GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Mechanical Design Integration Peer Review, March 2003 2. System Engineering Martin Nordby nordby@slac.stanford.edu 24 March 2003 rev 3 LAT-PR-01278 Section 2 2-1 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 2. System Engineering • • • • • Action items from PDR and Delta PDR Requirements & specifications – Requirements flow-down – Requirements list showing key requirements Interface control – List of all interfaces and status – Major trades in support of interface finalization – Documentation status, open issues/TBX’s and closure plans Technical budget allocation updates – Technical budgets (mass, volume, power/thermal) – Allocation flow down to subsystems Parts and materials – Parts, material, and process list status – Pending issues LAT-PR-01278 Section 2 2-2 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 PDR Action Items • • • 23 action items were assigned to Mechanical Systems at the January PDR All have been addressed, and submitted for closure Actions grouped into 5 classes – Thermal Design: re-evaluate thermal interface requirements and re-design thermal system accordingly – Structural Design: use positive shear restraint, when possible, at all key interfaces – Fabrication and Integration: evaluate integration contingency and costs – Environmental Testing: amplify test plans – Risk: mitigate and manage development and fabrication risks LAT-PR-01278 Section 2 2-3 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 PDR Action Items (cont 1) • Thermal Design: Re-evaluate thermal interface requirements and re-design thermal system accordingly – System-level trades have been accomplished with GLAST Mission input – External interface definition has been improved: LAT IRD updated with significant additions. Optical properties of viewable SC surfaces have been bounded. – Switched radiator coating to 0.25 mm FOSR, with emissivity = 0.85 (6% improvement) – Sensitivity studies of key LAT internal interfaces has been completed and interface designs modified as needed (TKR/Grid, E-Box/X-LAT are two examples) – Re-packaging of Radiators has been completed for Delta PDR and updated with Spectrum involvement – Responsibilities clarified: LAT is now responsible for survival heater control. All survival heater control is passive, including anti-freeze heaters on the VCHP’s. – Added anti-freeze heaters to VCHP’s (power included in survival budget – LAT attitude has been double-checked: for 0 < beta < 52 degrees, beta = 0 is the LAT hotcase orientation LAT-PR-01278 Section 2 2-4 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 PDR Action Items (cont 2) • • • Structural Design: use positive shear restrain, when possible, at all key interfaces – Positive shear restraint in the form of pins, shoulder bolts, and lap joints are being used at all critical interfaces in the LAT except the CAL-Grid interface, where additional shear restraint is needed. At this location bolt pre-load and friction are being used. Fabrication and Integration: evaluate integration contingency and costs – An impact assessment has been made of replacing a TKR module. Environmental Testing: Amplify test plans – LAT Verification Plan has been greatly amplified and released • • Strength qualification plans included Sine test philosophy is included – – • Added Grid Box thermal-vacuum testing to the Mechanical Systems Test Plan and matrix Preliminary analysis of cool-down times for thermal-vacuum cycling have been completed. – Subsystem and LAT test temperature have been established, and are collected in LAT-SS00778, “LAT Environmental Specification.” Risk: Mitigate and manage development and fabrication risks – The LM heat pipe facility has been returned to the Sunnyvale plant and was certified in December 2003. – Six-month schedule extension has reduced schedule risk associated with cost-driven late fabrication of Radiators – A Delta-PDR for Mechanical Systems was successfully held in July, 2002. – LAT program risk management has been fully re-vamped, and all Mechanical Systems risks are continuously