GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software System Engineering

advertisement
GLAST LAT Project
Gamma-ray Large
Area Space
Telescope
DOE/NASA Peer Critical Design Review, March 19-20, 2003
GLAST Large Area Telescope:
Electronics, Data Acquisition &
Flight Software
System Engineering
Gunther Haller
Stanford Linear Accelerator Center
Manager, Electronics, DAQ & FSW
LAT Chief Electronics Engineer
haller@slac.stanford.edu
(650) 926-4257
G. Haller
4.1.7 Elex System Engineering V7
1
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
System Engineering Outline
•
•
•
•
•
•
•
•
•
•
•
System Overview
Changes since PDR
External Interfaces
Internal Interfaces
Technical Budget
Verification & Test
Risk
FMEA
Reliability Allocations
Parts and Spares Plan
Drawing Tree
G. Haller
4.1.7 Elex System Engineering V7
2
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Data-Acquisition (DAQ) System Overview
•
•
•
•
•
•
Configuration, triggering, event-flow
control and readout, monitoring, and
supply of power to
– 16 Calorimeter and Tracker
towers with a total of 850,000
tracker channels and 3,000
calorimeter channels
– 12 ACD front-ends with a total of
208 ACD channels
Interface to spacecraft for control,
data, monitoring, and power
Trigger system (hardware selection
of possibly interesting events)
Event filtering
Housekeeping
Operational thermal control
G. Haller
Spacecraft
LAT
VCHP
Heater
Control
4.1.7 DataAcquisiton
(DAQ) System
C
A
L
T
K
R
Tower 0
C
A
L
T
K
R
Tower 1
C
A
L
T
K
R
Tower 15
A
C
D
A
C
D
A
C
D
0
1
11
4.1.7 Elex System Engineering V7
3
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
LAT Electronics Hierarchy
•
•
•
•
•
•
Tower Electronics Module
– Interface to calorimeter and tracker on
each tower
– Monitoring
– Combination of sub-system trigger
signals to primitives
– Event buffering
GAS Unit
– Command-response unit receives and
distributes command, clock, and data
– Global trigger unit generates LAT-wide
readout decision signals based on
trigger primitives from TEM’s and ACD
– Event-builder unit builds complete
LAT events out of asynchronous
event-fragments; Forward complete
events to dynamically selected target
EPU’s or spacecraft
– ACD electronics module tasks much
like TEM for TKR/CAL
EPU: Event processor unit runs filter
algorithm to reduce 10kHz input event rate
down to 30 Hz (with two EPU’s)
SIU: Spacecraft interface unit controls LAT
and interfaces to spacecraft
Instrument software runs on EPU and SIU
processors only
Power system not shown
G. Haller
SC
SC Science
Commanding
Data
EPU 0
EPU 1
SIU
GAS Unit
Event
Builder
TEM 0
C
A
L
T
K
R
Command
Response
Unit
Global
Trigger
TEM 1
C
A
L
T
K
R
TEM 15
C
A
L
T
K
R
ACD Electronics
Module
A
C
D
A
C
D
A
C
D
0
1
11
4.1.7 Elex System Engineering V7
4
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
LAT Electronics Physical
TKR Front-End Electronics (MCM)
ACD
ACD Front-End Electronics (FREE)
TKR
CAL Front-End Electronics (AFEE)
CAL
16 Tower Electronics Modules
– DAQ electronics module (DAQ-EM)
– Power-supplies for tower electronics
Global-Trigger/ACD-EM/Signal-Distribution Unit*
Spacecraft Interface
Unit
– Spacecraft
Interface Board
(SIB): Spacecraft
interface for
MIL1553 control &
data
– LAT control CPU
– LAT
Communication
Board (LCB): LAT
command and
data interface
3 Event-Processor Units (2+1 spare)
– Event processing CPU
– LAT Communication Board
– SIB
EPU-1
EPU-2
Pw r Dist. Box
spare
spare
GASU
spare
spare
spare
SIU-P
SIU-R
EPU-3
