DEVELOPMENT OF EXTENDED PERIOD SIMULATION MODEL FOR THE CITY OF MODESTO A Project Presented to the faculty of the Department of Civil Engineering California State University, Sacramento Submitted in partial satisfaction of the requirements for the degree of MASTER OF SCIENCE in Civil Engineering by Glenn Durgesh Prasad FALL 2012 © 2012 Glenn Durgesh Prasad ALL RIGHTS RESERVED ii DEVELOPMENT OF EXTENDED PERIOD SIMULATION MODEL FOR THE CITY OF MODESTO A Project by Glenn Durgesh Prasad Approved by: __________________________________, Committee Chair Dr. Saad Merayyan __________________________________, Second Reader Dr. Kurt Ohlinger ____________________________ Date iii Student: Glenn Durgesh Prasad I certify that this student has met the requirements for format contained in the University format manual, and that this Project is suitable for shelving in the Library and credit is to be awarded for the Project. __________________________, Graduate Coordinator Dr. Cyrus Aryani, P.E., G.E. Department of Civil Engineering iv ___________________ Date Abstract of DEVELOPMENT OF EXTENDED PERIOD SIMULATION MODEL FOR THE CITY OF MODESTO by Glenn Durgesh Prasad Through this project, an Extended Period Simulation (EPS) model was developed in order to provide the City of Modesto (City) with an easily adaptable tool that incorporates advanced supervisory controls within the existing distribution system, while predicting the water distribution system behavior within a reasonable accuracy. Once created, the EPS model was used to develop an understanding of the general water system behavior during varying demand conditions. Through specific case studies, the EPS model was further used to evaluate two important water resource planning concepts currently explored by the City. Hence, this Project is divided into three main parts: (1) Development of an Extended Period Simulation (EPS) Model; (2) Case Study 1: Surface Water Optimization Source Tracing Model; and (3) Case Study 2: Aquifer Storage and Recovery (ASR) Hydraulic EPS Model. Since an understanding of the water system was critical, each task within the Project was developed through close communication with City’s operations, planning and v design staff. Extensive pressure and flow data collected by the City was incorporated into the EPS model development. Prior to the model calibration, a brief GIS-based water system assessment was conducted that exclusively examined the City’s distribution pipe network, in terms of its material and age. During this time, the City Water Operations staff was consulted regarding the general condition of the City’s water pipe network. The EPS model was calibrated with an overall accuracy of 10% utilizing more than 500 measured flow and pressure data points. While the model predicted well in North Modesto, there are still model refinements necessary in the South Modesto Area. Primarily, tank control data will be needed to further refine model calibration. The Surface Water Optimization Source Tracing Model outlined the extent of surface water delivery within the City’s distribution system in a given 24 hour period. Surface water, which is conveyed through the Modesto Irrigation District (MID) transmission main was only delivered within close proximity to the mains. This was primarily occurring because the receiving system was also supplied by groundwater wells operating at similar pressure levels. The City should consider using the model for a future surface water optimization study, which may look at the reevaluation of the well cluster operation systems. The Aquifer Storage and Recovery (ASR) Hydraulic EPS model demonstrated that the City could supply up to 10 million gallons per day (MGD) of available excess surface water during winter conditions for an ASR program to an area immediately west of the City, near West Tank. The EPS model indicated that during summer demands, if vi the western portion of the City was selected for the ASR program, the City could face difficulties in extracting ASR water and supplying it to the distribution system, with the current well cluster supervisory controls in place. It is recommended that the City should tailor the cluster controls to allow for desired ASR water supply. The evaluation in this project was only from a hydraulic distribution system standpoint and no hydrogeologic analysis was performed to confirm aquifer characteristics within the proposed location. This analysis was conducted as a demonstration to the City of the nature of a future ASR Facility Layout Analysis that should be performed as part of an ASR Feasibility Study. _______________________, Committee Chair Dr. Saad Merayyan _______________________ Date vii DEDICATION To My Wife and My Parents viii ACKNOWLEDGEMENTS I would like to express my gratitude towards everyone who helped me complete this Project. I would like to convey my appreciation to Dr. Saad Merayyan, for his guidance and the Department of Civil Engineering at California State University Sacramento, for accepting my Project. This Project would not have been possible without the support of the Utility Planning and Projects Department of the City of Modesto, led by Rich Ulm. A special thanks to Jack Bond for heading the Capital Planning water modeling efforts and authorizing the development of the Extended Period Simulation Model for the City. I would like to furthermore thank the entire Water Operations Division of the City for their input, and trust in the City's water model. I would like to convey my sincere appreciation towards my parents for believing in me and helping me achieve various goals in my life, including the completion of this Project. Thanks to my brother for becoming my motivation in life. I wish to express my love and gratitude towards my five year old nephew, Amon, for spilling juice over my Project Report and thereby accelerating my efforts towards a new horizon. Finally, for good reason, I am deeply indebted to my wife, Chaya for her support all the way. ix TABLE OF CONTENTS Page Dedication ............................................................................................................................. viii Acknowledgments.................................................................................................................... ix List of Tables ......................................................................................................................... xii List of Figures ....................................................................................................................... xiii Abbreviations ........................................................................................................................... xv Chapter 1. INTRODUCTION ...................... ……………………………………………………….. 1 1.1 Background ............................................................................................................ 1 1.2 Water Supply Overview ........................................................................................ 1 1.3 Water Demand Overview ...................................................................................... 3 1.4 Unaccounted for Water ........................................................................................... 3 1.5 Water System Operations Overview ....................................................................... 4 2. LITERATURE REVIEW ................................................................................................... 7 3. DEVELOPMENT OF EXTENDED PERIOD SIMULATION MODEL ........................ 10 3.1 Earlier Steady State Model Description ............................................................... 10 3.2 Water Model Updates ........................................................................................... 11 3.3 Field Data Collection ............................................................................................ 12 3.4 Well Cluster Controls ........................................................................................... 13 3.5 Summer Diurnal Patterns ...................................................................................... 17 3.6 Model Simulation Options and Time Settings ...................................................... 19 3.7 EPS Model Calibration ......................................................................................... 