GLAST LAT Project Gamma-ray Large Area Space Telescope 1 November 2004 GLAST Large Area Telescope: Test Planning Selected Topics Pat Hascall SLAC System Engineering Manager phascall@slac.stanford.edu x4266 LAT System Engineering 1 GLAST LAT Project 1 November 2004 Agenda • • • • Changes to Tracker tests Receiving test optimization Grid integration test optimization Status/plans for Performance and Ops Test Plan LAT System Engineering 2 GLAST LAT Project 1 November 2004 Changes to Tracker Tests New Old Section section Changes General Added sentence to define the purpose for the test TE101 TE101 Added testing of each flex cable independently Added variation of bias voltage from 0 to 120V TE303 None Added test of GTFE noise occupancy. This uses cosmics, where TE601 uses charge injection TE304 TE303 Title change, some change to test description TE305 None Added test, same as TE304 except layers are enabled rather than GTFEs TE306 TE304 Title change TE307 None Added test, similar to TE305, except uses 2 threshold values rather than a threshold scan TE403 TE502 Added phrase that the test can be merged with SVAC collection TE603 TE603 Removed analysis method text TE501 Test deleted – Layer noise occupancy – replaced by TE303 LAT System Engineering 3 GLAST LAT Project 1 November 2004 Current Tracker Flow • Received at SLAC • EGSE TEM/TPS installed and Piza tests repeated as a post ship test – Non GASU test stand – Procedures used TBD • Turned over to I&T (potentially with EGSE TEM/TPS removed) and receiving tests performed – Non GASU test stand – I&T procedures used • EGSE TEM/TPS removed, integrated with CAL and flight TEM/TPS LAT System Engineering 4 GLAST LAT Project 1 November 2004 Tracker Flow Discussion • • Propose combining post ship test and receiving test – Both tests use the same scripts (with a few exceptions, discussed below) – Both tests use the same version of EGSE – If the tests are not combined, then there should be a single mate to an EGSE TEM/TPS and test crate so the post ship test and receiving test share a test configuration Special cases/issues – TE101 uses a breakout box on the flex cables • Only run once for the post ship test • Tracker team will run using Tracker procedures (need to verify the procedures exist in a form that can be run at SLAC) – Tests TE601 to TE704 are not run at Pizza, but are used to characterize the tracker and potentially sell off some requirements • Under the combined test approach, these tests would be first run under I&T control after the tracker tower is “received” LAT System Engineering 5 GLAST LAT Project 1 November 2004 Grid Integration Test Optimization • • Current plan (for third and higher towers) – Mechanically integrate tower n into the grid • Connect GASU based external test crate and run LPT – Mechanically integrate tower n+1 into the grid • Connect GASU based external test crate and run LPT – Mate flight cables to towers n and n+1 – Perform LPT on towers n and n+1 using EM GASU – If needed, remate cables to other towers – CPT/LPT and SVAC tests on towers 1 to n+1 The LPT on towers n and n+1 do not add significant value and should be deleted – They break up the cabling process (in some cases) into two phases – The benefit is an earlier indication of a problem in mating the flight cables to the GASU or PDU (low probability) – Eliminating this test will not significantly hamper troubleshooting if a problem does occur LAT System Engineering 6 GLAST LAT Project 1 November 2004 Performance and Operations Test Plan Plan • Goal is to start the release process within the next few weeks – Tracker test changes incorporated into document – Calorimeter test changes (configuration changes, order of tests) expected to be defined within a week – Trigger test definitions • Meeting with Su Dong this afternoon to determine what test definitions are currently available, and will incorporate those – SVAC test definitions • Eduardo is defining • Will incorporate either high level descriptions or pointer to Eduardo’s document – End-to-End test definitions • Will baseline existing set, may be changes based on feedback from the yet to be determined review committee LAT System Engineering 7