Power-Distribution Unit (PDU)*
– Spacecraft interface,
power
– LAT power distribution
– LAT health monitoring
* Primary & Secondary Units shown in one chassis
G. Haller
4.1.7 Elex System Engineering V7
5
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Changes since PDR
•
Spacecraft Selection and Meetings:
– PDU was moved to opposite side
of SIU to match SC power/C&DH
physical partitioning
– Signal levels (discretes, 1 PPS,
Science Interface, GBM GRB
signal) were officially changed to
LVDS (before undefined or RS422),
March 03
– Recently finalized power, analog
monitoring, and discrete interface
to SC
– Defined MIL1553 command
set/interface
– Separated SIU prime and
redundant into separate (and
identical) crate assemblies since
cross-connection to SC prime and
redundant was solved on the SCLAT interface level and lead to
removal of direct SIU-SIU interconnections
G. Haller
Before SC selection
spare
EPU-1
EPU-2
EPU-3
spare
spare
GASU
spare
spare
SIU P/R
Pwr Dist. Box P/R
After SC selection
EPU-1
EPU-2
Pwr Dist. Box
spare
spare
GASU
spare
spare
spare
SIU-P
SIU-R
EPU-3
4.1.7 Elex System Engineering V7
6
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Changes since PDR (Con’t)
•
•
Event-Builder was moved from CPU crates to GAS
unit
– Reduced complexity of inter-connections
– Reduced hardware from 3 event-builder
blocks to 2 (1 prime, 1 redundant), and power
dissipation from two event-builder blocks to
one
SIU crate was modified to be the same as EPU crate
– Removes mechanical, thermal, electrical
design effort for one assembly
– Moved SC science interface from Spacecraft
Interface Board in SIU to event-builder in
GASU
– Additional benefit that SIB board is almost
identical to existing SECCI version (both
boards are designed by NRL/Silver
Engineering), major simplification
– Science interface on GASU is small change
since GASU already transmits event data to
LAT CPU’s, so additional target is incremental
– Added SIB board in each EPU crate to provide
local EEPROM
• Simplification in software effort.
• No remote booting code
development/testing required.
G. Haller
SC
SC Science
Commanding
Data
EPU 0
EPU 1
SIU
GAS Unit
Event
Builder
TEM 0
C
A
L
T
K
R
Command
Response
Unit
Global
Trigger
TEM 1
C
A
L
TEM 15
T
K
R
C
A
L
T
K
R
ACD Electronics
Module
A
C
D
A
C
D
A
C
D
0
1
11
4.1.7 Elex System Engineering V7
7
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
External Interfaces
• All external DAQ interfaces released with the exception of
spacecraft interface and mechanical/thermal interface (mainly
to X-LAT plate)
G. Haller
Interface
Document
Status
Calorimeter
LAT-SS-00238
released
Tracker
LAT-SS-00176
released
ACD
LAT-SS-00363
released
Mechanical/Thermal
LAT-SS-01794
in progress
Spacecraft
GSFC-433-IRD
in progress at GSFC
but content stable
4.1.7 Elex System Engineering V7
8
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Internal Interfaces
• All internal interfaces are final, documents are being updated,
release before CDR
G. Haller
Interface
Document
Status
Tower Electronics Module
LAT-TD-00605
finalizing
TEM Power-Supply Unit
LAT-SS-01281
finalizing
GAS Unit
LAT-SS-01544
LAT-TD-00639
LAT-TD-01545
LAT-TD-01546
LAT-TD-01547
finalizing
SIU/EPU
LAT-SS-01539
finalizing
PDU
LAT-SS-01542
finalizing
VCHP Control Unit
LAT-SS-00715
finalizing
4.1.7 Elex System Engineering V7
9
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
DAQ Technical Budget Summary
Technical Resources
• DAQ Mass
– Sub-system allocation: 220 kg
