GLAST LAT Project March 24, 2003 GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope Tracker Subsystem WBS 4.1.4 Structural Design and Analysis Overview Erik Swensen HYTEC, Inc. Tracker Mechanical Engineer swensen@hytecinc.com HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 1 GLAST LAT Project March 24, 2003 Presentation Outline • • • • • • Design Requirements Historical Perspective Tower Structural Design Overview Material Selection & Allowables Tower Structural Analysis Overview Attachment Component Design & Analysis Overview – Flexures – Thermal Straps • Testing – Completed & In-progress tests – Scheduled tests • Open Issues HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 2 GLAST LAT Project March 24, 2003 Design Requirements: Quasi-Static Loads • Static-Equivalent Accelerations Launch Event Design Lift-Off/ 1 MECO 0.2 6.8 2 Accept3 Qual 3 Unit 3.7 6.8 4.6 8.5 g g Lateral Axial Transonic 2.34 4.43 Rot X/Y 20.2 rad/s Rot Z Scale Factor 20.2 rad/s2 2 1.25 Source (1) “Summary of the GLAST Preliminary CLA Results,” Farhad Tahmasebi, 11 Dec 2001. (2) 433-IRD-0001, “Large Area Telescope (LAT) Instrument – Spacecraft Interface Requirements Document,” May, 2002. (3) “LAT Tracker Random Vibration Test Levels,” Farhad Tahmasebi, 27 Feb 2002. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 3 GLAST LAT Project March 24, 2003 Design Requirements: Grid Motion • Tracker-to-Grid Maximum Interface Distortion – Superimposed on MECO design limit loads – NOT superimposed on vibration analysis or testing Flexure Location 0° Midside Flexure +45° Corner Flexure +90° Midside Flexure +135° Midside Flexure -180° Midside Flexure -135° Midside Flexure -90° Midside Flexure -45° Midside Flexure Displacements Radial (µm) Vertical (µm) 46 93 81 165 14 91 -60 24 -29 0 20 0 0 0 -11 13 Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 4 GLAST LAT Project March 24, 2003 Design Requirements: Flexure Loads • Corner Flexure Maximum Design Limit Loads – Maximum from two CLA cycles Load Direction Shear Tension Compression Flexure Design Limit Loads (N) 1003 1277 1277 Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. • Side Flexure Maximum Design Limit Loads – Maximum from two CLA cycles Load Direction Shear Tension Compression Flexure Design Limit Loads (N) 2266 391 391 Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 5 GLAST LAT Project March 24, 2003 Design Requirements: Sine Vibe Frequency (Hz) Acceptance Test Levels 5 to 6.2 Thrust 6.2 to 50 Lateral 5 to 50 Axis Test Levels Sweep Rate 1.27 cm (0.5 in.) double amplitude 1.0 g (zero to peak) 0.7 g (zero to peak) 4 oct/min N/A 4 oct/min Proto-Flight Qualification Test Levels 5 to 7.4 1.27 cm (0.5 in.) double amplitude Thrust 7.4 to 50 1.4 g (zero to peak) 5 to 6.2 1.27 cm (0.5 in.) double amplitude Lateral 6.2 to 50 1.0 g (zero to peak) Qualification Test Levels 5 to 7.4 1.27 cm (0.5 in.) double amplitude Thrust 7.4 to 50 1.4 g (zero to peak) 5 to 6.2 1.27 cm (0.5 in.) double amplitude Lateral 6.2 to 50 1.0 g (zero to peak) 4 oct/min 4 oct/min 2 oct/min 2 oct/min Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 6 GLAST LAT Project March 24, 2003 Design Requirements: Random Vibe • GEVS General Spec applied along all three axes independently 20 50 800 2000 Overall Frequency (Hz) 20 80 500 2000 Overall ASD Level (G2/Hz) Acceptance Qualification 0.01 0.02 0.06 0.12 0.06 0.12 0.01 0.02 8.7 Grms 12.3 Grms Revised ASD Test Level* (G2/Hz) 0.01 0.04 0.04 0.01 6.8 Grms Acceleration Spectral Density Function 1.000 Qualification Acceptance Revised RV ASD ASD (G 2/Hz) Frequency (Hz) 0.100 0.010 10 100 1000 10000 Frequency (Hz) Source: GEVS-SE Rev A, “General Environmental Verification Specification for STS & ELV Payloads, Subsystems, and Components,” June 1996, Section 2.4.2.5. * Pending approval from GSFC & SLAC program offices. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 7 GLAST LAT Project March 24, 2003 Design Requirements: Dynamic Clearance • Maintain positive clearance between adjacent TKR tower modules (tower-to-tower collisions) (Source: Tracker-LAT ICD) – Maintain minimum allocation of 1.5mm for dynamic response of towers • After fabrication/assembly tolerances, alignment, EMI shielding, static response, & thermal distortion are considered – Maximum dynamic response goal <145 µm RMS (Acceptance) • Assumes adjacent towers are out-of-phase • Maintain positive clearance between adjacent trays (tray-to-tray collisions) – Maintain minimum clearance of 2mm between adjacent trays • Silicon-to-silicon clearance – Minimum frequency goal of 500 Hz • Fixed base boundary conditions at tray attachment locations • Assumes adjacent trays are out-of-phase HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 8 GLAST LAT Project March 24, 2003 Design Requirements: Temperature • Tracker Temperature Requirements – Maximum heat load = 8.7W – Maximum Temperature @ top of tower module = 30°C • Tracker-to-Grid Interface Temperatures State Qualification Acceptance Test Operating Low Temp Limits (°C) -30 -20 -15 High Temp Limits +50 +30 +30 Survival (°C) Low = -30 High = +50 N/A Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 9 GLAST LAT Project March 24, 2003 Additional Requirements • Stay Clear Dimensions (Source: Tracker-LAT ICD) – Straightness ≤ 300 µm from top to bottom – Maximum outside dimensions (x & y) ≤ 371.7 mm – Maximum height ≤ 640 mm above grid surface • Launch Pressure (Source: LAT Environmental Specification) – Shall survive the time rate of change of pressure per the Delta II Payload Planner’s Guide, Section 4.2.1, Figure 4.2. – Extreme pressure conditions are experienced in the first 70 sec of fairing venting. • Venting (Source: Tracker-LAT ICD) – Sufficient venting of all TKR components is required to allow trapped gasses to release during launch. • EMI Shielding (Source: Tracker-LAT ICD) – Each TKR tower shall be covered on all 6 sides by at least 50 µm of aluminum electrically connected to the Grid. HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 10 GLAST LAT Project March 24, 2003 Historical Perspective • Build-Test-Build Design Approach – Limited schedule and budget to do all the analysis and material testing judged necessary – Tracker Tower ’01 Prototype was viewed as an engineering evaluation model to reduce risk to the E/M Tower Testing • Identify weaknesses in design early to allow for modifications • Compressed schedule after E/M testing made it crucial to insure against failures at that juncture HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 11 GLAST LAT Project March 24, 2003 Hist Persp: Mechanical Prototypes • Full-scale tray prototypes – 14+ trays total (3 top/bottom, 7 thinconverter, 4 thick-converter) • Full-scale tower prototype – 10 composite trays w/ silicon payload – 9 aluminum mass mockups – YS-90A Sidewalls • Prototype Tower Function – Test component fabrication/assembly procedures – Test tray assembly tooling – Test tower assembly procedures – Validation of finite element models – Test to environmental requirements at the tray and tower level – Reduce risk to E/M by identifying weaknesses at prototype level HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 12 GLAST LAT Project March 24, 2003 Hist Persp: Random Vibration Testing • Qualification level random vibration testing performed along the lateral and thrust axes to GEVS general specification • Failures during 1st RV test – Thermal gasket plastically deformed @ -12dB • Loss of thermal interface – Loss of preload in sidewall fasteners • @ 0dB in thrust direction • @ -3dB in lateral direction – Hairline fracture identified in one corner after 0dB lateral test • Prototype activities have a silver lining – No evidence of structural damage @ -6dB (1.25dB below proposed spec) – Established manufacturing and assembly procedures for flight articles – Minimizes risk of E/M tower by exposing weaknesses early HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 13 GLAST LAT Project March 24, 2003 Tracker Tower Mechanical Configuration • 5 Tray configurations supported by Thermal/Mechanical sidewalls • 16 Towers separated by 2.5mm Thermal/Mechanical Sidewalls (4) Top Tray (1) {Not Shown for Clarity} Thin-Converter Trays (11) Thick-Converter Trays (4) Standard Trays, No Converter (2) Bottom Tray (1) Thermal Straps - Copper (4) HPS-102090-0002 Tower-to-Grid Flexure Attachment (8) Tracker Peer Review, WBS 4.1.4 Section 2-D 14 GLAST LAT Project March 24, 2003 Tracker Tower Configuration • Full coverage Gr/CE tower sidewalls used for heat removal, stiffness, EMI shielding • Radial blade flexure configuration for CTE mismatch with the Al grid • Copper heat straps to conduct heat away from the tower and into the grid HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 15 GLAST LAT Project March 24, 2003 Thermal/Mechanical Sidewalls • Laminate Design – [0/90fabric, 0, 157.5, 22.5, 45, 90, 135|s – 50 µm Aluminum layer for EMI shielding on outer surface • Material – Baseline @ PDR was YS-90A/RS-3 – Changed to