in Figure 10. 46 Ground Elevation 47 ft Figure 10 Weir Elevation at the UNWI 4/5 Junction Structure The length of the weir was determined by using the following equation: Q=Cw*L*h(3/2) [3] Where: Q= wastewater flow (mgd) Cw= Weir coefficient L= length of weir (feet) h= height of water over the weir 47 The height of water over the weir was assumed to be 1.0 foot, the weir length was increased by 0.25 feet for each calculation iteration, and the weir coefficient was assumed to be 3.3 which is a typical value for rectangular discharge weirs. Based on the design flow of 26 mgd and the head over the weir of 1 foot, the length of the weir was determined to be 12.25 feet in length. However, the weir length was set at 13 feet to accommodate other design concerns such as existing pipe and structure rebar design. The head over the weir would be 0.96 feet at a flow of 26 mgd. Based on the results of the weir length analysis, a weir length of 13 feet was selected since the design flow is satisfied and the head over the weir is less than 1 foot. The weir calculation results are summarized in Table 7. Table 7 Weir Calculation Results Flow Q (mgd) 26.13 26.08 26.79 Head over Weir (ft) 1.00 0.96 0.80 Length of Weir 12.25 13.00 17.50 Pump Station The pump station was designed to discharge 3 mgd of flow during periods when the total flow was less than 26 mgd. The pump hydraulics consisted of determining the wet well size, force main size, the pump on/off levels, and the net positive suction head available (NPSHA). 48 The assumptions were made that the pump station would be 10 foot in diameter and the hydraulic grade line would match the hydraulic grade line (HGL) in the junction structure. The wet well size was chose to be 10-foot diameter, since this could easily be constructed using 120-inch diameter pipe sections. The pump wet well volume was based on minimum operational requirements for the pump using the industry standard of maximum pump start of 6 times per hour. The wet well volume equation is Q*t/2, where Q is the flow in gpm and t is the pump cycle time. This equation is based on the wet well and pumps having uniform pumping rate and the minimum pump cycle time occurring when the rate of inflow is equal to one half the discharge rate. Additionally, the effective wet well volume is based on 2.5 times the discharge rate to ensure that the maximum pump starts per hour does not exceed 6 times which is recommended for pumps having a uniform pumping rate. Using 2100 gpm and 10 feet diameter, the volume of 5250 gallons is calculated. The pump wet well and the 66 inch pipe HGL would naturally equalize to the same elevation due to the connection of these two structures. Therefore, an iterative process was used to determine both the HGL in both structures (UNWI 4/5 and the pump wet well). The volume of the UNWI 4/5 Structure channel was 49 assumed to be rectangular and the volume was expressed as the height the water times width of the channel. The channel width is 5.5 feet and the depth of the water is an unknown. The pump wet well is cylindrical and the volume can be expressed as V = h x A; where V is volume (gallons), h is height of water (feet), and A is the area of the wet well (square feet). The wet well area is the area a circle (PI *D2/4); where D is the diameter (feet). The height of the water in the wet well was calculated to be 8.94 feet. The HGL minus the water height is equal to the invert in each structure. The invert was already determined to be 20.42 for the UNWI 4/5 Junction Structure. Therefore, there are two equations: HGL1 = 20.42 + h1 HGL2 = Wet Well Invert + 8.94 Setting the two equations equal to each other the resulting equation is: 11.48 + h1 = Wet Well Invert Solving this equation using trial and error, the results are shown in Table 8. 50 Table 8 HGL and Water Depths in the UNWI 4/5 Structure and Pump Wet Well Description Invert Elevation (ft) UNWI 4/5 Structure 20.42 Wet Well 15.94 Height of Water (ft) 4.46 8.94 HGL Elevation (ft) 24.88 24.88 Based on the results, during pumping the HGL in the UNWI 4/5 Junction Structure will be approximately 1 foot above the HGL at the build out flow. For this to occur, the pump on/off level will need to be set near the HGL elevation. The force main was sized using Q=VA, with the flow discharge equaling 3 mgd and holding the velocity at 5 fps. The force main size was determined to be 10 inches in diameter. The pump on/off levels were based on the junction structure hydraulics and the pump hydraulics. The design of pump systems requires an analysis of the potential for low pressure at the suction side of the pump to ensure that the pump fluid does not reach the boiling point. The boiling point of a fluid is reached when the fluid is below the vapor pressure at fluid temperature. The pressure analysis is