GLAST Large Area Telescope WBS 4.1.B Instrument Science Operations Center Monthly Status Review

advertisement
GLAST LAT Project
Gamma-ray Large
Area Space
Telescope
Monthly Status Review - ISOC, 3 Nov 2004
GLAST Large Area Telescope
WBS 4.1.B
Instrument Science Operations Center
Monthly Status Review
3 Nov 2004
Rob Cameron
rac@slac.stanford.edu
650-926-2989
1
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
October Activity (1)

Management
– Presented ISOC overview to LAT IFC meeting
– Provided ISOC plans presentation for DOE mini-review
– Provided ISOC overview for LAT All Hands meeting
– SLAC “Safety comes first” standdown
• Core ISOC staff were able to resume LAT project work
relatively rapidly
 Work on CDR RFAs
– RFA#6: “Launch Critical Support Plan”
• More details learnt about GSFC IONet and CNE networks
– RFA#7: “Red/Yellow Limits”
• Temperatures: red limits at Acceptance Temp, yellow limits
5C inside AT. Will confirm with LAT Systems Eng that LAT
thermal model supports these limits.
• Other limits will be worked with LAT Systems Eng.
2
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
October Activity (2)


ISOC Requirements
– Participating in moves of FSW requirements to ground
elements
– Expanding mission planning requirements to capture
more details of products and interfaces
– Addressing I&T concern about completeness of planned
ISOC capabilities. Have reviewed ISOC requirements with
I&T online software developers. Will review ISOC
requirements with I&T SVAC.
ISOC Architecture
– Work continues on ISOC IT security plan and secure
network configuration
– Met with SCS management to understand SLAC network
security and available support for 24/7 ISOC operation
3
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
October Activity (3)


Flight Software coordination
– ISOC has worked with FSW team to define contents of
FSW User Guide
– ISOC-FSW TIMs continue: reviewed housekeeping
telemetry structure and usage
– Addressed ITAR concerns to ensure FSW T&C handbook
is compatible with SAI requirements and PDB
Mission Planning
– Had presentations on STK and SatTrack
– STK cost is $100k-$200k (1 or 2 fixed base or floating
licenses)
– SatTrack cost is $10k per computer. Used at Berkeley
SSL for RHESSI, FAST, WIND and to be used for THEMIS
– Use: event prediction, e.g. SAA transits, target visibility,
plus graphic display
4
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
ISOC Staffing



ISOC
– Bryson Lee started as software developer on Nov 1. Will
also work
– Interviewed 3 candidates for Test Developer position,
without success. B. Lee will support test development in
the near term.
FSW
– Reworking FSW staffing plans with inputs from Gunther
Haller
– Planning for future redeployment of programmer support to
other ISOC needs after FQT
SAS
– Search for SAS software infrastructure person started
5
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
ISOC Operations Facility

Long-term ISOC facility
– 2 meetings with Roger Blandford (KIPAC Director) on ISOC
use of Kavli building at SLAC.
– SLAC Kavli building completion is expected in late 2005
– Discussions have focused on “Light Lab” space, approx.
1600 sq. ft. for ISOC operations and some office area, plus
offices for other ISOC staff and visiting scientists. Space
should be available at building completion.
– ISOC requirement until Launch + 5 years is used for
discussions
– Many issues still to be worked: floorplan and build out cost
and schedule for lab space
– No firm agreement in place yet until more details are known
– Short term planning has dependencies on long-term plans
6
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
KIPAC
7
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
ISOC Facility
8
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
Plans for November




Start more detailed planning of ISOC participation in LAT I&T
activities at SLAC and NRL.
– Ensure minimal disturbance of I&T activities, but use the
opportunity to exercise ISOC
– Mainly telemetry capture and processing
– Investigate some limited command/control opportunities
– Need FSW on LAT
– Next stage: work with GOWG on details of ISOC activities
during I&T at SAI
Continued definition and development of ISOC software
elements
Continue to work on Kavli building usage for ISOC
Yet more work on ISOC staffing plans and M&S requirements
9
GLAST LAT Project
Monthly Status Review - ISOC, 3 Nov 2004
ISOC Demonstration




As defined in development schedule shown at ISOC CDR, there
will be several pre-launch demonstrations of ISOC functions
– November 2004
– January 2005
– March 2005
– May 2005
– October 2005
– January 2006
Demos interspersed before and between GRTs
Will be coordinated with Monthly Status review or other events
Presentation material available at ISOC WWW site:
http://www-glast.slac.stanford.edu/ioc/Demo.htm
10
Download