– Detailed estimate: 199.3 kg
• DAQ Power
– Subsystem allocation: 318 W
– Detailed estimate: 313.8 W
• CPU Cycles
– Allocation: 2 CPU’s
– Detailed estimate: < 1 CPU
•
For detailed breakdown see Power/Mechanical/Software presentations
G. Haller
4.1.7 Elex System Engineering V7
10
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Verification & Test
Model Development
Hardware
Design
Software
Design/Develop
•
Fab
Test
Develop/Test
Formal Test
Release to I&T
Hardware and software development closely integrated
– Design of hardware versus software complexity optimized continuously
– Software runs with LAT engineering model electronics
– Continuous hardware versus software verification
– Full system including sub-system electronics from and at other institutions
– Independent verification process
• Exchange of hardware and software ->
–
–
–
–
–
G. Haller
ACD hardware, TKR hardware, CAL hardware
DAQ hardware
Flight software, I&T software
ACD Scripts, TKR scripts, CAL scripts, DAQ scripts
No integration at flight- LAT integration stage of components which have not
operating fully integrated in earlier stages
• Exception is spacecraft, since simulator is only simulating and is not real
hardware/software
4.1.7 Elex System Engineering V7
11
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Verification & Test (Con’t)
Development Cycles
EM 1
Release to I&T
EM2
Release to I&T
FU
•
•
•
Release to sub-systems
Release to sub-systems
Release to I&T
Three development cycles
– Engineering Model 1
• Single tower, single CPU
– Engineering Model 2
• Multiple tower, single CPU
– Flight Model
• Multiple towers, multiple CPU’s
Peer-Reviews after end of each development cycle
In addition regular LAT reviews (Manufacturing Readiness Review, etc)
G. Haller
4.1.7 Elex System Engineering V7
12
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Verification Matrix (Doors Example Page)
ID
VM
TDF3-7
The Level 1 Trigger (L1T) system shall be used to detect an interesting event and provide a
signal to the detector subsystems to capture and read out the event data.
Demo
TDF3-105
The trigger (TRG) system shall determine whether the event is interesting based on trigger
input signals received from the detector systems.
Demo
TDF3-9
The L1 trigger system shall accept trigger inputs from the ACD, TKR, CAL and dataflow
subsystems.
Demo
TDF3-11
The L1 trigger system shall time-align trigger inputs from the ACD, TKR, CAL and dataflow
subsystems to a precision better than 100 ns.
Test
TDF3-13
The L1 trigger system shall implement multiple overlapping triggers to allow cross-trigger
monitoring.
Test
TDF3-15
The L1 trigger logic shall generate a trigger acknowledge signal (L1TACK) and a trigger type
(e.g. CNO) for distribution to the subsystems.
Demo
TDF3-17
The L1 trigger logic shall generate the Trigger Acknowledge output with a latency of less than
1.3 mus.
Test
TDF3-106
The latency from the time the particle traverses the LAT to when the input signals need to be
recorded at the earliest shall be 2 ms.
Test
TDF3-19
The L1 trigger contribution to the overall trigger jitter shall be less than ± 50 ns.
Test
TDF3-107
The overall trigger jitter for the LAT shall be ± 200 ns.
Test
TDF3-51
G. Haller
TDF L3 Performance Specification
The dataflow system shall reduce the event rate accepted by the L1T to an output rate
commensurate with the spacecraft interface as specified in 433-IRD-0001, keeping events
meeting the science objectives.
Verif.