20 x 3.7.1 Calibration Methodology ...................................................................... 20 3.7.2 Water System Pipe Condition Assessment ........................................... 23 3.7.3 Model Run and Results ......................................................................... 28 4. CASE STUDY 1: SURFACE WATER SUPPLY OPTIMIZATION USING SOURCE TRACING MODEL .................................................................................... 32 4.1 Importance of Surface Water Optimization .......................................................... 32 4.1.1 Surface Water Availability and Reliability ........................................................ 32 4.1.2 Surface Water Quality versus Groundwater Quality ......................................... 33 4.1.3 Groundwater Management / Replenishment...................................................... 34 4.2 Surface Water Optimization Source Tracing Model............................................. 34 4.4 Well Field Optimization Project Phase II ............................................................. 38 5. CASE STUDY 2: AQUIFER STORAGE AND RECOVERY HYDRAULIC EPS MODEL ............................................................................................................................. 40 5.1 Importance of an Aquifer Storage and Recovery Project ..................................... 40 5.2 Purpose and Limitations of the ASR Hydraulic EPS Model ................................ 42 5.3 Development of the ASR Hydraulic EPS Model .................................................. 45 5.4 Evaluation of ASR Water Diversion Point Locations .......................................... 46 5.5 ASR Hydraulic EPS Modeling Results................................................................. 47 6. CONCLUSIONS AND RECOMMENDATIONS ........................................................... 51 Appendix A: Model Data Entry for Well Cluster Controls ..................................................... 55 Appendix B: Water Pipe Grouping Maps for Calibration ....................................................... 85 Appendix C: Surface Water Optimization Source Tracing Model .......................................... 97 References .............................................................................................................................. 111 xi LIST OF TABLES Tables Page 1. Summary of Well Cluster Operating Parameters............................................... 15 2. Pipe Categorization Based on Material and Age Groups .................................. 25 xii LIST OF FIGURES Figures Page 1. Surface Water Supply to the City of Modesto ................................................... 2 2. City of Modesto Water System Layout ............................................................. 6 3. Input of Rule Control Data for Cluster-Based Operation .................................. 14 4. June, 14 2011 Water Production Demands – Global Summer Diurnal Curve .. 18 5. EPS Model Simulation Options ......................................................................... 19 6. EPS Model Simulation Time Options................................................................ 20 7. Calibration Objective Functions Used by Calibrator® ...................................... 21 8. Junction Pressure Entered into the EPS Model.................................................. 22 9. MID Pipe Flow Data Entered into the EPS Model ............................................ 22 10. Old Water Pipeline with Extensive Sedimentation............................................ 23 11. Water Operations Staff Removing Sand Out of a Water Main ......................... 24 12. Pipe Group 1 (AC, CI: 1980 – Present) ............................................................. 26 13. Pipe Group 2 (AC, CI: 1940 – 1979) ................................................................. 27 14. Entering Pipe Group Categorization into the EPS Model ................................. 28 15. Calibration Options ............................................................................................ 29 16. Exporting Calibrator® Results to Active Pipe Set ............................................ 30 17. Surface Water Optimization Source Tracing Model (Hour 09:00) ................... 36 18. Surface Water Optimization Source Tracing Model (Hour 24:00) ................... 37 19. City of Modesto Water Demand versus Available Water Supplies in AFY...... 41 xiii Figures Page 20. Aquifer Storage and Recovery Components Diagram....................................... 44 21. January 14, 2011 Demand Pattern for ASR Hydraulic EPS Model .................. 46 22. Winter Demands versus Suggested ASR Operations ........................................ 49 xiv ABBREVIATIONS AFY................................................................Acre-foot per Year ARTDA ..........................................................Amended and Restated Delivery Agreement CIP .................................................................Capital Improvement Projects DWR ..............................................................California Department of Water Resources EPS.................................................................Extended Period Simulation GA ..................................................................Genetic Algorithm MG .................................................................Million Gallons MGD ..............................................................Million Gallons per Day MID ................................................................Modesto Irrigation District MRWTP .........................................................Modesto Regional Water Treatment Plant PRV ................................................................Pressure Reducer Valve PSI ..................................................................Pounds per Square Inch SCADA ..........................................................Supervisory Control and Data Acquisition UWMP ...........................................................Urban Water Management Plan WFO-P2 .........................................................Well Field Optimization Project Phase II xv 1 CHAPTER 1 INTRODUCTION 1.1 Background The City of Modesto (City) is the largest urban water purveyor in the Modesto subbasin of the San Joaquin Hydrologic basin. The City serves water to more than 230,000 constituents (including Modesto, Empire and Salida), as well as major industries that provide goods and supplies worldwide. A constant and reliable urban water supply is necessary for a sustainable urban environment, and is also vital to its economic growth. 1.2 Water Supply Overview The City’s water supply comprises a 30 million gallon per day (MGD) surface water supply, along with more than a hundred groundwater wells. The surface water supply is provided by Modesto Irrigation District (MID) through an Amended and Restated Transfer and Delivery Agreement (ARTDA). MID is one of the oldest irrigation districts in California and has pre-1914 water rights on the Tuolumne River. Surface water from the Tuolumne River is treated about fourteen miles east of the City, at the MID Regional Water Treatment Plant (MRWTP) and delivered solely to the City, connecting into the western side of its distribution system (see Figure 1). 2 0 3 1.3 Water Demand Overview In the 2010 Water System Engineer’s Report (Engineer’s Report), it was estimated that the City’s average daily demand (using a 10 year average) was 70.3 MGD, while the maximum and peak hour demands were 117.5 MGD and 165.2 MGD respectively. The total base water demand comprises residential, industrial, commercial, and institutional customers. During the development of the Engineer’s Report, the 50 top users within the City were identified and their annual water usage was quantified. Most of these users were industrial and institutional water users. 