K13D2U/RS-3 for improved thermal performance Sidewall Outside Surface • Function – Heat transfer: conduct tray heat to bottom tray and grid – Stiffness: support individual trays, transfer load to bottom tray • K13D2U material testing – Material order is in-progress – Expected completion by June ‘03 Sidewall Inside Surface HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 16 GLAST LAT Project March 24, 2003 Sidewall Mounting • All trays except bottom tray attachment – M2.5, CRES A286 fasteners – NO metallic inserts in sidewall • Bottom tray attachment – M2.5 & M4, CRES A286 fasteners – Metallic top-hat design inserts in sidewall M4 View of Bottom Tray Sidewall Inserts M4 Bottom Sidewall Section M4 (M2.5 fasteners unless marked otherwise) HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 17 GLAST LAT Project March 24, 2003 Tray Sandwich Structure • Lightweight 4 piece machined closeout frame, bonded to face sheets and core to form a sandwich structure Gr/CE Face Sheet C-C Structural Closeout Wall Thermal Boss 1 lb/ft3 Aluminum Honeycomb Core HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D C-C MCM Closeout Wall 18 GLAST LAT Project March 24, 2003 Tray Configurations • Thin-Converter and No-Converter trays are structurally identical – Machined C-C closeout walls – 1 lb/ft3 core – Two 4-ply facesheets • Balanced about the tray neutral axis • Top tray uses a modified C-C closeout – Machined C-C closeout walls – 1 lb/ft3 core, ¾ thickness – Two 4-ply facesheets • Thick-Converter Trays use the same C-C closeout – Machined C-C closeout – 3 lb/ft3 core – Two 6-ply quasi-isotropic facesheets HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D Thin-Converter Tray Prototype Top Tray Prototype 19 GLAST LAT Project March 24, 2003 Machined Closeout Wall Prototypes • Closeout frame is machined from 3D C-C material into the net shape • Metallic inserts are bonded in frame for sidewall fasteners • The frame is bonded in the four corners and mechanically connected using a mortise and tenon joint Outside Outside Inside Inside MCM Closeout Wall HPS-102090-0002 Structural Closeout Wall Tracker Peer Review, WBS 4.1.4 Section 2-D 20 GLAST LAT Project March 24, 2003 Tracker Tray with Payload • Tray payload is bonded to the sandwich structure using epoxy, with the exception of silicone used to bond SSD’s – Silicone decouples the thermal/mechanical effects from the tray SSD’s BiasCircuit Structural Tray Converter Foils BiasCircuit SSD’s HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D TMCM 21 GLAST LAT Project March 24, 2003 Top Tray Configuration • Uses same materials as the thinconverter trays • ¾ thick honeycomb core vs. thinconverter trays Top View (illustration of lifting features) SSD’s Converter Foils Gr/CE Facesheet BiasCircuit 1 lb/ft3 Aluminum Honeycomb Core C-C Closeout Frame TMCM HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 22 GLAST LAT Project March 24, 2003 Bottom Tray Sandwich Structure • Lightweight 4 piece C-C & M55J machined closeout frame, bonded to face sheets and core to form a sandwich structure 3 lb/ft3 Aluminum Honeycomb Core 6-Ply Gr/CE Face Sheet Structural Closeout Wall Thermal Boss Titanium Corner Reinforcement HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D MCM Closeout Wall 23 GLAST LAT Project March 24, 2003 Bottom Tray Closeout Walls • Bonded M55J/RS-3 internal frame for strength and stiffness • Machined C-C outside laminate for thermal transfer of MCM heat M55J/RS-3 Internal Frame C-C Outside Laminate MCM Closeout Wall Typical Closeout Wall Cross-Section (not to scale) Structural Closeout Wall HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 24 GLAST LAT Project March 24, 2003 Corner Joint Details Pins (Reinforce Butt-Joint) Sandwich Structure w/ Reinforcement Brackets (Typ, 4 places) MCM Closeout Wall Bonded Butt-Joint Corner Reinforcement Bracket (Bonded) Structural Closeout Wall HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 25 GLAST LAT Project March 24, 2003 Corner Reinforcement Bracket • Machined Titanium Reinforcement Bracket – Strength & Stiffness Sandwich Structure w/ Reinforcement Brackets (Typ, 4 places) Typical Machined Taper (Reduce Peel Stress) Corner Block (Shear Reinforcement) Slots for M55J Closeouts (Bonded Interface) Inside View of Corner Reinforcement Bracket HPS-102090-0002 Corner Flexure Mounting Slot (Press Fit, 2 Pins, 1 Fastener) Tracker Peer Review, WBS 4.1.4 Section 2-D 26 GLAST LAT Project March 24, 2003 Bottom Tray with Payload • • Payload