updated and action plans evaluated. LAT-PR-01278 Section 2 2-5 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Delta PDR Action Items • • • 19 action items were assigned to Mechanical Systems at the July Delta-PDR All have been addressed and submitted for closure Actions are grouped into 5 classes – Thermal Design: Investigate off-design thermal cases and impact of trades on parallel heat transfer paths within the LAT – Structural Design: Evaluate stress concentrations within, and venting of Radiators – Fabrication and Integration: assess inspection and contamination issues as they may affect LAT – Environmental Test: finalize thermal test levels and cycles – Risk: Implement a continuous risk management systems for Mechanical Systems LAT-PR-01278 Section 2 2-6 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Delta PDR Action Items (cont 1) • • Thermal Design: Investigate off-design thermal cases and impact of trades on parallel heat transfer paths within the LAT – Analysis of the impact of heat pipe failures have been completed. The designs are fully redundant, being able to accommodate the loss of any heat pipe – Shimmed and bolted interface conductances and radiative couplings have been updated to reflect the final CDR designs – Transfer orbit thermal analysis has been started, using the draft timeline from Spectrum Structural Design: Evaluate stress concentrations within, and venting of Radiators – Complete stress analysis of the Radiator VCHP’s has been completed, and will be shown at CDR – Venting of Radiator panels has been addressed with vented honeycomb and close-outs. LAT-PR-01278 Section 2 2-7 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Delta PDR Action Items (cont 2) • • • Fabrication and Integration: assess inspection and contamination issues as they may affect LAT. – IR camera inspection of the Radiators has been budgeted. – Ground cooling requirements during LAT integration have been defined (LAT-TD-00997) – LAT CCP has been released, and all subsystems are working to it. A LAT lowtemperature bake-out is part of that. Environmental Test: finalize thermal test levels and cycles. – Test temperatures for all subsystems and the LAT have been finalized (LAT-SS-00778), and include a minimum AT margin of 5 C and QT margin of 10 C over operating – LAT Verification Plan has baselined 8 thermal cycles of the VCHP joints. – LAT thermal test program staffed adequately Risk: implement a continuous risk management systems for Mechanical Systems – The LAT has completely updated its CRM system, using the GLAST program system at NAS/GSFC. This is managed by the LAT System Engineer, and includes risks and mitigation plans for all subsystems, including Mechanical Systems. LAT-PR-01278 Section 2 2-8 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Requirements Flow-Down Mission Science Requirements Document 433-SRD-0001 Science Rqmts Mission System Specification 433-SPEC-0001 LAT Design Specification Subsystem LAT-SS-00010 Mechanical Subsystem Specification LAT-SS-00115 TCS Performance Specification LAT-SS-00715 LAT Environmental Specification LAT-SS-00778 Ground System Rqmts Interface Rqmts LAT IOC Performance Specification LAT-SS-00015 LAT-SC Interface Control Document Trigger & Dataflow Subsystem Specification LAT-SS-00019 TKR Subsystem Specification ACD Subsystem Specification LAT-SS-00017 LAT-SS-00016 Radiator Design Specification LAT Dataflow Specification LAT TKR Design Specification LAT-SS-00394 LAT-SS-00285 LAT-SS-00134 X-LAT Plate Design Specification LAT-SS-01240 LAT Trigger Specification LAT-SS-00284 LAT Readout Electronic Specification LAT-SS-00152 Grid Box Design Specification LAT Flight SW Specification LAT-SS-00775 LAT-SS-00399 LAT-PR-01278 Section 2 Interface Rqmts Mission Rqmts LAT-SC Interface Requirements Document 433-IRD-0001 LAT Performance Specification LAT IOC/MOC/ SSC Interface Control Documents Power Subsystem Specification LAT-SS-00136 CAL Subsystem Specification Tower Power Supplies Specification LAT-SS-01537 CAL Design Specification LAT-SS-00018 LAT-SS-00210 LOF Subsystem