1.4 Unaccounted for Water Currently, the City’s water system is not entirely metered. For this reason, measuring actual demand for each customer is not possible. Nonetheless, the City has a very robust Supervisory Control and Data Acquisition (SCADA) system that measures water production from each well, as well as continuous pressures and flows at key locations throughout the City. Based on data from other similar cities, it had been estimated in the Engineer’s Report that the City could be losing about 15% of the total water produced. These losses are termed “Unaccounted for Water” and are mainly attributed to losses due to water leaks, pipe repairs, pipeline flushing, hydrant testing and fire flows. Hence the City has established the following relationship: Water Produced = Water Supplied = Water Demand + Unaccounted for Water 4 1.5 Water System Operations Overview The surface water supply from the MRWTP is conveyed 14 miles west into the Terminal Reservoirs, which comprises two five million gallon (MG) tanks. Surface water from the Terminal Reservoirs is then conveyed through about 14 miles of pipeline running through the City, ranging from 24 inch to 48 inch diameter, known as the MID Transmission Main. The City has limited control over the quantity of surface water supplied through the Terminal Reservoir. The City's operation staff maintains daily communication with MID staff to ensure proper surface water delivery. The surface water supply is conveyed throughout the City through the MID Transmission Main, as shown in Figure 2. This water is then regulated through several Pressure Reducer Valves (PRVs) to ensure appropriate pressure reduction before entering the City's water distribution system. The groundwater wells are grouped into 20 operational clusters. Each cluster comprises a collection of groundwater wells that operate based on pressure measurements at a single common pressure point. The collections of wells within a cluster have a specified operating sequence, which was defined based on field experience of existing and past City staff. The wells are sequenced such that the highest priority well is operated continually to satisfy system demands. If the pressure point reading within a cluster goes below the set point (50 - 60 psi in most cases), then the second well in the sequence turns on. If the target pressure at the pressure point is met, then the second well shuts off. Otherwise, the third well turns on. This process is repeated until all the wells within the cluster are brought online as needed. The steady state model developed for the City did 5 not have the capability of activating wells based on the City’s defined cluster sequences. The decision of which wells to bring online was primarily at the modeler's discretion. The Extended Period Simulation (EPS) model developed through this study provided the model this capability. 6 7 CHAPTER 2 LITERATURE REVIEW The Literature Review conducted during this Project, was primarily used to research available information on the development of Extended Period Simulation (EPS) models, evaluate the technological advances in water modeling, and compare the relative status of the City of Modesto’s water system model. Critical review of some technical publications was also performed and compared with the challenges faced by the City to expand on its modeling capabilities. Water distribution system models invariably attempt to solve two fundamental equations in pipe network hydraulics. These two equations are the Continuity Equation and the Momentum Equation. While these two equations have remained the focus of hydraulic models for decades, our ability to solve these equations has dramatically changed throughout history. The AWWA Manual M32: Computer Modeling of Water Distribution Systems, a brief history of computer modeling is described in the first Chapter. The authors explain how before 1960’s, manual calculations were primarily used for water modeling. This was often a laborious task that was only practical for solving single looped systems. As computers advanced, so did our ability to solve water distribution models quickly and easily. The release of EPANET by the United States Environment Protection Agency in 1993 as a public-domain software (Rossman, 1993) not only made 8 it accessible to water resource engineer’s worldwide, but also opened doors for other software developers to expand its capabilities. In M32, authors indicate how present day software packages have focused on Geographic Information Systems (GIS) as to allow the centralization of data to reduce the effort required to develop models. Present day water system models also have the capability to receive real time data from SCADA systems. This includes the InfoWater® software package developed by Innovyze that was used for this Project. In Water Distribution System Handbook, Larry Mays et al. explores the linking of SCADA systems with distribution system models. In this book, a model with such linkage is explained to serve as a tool for operator training, emergency response preparation, energy management and understanding water quality behavior. Chapter 16 of this book also explains various optimization models that can be developed after the model is integrated with field measurements. The authors of the Water Distribution System Handbook later acknowledge that “several water utilities in the United States are using hydraulic network models in their operations, but few are actually allowing system operators to use the models” (Mays, 2000). The City of Modesto falls under the latter of the two types of utilities, where operations staffs are not utilizing the relevant capabilities of the model to the fullest. The primary reason for this is the limitations of the City’s steady state (snapshot in time) hydraulic model. The City’s current model was developed in order to create a Capital Improvements Program (CIP) and not to solve ongoing (nearterm) operational issues. Lack of modeling expertise is another reason why the model 9 has not been utilized by operations staff. While technical adequacy may be attained by implementing staff training programs, the City’s Water Operations division’s bigger challenge will be dedicating consistent financial resources towards the development, maintenance and purchase of equipment needed to utilize a system that incorporates the hydraulic model as the core element in their decision making process. The City’s most current report that deals intensively with hydraulic modeling is the 2010 Water Systems Engineer’s Report. The 2010 Joint Urban Water Management Plan also lays out the City’s roadmap in terms of planning for water supplies and demonstrating compliance with state-mandated conservation programs. None of these documents have specifically stressed the need for an Extended Period Simulation Model for the City. The 2010 Engineer’s Report does include Water System Evaluation (Category 17), a $4.9M program, as one of its CIP’s that will fund “as-needed” water system studies. This program will also fund the maintenance of the hydraulic modeling software and hydraulic model updates. Both reports have demonstrated the use of existing 30 MGD surface water supply and have highlighted the need for additional 30 MGD (total of 60 MGD) surface water supply in the near future. An Extended Period Simulation model will be needed to conduct necessary analysis to ensure proper delivery operations and conveyance of the additional surface water supply. Future conjunctive use projects such as Aquifer Storage and Recovery (ASR) will also require the need for the EPS Model. 10 CHAPTER 3 DEVELOPMENT OF EXTENDED PERIOD SIMULATION MODEL 3.1 Earlier Steady State Model Description The City’s earlier model was a steady state model (snapshot in time), which was a planning level model primarily developed to help the City setup its Capital Improvement Projects (CIP) Program. In the 2005 City of Modesto Hydraulic Model Update, a software evaluation was conducted that compared a number of software packages based on user-friendliness, analysis capabilities, demand allocation methods and cost. During this evaluation, the H2ONET computer package developed by Innovyze (formally MWHSoft), was selected. In 2009, the City decided to bring the model in-house and a brief re-evaluation was conducted. After 2005, the City had expanded on its GIS capabilities, and therefore, it was most appropriate to convert the model to the GIScompatible version of H2ONET, which is InfoWater®. The InfoWater® software package was utilized in this study. The early steady state InfoWater® model contained six main scenarios (i.e. Existing Average Day, Existing Maximum Day plus Fire Flow, Existing Peak Hour, Future Average Day, Future Maximum Day plus Fire Flow, and Future Peak Hour Scenarios). In order to develop a particular scenario, the corresponding water production was calculated based on land use designations and water duty factors and the demands were 11 distributed