attached to top side only Tray payload is bonded to the sandwich structure using epoxy, with the exception of silicone used to bond SSD’s – Silicone decouples the thermal/mechanical effects from the tray below SSD’s Bias-Circuit Structural Tray HPS-102090-0002 TMCM Tracker Peer Review, WBS 4.1.4 Section 2-D 27 GLAST LAT Project March 24, 2003 Mat’l Selection: Structural/Thermal Component Material Tray Sandwich Structure Facesheets Honeycomb Core Closeout Walls (All) Closeout Walls (Bottom Only) Corner Brackets (Bottom Only) Metallic Inserts Pins (Bottom Only) Structural Adhesives YSH-50/RS-3 3 3 1 lb/ft & 3 lb/ft 5056 Aluminum 3D Carbon-Carbon M55J/RS-3 6AL-4V Titanium (Annealed) 7075-T76 Aluminum 304 Stainless HYSOL EA-934NA HYSOL EA-9394 Redux 312 UL Thermal/Mechanical Sidewalls Gr/Ce Fabric Plies YS-90A/RS-3 Gr/Ce Unidirectional Plies K13D2U/RS-3 EMI Shielding 5056 Aluminum Foil EMI Tape 3M-1170 Tape Conductive Paint Lord Z307 Metallic Inserts 7075-T76 Aluminum Adhesive CYTEC/Fiberite FM 73M Tower Flexures 6AL-4V Titanium (STA) Heat Straps H04 Copper (w/ nickle plating) Fasteners Cres-A286 Steel Pins 304 SST HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 28 GLAST LAT Project March 24, 2003 Material Allowables: Stresses Material Stress Direction Ult Material Allowable (MPa) Ult Material Allowable Method of Verification (ksi) Tray Sandwich Structure Assemblies 3D Carbon - Carbon YS-50/RS-3 (4 Ply) YS-50/RS-3 (6 Ply) Alum H/C Core 1.0 PCF Alum H/C Core 3.0 PCF 3D M55J/RS-3 (Quasi-Iso Layup) HPS-102090-0002 x 69.0 10.0 B Basis Test Data- Compr y 54.5 7.9 B Basis Test Data- Compr z 10.3 1.5 B Basis Test Data xy 52.1 7.6 B Basis Test Data zx 25.2 3.7 B Basis Test Data yz 13.9 2.0 Stress Direction Material Ult Material Allowable (MPa) Ult Material Allowable Method of Verification (ksi) Tray Sandwich Structure Assemblies (Cont) tu 896.6 130.0 MIL-HDBK-5H ty 827.6 120.0 MIL-HDBK-5H u 544.8 79.0 MIL-HDBK-5H tu 496.6 72.0 MIL-HDBK-5H ty 427.6 62.0 MIL-HDBK-5H B Basis Test Data u 289.7 42.0 MIL-HDBK-5H Thermal/Mechanical Sidewalls x 206.0 29.9 Test Data & Comp Analysis y 206.0 29.9 Test Data & Comp Analysis xy 155.0 22.5 Test Data & Comp Analysis Titanium 6AL-4V (Annealed) Aluminum 7075-T76 YS-90A/RS-3 x 206.0 29.9 Test Data & Comp Analysis y 304.0 44.1 Test Data & Comp Analysis xy 178.0 25.8 Test Data & Comp Analysis compr 0.241 0.035 Hexcel TSB 120 zx 0.310 0.045 Hexcel TSB 120 yz 0.172 0.025 Hexcel TSB 120 compr 1.793 0.260 Hexcel TSB 120 zx 1.379 0.200 Hexcel TSB 120 yz 0.759 0.110 Hexcel TSB 120 K13D2U/RS-3 x 196.4 28.5 Test Data & Comp Analysis y 122.0 17.7 Test Data & Comp Analysis x 196.4 28.5 YS-90A Data (need confirmation) y 122.0 17.7 YS-90A Data (need confirmation) Tower Assembly Copper UNS C10100 ;H04 Temper - (Thermal Strap) Titanium 6AL-4V (STA) (Base Flexures) tu 344.8 50.0 Common Vendor data ty 310.3 45.0 Common Vendor Data u 195.2 28.3 Common Vendor Data tu 1103.4 160.0 MIL-HDBK-5H ty 1034.5 150.0 MIL-HDBK-5H u 689.7 100.0 MIL-HDBK-5H bond 21.4 3.1 Hysol Product Data fw 20.7 3.0 Hysol Product Data bond 29.0 4.2 Hysol Product Data x 332.1 48.2 80% of Vendor Data - compr y 332.1 48.2 80% of Vendor Data - compr z 14.7 2.1 80% of Vendor Data - FW tension xy 187.0 27.1 80% of Vendor Data fw 20.7 3.0 Hysol Product Data zx 52.4 7.6 80% of Vendor Data bond 35.2 5.1 CYTEC/Fiberite Product Data yz 52.4 fw 20.7 3.0 Used EA9394 data HYSOL 934NA Adhesive HYSOL 9394 Adhesive CYTEC FM73 Film Adhesive 7.6 80% of Vendor Data Tracker Peer Review, WBS 4.1.4 Section 2-D 29 GLAST LAT Project March 24, 2003 Material Allowables: Forces Material Force Direction FUlt Material FUlt Material Allowable Allowable Method of Verification (N) (lbf) Bolt/Insert Attachments 2.5mm Sidewall No Insert 2.5mm Sidewall w/Insert 4mm Sidewall w/Insert 2.5mm CC w/Insert 2.5mm CC/M55J w/Insert 4mm CC/M55J w/Insert 1.6mm Screw (MCM Board) 2.5mm Screw (Countersunk) 4mm Screw (Countersunk) 4mm Screw (Cap Hd) HPS-102090-0002 Fs Fs// Faxial Fs Fs// Faxial Fs Fs// Faxial Fs Fs// Faxial Fs Fs// Faxial Fs Fs// Faxial 1231 277 B Basis Test Data - YS90 1260 284 B Basis Test Data - YS90 504 113 B Basis Test Data - YS90 1556 350 B Basis Test Data - YS90 1454 327 B Basis Test Data - YS90 656 148 B Basis Test Data - YS90 3073 691 B Basis Test Data - YS90 2764 622 B Basis Test Data - YS90 504 113 based on 2.5mm data 449 101 B Basis Test Data - YS90 449 101 based on perp. Data 1182 266 80% of min 1221 275 analysis w/1.25 FS 1221 275 based on perp. Data 1182 266 from CC