Specification LAT-SS-00021 SAS Subsystem Specification LAT-SS-00020 LAT Operations Facility Specification LAT-SS-01783 SAS Design Specification LAT-SS-00505 ACD Design Specification LAT-SS-00352 Legend GLAST Mission Spec’s LAT Spec’s Subsystem Spec’s 2-9 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Key LAT Structural and Thermal Requirements Parameter LAT Configuration LAT mass allocation Max Radiator area (#) Configured as 2 separate Radiators Radiator max width (#) Positioned according to IRD App. A (#) Mount point for SC support as shown in IRD Appendix A (#) Structural, Loads Fixed-base first-mode TKR alignment during normal LAT operation Capable of exposure to static-equivalent launch loads Capable of exposure to sinusoidal vibration launch loads Capable of exposure to acoustic launch loads LAT-PR-01278 Section 2 Requirement Design Margin Comply Ver. Method < 3000 kg < 5.88 m2 2679.4 kg 5.57 m2 OK 1.896 m 1.863 m 320.6 kg 0.31 m2 Y Y Y Y Y M I I I I Y I Y T Y T, A OK Y T, A OK Y T OK P T < 1.903 m > 1.84 m sep 1.177 m below LIP 7 mm 22.6 mm OK > 50 Hz 11% < 7arc-sec 1s 4.1 arc-sec peak2.9 arc-sec + 5s to-peak radial 2-10 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Key LAT Structural and Thermal Requirements Parameter Thermal Capable of normal operation when loaded by 75 W/Rad of heat from SC solar arrays Capable of normal operation with Rad-Solar Array view factor = 0.1 Orbit range of 450 km min to 575 km max Provide thermal control with LAT pointed 2pi/24/7/365 during any normal LAT mode Capable of maintaining thermal control during exposure to IR, Albedo, Solar fluxes Capable of maintaining thermal control when exposed to solar flux from SC re-points Power Max process power indefinite dissipation Peak process power dissipated for 10 min VCHP heater power when LAT is on (at Vmin) VCHP heater power when LAT is off (at Vmin) Orbit-average survival heater power at min voltage (not incl control authority) Peak survival heater power During Obs t-vac, TCS capable of full functionality "lying on its side" LAT-PR-01278 Section 2 Requirement Design Margin Comply Ver. Method 75 W/Rad 73.4 W/Rad OK Y T, A Y A Y A OK Y T, A OK Y T, A OK Y T, A Y T, A Y T, A Y Y D D OK 450 - 575 km 450 km OK 650 W @ 612 W LAT + 38 W 1 C operating + T(max) Rad @ 24 C 5 C calc 720 W for 10 720 W for 20 min @ 10 min, 7 C min @ T(max) <T(max) < 38 W 13 W @ 27 V 25 W < 50 W 42 W @ 27 V 8W < 220 W 142 W 55% (78 W) Y D < 560 W 362 W (incl 30% control auth) 55% (198 W) Y D Y T, A OK 2-11 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Block Diagram MLI Surrounding ACD ACD Base Elec Ass’y alum frame CAL Modules alum bottom plate TKR Module CFC tray, side walls Grid monolithic alum structure Spacecraft LAT mounting structure Spacecraft SC bus structure Solar Arrays S.A. mount Elec. Boxes alum electronics box EMI Skirt Shields E-Boxes, supports X-LAT Pl X-LAT Plate monolithic alum structure Radiator Mnt Bkt Support Radiators at corners of Grid Htr Switch Boxes Operate Radiator heaters LAT Radiators on +/- Y sides of LAT Grid MLI Insulation MLI surrounding underside of LAT LAT Block Diagram LAT-PR-01278 Section 2 2-12 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT System Schematic Diagram ACD Thermal Structural EMI/Grounding Accommodation Direction of arrow signifies direction of reliance, structural support or heat flow TKR Grid Base Ass’y Rad Mnt Bkt Radiator EMI Skirt Electronics X-LAT Plate Spacecraft Htr Sw Box Radiator Solar Array CAL EMI Skirt Htr Sw Box Rad Mnt Bkt Solar Array LV Payload Attach Fitting LAT Schematic Diagram LAT-PR-01278 Section 2 2-13 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Internal Interfaces Interface TKR Grid CAL Grid E-Boxes CAL E-Boxes X-LAT ACD Grid TKR ACD Structural 8 Ti flexures/bay, bolted and pinned to Grid Bolted tabs in CAL back plate develop shear at joint 4 Ti stand-offs/bay support EBox stack off CAL module E-Boxes support X-LAT Plate against out-of-plane deflection Corner bolts and mid-side bolts/pins Rad Mnt Bolted/pinned joints carry all Radiator Bkt Radiator loads Rad Mnt