Demo
4.1.7 Elex System Engineering V7
13
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Test Matrix
Applies to each board and assembly. In this slide the tests at each level are listed
Sine Sweep
Random Vib
Acoustic
Pressure Profile
Mass Property
Interface Verification
EMI/EMC
ESD Compatibility (Grnding)
Functional/Performance
Thermal Vacuum
Thermal Balance
Thermal Cycle
Humidity
Backout
Radiation
Inspection
Comments
Sine Burst
Environmental/Other
-
-
-
-
-
-
M
TA
-
-
TA
-
-
TA
M
A
A
I
C Board
1
E
C Board
1
Q
-
-
C Chassis
1
Q
A
A
C Pow er Supply
1
Q
-
-
C Board
17
F
-
C Chassis
17
F
-
C Pow er Supply
17
F
S Box
1
S Box
16
S Box
1
-
-
-
-
M
TA
-
-
TA
-
-
TA
M
A
A
I
A
A
-
-
M
TA
-
-
TA
-
-
TA
M
A
A
I
-
-
-
-
M
TA
-
-
TA
-
-
TA
M
A
A
I
-
-
-
-
-
M
TA
-
-
TA
-
-
TA
M
A
-
I
-
-
-
-
-
M
TA
-
-
TA
-
-
TA
M
A
-
I
-
-
-
-
-
-
M
TA
-
-
TA
-
-
TA
M
A
-
I
Q
TQ
TQ
TQ
TQ
A
A
M
TQ
TQ
TQ
TQ
TQ
A
-
M
A
-
I
F
TA
-
-
TA
-
-
M
TA
-
-
TA
TA
A
-
M
A
-
I
4 cycle T/V
S
TA
-
-
TA
-
-
M
TA
-
-
TA
TA
A
-
M
A
-
I
8 cycle T/V
Assem bly Level
S= Subsystem
C=Component
G. Haller
Electrical
Static Load
Unit Type
Component (ITEM)
Mechanical
Quantity
Assembly Level
Hardware
Unit Type
PF=Proto Flight
F=Flight
S=Spare
Q=Qual
E=Engineering / VerificationModel
Verification Method
T=Test
A=Analysis
M=Measurement
I=Inspection
Buy-Tested at supplier
Buy-Tested at supplier
QS=Qual by Similarity
TQ=Test, Qual Levels
TA=Test, Acceptance Levels
4.1.7 Elex System Engineering V7
14
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Electrical & Environmental Test Flow
LAT
Qual
Accept
•LAT Test
•LAT Test
TEM DAQ/PS
Qual
Accept
•Elec
•Elec
PDU
EPU
SIU
TEM DAQ
GASU
TEM PS
Qual
Accept
Qual
Accept
Qual
Accept
•Elec
•Sine Vibe
•Random Vibe
•Thermal Vac
•EMI/EMC
•Elec
•Static Load
•Random Vibe
•Thermal Vac
•Elec
•Sine Vibe
•Random Vibe
•Thermal Vac
•EMI/EMC
•Elec
•Static Load
•Random Vibe
•Thermal Vac
•Elec
•Sine Vibe
•Random Vibe
•Thermal Vac
•EMI/EMC
•Elec
•Static Load
•Random Vibe
•Thermal Vac
G. Haller
4.1.7 Elex System Engineering V7
15
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Risk
• No single DAQ system failure can degrade LAT Electronics
capabilities below minimum science requirements
• Failure in SIU, PDU, or GASU can require use of the respective
redundant unit
• Failure in one of the two EPU’s can require use of the
redundant EPU unit. A second failure will reduce the available
EPU CPU power by a factor of 2.
• Failure in TEM power-supply or TEM DAQ module can lead to
– Loss of a full tower (most of the assembly is single string)
– Loss of the calorimeter or parts of it
– Loss of the tracker or parts of it
G. Haller
4.1.7 Elex System Engineering V7
16
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Electronics Risk Summary
ID #
Risk Rank
Risk Description
•Flight-Software schedule is tight
• Depends on execution of LAT software development approach.
Elec/224
Moderate
• Delays in incremental review process may impact cost & schedule
Risk Mitigation
•Detailed software development plan, schedule and review
points established (3/24/03).
• Early integration of software to target hardware via EM plan
(Sept 03)
• Extensive use of test bed (Feb 04 and beyond)
• Tower Power Supplies Cost & Schedule depend on bids received in
response to RFP
• Proposals may exceed allocated schedule & funding
Elec/221
Moderate
• Bids expected 3/25/03
• Assess schedule problem
• Determine cost impact to maintain
schedule
• Negotiate with vendor to minimize impact
• Develop minimum impact re-plan & pursue CCB approval
G. Haller
4.1.7 Elex System Engineering V7
17
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Electronics Risk Summary
ID #
Elec/223
Risk Rank
Low
Risk Description
• Two types of Tower Electronics Module ASICs submitted 1/18/03.
• 3 month turn around results in late reaction required if flaw is found
upon delivery and test resulting in schedule and cost impact
Risk Mitigation
• Protect schedule for additional ASIC run.
