SVAC Data Taking during LAT Integration @ SLAC

advertisement
GLAST LAT Project
Gamma-ray Large
Area Space
Telescope
SE Test Planning meeting October 4, 2004
SVAC Data Taking
during
LAT Integration
@ SLAC
Oct 4, 2004
Eduardo do Couto e Silva
SLAC
eduardo@slac.stanford.edu
650-926-2698
E. do Couto e Silva
1/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
SVAC Data Runs during LAT Integration @ SLAC
•
All this information will be included in
– “SVAC Plan for LAT Integration – LAT-MD-00575”
•
The SVAC data taking consists of cosmic rays and VG data for
– Low level instrument characterization (performance)
– Calibrations
•
We optimized the data taking time during Integration
– Calibration and characterization use the same data
•
Data is taken with the hardware in the following configurations
– Partially populated LAT (see next slide)
– Full LAT in vertical orientation
– Full LAT in horizontal orientation
• This is the configuration @ NRL during environmental tests
E. do Couto e Silva
2/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Partially Populated LAT – Cosmic Rays
12
13
14
15
12
13
14
15
12
13
14
15
12
13
14
15
8
9
10
11
8
9
10
11
8
9
10
11
8
9
10
11
4
5
6
7
4
5
6
7
4
5
6
7
4
5
6
7
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
1 Tower
(Single bay, special grid)
2 Towers
4 Towers
6 Towers
8 Towers
12
13
14
15
12
13
14
15
12
13
14
15
12
13
14
15
12
13
14
15
8
9
10
11
8
9
10
11
8
9
10
11
8
9
10
11
8
9
10
11
4
5
6
7
4
5
6
7
4
5
6
7
4
5
6
7
4
5
6
7
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
0
1
2
3
10 Towers
12 Towers
14 Towers
16 Towers
LAT
•
TWO DAYS OF DATA TAKING FOR EACH CONFIGURATION
•
Day 1: 24 hours or less (TBD) for charge injection and/or support calibrations
– To provide input to calibrations with cosmic rays
– To be divided between TKR and CAL
•
Day 2: 24 hours of cosmic rays at nominal settings for each configuration
– low level instrument characterization
– Calibrations with cosmic rays
E. do Couto e Silva
3/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Partially Populated LAT - SVAC Data: Day 1
•
TKR Calibrations (max 12 hours, preferably 8 to stay within 1 shift)
– Electronic calibrations of TOT/GTFE (4-5 hours)
– Other electronic calibrations (~ 4 hours)
•
CAL Calibrations (max 12 hours, preferably 8 to stay within 1 shift)
– Electronic calibrations for each GCFE (2 hours)
– FLE/FHE scans with muons (~ 2 hours)
– Muon data taking –(4 hours)
– TKR: trigger enabled
– FLE: ~ 100 MeV but disabled
– FHE: ~ 1 GeV enabled
• Flight settings
– LE rails: ~ 1.6 GeV
– HE rails: ~ 100 GeV
• Auto Range: one range readout
– Zero-suppression: enabled
– LAC threshold ~ 1 MeV
– CAL TACKdelay 70 (TBR)
E. do Couto e Silva
4/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Partially Populated LAT - SVAC Data: Day 2
•
•
1 hour of CAL pedestals with Zero suppression OFF
23 hours of cosmic ray data taking with the following settings
•
TKR nominal settings
– Flight Configuration
– TKR trigger enabled
– TKR delay 0 (TBR)
– TKR hit threshold (0.25 MIP)
•
CAL Nominal Settings
– Flight Configuration
–
–
–
–
TKR: trigger enabled
FLE: ~ 100 MeV but disabled
FHE: ~ 1 GeV, enabled
CAL TACKdelay 70 (TBR)
– Muon Gain:
– LE rails: ~1.6 GeV
– HE rails: ~4 GeV
– Intermediate Data Volume:
– Auto-range, four-range readout
– Zero-suppression: enabled
– LAC threshold ~ 1 MeV
E. do Couto e Silva
5/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
SVAC Data Taking after LAT assembly (1)
• 15 days (24 h/day) at vertical orientation
– 10 days – Best GND calibration sample
JJ recommends
zero suppression off
if we can afford it
– TKR nominal settings
– CAL HE muon gain: (zero suppression ON, LAC: 1 MeV ,
autorange, four range readout)
– ACD nominal settings (Zero Suppression OFF, disable
veto)
– 2 days – zero suppression data with full LAT
– TKR nominal settings
– CAL HE muon gain: (zero suppression OFF, autorange,
four range readout)
– ACD nominal settings (Zero Suppression OFF, disable
veto)
– 2 days – test as you fly (TKR and CAL only)
– TKR nominal settings
– CAL Flight gains: (zero suppression ON, LAC: 1 MeV ,
autorange, one range readout)
– ACD nominal settings (Zero Suppression