Bolted/pinned joints carry Grid Bkt Radiator and Switch Box loads VCHP's mount to HP patch Grid Radiator plate hanging from Grid Switch Rad Mnt Switch box bolted to Rad Mnt Box Bkt Bkt E-Boxes EMI Skirt EMI Skirt Grid Bolted joint X-LAT EMI Skirt Bolted, pinned joint X-LAT Radiator LAT-PR-01278 Section 2 Thermal Cu thermal straps from TKR sidewalls dry-bolted to Grid Tab dry-joint under high bolt pre-load transfers CAL heat to Grid Low-conductivity stand-offs and surface finishes minimize heat transfer Thermal straps transfer E-Box heat to XLAT Plate Bolted dry joint and radiative coupling transfers ACD heat to Grid TKR black-painted sidewalls view ACD inner CFC honeycomb facesheet Isolating gasket minimizes survival heatleak from Grid Grounding/Shielding Accommodation Slots in Grid provide race ways for TKR flex cables Mating alum surfaces are alodined for AC/DC grounding E-Box and CAL alum surfaces alodined for AC/DC grounding Mating alum surfaces are alodined for AC/DC grounding Interface is low risk and is finalized Interface design not yet finalized or tested Interface design is incomplete Mating alum surfaces are alodined for AC/DC grounding VCHP-DSHP silicone wet joint is primary heat path for Grid heat Silicone wet joint removes small heat load to Rad Mnt Bkt Shielded cables carry ground Skirt shields internal E-Boxes Taped for EMI shielding Taped for EMI shielding Connectors mount to Skirt VCHP-XLHP silicone wet joint is heat path for Elec heat off X-LAT 2-14 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Trades Associated With Internal Interface Finalization Trade Topic ACD and TKR survival temperatures and impact of black paint on TKR sidewalls Radiator panel cut-outs and top profile Electronic box mounting CAL bolted joint to the Grid TKR to Grid thermal joint LAT-PR-01278 Section 2 Status Study Conclusion Complete Evaluate impact of using high-emissivity black paint Black paint raises ACD survival temps, which increases on TKR and ACD survival temps margins at QT, while having little impact on TKR survival temps. Also adds redundant thermal path for TKR Complete Find balance between maximizig radiating surface Stepped profile was baselined. Area is maximized, while area, structural stiffness of panel top, and providing good access volume under the ACD. Panel integration access to VCHP joints stiffness is not significantly affected. Complete Investigate hard-mounting the E-Boxes to the CAL Changed baseline to hard-mount to CLA, to simplify plate, and making compliant thermal joints to the X- structural and I&T plans. Incorporated thermal straps into LAT Plate the X-LAT Plate for heat removal Working Investigate alternate design implementations for the Test results of friction testing have been used to finalize the bolted joint, and the impact of new grounding design. Alodine surface treatment baselined, but electrical requirements testing has not been complete. Shear allowables and margins still being worked Complete Develop new thermal interface in response to Cu thermal strap baselined. This improves thermal joint changes in the TKR bottom tray design changes reliability. Changes to Grid interface decreases integration risk, at cost of increased time to bolt on straps 2-15 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Internal Interface TBX’s and Open Issues • Tracker-LAT interface – 0 TBX’s in ICD – Interface drawing in draft: working on final tolerancing – Open issue: TKR-Grid copper thermal straps • • • • Calorimeter-LAT interface – 0 TBX’s in ICD – Interface drawing in final draft – Open issue: CAL-Grid bolted friction joint • • • • • • Being worked by TKR group Detailed design is complete and in the interface drawing and testing is underway Closure plan – TKR to complete thermal testing as part of EM test plan closure Being worked by Mechanical Systems Friction testing is complete and preliminary joint allowables established EM testing of joint and 1 x 4 Grid will complete qualification process Friction joint design has been questioned by GSFC Currently under discussion with GSFC mechanical branch