on relevant demand nodes. The top fifty water users within the City were also identified and their corresponding water demand was quantified and applied separately to the appropriate node within the steady state model. Once the demands were assigned, the status of wells throughout the system was adjusted to achieve the desired flow at the MID terminal reservoir. It was assumed (and confirmed from measurements) that during an Average Day scenario, the MID terminal reservoir typically produced 30 MGD, whereas, during a Peak Hour scenario, the MID Terminal Reservoirs could produce up to 45 MGD. The decision as to which wells will remain on or off was made by the modeler, considering several factors such as pump efficiency, proximity to the MID terminal reservoirs and most importantly, the response to MID terminal reservoir flows. For example, if the computed flow from terminal reservoir was 35 MGD during Average Day Demand conditions, wells were turned on to provide more groundwater supply and therefore reduce surface water supply needed to 30 MGD. If turning on a well didn’t provide any computed flow increase at the MID terminal reservoir, another well was tried until the desired flow at MID terminal reservoir was achieved. This decision making process, which was necessary each time the demand had considerably increased or decreased, was a major drawback of the earlier steady state model. 3.2 Water Model Updates All water system improvements made after the delivery of the Steady State Model in 2009 was added to the model. This included activating recently added constructed PRVs along the MID transmission main, as well as Tank 12 (West Tank) and its booster pump 12 stations. The water model update was performed in collaboration with the City's Water Design staff. All infrastructure activated in the model was confirmed consistent with the as-built plans for the water system improvements. Water Operations field crews, who had installed pipelines were consulted as needed. 3.3 Field Data Collection The City collects and stores thousands of data points throughout the day through its SCADA system. At the end of each day, this data is archived and is shared with various City departments that deal with water system operations, design and planning. Examples of stored data include: 1. Monthly flow data for each well 2. Monthly and hourly flow data by system (Note: The City serves other areas outside the City of Modesto water service area) 3. Hourly pressure and flow measurements for each well cluster 4. Daily wells out of service reports Due to the vast amounts of data collected and reported each day, it was logical to develop the EPS model in such a way that included flexibility to update and re-calibrate the model (if needed) based on any given demand conditions. Field data collected for June 14, 2011 was used for the development and calibration of the EPS model. Demands on this day ranged from a low of about 60 MGD to a high of about 95 MGD. Hence it should be noted that the calibration performed is valid within these demand ranges. Although 2011 13 had been a low water use year, it was still selected during the development because for this Project, it was more important to keep the model updated to current conditions, than simulating maximum demand conditions. January 2011 data was used for the winter model created for the Aquifer Storage and Recovery (ASR) demonstration model. A total of 480 pressure point data was collected for the project. This included hourly pressure data for each of the 20 well clusters (24 hours per cluster x 20 well clusters equals 480 data points). In addition, hourly flow data corresponding to the MID pipeline was collected for 24 hours on January 2011. 3.4 Well Cluster Controls One of the significant enhancements to the Model during this Project was the addition of the Well Cluster Controls. These controls were simulated as Rule Controls within InfoWater®. Unlike Simple Controls in InfoWater®, Rule Controls allow for complex instructions to mimic the decision making capability that currently exists in the field through the City's SCADA system. A total of 68 Rule Controls were added to the model to allow wells to turn on or off based on the pressure point readings and their operating sequence. Figure 3 shows how the user may enter and edit rule controls into the InfoWater® computer program. 14 Figure 3: Input of Rule Control Data for Cluster-Based Operations The remaining Rule Control entries have been provided in Appendix A. All Rule Controls entered within the model were given equal priority. Table 1 summarizes the cluster operations data that was used to develop the Rule Controls. The City wishes to maintain system pressure around 60 psi and therefore, the wells operating within a cluster are designed to meet the target delivery pressure. 15 Cluster # Cluster 1 Cluster 1 Cluster 2 Cluster 2 Cluster 2 Cluster 2 Cluster 2 Cluster 2 Cluster 2 Cluster 3 Cluster 3 Cluster 3 Cluster 3 Cluster 3 Cluster 3 Cluster 3 Cluster 3 Cluster 4 Cluster 4 Cluster 4 Cluster 4 Cluster 4 Cluster 5 Cluster 5 Cluster 5 Cluster 5 Cluster 6 Cluster 6 Cluster 6 Cluster 6 Cluster 6 Cluster 6 Cluster 7 Cluster 7 Cluster 7 Cluster 7 Cluster 7 Cluster 7 Cluster 8 Cluster 8 Cluster 8 Cluster 8 Cluster 8 Cluster 9 Cluster 9 Cluster 9 Cluster 10 Cluster 10 Cluster 10 Well # Well 226 Well 42 Well 25 Well 43 Well 262 Well 48 Well 264 Well 50 Well 24 Well 54 Well 259 Well 58 Well 52 Well 39 Well 46 Well 37 Well 62 Well 241 Well 237 Well 236 Well 34 Well 44 Well 8 Well 17 Well 16 Well 56 Well 14 Well 18 Well 21 Well 267 Well 269 Well 300 Well 65 Well 32 Well 41 Well 265 Well 278 Well 45 Well 3 Well 57 Well 4 Well 7 Well 2 Well 36 Well 1 Well 6 Well 40 Well 211 Well 59 Sequence Offline 1 1 2 3 4 5 6 7 1 2 3 4 5 6 7 8 1 2 3 4 5 1 2 3 4 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 1 2 3 1 2 3 Pressure Point (Model Node) 16046 16046 17534 17534 17534 17534 17534 17534 17534 16468 16468 16468 16468 16468 16468 16468 16468 11064 11064 11064 11064 11064 14650 14650 14650 14650 14274 14274 14274 14274 14274 14274 10040 10040 10040 10040 10040 10040 11502 11502 11502 11502 11502 14192 14192 14192 13286 13286 13286 Table 1: Summary of Well Cluster Operating Parameters Setting (psi) 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 16 Cluster # Cluster 10 Cluster 10 Cluster 10 Cluster 11 Cluster 11 Cluster 11 Cluster 11 Cluster 11 Cluster 11 Cluster 11 Cluster 12 Cluster 12 Cluster 12 Cluster 12 Cluster 12 Cluster 13 Cluster 13 Cluster 13 Cluster 13 Cluster 13 Cluster 13 Cluster 14 Cluster 14 Cluster 14 Cluster 14 Cluster 14 Cluster 14 Cluster 15 Cluster 15 Cluster 15 Cluster 16 Cluster 16 Cluster 16 Cluster 16 Cluster 19 Cluster 19 Cluster 19 Cluster 19 Cluster 20 Cluster 20 Cluster 20 Cluster 20 Cluster 20 Cluster 21 Cluster 21 Cluster 22 Cluster 22 Cluster 22 Well # Well 307 Well 204 Well 47 Well 53 Well 229 Well 301 Well 304 Well 10 Well 232 Well 283 Well 29 Well 30 Well 223 Well 305 Well 287 Well 38 Well 100 Well 55 Well 49 Well 19 Well 66 Well 212 Well 279 Well 225 Well 292 Well 308 Well 291 Well 247 Well 285 Well 312 Well 250 Well 313 Well 297 Well 288 Well 299 Well 298 Well 281 Well 280 Well 293 Well 277 Well 310 Well 294 Well 296 Well 33 Well 22 Well 61 Well 64 Well 51 Sequence 4 5 6 1 2 3 4 5 6 7 1 2 3 4 5 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 1 2 3 Pressure Point (Model Node) 13286 13286 13286 12748 12748 12748 12748 12748 12748 12748 13620 13620 13620 13620 13620 18932 18932 18932 18932 18932 18932 13498 13498 13498 13498 13498 13498 19634 19634 19634 2282 2282 2282 2282 2394 2394 2394 2394 13470 13470 13470 13470 13470 17210 17210 20034 20034 20034 Setting (psi) 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 Table 1: Summary of Well Cluster Operating Parameters (Continued) 17 It is recommended that the City re-evaluate and prioritize all of its wells based on factors such as motor age, operational efficiency, impacts to groundwater levels etc. The cluster controls should then be redefined. Further effort should be pursued to integrate the MID Terminal Reservoirs into the cluster operating controls. This will help the City to maximize surface water and thereby, execute an efficient conjunctive use program. The City is currently in the process of evaluating all its wells through the Well Field Optimization Project Phase II. This project will collect data regarding all the wells, and evaluate them based on performance. Finally, a database along with a web-based interface will be developed as part of a separate Well Field Optimization Project that will centralize all collected data and allow City staff to determine different well operation configurations (clusters) that will help the City meet a particular objective (such as minimize pumping cost, minimize impact to groundwater, maximize production etc). Further details regarding this project are provided in Chapter 4. 