• Evaluate work arounds to mitigate late delivery of flight
ASICs and recover schedule margin.
• If untenable ASIC flaws occur, implement worst case
backup (FPGAs)
• Cost & Schedule of CPU Board depend on bids received in response
to RFP to be sent out end of Mar-03. Bidding cycle 4-weeks
Elec/222
G. Haller
• For now NRL CPU board effort is stopped. If there is a
problem with the BAE board, would revive the effort
Low
4.1.7 Elex System Engineering V7
18
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
FMEA
Fault Tree Analysis – LAT-TD-01757-01 (Draft)
• FTA’s completed on EPU’s, GASU’s,
PDU’s, SIU’s, TEM’s, & TEM/PS’s
Rev 24,
Tower Electronic Module Power Supply Fault Tree
(L-TPS)
11 Mar. 2003
Page 10 of 13
Rev
24,
Tower Electronic Module Fault Tree
11 Mar. 2003
(L-TEM)
Page 9 of 13
Rev
24,
Spacecraft Interface Unit Fault Tree
11 Mar. 2003
(L-SIU)
Page 7 of 13
• Most components multiply redundant
(More than one redundant
component)
Power Distribution Unit/SC Power
Bus Fault Tree
Rev 24,
11 Mar. 2003
Page 6 of 13
Rev 24,
11 Mar. 2003
• No single point failures without
ground contingency – (Software)
(L-PDU)
Global-Tirgger/ACD-EM/Signal Distribituion Unit
(GASU) Fault Tree
Page 5 of 13
(L-GAS)
Rev 24,
11 Mar. 2003
Loss of GASU System Function
C-12, GAS-INS
Electronic Processing Unit Fault Tree
Page 4 of 13
(L-EPU)
Loss of EPU Sytem Function
C-5, EPU-INS
• Non-redundant with in redundant
systems identified.
Loss of EPU
Loss of EMI Shielding
Loss of EPU S/W Function
Loss of GASU/EPU Comm.
C-26, STR-EPU/SIU/GAS
EPU Malfunction
L-EPU-07
EPU RAD750 Board Failure
(EPU Redundant - 2 of 3)
L-EPU-01
EPU Backplane Failure
(EPU Redundant - 2 of 3)
L-EPU-02
EPU SI Board Failure
(EPU Redundant - 2 of 3)
L-EPU-03
Loss of Electronics Bay Cooling
C-33, TML1- PDU,SIU,GAS,EPU
GASU/EPU Connector/Cable
Failure (Open)
L-EPU-05
EPU LC Board Failure
(EPU Redundant - 2 of 3)
L-EPU-04
Loss of EPU Power
C7, GAS-EPU
EPU Code
Failure
Software Contingency
Reload Filter software
EPU Power-On Chip Failure
(EPU Redundant - 2 of 3)
GASU/EPU Connector/Cable
Failure (Short to ground/signal)
(EPU Redundant)
L-EPU-14
L-EPU-06
Loss of EPU Power Feed
C-9, PDU-EPU
Failure Mode & Effects Analysis LAT-TD-00374-01 (Being Drafted)
PDU/EPU Power Feed
Connector/Cable Failure (open)
L-EPU-09
PDU/EPU Power Feed Conn./
Cable Failure (Short to ground/
signal) (EPU Redundant)
L-EPU-08
Legend
- OR Gate

- SUM Gate
- AND Gate
• Failure modes identified
Failure Consequence
(connection with other
FTA sheets)
Ground Contingency
EPU/PS PolyFuse Failure
(EPU Redundant)
L-EPU-15
EPU/PS Connection
Failure (Open)
L-EPU-11
EPU 5.0V PS Failure
(EPU Redundant - 2 of 3)
L-EPU-13
EPU 3.3V PS Failure
(EPU Redundant - 2 of 3)
L-EPU-12
EPU/PS Conn. Failure (Short to
ground/signal) (EPU Redundant)
L-EPU-10
Non-Redundant Failure
Non-Redundant Failure
within Redundant System
Redundant Failure
Non-LAT Hardware
failure
Failure Consequence
Ref. To: LAT-SS-00010 L-II(b)
Graceful Failure
Consequence
Failure Consequence &
Propagation
• Effects analysis underway
• Probability being linked to component failure
• No criticality 1, or 2 failures
• Few 2R failures, mostly 2MR thru 5 failures