ACD-LAT ICD interface – 4 TBX’s in ICD: all have been resolved and will be included in the next revision (in release cycle) – Interface drawing in final draft: finalize fit of mating pieces – Open issues: none LAT-PR-01278 Section 2 2-16 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Internal Interface TBX’s and Open Issues (cont) • Electronics-LAT interface – # TBX’s – Interface drawing in second draft: awaits X-LAT interface resolution – Open issue: X-LAT Plate to Electronics box thermal joint • • • – Open issue: Heater Switch Box mounting • • – Baseline thermal strap design identified to not meet thermal or structural requirements LAT tiger team convened to resolve interface issues—preliminary thermal design developed, using vel-therm and parallel thermal paths Closure plan – Incorporate preliminary thermal design into LAT system model to confirm design meets interface temperature requirements (underway) – Finalize X-LAT and E-box structural interface to work around thermal design Switch box design has been finalized, but interface to Radiator Mount Bracket is TBD Closure plan – Establish interface req’s: loads, heat transfer – Finalize mounting design: bolt sizing, thermal and electrical interface Open issue: Finalize TCS interface requirements • • Details of interface and functionality requirements have not been finalized Closure plan – Finalize TCS Performance Specification – Use this to spec interface and functionality requirements for Elec-LAT ICD LAT-PR-01278 Section 2 2-17 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Interface Requirements Documentation Status Document LAT Instrument LAT-DS-00040-5: LAT Instrument Layout LAT-DS-00038-3: LAT Instrument Layout Calorimeter LAT-DS-00233-3: CAL-LAT Interface Definition Drawing LAT-SS-00238-4: CAL-LAT Mech, Therm, Elec Interface Control Document ACD LAT-DS-00309-1: ACD-LAT Interface Definition Drawing LAT-SS-00363-4: ACD-LAT Mech, Therm, Elec Interface Control Document Tracker LAT-DS-00851-1: TKR-LAT Interface Definition Drawing LAT-SS-00138-5: TKR-LAT Mech, Therm Interface Control Document LAT-SS-00176-2: TKR-LAT Elec Interface Control Document Electronics LAT-DS-01630-1: Electronics-LAT Interface Definition Drawing LAT-SS-01794-1: Elec-LAT Mech, Therm Interface Control Document Status Released 6 May 02. Revision in progress Rev 3 complete; out for review Final draft out for subsystem review Released 13 Mar 03 Final draft out for subsystem review Released 17 Dec 02 First draft in-progress In Signature Cycle Released 27 Jan 03 First draft in-progress First draft in-progress LAT Internal Interface Control Specifications LAT-PR-01278 Section 2 2-18 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT External Interfaces Interface Radiator Solar Arrays Structural SC struts restrain Radiator SC Bus against out-of-plane loads Radiator Thermal MLI on both surfaces to minimize radiative coupling Cold-/hot-case SA backloading affect peak LAT temp's, survival heater needs SC Bracket below Grid accepts Flexures bolts, pins from Flexure SC EMI Skirt Flexures Grid X-LAT SC Bus MLI on both surfaces to minimize radiative coupling Grounding/Shielding Accommodation Radiator size/position fit around SC, flexures Cut-out in Radiator allows SA boom to pass through Grid Bracket allows for SC attach Skirt is recessed for clearance to flexure Cable tie-downs to support SC cables Interface is low risk and is finalized Interface design not yet finalized or tested Interface design is incomplete LAT-PR-01278 Section 2 2-19 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Trades Associated With External Interface Finalization Trade Topic Status Study Effect of solar array properties Complete Evaluate definition of cold-case SA that is suitably and view factor on LAT coldconservative for Spectrum, without driving LAT to /survival-cases higher survival heater power needs Radiator panel size and Complete Finalize Radiator size to work with Spectrum solar location arrays LAT-SC flexure mounting Working Develop a balanced interface design to attenuate feature loads into the Grid