3.5 Summer Diurnal Patterns Global system-wide water production information was gathered through the SCADA system and a global demand pattern was calculated. This demand pattern was applied globally on every demand node within the Model. This way, the final overall demand pattern was the same as that observed in the field. Figure 4 shows the final diurnal curve that was developed based on system-wide water production. 18 While this method of applying overall demand pattern is convenient and adequate for the purposes of this project, it is recommended that more refined demand pattern assignments be applied as part of City’s future work. This work will entail calculating demand patterns, either through clusters (zones) or based on land use. Once the City starts metering its customer’s water use, cluster based or land use based demands should be calculated and applied to the EPS model to make the demand simulation more realistic. June 14, 2011 Water Production June 14, 2011 Water Production 100.0 90.0 Water Production (MGD) 80.0 70.0 60.0 50.0 40.0 30.0 20.0 10.0 23.00 - 24.00 22.00 - 23.00 21.00 - 22.00 20.00 - 21.00 19.00 - 20.00 18.00 - 19.00 17.00 - 18.00 16.00 - 17.00 15.00 - 16.00 14.00 - 15.00 13.00 - 14.00 12.00 - 13.00 11.00 - 12.00 9.00 - 10.00 10.00 - 11.00 8.00 - 9.00 7.00 - 8.00 6.00 - 7.00 5.00 - 6.00 4.00 - 5.00 3.00 - 4.00 2.00 - 3.00 1.00 - 2.00 0.00 - 1.00 0.0 Time Interval Figure 4: June 14, 2011 Water Production Demands – Global Summer Diurnal Curve 19 3.6 Model Simulation Options and Time Settings The Simulation Options in the model were altered for the EPS model as shown in the figure below. It is in the simulation options where rule controls are enabled. Figure 5: EPS Model Simulation Options 20 Figure 6: EPS Model Simulation Time Options 3.7 EPS Model Calibration 3.7.1 Calibration Methodology The EPS model was calibrated using the Calibrator® module within the InfoWater® Suite package. The Calibrator® module uses Advanced Genetic Algorithm (GA) to solve an implicit nonlinear optimization problem, subject to user specified constraints. The three choices for the objective function are provided below: 21 (Source: Innovyze, Inc. 2007) Figure 7: Calibration Objective Functions Used by Calibrator® Type 1 objective function has been recommended in the Calibrator® User Guide and was selected for calibration of the EPS model. The Calibrator® allows the user to enter measured pressure and flow data, which is then matched with simulated results of the EPS model by adjusting the pipe roughness values within similar defined Pipe Groups. All 480 data points collected for the pressure points on June 14, 2011 were entered into the model for calibration. Twenty four (24) MID hourly pipe flow data for this day was also entered for calibration. The following figures show how the pressure points and MID pipe data points were entered into the EPS model. 22 Figure 8: Junction Pressure Entered into the EPS Model Figure 9: MID Pipe Flow Data Entered into the EPS Model 23 3.7.2. Water System Pipe Condition Assessment Before the final calibration process, a brief qualitative condition assessment was done on the City’s aging distribution pipeline system, using the model database and the City’s Geographic Information System (GIS) database. Water Operations staff was also consulted regarding the general condition of pipelines in the City and they indicated that old steel pipes in the City’s distribution system were the primary concern. Cast Iron and steel pipelines often have corrosion or sedimentation, which in some cases is quite extensive since some pipes are nearly eighty years old. A few pictures of smaller pipes within the system indicate approximately 30 - 50% blockage in flow area. Figure 10: Old Water Pipeline with Extensive Sedimentation 24 In some cases, pipelines close to wells have sedimentation from sands that originate from within the well casings. Figure 11 shows Water Operations staff removing sand from the water main during an installation. Figure 11: Water Operations Staff Removing Sand Out of a Water Main. Reasonable effort was made to incorporate these factors affecting pipelines and their calibration as closely as possible into the EPS model. All pipes in the model had to be classified into groups (of similar C factors) based on the pipe material and age. This categorization is tabulated in Table 2. 25 Pipe Roughness Pipe Groups 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Material AC, CI AC, CI AC, CI AC, CI CL DI, DIP DI, DIP DI, DIP DI, DIP GI GI GI GI PVC PVC PVC PVC UNKOWN UNKOWN UNKOWN UNKOWN Year from 1980 1940 1939 unknown unknown 1980 1940 1939 unknown 1980 1940 1939 unknown 1980 1940 1939 unknown 1980 1940 1939 unknown Year to Present 1979 and less unknown unknown Present 1979 and less unknown Present 1979 and less unknown Present 1979 and less unknown Present 1979 and less unknown Lower Range 115 90 60 60 60 80 70 60 60 95 70 60 60 125 100 60 60 125 100 60 60 Upper Range 140 115 90 140 130 100 80 70 100 120 95 70 120 150 125 100 150 150 125 100 150 Result (Calibrator Module) 140 105 72 140 75 96 78 62 100 95 85 70 120 150 125 76 150 135 125 68 96 Table 2: Pipe Categorization Based on Material and Age Groups Existing information within the City’s GIS system was used to visualize areas where pipes were older. GIS data was queried to classify the water pipes. Results of this spatial analysis have been shown in Figure 12 and 13. A map of each pipe group tabulated above has been provided in the Appendix. 26 27 28 3.7.3 Model Run and Results The pipe database within the EPS model was update according to the Pipe Group categorization. Figure 14 shows how the categorization information that was entered into the Calibrator® Module. The module was then run using the options shown in Figure 15. Figure 14: Entering Pipe Group Categorization into the EPS Model 29 Figure 15: Calibration Options The EPS model achieved the desired fitness threshold of 10% in 65 trials, using the Advanced Genetic Algorithm. The average global difference in pressure measurements was 4.2 %. The calibrated values for pipe roughness were applied to the pipe dataset from within the EPS model. Figure 16 shows how results from the Calibrator® were directly exported to the active pipe set within the EPS model. 30 Figure 16: Exporting Calibrator® Results to Active Pipe Set Refinements were made as necessary to simulate field conditions as closely as possible. A calibration result within the required tolerance level was reached. However, while the model predicted well in some areas, other areas within the City, particularly the South Modesto area, had lower pressure zones than what was measured in field conditions. One main reason for discrepancy is that the model uses decisions based on clusters, as entered in the Rule Controls. It is not uncommon for City Water Operations to switch to hand control and operate clusters manually. The second reason for discrepancy could be related to the tank operations. SCADA based controls (such as filling schedules and pressure set points) were not added to the tanks as part of this Project. This work is 31 recommended as part of future improvements to the EPS model. Results at individual pressure points throughout the distribution system have been provided in the Appendix. 32 CHAPTER 4 CASE STUDY 1: SURFACE WATER SUPPLY OPTIMIZATION USING SOURCE TRACING MODEL 4.1 Importance of Surface Water Optimization The City currently gets 30 MGD of surface water supply from the Modesto Irrigation District, through an Amended and Restated Transfer and Delivery Agreement (ARTDA). The first water delivery was made in 1995 and an expansion of the treatment plant is nearly complete, which will provide the City with an additional 30 MGD of surface water supply in the near future (bringing the City’s total surface water supply availability to 60 MGD). At the moment, no other City within the Modesto groundwater subbasin or the neighboring Turlock groundwater subbasin (totaling approximately 927 square miles) has surface water available to its customers. There are three main reasons why the City wishes to optimize its surface water supplies, as described in the following sub-sections. 