important to prevent cavitation, reduced efficiency and damage. The 51 net positive suction available (NPSHA) is an equation used to compare the total head at the suction side of the pump close to the impeller and the vapor pressure of the fluid at the associated temperature. This suction head equation is based on the Energy Equation and expressed as the sum of the static and velocity head. The vapor pressure head is expressed as the ration of the vapor pressure to the vapor head. NPSHA is expressed as the difference between suction head and pressure heads. The NPSHA was calculated using the following equation: NPSHA= Hbar+hs-Hvap-Hvol- FS Where: Hbar = barometric pressure, 32.7 ft hs = static head (vertical height between pump impeller center line and water surface) (ft) Hvap = vapor pressure, 1.6 feet Hvol = 2 feet FS= Factor of Safety, 3 feet The static head was calculated to be 8.2 feet, based on the discharge piping invert elevation set at 25.47 feet and subtracting the impeller centerline (15.94 +1.33) feet. The pipe minor and friction losses were assumed to negligible. The NPSHA was calculated to be 34.3 feet based on the stated equation (32.7+8.2-1.6-2- 52 3=34.3). The pump was chosen based on these pumping characteristics and keeping the net positive suction head required for the pump below the calculated NPSHA to prevent cavitation. 4.3.2 28th Street Junction Structure The 28th Street Junction Structure was designed to channelize flow from 2 incoming pipes and accommodate pipe diameter changes. The hydraulic design criteria is the same for the UNWI 4/5 Junction Structure. The hydraulic analysis of this structure also considered maintaining some flow below the pipe crown to allow air flow along the interceptor to minimize odor generation. A schematic of the water surface elevation along Segment B is shown on Figure 11. Ground Elevation 47 ft Ground Elevation 79 ft Figure 11 Schematic of Interim Design flow HGL along Segment A 53 This structure is the junction for convergence of 2 pipes, the upstream UNWI Section 6 and the Upper Dry Creek Relief pipe. The Upper Dry Creek Relief is a 36-inch diameter pipe that will enter this structure from the north along 28th Street. The crown elevation of both the 48-inch and 66-inch pipes were matched at elevation 52.02 feet to prevent submergence of the 66 inch pipe. The invert elevation of the Upper Dry Creek Relief pipe was set approximately 1 foot above the invert of the 48-inch pipe to ensure a freeboard within the pipe to prevent submergence. . 54 Chapter 5 PROJECT CONCLUSIONS Construction of the UNWI 5/6 was completed in 2006 and is now operational. The hydraulic analysis of this interceptor was comprehensive and included considerations for flow regimes, hydraulic jumps, and odor control. The UNWI 4/5 Junction Structure was designed to operate under minimum, interim, and build out flow scenarios. At this time, SRCSD staff have not been able to use the pump station due to the valve failure between the UNWI 4/5 Structure and the pump wet well. The valve is stuck partially open likely due to debris stuck in the valve seating or mechanical failure for some other reason. Maintenance of the valve would require either draining the structure channel and removing the debris or digging up the valve and replacing it. The valve would be difficult to access since it is located between two structures that would require support and the valve is buried approximately 15 feet deep. Currently, SRCSD has decided to allow the channel to back up and send the flow over the weir since odor has not been a concern. Based on the difficulty maintaining the isolation valve between the pump wet well and the UNWI 4/5 structure, I would consider the following design changes: 55 Installing a gate valve within the pump wet well for ease of access for maintenance, and Designing the inlet piping between the UNWI 4/5 Structure with a slope to increase velocity and minimize debris sedimentation. . 56 APPENDICES 57 APPENDIX A UNWI 4/5 Junction Structure Drawings 65 APPENDIX B 28th Street Junction Structure Drawings 67 APPENDIX C County Design Criteria 68 Figure C-1 County Design Criteria 69 REFERENCES [1] Montgomery Watson. Final Report- Sacramento Sewerage Expansion Study- 1994 Update. Prepared for Sacramento Regional County Sanitation District and Sacramento County Sanitation District No. 1. August, 1994. [2] Carollo Engineers, Inc. Upper Northwest Interceptor Design Report. May, 1999. [3] Ranald V. Giles, Jack B. Evett, and Cheng Liu. Fluid Mechanics and Hydraulics 3rd Edition. McGraw-Hill, 1994. [4] Linsley, Ray K., Franzini, Joseph B., Freyberg, David L., Tchobanoglous, George. WaterResources Engineering. 4th ed. New Jersey: McGraw-Hill,1992. [5] McGhee, Terence J. Water supply and sewerage. 6th ed. New Jersey: McGraw-Hill, 1991.