and make the joint more accessible during Observatory integration LAT-PR-01278 Section 2 Conclusion Agreed-to SA parameters delineated in LAT-TD-00224. Heater power allocations finalized in LAT IRD Stay-clear dimensions and placement finalized, along with cut-outs for solar array accommodation Wing bracket base lined to reduce stress concentrations in the Grid, whil providing a bolted joint with better access from the sides. This cleans up the SC flexure design. Impact of pin envelope requirements on EMI Skirt stayclear is still in work 2-20 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 External Interface TBX’s and Open Issues • Interface requirements documents – Interface design maturation has superseded much of requirements documents – Closure plan • • SC Flexure to LAT mounting design is not finalized – Actively working design concepts with Spectrum – Hanging Wing bracket design concept is baselined – Working SC shear pin envelope with respect to EMI Skirt stay-clear – Impact on LAT design is well-understood – Closure plan • • • Work with GLAST project to update IRD, MSS to be bring them up to date with latest agreements Work to final concept by mid-April Incorporate into LAT-DS-00040 drawing and Spectrum ICD by LAT CDR Lateral center-of-mass requirement flow-down to LAT – LAT center of mass requirement is being developed by Spectrum as part of ACS maturation, in conjunction with LAT input – LAT has evaluated expected worst-case center-of-mass offsets – Closure plan • Spectrum: evaluate impact of this on ACS/de-orbit and propose compromise LAT-PR-01278 Section 2 2-21 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Metrics: Mass Parameter LAT Mass LAT center of mass above L.I.P. Estimate 504.9 1375.8 270.1 329.3 199.3 2679.4 320.6 12.0% Alloc. 510.0 1440.0 280.0 345.0 220.0 2795.0 3000.0 * AIAA G-020 recommended min reserve = 7.2% Center of Mass (mm) CMx 1.26 CMy -0.54 CMz -86.89 Ht off LIP 149.31 3000 LAT Margin 5.4% 2900 I-PSR dPDR 10.9% I-CDR LAT Reserve 2800 Mass (kg) March 2003 Mass (kg) TKR CAL ACD Mech Elec LAT Total Rsrv/Margin Rsrv/Margin* Allocation Requirement Design Margin Comply < 3000 kg 2679.4 kg 320.6 kg Y < 185 mm 149.3 35.7 mm Y I-PDR Subsystem Allocation 2700 Prop I-SRR 2600 -20 < CMx < 20 -20 < CMy < 20 CMz < -51.2 Ht < 185 Mass Budget Review Threshold 2500 Total Allocated to S.S. LAT Mass Estimate Second Moment of Inertia (kg-m2) Ixx 1057.7 1500.0 Iyy 1014.9 1500.0 Izz 1339.5 2000.0 Oc t -9 9 Ja n- 0 0 Ap r- 0 0 Ju l-0 0 Oc t -0 0 Ja n- 0 1 Ap r- 0 1 Ju l-0 1 Oc t -0 1 Ja n- 0 2 Ap r- 0 2 Ju l-0 2 Oc t -0 2 Ja n- 0 3 Ap r- 0 3 Ju l-0 3 Oc t -0 3 Ja n- 0 4 Ap r- 0 4 Ju l-0 4 Oc t -0 4 Ja n- 0 5 Ap r- 0 5 2400 Date LAT Mass Status Source: LAT-TD-00564-06 “LAT Mass Status Report, Mass Estimates for March 2003,” 7 March 2003 LAT-PR-01278 Section 2 2-22 • U GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Metrics: Mass (cont) Subsystem Mass Estimates (kg) Subsystem TKR CAL ACD Mech (+) DAQ Elec (#) LAT Total % of Total Current Alloc. 510.0 1440.0 280.0 345.0 220.0 2795.0 PARA CALC MEAS Total 0.0 53.0 35.5 143.2 150.6 382.3 14.3% 504.9 26.5 209.6 186.0 48.7 975.8 36.4% 0.0 1296.3 25.1 0.0 0.0 1321.3 49.3% 504.9 1375.8 270.1 329.3 199.3 2679.4 100.0% "Current" Allocations per CCB action on 7 Mar 03 AIAA Reserve Estimate (*) 2.0% 3.0% 12.4% 21.0% 20.0% 7.2% Center of Mass Location CMx CMy CMz (mm) (mm) (mm) 0.00 0.00 229.95 0.00 0.00 -148.75 0.00 0.00 318.19 0.00 0.00 -485.61 16.90 -7.20 -352.88 1.26 -0.54 -86.89 Grid height 236.20 Ht above LAT Interface Plane 149.31 LAT Subsystem Mass Status (*) Recommended reserves estimated using guidelines given in ANSI/AIAA G-020-1992 "Estimating and Budgeting Weight and Power Contingencies for Space Craft Systems“ (+) “Mech” includes the Grid, X-LAT Plates, Radiators, and EMI Shield pieces (#) “DAQ Elec” includes all power, communications, and trigger and dataflow systems (PDU, SIU, TEM/TPS/GASU respectively) Source: LAT-TD-00564-06 “LAT Mass Status Report, Mass Estimates for March 2003,” 7 March 2003 LAT-PR-01278 Section 2 2-23 