4.1.1 Surface Water Availability and Reliability The City obtains surface water from the Modesto Irrigation District, which was formed on July 23, 1887, becoming the second irrigation district to be established under the California Irrigation Districts Act (Wright Act). During its early years, the MID developed numerous pre-1914 rights for the Tuolumne River water. Pre 1914 water rights are ranked high in the hierarchy 33 of California’s water rights system, as perceived by the California State Water Resource Control Board. The ARTDA provides the City with a solid legal framework to assure reliable delivery of surface water when needed. In contrast, groundwater supplies are very unreliable, in terms of its water quality and availability. 4.1.2 Surface Water Quality versus Groundwater Quality Surface water needs to be optimized due to its high water quality. Surface water delivered to the City originates from the Tuolumne River, which has a 1,880 square mile watershed that extends to the High Sierra. Most of the river’s flow comes from snowmelt, making this a high raw water quality source. Furthermore, the raw water is treated at the Modesto Regional Water Treatment Plant (owned and operated by the Modesto Irrigation District). The 30 MGD plant is a conventional treatment facility providing flocculation, sedimentation, and filtration, along with ozonation for primary disinfection, thus bringing water quality to Title 22 drinking water standards (City of Modesto, 2010). Groundwater quality, on the other hand, continually faces regulatory challenges due to water contamination. The City’s groundwater supply is affected by a range of contaminants, including Arsenic, Nitrates, Perchloroethylene (PCE), Gross Alpha (indicator of a radionuclide source) 34 and Uranium. More than half of the wells offline for contaminants are due to Uranium and Gross Alpha, which is very expensive and difficult to treat. Therefore, in terms of water quality, it is logical for the City to optimize the use of high quality surface water as much as possible. 4.1.3 Groundwater Management/ Replenishment Groundwater replenishment is another reason to optimize surface water needs. Groundwater is a resource that is shared with other agricultural and municipal agencies, as well as private well owners within the groundwater subbasins. Over-pumping from any one agency within the groundwater basin can cause a basin overdraft, directly affecting other groundwater purveyors within the subbasin. To avoid over-pumping, the City practices in-lieu banking, which is a conjunctive use strategy for agencies utilizing both surface and groundwater. The objective of in-lieu banking is to mostly utilize surface water during colder months and allow for groundwater replenishment. Then in summer months, surface water can be used in conjunction with groundwater to meet high peaking demand conditions. 4.2 Surface Water Optimization Source Tracing Model As part of this project, a Surface Water Optimization Model was developed within InfoWater® to demonstrate the use of the EPS model in order to answer operational questions related to the optimization of surface water. Once the EPS model was built, the 35 source tracing option was used to trace the movement of surface water from the MID Terminal Reservoirs. Results of the Source Tracing Model indicate that surface water moves more quickly across the City through the transmission main, then it does in the distribution systems close to the Terminal Reservoir. The source tracing model was used to provide a visualization of the surface water movement within a 24 hour period. This visual aid can be used to explain to Water System Operators how they can alter their cluster controls for better spread and consumption of surface water. Figure 17 and 18 shows simulation results at the 9th and 24th hour respectively, of the MID surface water source tracing model. The dots indicate the nodes where all or a portion of the water is surface water from MID terminal reservoir). During low demand periods of January and February 2012, it was noticed that the MID Terminal Reservoir was only able to deliver 20 MGD of surface water flow. With the help of the source tracing model, decisions can be made as to which wells to turn off to allow more surface water consumption. Note that although the City uses 20 MGD, the City is still charged for the full 30 MGD whether it is used or not. 36 37 38 4.4 Well Field Optimization Project Phase II The Well Field Optimization Project Phase II is a state funded basin-wide (Modesto Subbasin) project led by the City of Modesto as the lead agency, with an objective to provide more efficient operations of the well field systems. Other agencies involved in the Project include the City of Oakdale, Riverbank and the Stanislaus County. While this work is beyond the scope of the current study, there are various elements of the Well Field Project that can be used to enhance the developed EPS model. A facilities inventory for all the wells in the City of Modesto was completed from various sources. Data collected for the City included information such as well logs/ construction information, pump motor ratings, soil tests, water quality, hydrogeologic information of the underlying aquifers, well efficiency and well level information. Once the data is collected, it will be compiled into a centralized database system. All the wells will be closely evaluated based their performance and condition and will then be categorized into four main categories as indicated below: Category A: Online wells that are in good operating condition (these wells are efficient, and have no known water quality concerns and do not require rehabilitation). Category B: Online wells with marginal or poor operating condition (would benefit from rehabilitation). 39 Category C: Offline wells with good operating potential; if rehabilitated or put to alternate use, such as irrigation. The best use of the well will be recommended (these wells have a high pumping capacity and would be beneficial if brought online). Category D: Offline wells with poor operating condition. The wells are low producing wells that will not have a significant contribution to the water supply system (should be either completely rehabilitated or abandoned and destroyed). Once the all wells have been ranked, a web-based Decision Support System (DSS) will be developed by in-house City of Modesto Information Technology staff with guidance from the Capital Planning team. Eventually, a web-based DSS will be developed that will allow modelers as well as water operations staff to determine the best set of wells to operate to meet a particular objective, such as, minimizing energy costs due to pumping, minimizing groundwater level impacts, maximizing production etc. The web-based DSS application was selected as opposed to a stand-alone application, since the web-based DSS will be more accessible for data inquiries and updates. This Well Field Optimization Project Phase II will be critical while re-evaluating the cluster system. Best operation clusters obtained from the DSS will then be incorporated into the EPS model for verification of hydraulic performance under varying winter, summer and emergency demand conditions. 40 CHAPTER 5 CASE STUDY 2: AQUIFER STORAGE AND RECOVERY HYDRAULIC EPS MODEL 5.1 Importance of an Aquifer Storage and Recovery Project In California, various forms of Aquifer Storage and Recovery (ASR) have been studied, explored and in some cases partially or fully implemented. For the purposes of this case study, ASR is defined as the direct injection of potable water into deeper aquifers, for future recovery from the same location to satisfy higher seasonal demands. As stated earlier in Chapter 4.1.3, the City wishes to use conjunctive use strategies, supplying winter demands with surface water (allowing groundwater to replenish) and summer demands with both groundwater and surface water. Figure 19 from the City’s 2005 Urban Water Management Plan (UWMP) shows the water supply and demand projections that were reported to DWR. It can be seen that based on these early projections, the City will continue to have surplus water for about 20 years after construction of the Phase 2 of the MRTWP. It should be noted Phase II did not come online in 2008, as anticipated in the 2005 UWMP. The Phase II plant is nearly constructed but the actual surface water delivery is still being worked about between MID and the City of Modesto. 