insert data 1360 306 from CC Test Data 1360 306 based on perp. Data 1182 266 use 2.5mm Test data Ft 272 61 Test Data - 80% of min Ft Fs Ft Fs Ft Fs 2979 670 Analysis & MIL-HDBK-5H 920 207 Analysis & MIL-HDBK-5H 5800 1305 Analysis & MIL-HDBK-5H 2642 594 Analysis & MIL-HDBK-5H 7832 1762 Analysis & MIL-HDBK-5H 3925 883 Analysis & MIL-HDBK-5H Tracker Peer Review, WBS 4.1.4 Section 2-D 30 GLAST LAT Project March 24, 2003 Analysis FS & MS Requirements • Factors-of-Safety on static loads/stresses – Factors-of-Safety to Yield = 1.25 – Factors-of-Safety to Ultimate = 1.4 • Factors-of-Safety on random vibration loads/stresses – Factors-of-Safety to Yield = 1.00 – Factors-of-Safety to Ultimate = 1.12 – Lower Factors-of-Safety on RV vs Static • 3σ on GEVS general spec is conservative • Used lower damping (Q = 10) vs test results indicate (Q ~7) – Higher amplification of tower response → higher loads/stresses • Margins-of-Safety – Margin-of-Safety Equation = Sallowable/(FS * Smax) – 1 – All Margins must be above 0.00 Reference: NASA-STD-5001 HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 31 GLAST LAT Project March 24, 2003 Tower Finite Element Modeling Element/Node Count Number Number Number Number Number Number of of of of of of Grids = BAR Elements = Spring Elements = Solid Elements = Plate Elements = Rigid Elements = 227653 1038 63316 120628 56442 219 Mass Properties of FEM Mass = 32.48 kg Center of Gravity Location: Xcg = -1.06E-5 m Ycg = -4.26E-7 m Zcg = 0.2623 m HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 32 GLAST LAT Project March 24, 2003 Tower Finite Element Modeling (Con’t) Model Checks • Free-Free Modal and Rigid Body checks were run on the stiffness matrix • No model grounding or ill-conditioning of the stiffness matrix HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 33 GLAST LAT Project March 24, 2003 “CLA” Finite Element Model • Reduced model delivered to SLAC early March ‘03 Element/Node Count Number Number Number Number Number Number of of of of of of Grid Points = BAR Elements = Spring Elements = Mass Elements = Plate Elements = Rigid Elements = 991 740 48 8 644 24 Mass Properties Mass = 32.50 kg Center of Gravity Location: Xcg = 4.4E-8 m Ycg = 3.9E-8 m Zcg = 0.26 m HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 34 GLAST LAT Project March 24, 2003 Tower Modal Analysis 1st Bending Mode - Y Direction – 182.1 Hz HPS-102090-0002 2nd Bending Mode - X Direction – 183.6 Hz Tracker Peer Review, WBS 4.1.4 Section 2-D 35 GLAST LAT Project March 24, 2003 Tower Modal Analysis (Con’t) 1st Axial Mode - Z Direction – 379.0 Hz HPS-102090-0002 1st Torsional Mode - About Z – 461.8 Hz Tracker Peer Review, WBS 4.1.4 Section 2-D 36 GLAST LAT Project March 24, 2003 Tower RV Analysis: Accelerations • Equivalent quasi-static accelerations from random vibration input Vibration Direction Input Levels 1 Sigma Response at CG 3 Sigma Response at CG Accept. Qual Accept. Qual Accept. Qual Lateral X 8.6 12.3 11.1 15.7 33.2 47.0 Lateral Y 8.6 12.3 11.2 15.8 33.5 47.3 44.4 63.0 Axial Z 8.6 12.3 14.8 21.0 * Note: Values used in quasi-static analysis and static proof tests 19th Tray Response Grms 10th Tray Response 35 30 Accept. 25 Qual 20 15 10 5 0 Bottom Tray Response HPS-102090-0002 0 0.15 0.3 0.45 0.6 Response location from Bottom (m ) Tracker Peer Review, WBS 4.1.4 Section 2-D 37 GLAST LAT Project March 24, 2003 Tower RV Analysis: RMS Displacements Displacement Direction (µm) Y Z RV in X (1RMS) 117 1 25 RV in Y (1RMS) 1 118 24 RV in Z (1RMS) 4 1 17 0.24 0.23 4.86 Min M.S. • Maximum RMS Response to Acceptance Level RV Input • Min MS is +0.23 Lateral Response to Lateral Y Input (Q = 10) 100.000 Qual Base Input 12.3 Grms Qual. Tip Response 31.3 Grms Acceptance Base Input 8.7 Grms 10.000 Accept. Tip Response 22.1 Grms "Revised" Base Input 6.8 Grms "Revised" Tip Response 17.8 Grms Acceleration (G^2/Hz) X 1.000 0.100 0.010 0.001 10.0 100.0 1000.0 Frequency (Hz) HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 38 GLAST LAT Project March 24, 2003 Tray Finite Element Modeling • Tray FE models were constructed for all five tray types • Modal and random vibration analysis performed • Results are summarized in HTN102070-0005 Detailed HYTEC Tray FEM (Top, Thin-, No-Converter) Detailed INFN Tray FEM (Thick-Converter) HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 39 GLAST LAT Project March 24, 2003 FE Modal Analysis Results Tray Description Top Tray Thin-Converter Tray Thick-Converter Tray No-Converter Tray Bottom Tray