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Metrics: Dimensions • LAT instrument and subsystem stay-clears are governed by Interface Definition Drawings – LAT-SC stay-clears delineated in LAT-DS-00040-8 (reproduced in 433-IRD-0001) – Subsystem stay-clears, interface features, datums, and tolerances established by the IDD’s with each subsystem Delta PDR Dimensions Parameter Req Design LAT width at ACD < 1800 1796 LAT width at Grid < 1800 1796 Instrument height above LIP < 1100 1047 Height below LIP < 300 258.25 Radiator inside spacing > 1890 1895.5 Radiator width < 1851 1850 LAT circle diameter inside fairing < 2743 2718 Req < 1800 < 1820 < 1100 < 300 >1840 < 1903 < 2743 CDR Dimensions (#) Design Margin Comply 1796 SC 4 Y 1806 SC 14 Y 1081.5 SC 18.5 Y 258.25 41.75 Y 1843 SC 3 Y 1900 SC 3 Y 2718 25 Y (#) Requirements per agreement among LAT, GLAST, Spectrum Astro. IRD requirements not yet updated by GLAST Key LAT Stay-Clear Dimensions Source: LAT-DS-00040-08 “LAT Instrument Stay Clear,” 12 Feb 2003 Draft LAT-DS-01221-01, “Radiator-LAT Interface Definition Drawing,” 26 Feb 2003 Draft LAT-DS-00309-03, “ACD-LAT Interface Definition Drawing,” 20 Feb 2003 Draft LAT-PR-01278 Section 2 2-24 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Metrics: Dimensions (cont) LAT Stay-Clear Assembly LAT-PR-01278 Section 2 2-25 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Metrics: Power Parameter Requirement LAT orbit-average power < 650 W Peak power < 750 W Design 590 W 720 W Margin Comply 60 W Y 30 W Y Special Status Normal Operations Quantity Tran- Cold Hot 10 Min Surv. Alloc. Unit Hot Cold sition Case Case Peak Total 50.0 95.3 534.8 590.0 650.0 719.8 W Total on Grid 0.0 0.0 210.6 234.0 252.1 291.2 W TKR 139.5 155.0 162.8 192.9 W 16 CAL 60.3 67.0 75.8 83.4 W 16 ACD 10.8 12.0 13.6 14.9 W 1 Total on X-LAT 0.0 45.3 286.2 318.0 359.9 390.5 W TEM 43.2 48.0 54.3 58.1 W 16 TPS 148.5 165.0 186.7 203.2 W 16 GASU 19.8 22.0 24.9 27.8 W 1 1 SIU 27.2 21.6 24.0 27.2 29.7 W 1 1 EPU 38.7 43.0 48.7 53.0 W 2 1 PDU 18.1 14.4 16.0 18.1 18.6 W 1 1 Radiators 50.0 50.0 38.0 38.0 38.0 38.0 W 16 16 Comments Evenly distributed up 4 sides of TKR module Evenly distributed up 4 sides of CAL Evenly distributed around 4 sides of BEA 1 board/bay 1 P.S. board/bay for TEM 1 lg board spanning 4 center bays 2 bds in 2 bays (1 hot, 1 cold) 2 bds in 2 bays, both hot (+ 1 cold spare) 2 bds in 2 bays (1 hot, 1 cold) Bottom of Radiator panels at VCHP's LAT Dissipated Power Values Source: LAT-TD-00225-04 “A Summary of LAT Dissipated Power for Use in Thermal Design”, 13 Mar 2003 LAT-PR-01278 Section 2 2-26 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Metrics: Power (cont 1) Cold Case Power Dissipation Hot Case Power Dissipation LAT +Y LAT +Y +Y Side LAT Radiator Bay 12 EPU-B Bay 13 Empty Bay 14 Empty Bay 15 Empty Bay 12 EPU-B Bay 13 Empty Bay 14 Empty Bay 15 Empty 0 0 0 0 0 0 0 0 Bay 8 PDU-B Bay 9 GASU Bay 10 GASU Bay 11 SIU-B Bay 8 PDU-B Bay 9 GASU Bay 10 GASU Bay 11 SIU-B 9.9 0 0 0 12.4 0 Bay 6 GASU Bay 7 SIU-A Bay 4 PDU-A Bay 5 GASU Bay 6 GASU Bay 7 SIU-A 9.9 21.6 18.11 0 12.4 27.2 0 -X Side Bay 4 PDU-A Bay 5 GASU 14.4 Boxes TEM/TPS: X-LAT Tot Legend: GASU SIU PDU EPU -A -B +Y Side LAT Radiator LAT +X +X Side Sun Side -X Side Bay 0 EPU-A Bay 1 Empty Bay 2 Empty Bay 3 EPU-A Bay 0 EPU-A Bay 1 Empty Bay 2 Empty Bay 3 EPU-A 19.4 0 0 19.4 24.3 0 0 24.3 94.5 191.7 286.2 -Y Side LAT Radiator LAT Top View Global trigger, ACD, and Switching Unit Spacecraft Interface Unit Power Distribution Box LAT Event Processor A-side, powered box B-side, unpowered cold spare Boxes TEM/TPS: X-LAT Tot 118.8 241.0 359.9 LAT +X +X Side Sun Side -Y Side LAT Radiator LAT Top View Notes: 1. All power is in watts LAT Dissipated Power Distribution Source: LAT-TD-00225-04 “A Summary of LAT Dissipated Power for Use in Thermal Design”, 13 Mar 2003 LAT-PR-01278 Section 2 2-27 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT Materials and Parts • • • Material requirements – Source: 433-MAR-0001, “Mission Assurance Requirements” – LAT: LAT-SS-00107-01, “Mechanical Parts Plan” Material Usage Agreement (MUA) needed for non-compliant materials – All materials have been assessed by GSFC materials branch to be compliant to standards and used in conventional methods – Currently the project requires no MUA’s Relevant procedures and guidelines for material selection – Metallic Materials for Stress Corrosion Cracking Resistance in Sodium Chloride Environment (MSFC-STD-3029) – Fastener Integrity Requirements (541-PG-8072.1.2) – Standard Test Method for Total Mass Loss and Collected Volatile Condensable Materials for Outgassing (ASTM-E-595) ACD CAL Elec I&T Mech TKR Total Total Materials SLAC IPO GSFC Submitted Pending Accepted Approved 97 97 97 0 45 41 41 4 24 21 21 3 0 0 0 TBD 117 104 104 13 51 41 41 10 334 304 304 30 Total Materials Count on LAT M&P List Source: LAT-DS-00405, “LAT Mechanical Materials and Parts List,” March 2003 LAT-PR-01278 Section 2 2-28 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT M&P List: Inorganic, Polymer and Composite Materials • • Inorganic materials – Inorganic materials submitted to LAT IPO as of 19 March 2003 Polymers and Composites – Polymer and composite materials submitted to LAT IPO as of 19 March 2003 ACD CAL Elec I&T Mech TKR Total Inorganic Materials SLAC IPO GSFC Submitted Pending Accepted Approved 36 36 36 0 13 13 13 0 6 4 4 2 0 0 0 TBD 80 68 68 12 19 19 19 0 154 140 140 14 Inorganic Materials Count on LAT M&P List ACD CAL Elec I&T Mech TKR Total Polymer and Composite Materials SLAC IPO GSFC Submitted Pending Accepted Approved 47 47 47 0 26 22 22 4 12 11 11 1 0 0 0 TBD 23 22 22 1 27 17 17 10 135 119 119 16 Polymer and Composite Materials Count on LAT M&P List Source: LAT-DS-00405, “LAT Mechanical Materials and Parts List,” March 2003 LAT-PR-01278 Section 2 2-29 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 LAT M&P List: Lubricants and Processes • • Lubricants – Lubricants used only in static applications, largely for bolts – No moving parts within the LAT – Lubricants submitted to LAT IPO as of 19 March 2003 Processes – M & P list collects process information for all heat treating and surface treatment processes – Processes submitted to LAT IPO as of 19 March 2003 ACD CAL Elec I&T Mech TKR Total Lubricants SLAC IPO GSFC Submitted Pending Accepted Approved 1 1 1 0 0 0 0 0 2 2 2 0 0 0 0 TBD 4 4 4 0 2 2 2 0 9 9 9 0 Lubricant Count on LAT M&P List ACD CAL Elec I&T Mech TKR Total Processes SLAC IPO GSFC Submitted Pending Accepted Approved 13 13 13 0 6 6 6 0 4 4 4 0 0 0 0 TBD 10 10 10 0 3 3 3 0 36 36 36 0 Processes on LAT M&P List Source: LAT-DS-00405, “LAT Mechanical Materials and Parts List,” March 2003 LAT-PR-01278 Section 2 2-30 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Materials List Pending Items • • • • Pending items as of 19 March 2003 Reasons for status – Specific material not yet chosen – Waiting for “TBD’s” to be filled in – Outgassing testing in progress Mechanical Parts Review Board will evaluate materials once missing information is collected from test results or work with manufacturer Final step is to validate materials list – Cross-check against drawing list – Check for missing materials and processes ACD CAL Elec I&T Mech TKR Total Materials Pending Approval Lacking Needs Tested Material Change Total Info for Qual for OutID is TBD Material Pending Approval Testing gassing 0 0 0 0 0 0 0 0 0 0 4 4 0 2 0 1 0 3 TBD TBD TBD TBD TBD TBD 12 1 0 0 0 13 0 0 2 1 8 10 12 3 2 2 12 30 Materials Pending Materials Branch Approval Source: LAT-DS-00405, “LAT Mechanical Materials and Parts List,” March 2003 LAT-PR-01278 Section 2 2-31 GLAST LAT Project Mechanical Design Integration Peer Review, March 2003 Summary and Further Work • • Summary – Internal and External interfaces have been clearly defined – Remaining interface issues are identified and a closure plan is in progress – Mass and Power allocations are understood and being tracked with subsytems – M&P list is up-to-date with subsystems Further Work – Complete interface documentation – Complete interface closure plans to finalize interfaces – Validate M&P list against subsystem drawing trees LAT-PR-01278 Section 2 2-32