41 Figure 19: City of Modesto Water Demand versus Available Water Supplies in AFY (Source: City of Modesto, 2005 UWMP) The City along with the City of Ceres and the City of Turlock, are planning the Regional Surface Water Supply Project (RSWSP), which will construct another water treatment plant to serve its constituents within the neighboring Turlock Subbasin. Because the treatment plants are built considering buildout demand projections, in early years following construction, the City will have a water surplus. Due to the surplus water supplies, apart from in-lieu banking of groundwater, the City wishes to explore ASR options. Water banked using ASR can not only be used to satisfy 42 high summer demands, but can also be available during drought conditions, when MID cuts back on municipal surface water supply due to higher delivery priorities to its agricultural customers. 5.2 Purpose and Limitations of the ASR Hydraulic EPS Model The goal of this Evaluation is to demonstrate how the EPS model can be used to identify potential surface water diversion points within the City’s water distribution system, as well as evaluate the overall system hydraulic performance. Since an ASR diversion will probably induce the highest single point demand (diversion) on the distribution system, which can have adverse pressure impacts, a thorough hydraulic performance of the distribution system simulating ASR operations is critical. The ASR operations and scheduling should be done such that the ASR demand impacts to the distribution system are minimal. A successful ASR project requires a favorable target aquifer(s), in terms of storage capacity and geochemistry. Such projects also require great financial commitment. Figure 20 shows the various components that could be involved in an ASR Project. Determining target aquifers within the groundwater subbasins, and exploring the current regulatory setting in Northern California is beyond the scope of this evaluation and is recommended in a preliminary feasibility study. The work highlighted in this Project should be performed between the ASR feasibility study and the future pilot 43 demonstration project. The ASR Hydraulic EPS model developed as part of this Project should be used to perform future ASR diversion-point alternative studies. 44 45 5.3 Development of the ASR Hydraulic EPS Model The ASR Hydraulic EPS model was used in evaluating a location within the distribution system for ASR diversion, as well as quantifying the amount of ASR injection that the hydraulic system can tolerate at the evaluated location (strictly looking at distribution system hydraulics). In order to conduct the evaluation, a winter EPS model simulating ASR injection (demand), and a summer EPS model demonstrating ASR supply into the distribution system had to be developed. This development was straightforward with the well cluster rule controls in place as part of work performed within this project. For the winter injection scenario, January 14, 2012 demand conditions were used in the model because this was the most recent winter day for which data was collected at the time of analysis. The demand pattern was developed from the collected field data and has been shown in Figure 21. 46 January 2011 Water Production January 2011 Water Production 70.0 Water Production (MGD) 60.0 50.0 40.0 30.0 20.0 10.0 23.00 - 24.00 22.00 - 23.00 21.00 - 22.00 20.00 - 21.00 19.00 - 20.00 18.00 - 19.00 17.00 - 18.00 16.00 - 17.00 15.00 - 16.00 14.00 - 15.00 13.00 - 14.00 12.00 - 13.00 11.00 - 12.00 10.00 - 11.00 9.00 - 10.00 8.00 - 9.00 7.00 - 8.00 6.00 - 7.00 5.00 - 6.00 4.00 - 5.00 3.00 - 4.00 2.00 - 3.00 1.00 - 2.00 0.00 - 1.00 0.0 Time Interval Figure 21: January 14, 2011 Demand Pattern for ASR Hydraulic EPS Model 5.4 Evaluation of ASR Water Diversion Point Locations The Surface Water Optimization Source Tracing Model developed in Chapter 4 was used to evaluate potential ASR diversion point locations. Based on the EPS source tracing model results (Figures 17 and 18), it was seen that surface water quickly reaches the northeast portion of the distribution system. Since this zone generally has higher pressures, a diversion point at this location will not adversely affect the distribution system pressures based on modeling results. Alternatively, more suitable ASR location could be at the western portion of the City, near Tank 12, where surface water is conveyed by the MID transmission main. This location would be ideal because surface 47 water stored as part of the ASR project can be recovered to not only supply North Modesto, but also South Modesto. Currently, water that is obtained from MID (Modesto Subbasin) is not sent to South Modesto (Turlock Subbasin) due to place of use conditions pertaining to MID’s water rights. If ASR water is injected in the deeper aquifers of the western portion of the City, groundwater rights of the City may be exercised upon extraction. This means that the water injected could be put to beneficial use in South Modesto, which has immense water supply deficiencies, as well as a multitude of water quality issues. The City is advised to conduct a thorough water rights evaluation surrounding this issue as part of a future feasibility study. A secondary advantage of selecting the western portion of the City (west of Highway 99) is that this area has been identified by USGS as having a 200 feet deep corcoran clay layer. Due to these clay lenses, this area may have some semi-confined or confined aquifers that may be suitable for an ASR project. Until more comprehensive hydrogeological studies are conducted as part of the preliminary ASR feasibility study, these assumptions remain speculative. 5.5 ASR Hydraulic EPS Modeling Results The ASR Hydraulic EPS model showed that during winter demand conditions, a single diversion point in western Modesto could handle an average daily ASR demand of 10 MGD, without causing significant impacts to the water distribution system. 48 On January 14, 2012, MID terminal reservoirs provided the City with an average of 20 MGD, with production lowering to 11 MGD at 6:00 am. The modeling results show that an additional 10 MGD can be supplied by MID and banked on the western portion of the City near West Tank during winter season. However, the modeling results indicate that the system cannot handle a constant average 10 MGD ASR diversion throughout the 24 hours and maintain distribution system pressures within normal operating range (i.e. pressures above 40 psi). Hence, a more realistic ASR schedule had to be developed. It is logical that when the winter demands are higher, more water should be used to satisfy customer demand and less water should be diverted for ASR. Likewise, when the winter demands are lower, there is less need for surface water and therefore, this can be banked. Using the EPS Hydraulic model, a viable ASR schedule was developed as shown in Figure 22, with injection rates ranging from 7 MGD to 12 MGD. Notice that during higher demands, the ASR injection flow diversion is lowered, whereas it is increased during lower demand periods. 49 70 60 Demand (MGD) 50 40 Winter Demand ASR Operations 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Time Figure 22: Winter Demands versus Suggested ASR Operations The schedule indicated above shows an average injection rate of 10 MGD, which would be equivalent to an ASR program with approximately 7 wells, injecting at a rate of 1,000 gpm. If such a schedule is continued for a 3 month period, a total storage of 2,734 ac-ft will be attained. To bring the results into perspective, this is equivalent to about a third of the City of Roseville’s long term ASR program goal of 10,000 ac-ft per year (Source: http://www.roseville.ca.us/eu/water_utility/aquifer_storage_n_recovery.asp). The summer EPS model showed limitations of the system to receive 10 MGD at the connection point from the ASR system to the distribution system. With it’s proximity to the West Tank, its supply was limited to 2.5 MGD. This limitation also appears to be due 50 to the City’s current well cluster operation sequences. This issue should be resolved by reevaluating the well clusters in a future study. 