Frequencies (Hz) Without Payload With Payload Stiffness Effects Stiffness Effects 569 584 N/A 718 767 673 711 518 764 788 • Fixed Base Boundary Conditions – Simply supported at sidewall attachment locations • Payload stiffness effects include Tungsten and bias-circuits – Silicon applied as mass only Typical 1st Mode Shape of the Thin-Converter Tray HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 40 GLAST LAT Project March 24, 2003 Bottom Tray Finite Element Modeling • Fidelity of FEM is sufficient to calculate stresses • Analysis in tower configuration • Static analysis to estimate stresses during design phase – Equivalent static accelerations calculated to simulate 3σ random vibe environment • Random Vibe Analysis to calculated RMS stresses to finalize design HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 41 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Design Limit Loads • Liftoff & Transonic Minimum Margin-of-Safety – Minimum Margins & Failure are shown MS= 9.95 Ply Failure MS= 10.38 Core Crush MS= 10.77 Ply Failure MS= 7.18 M55J Flatwise Tension MS= 7.32 Ti Ftg Bond Shear MS= 7.21 M2.5 Bolt Shear HPS-102090-0002 MS= 5.20 M4 Bolt Shear Tracker Peer Review, WBS 4.1.4 Section 2-D Tension Zero Compression 42 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Design Limit Loads • Main Engine Cut-Off (MECO) Minimum Margin-of-Safety – Minimum Margins & Failure are shown – Grid Distortion included MS= 3.28 Ply Failure MS= 2.78 Core Crush MS= 3.59 Ply Failure MS= 1.41 M55J Flatwise Tension MS= 6.12 M2.5 Bolt Shear MS= 2.64 Ti Ftg Bond Shear Tension MS= 6.13 C-C Flatwise Tension HPS-102090-0002 MS= 3.45 M4 Bolt Shear Tracker Peer Review, WBS 4.1.4 Section 2-D Zero Compression 43 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Random Vibrations • RMS stresses calculated from random vibration analysis – 3σ stresses used in margin calculation • Sandwich structure Minimum Margin-of-Safety shown MS= 1.13 [RV in X] Ply Failure MS= 1.36 [RV in X] Ply Failure MS= 0.84 [RV in X] Core Crush Tension Zero Compression HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 44 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Random Vibrations • RMS stresses calculated from random vibration analysis – 3σ stresses used in margin calculation • M55J/RS-3 Closeout Frame Minimum Margin-of-Safety shown MS= 1.40 [RV in Y] M55J IL Shear MS= .40 [RV in X] Flatwise Tensile MS= 2.44 [RV in Y] M55J Ply Failure Tension Zero Compression HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 45 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Random Vibrations • RMS stresses calculated from random vibration analysis – 3σ stresses used in margin calculation • C-C Closeout Frame Minimum Margin-of-Safety shown MS= .47 [RV in X] C-C IL Shear (Near Bolt) MS= 1.65 [RV in Y] C-C IL Shear (Boss transition) Tension Zero Compression HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 46 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Random Vibrations • RMS stresses calculated from random vibration analysis – 3σ stresses used in margin calculation • Closeout Frame Assy Minimum Margin-of-Safety shown MS= .51 [RV in X] Ti Ftg Bond Shear MS= .34 [RV in Y] M2.5 Bolt Shear HPS-102090-0002 MS= 2.18 [RV in X] M55J to CC Bond Shear MS= .54 [RV in Y] Flexure Bond Shear Tracker Peer Review, WBS 4.1.4 Section 2-D Tension Zero Compression 47 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Random Vibrations • RMS stresses calculated from random vibration analysis – 3σ stresses used in margin calculation • Ti Corner Bracket Minimum Margin-of-Safety shown MS= 3.40 Max VM Stress [RV in Y] Tension Zero Compression HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 48 GLAST LAT Project March 24, 2003 Side Wall Margins of Safety • Insert MS is calculated using the interaction of the vertical and lateral loads M4 Side Wall Insert Shearout Load Case Min MS L/O 5.20 MECO 2.18 RV in Y 0.04 Side Wall Ply Failure MS= .40 M4 Side Wall Insert Shear [RV in X] Load Case Min MS L/O 1.70 MECO 1.02 RV 1.56 Tension Basic Interaction Eqn: MS = 1/sqrt[Rx^2+Ry^2] –1 (Where: Rx = σx/ σallowable) HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D Zero Compression 49 GLAST LAT Project March 24, 2003 Tray’s 2-19 Minimum Margins M2.5 C-C Shearout Load Case M2.5 C-C Shearout Min MS Load Case Min MS L/O 13.09 L/O 14.12 MECO 9.67 MECO 10.43 Random Vibe (X) 1.49 Random Vibe (Y) 1.20 C-C Section Stress w/SC Factor of 2.0 Load Case M2.5 C-C Shearout Load Case Min