G. Haller
4.1.7 Elex System Engineering V7
19
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Reliability Allocation
Mission
70%
(Pf = .3)
Observatory
85%
(Pf = .15)
LAT
85%
(Pf = .15)
DAQ
96%
(Pf = .04)
Tower Electronics
TEM DAQ
G. Haller
TEM PS
GASU
PDU
SIB
SIU
LCB
EPU
PSB
CPU
incl
FSW
Harness
Back
Plane
4.1.7 Elex System Engineering V7
20
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Parts Lists
• Parts Lists
– Electrical component list for DAQ submitted to Electrical
Parts Control Board and most parts are approved (see later
presentation)
– Mechanical components list for DAQ submitted to
Mechanical Parts Control Board
G. Haller
4.1.7 Elex System Engineering V7
21
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Spares Plan
Item
Need for
Flight
Qual
Flight
Spares
Spare
PCI boards
Tower DAQ Module Assembly
16
1
2*
n/a
Tower Power Supply Module Assembly
16
1
1*
n/a
GASU Assembly (contains prime and redundant unit)
1
1
0*
n/a
PDU Assembly (contains prime and redundant unit)
1
1
0*
n/a
SIU Assembly
2
1
0*
CPU/SIUSIB/PSB/LCB
EPU Assembly
3
0**
0*
EPU-SIB
* Qualification Models are flight spares
** EPU does not have separate qualification since crate is the same as SIU crate
G. Haller
4.1.7 Elex System Engineering V7
22
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Technical Issues and Status
• No known technical issues in respect to functionality and
performance except potentially
– TEM GTCC and GCCC ASIC (back from fabrication end of
3/03)
– Reliability; Analysis in progress
G. Haller
4.1.7 Elex System Engineering V7
23
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Drawing Tree (Example)
2
3
Tower Electronics
Module
LAT-DS-01481
Tower Electronics
Module DAQ
Assembly, TEM
Power Supply
LAT-DS-01643
LAT-DS-01482
TEM Box Base
Specification, TEM
Power Supply Assy.
LAT-DS-00554
LAT-DS-01651
TEM Box Lid
TEM Connector Plate
Box Base, Power
Supply Assy.
Box Lid, Power
Supply Assy.
LAT-DS-00555
LAT-DS-01026
LAT-DS-00995
LAT-DS-00996
TEM Connector Pin
Flange Screw
Bracket A
Bracket B
LAT-DS-01031
LAT-DS-01487
LAT-DS-01027
LAT-DS-01028
Bracket C
Bracket D
LAT-DS-01029
LAT-DS-01030
Specification, TEM
Power Supply CCA.
Interface Control
Document, Power
Supply CCA
Circuit Card
Assembly, TEM DAQ
Specification, TEM
DAQ
Test Procedure, TEM
DAQ
LAT-DS-01646
LAT-DS-01644
LAT-DS-01645
Specification, TEM
DAQ CCA
LAT-DS-01647
Test procedure, TEM
Power Supply Assy.
LAT-DS-01652
Test Procedure, TEM
DAQ CCA
LAT-DS-01648
Printed Wire Board,
TEM DAQ CCA
LAT-DS-01649
Schematic Diagram,
LAT_DS_01650
LAT-DS-01537
LAT-DS-01281
G. Haller
4.1.7 Elex System Engineering V7
24
GLAST LAT Project
DOE/NASA Peer Critical Design Review, March 19-20, 2003
Summary
•
•
•
•
•
•
•
•
Changes since PDR described
Interfaces documents released and under change control
Technical budget at CDR level with sufficient margin
Verification and test plans documented
Risks contained in LAT database with mitigations
FMEA and reliability well under way
Drawing tree well advanced
System engineering will be at CDR level by CDR time
– Main remaining item is completion of reliability analysis
G. Haller
4.1.7 Elex System Engineering V7
25
Download