51 CHAPTER 6 CONCLUSIONS AND RECOMMENDATIONS The Project detailed in this report was divided into three main parts: (1) Development of an Extended Period Simulation (EPS) Model; (2) Case Study 1: Surface Water Optimization Source Tracing Model; and (3) Case Study 2: Aquifer Storage and Recovery (ASR) Hydraulic EPS Model. The conclusions and final recommendations reached as part of this study have been summarized below. The City’s earlier InfoWater® model was a steady state model (snapshot in time) that had some limitations. The primary limitation outlined in this report deals with absence of any SCADA controls setup in the model. While for a steady state model simulating a high demand condition, a well configuration can be decided fairly quickly (since most wells will be online), the task can get very cumbersome for an EPS model, where demands are varying throughout the simulation. Through this project, it was determined that SCADA controls that exist in the field can be entered into the InfoWater® software. However, the process requires may require much research and close communication with staff constantly dealing with water system operations. Furthermore, the task of entering cluster control data is not straightforward and requires intimate knowledge of both the distribution system, as well as the software (no support is provided for Rule Controls by 52 Innovyze, the vendor for InfoWater®). Nonetheless, once entered, the model will become more accurate in terms of simulating field conditions. The EPS model was calibrated with an overall accuracy of 10% between more than 500 measured and modeled flow and pressure data points. While the model predicted well in North Modesto, there are still model refinements necessary in the South Modesto Area. It is recommended that further updates to the model be made to include control data for the water tanks. This data should incorporate tank filling and emptying schedules, as well as low and high tank level information. In Case Study 1, the Surface Water Optimization Source Tracing Model outlined the extent of surface water delivery within the City’s distribution system. Surface water, which is conveyed through the Modesto Irrigation District (MID) transmission main was only delivered within close proximity to the mains. Other zones within the City were mainly supplied by groundwater. Since treated surface water is of higher quality and reliability, the City should optimize its use. It is highly recommended that the City reevaluate its cluster operations (including operating sequence) through the EPS model in order to determine how to best optimize surface water and still meet other important criteria, such as minimizing impacts to groundwater and minimizing energy costs related to pumping. Other tools and data available to the City, such as the future web interface that will be developed for the Well Field Optimization Project Phase II, will need to be utilized in conjunction with the EPS model while re-evaluating the well clusters. In 53 general, well clusters should be modified to shutoff more wells to allow for surface water in the needed areas within the City. The EPS model can also be used to examine well run times to ensure that minimum runtime requirements can be met during the optimization. Further effort should also be pursued to integrate the controls governing the MID Terminal Reservoirs into the cluster operating controls. This will help the City to setup an automated process to maximize surface water and thereby, execute an efficient conjunctive use program. It is recommended that the optimization process be conducted both for the existing conditions (30 MGD surface water supply) as well as the buildout condition (60 MGD surface water supply). In Case Study 2, the Aquifer Storage and Recovery (ASR) Hydraulic EPS model demonstrated that the City could supply up to 10 million gallons per day (MGD) of available excess surface water during winter conditions for an ASR program to an area immediately west of the City, near West Tank. The EPS model indicated that during summer demands, if the western portion of the City was selected for the ASR program, the City could face difficulties in extracting ASR water and supplying it to the distribution system, with the current well cluster supervisory controls in place. The obvious solution for the City will be to tailor the cluster controls to allow for ASR water supply. The evaluation in this project was only from a hydraulic distribution system standpoint and no hydrogeologic analysis was performed to confirm aquifer characteristics within the proposed location. This analysis was conducted as a 54 demonstration to the City of the nature of the future ASR Facility Layout Analysis that should be performed as part of an ASR Feasibility Study. Finally, the EPS model can be used for many other purposes that have not been discussed in this project. Examples of studies that can be conducted by the City utilizing the EPS model include water quality studies (maintaining chlorine residuals), blending studies, system vulnerability studies, and energy cost studies. All of these studies will require the City to establish protocols to keep the model updated and calibrated. Since the City collects and stores pressure and flow data periodically, it is recommended that model recalibration and update protocols be established within the City. A model re-calibration and update effort every three years is recommended to the City, unless major improvements are made to the water system sooner. It is also recommended that during such time, fire flow tests be conducted to supplement field data. Fire flow tests may be able to help the modeler refine the model for fire flow scenarios, as well as detect any valves that may be turned off within the distribution system. The model should be maintained by the in-house modeling team, which should also be responsible of the model updates and calibrations. Keeping stakeholders in mind, the model should also be presented to other staff dealing with water system planning, design and operations in order to increase their overall confidence and understanding of the capabilities of the EPS model. 55 APPENDIX A MODEL DATA ENTRY FOR WELL CLUSTER CONTROLS 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 APPENDIX B WATER PIPE GROUPING MAPS FOR CALIBRATION 86 Pipe Group 1 (AC, CI: 1980 - Present) Pipe Group 2 (AC, CI: 1940 - 1979) 87 Pipe Group 3 (AC, CI: 1939 and earlier) Pipe Group 4 (AC, CI: Year Unknown) 88 Pipe Group 5 (CL: Year Unknown) Pipe Group 6 (DI, DIP: 1980 – Present) 89 Pipe Group 7 (DI, DIP: 1940 – 1979) Pipe Group 8 (DI, DIP: 1939 and earlier) 90 Pipe Group 9 (DI, DIP: Year Unknown) Pipe Group 10 (GI: 1980 – Present) 91 Pipe Group 11 (GI: 1940 – 1979) Pipe Group 12 (GI: 1939 and earlier) 92 Pipe Group 13 (GI: Year Unknown) Pipe Group 14 (PVC: 1980 – Present) 93 Pipe Group 15 (PVC: 1940 – 1979) Pipe Group 16 (PVC: 1939 and earlier) 94 Pipe Group 17 (PVC: Year Unknown) Pipe Group 18 (Unknown Material: 1980 – Present) 95 Pipe Group 19 (Unknown Material: 1940 – 1979) Pipe Group 20 (Unknown Material: 1939 and earlier) 96 Pipe Group 21 (Unknown Material: Unknown Year) 97 APPENDIX C SURFACE WATER OPTIMIZATION SOURCE TRACING MODEL 98 99 100 101 102 103 104 105 106 107 108 109 110 111 REFERENCES American Water Works Association. (2005). Manual of Water Supply Practice– M32s, Computer Modeling of Water Distribution Systems. Denver, Colorado City of Modesto Public Works Department, West Yost Associates. (2010). 2010 Water System Engineer’s Report. Modesto, California: Author. Retrieved from http://www.modestogov.com/uppd/reports/water/eir/systemab.asp City of Modesto Public Works Department, Modesto Irrigation District, RMC. (2007). Joint Urban Water Management Plan 2005 Update. Modesto, California: Author. Retrieved from http://www.modestogov.com/pwd/docs/reports/water/uwmp/0705_MID_UWMP.pdf Innovyze, Inc. (2007). Help for Calibrator (Documentation Release 2, Build 0.08) [Computer software]. Arcadia, California. Mays, L.W., Bosserman, B., Bouchart, F., Chase, D. V., Clark, R., Geldreich, E. E., Goldman, F. E., Goulter, I., Grayman, W. M., Karney, B. W., Kirmeyer, G. J., Lansey, K., Lingireddy, S., Male, J. W., Martin, C. S., Ormsbee, L. E., Rossman, L. A., Sakarya, A, Tung, Y., Uber, J., Walski, T. M., Ysusi, M. (2000). Water Distribution System Handbook.