MS Min MS L/O 8.25 L/O 33.01 MECO 2.59 MECO 12.38 Random Vibe (Y) 0.26 Random Vibe (Z) 0.87 Tension (Bottom Tray Not Shown) HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D Zero Compression 50 GLAST LAT Project March 24, 2003 Bottom Tray Margins: Revised RV Spec • Lowered Max Lateral Equiv. Static G’s from 47.3 to 27.0 – Minimum Margins & Failure are shown MS= 2.74 Ply Failure MS= 2.21 Core Crush MS= 3.14 Ply Failure MS= 1.46 M55J Flatwise Tension MS= 1.12 Ti Ftg Bond Tensile MS= 1.35 M2.5 Bolt Shear HPS-102090-0002 MS= 0.83 M4 Sidewall Insert Shearout Tracker Peer Review, WBS 4.1.4 Section 2-D Tension Zero Compression 51 GLAST LAT Project March 24, 2003 TKR Tower Margin-of-Safety Summary • Liftoff-and-Transonic – Minimum Margin-of-Safety is +1.70 • Sidewall ply failure • MECO + Grid Distortion – Minimum Margin-of-Safety is +1.02 • Sidewall ply failure • Random Vibration – Minimum Margin-of-Safety in X is +0.40 • M4 Side Wall Corner Insert Shearout – Minimum Margin-of-Safety in Y is +0.04 • M4 Side Wall Corner Insert Shearout – Minimum Margin-of-Safety in Z is +1.37 • M4 Side Wall Corner Insert Shearout • ALL Margins-of-Safety Meet Requirement (>0.00) HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 52 GLAST LAT Project March 24, 2003 Flexure-to-Grid Attachment Configuration • • 8-Blade Configuration – 4 blades in each corner – 4 blades along each side Allow radial distortion of grid due to thermal input HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 53 GLAST LAT Project March 24, 2003 Titanium Flexures • • • Material – 6Al-4V Titanium STA Tapered 3-Blade Design – Minimize length/maximize stiffness Center Stiffener to increase critical buckling 3-Blade Design (High Shear Strength, Maximize Axial Stiffness) Side Flexure Thick Center Section (Increase Euler Buckling) Tapered Blade (High Shear Strength, Minimum Normal Stiffness) Typical Blade Features HPS-102090-0002 Corner Flexure Tracker Peer Review, WBS 4.1.4 Section 2-D 54 GLAST LAT Project March 24, 2003 Flexure Finite Element Modeling • Detailed finite element model of each flexure type was constructed – Evaluated loads equivalent to 47.3 G’s lateral and 63 G’s vertical Corner Flexure FEM Side Flexure FEM HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 55 GLAST LAT Project March 24, 2003 Corner Flexure Margins Load Case Interface Design Loads Liftoff & Transonic MECO + Grid Distortion Random Vibration Loads Thermal Distortion (CTE Mismatch w/ Grid) Margin-of-Safety Ultimate Yield 0.83 0.92 2.16 2.32 1.86 2.00 0.29 0.35 1.13 von Mises Stresses from Shear Load 1.24 Note: All Margin calculations include fabrication tolerances von Mises Stresses from Normal Load Von Mises Stresses High Medium Low HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 56 GLAST LAT Project March 24, 2003 Side Flexure Margins Load Case Interface Design Loads Liftoff & Transonic MECO + Grid Distortion Random Vibration Loads Thermal Distortion (CTE Mismatch w/ Grid) Margin-of-Safety Ultimate Yield 0.77 0.86 1.84 1.98 1.89 2.04 0.41 0.48 1.01 von Mises Stresses from Shear Load 1.12 Note: All Margin calculations include fabrication tolerances von Mises Stresses from Normal Load Von Mises Stresses High Medium Low HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 57 GLAST LAT Project March 24, 2003 Heat Strap-to-Grid Attachment Configuration • 4-Strap Configuration – Sandwiched between the thermal boss and sidewall – RTV adhesive to improve heat transfer between interfaces (TKR side only) – Bolted interface w/ pressure plate (not shown) for dry interface HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 58 GLAST LAT Project March 24, 2003 Heat Strap Design Angle in Section Reduces Stiffness Slots in Section Reduces Stiffness Cross-Section Stress Relief (Holes) Illustration of Copper Layers Pressure Plate (Grid Interface) HPS-102090-0002 4 Stacked Cu Foils t = 0.2 mm each t = 0.8 mm total (Reduce Stress) Tracker Peer Review, WBS 4.1.4 Section 2-D 59 GLAST LAT Project March 24, 2003 Heat Strap Analysis: Stress Analysis • Maximum load case is the lateral random vibration – Shear deformation shown below • Minimum Margin-of-Safety is +0.52 Von Mises Stresses High Medium Low HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 60 GLAST LAT Project March 24, 2003 Testing • Mechanical testing of materials/joints – Composite material testing • Closeouts, facesheets, sidewalls, sandwich structure – Joints • M2.5 & M4 inserts in sidewall and closeouts – Bonding • Facesheets-to-closeout, corner joints • Thermal testing of materials/joints – Conductivity testing of composite materials • CTE mismatch testing: – Si detector bonding to composite sandwich structure – Bottom tray-to-grid attachment configuration • Venting of trays: Verify acceptable venting under vacuum • Modal Testing: Thin- & thick-converter tray modal survey • Random Vibration Testing: TKR tower ’01 prototype HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 61 GLAST LAT Project March 24, 2003 Tray Vibration Testing • Thin-Converter Tray Vibration Test – Performed in Albuquerque, NM – Fixed boundary conditions at Sidewall attachment locations – Modal survey in Thrust direction – Random vibration test to GEVS general spec @ qualification level • HPS-102090-0002 Conclusions – Measured 710 Hz fundamental frequency vs. 711 Hz FEA – No indication of damage after qualification level (0dB) RV test – No indication of Carbon dusting after test Tracker Peer Review, WBS 4.1.4 Section 2-D 62 GLAST LAT Project March 24, 2003 Tray Vibration Testing (Con’t) • Thick-Converter Tray Vibration Test – Performed in Milan, Italy – Fixed boundary conditions at Sidewall attachment locations – Modal survey in Thrust direction – Random vibration test to GEVS general spec @ qualification level • HPS-102090-0002 Conclusions – Measured 580 Hz fundamental frequency vs. 518 Hz FEA – No indication of damage after qualification level (0dB) RV test Tracker Peer Review, WBS 4.1.4 Section 2-D 63 GLAST LAT Project March 24, 2003 Static Proof Test of Bottom Tray Interface • • • • Validate bottom tray and flexure design with static proof test in the lateral and vertical direction, scheduled for May ‘03 – Proof test to ±110% of Max expected load (GEVS qualification level RV equivalent static load) • 47.3 g’s in lateral direction • 63.0 g’s in thrust direction Two bottom trays will be tested – 1 will be used in E/M RV test – 1 will be tested to failure 2nd tray included in test Static test goals – Measure interface stiffness – Proof test E/M bottom tray – Verify capability of bottom tray design – Verify flexure and heat strap design HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D {Sidewall not shown for clarity} 64 GLAST LAT Project March 24, 2003 Bottom Tray Test Configuration C.G. Reaction Point Tower Simulator Flight Equivalent Sidewalls (K13D2U/RS-3) Tray #2 Bottom Tray Heat Straps Flexures Grid Simulator Base Reaction Frame HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 65 GLAST LAT Project March 24, 2003 Lateral Test Configuration Base Reaction into Granite Table Load Cell {Not Shown} Spring Assembly Reaction Frame {Outer Plate Not Shown} HPS-102090-0002 Reaction Shaft/Nut Tracker Peer Review, WBS 4.1.4 Section 2-D Displacement Probes 66 GLAST LAT Project March 24, 2003 Vertical Test Configuration Base Reaction into Granite Table Reaction Shaft/Nut {Not Shown} Spring Assembly Reaction Frame Load Cell HPS-102090-0002 Displacement Probes Tracker Peer Review, WBS 4.1.4 Section 2-D 67 GLAST LAT Project March 24, 2003 E/M Testing • E/M prototype trays are being fabricated – E/M bottom tray is scheduled for delivery to INFN in June ’03 – Testing scheduled to begin at the end of June ’03 HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 68 GLAST LAT Project March 24, 2003 Open Issues • Need confirmation of material/joint allowables – C-C & M55J material testing is not complete • Completion by Instrument CDR – M2.5 & M4 bottom tray joint testing is not complete • Completion by Instrument CDR – K13D2U/RS-3 Sidewall testing is not complete • Completion by TBD • Static proof testing will be completed after Instrument CDR – Scheduled for May/June ‘03 HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 69 GLAST LAT Project March 24, 2003 Backup Slides HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D 70 GLAST LAT Project March 24, 2003 Thermal Distortion Ma T = 2°C T = 5°C [x=0 → T=2; x=h → T=0] [x=0 → T=5; x=h → T=0] CTE (ppm/°C) P'x (mm) P'z (mm) Q'x (mm) P'x (mm) P'z (mm) Q'x (mm) Aluminum 23.6 23.1 29.3 32.4 57.7 73.2 80.9 Beryllium 11.3 11.1 14.0 15.5 27.6 35.0 38.7 Gr-CE Composite z: -1.5 x: -0.5 -1.5 -1.9 -1.8 -3.7 -4.7 -4.4 CC Composite z: -1.5 x: -1.2 -1.5 -1.9 -2.2 -3.7 -4.7 -5.5 terial z • Pre-PDR Thermal Distortion analysis • Thermal Distortion of tower considered benign w/ Gr/CE structural materials • Thermal Distortion of grid is not – grid design responsibility P' P Q Q' T HPS-102090-0002 Tracker Peer Review, WBS 4.1.4 Section 2-D x 71