ON, disable veto)
E. do Couto e Silva
6/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
SVAC Data Taking after LAT assembly (2)
• 1 day (24 h/day) at vertical orientation - ACD Calibrations
– 6 hours – ROI 1: All ACD sides enabled
– ACD nominal settings (Zero Suppression OFF, enable trigger)
JJ recommends to OR
– TKR nominal settings and trigger disabled
all conditions or use
ROI 1 only
– CAL nominal settings and trigger disabled
(depends on what the
ACD noise rate is)
– 6 hours – ROI 2: S1 && S2
– ACD nominal settings (Zero Suppression OFF, enable trigger)
– TKR nominal settings and trigger disabled
– CAL nominal settings and trigger disabled
– 6 hours – ROI 3: S3 && S4
– ACD nominal settings (Zero Suppression OFF, enable trigger)
– TKR nominal settings and trigger disabled
– CAL nominal settings and trigger disabled
– 6 hours – ROI 4: Top && ( S1 || S2 || S3 || S4)
– ACD nominal settings (Zero Suppression OFF, enable trigger)
– TKR nominal settings and trigger disabled
– CAL nominal settings and trigger disabled
E. do Couto e Silva
7/13
GLAST LAT Project
1 Tower
(Single bay, special grid)
SE Test Planning meeting October 4, 2004
SVAC Data Taking – VG
12
13
14
15
12
13
14
15
12
13
14
15
8
9
10
11
8
9
10
11
8
9
10
11
4
5
6
7
4
5
6
7
4
5
6
7
0
1
2
3
0
1
2
3
0
1
2
3
2 Towers
8 Towers
LAT
•
For each configuration 1 DAY OF DATA TAKING (16 h/day)
•
3 hours of cosmic rays
– Used as a control sample for background subtraction
– Nominal settings with hardware oriented horizontally
– TKR trigger
– ACD nominal settings, zero suppression ON, disable veto
– CAL: high muon gain, one range readout.
•
13 hours VG at nominal settings for each configuration
– low level instrument characterization
– Nominal settings with hardware oriented horizontally
– TKR trigger
– ACD nominal settings, zero suppression ON, disable veto
– CAL: high muon gain, one range readout.
E. do Couto e Silva
8/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Can We Handle the Data Volume?
•
ACD
– (89 tiles + 9 ribbons) x 2 PMTs = 194 signals
– Zero suppression OFF = 194
– Zero suppression ON = 5
– We neglect noise occupancy for this calculation
» All numbers should be multiplied by ~ 2 to get the results in bytes
•
CAL
– 8 layers x 12 crystals x 2 ends x 16 towers = 3072 signals
–
–
–
–
•
Zero suppression OFF and 4 range = 4 x 3072 = 12238
Zero suppression ON (~2 crystals hit/layer in single tower) = 32
Zero suppression ON and 4 range = 4 x 32 = 128
We neglect noise occupancy for this calculation
» All numbers should be multiplied by ~ 2 to get the results in bytes
TKR
– 1536 strips x 36 layers x 16 towers x 10-4 occupancy = ~100 signals
» Number above should be multiplied by ~ 2 to get the results in bytes
E. do Couto e Silva
9/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Data Volume during LAT Integration
• 1 Tower
– TKR ~ 200
– CAL ~ 256
– ~460 x 25 Hz x 86400 s x 1 days = 0.01 TBytes
• 2 Towers
~ 0.02 TBytes
• 4 Towers
~ 0.04 TBytes
• 6 Towers ~ 0.06 TBytes
• 8 Towers
~ 0.08 TBytes
• 10 Towers ~ 0.10 TBytes
• 12 Towers ~ 0.12 TBytes
• 14 Towers ~ 0.14 TBytes
• 16 Towers ~ 0.16 TBytes
– Estimates were obtained by multiplying the rate by number
of towers available to trigger
• Total
~ 0.72 TBytes
E. do Couto e Silva
10/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Data Volume: LAT - “Long runs” (1)
12 13 14 15
• 2 weeks (24 h/day) at vertical orientation
9 10 11
– 10 days – Best GND calibration8 sample
4
5
6
7
12
13
14
15
12
13
14
15
8
9
10
11
8
9
10
11
4
5
6
7
4
5
6
7
0
1
2
3
– TKR ~ 200
0
1
2
3
0
1
2
3
– CAL ~ 256
2 Towers
1 Tower
8 Towers
(Single
bay,
special
grid)
– ACD ~ 388
» ~844 x 300 Hz x 86400 s x 10 days = 0.218 Tbytes
– 2 days – zero suppression data with full LAT
– TKR ~ 200
– CAL ~ 25576
– ACD ~ 388
» ~26000 x 300 Hz x 86400 s x 2 days = 1.347 Tbytes
– 2 days – test as you fly (TKR and CAL only)
– TKR ~ 200
– CAL ~ 64
– ACD ~ 388
» ~652 x 300 Hz x 86400 s x 2 days = 0.034 Tbytes
E. do Couto e Silva
11/13
LAT
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Data Volume LAT - “Long runs” (2)
• 1 day (24 h/day) at vertical orientation – ACD Calibrations
– Baseline GND calibration configuration for CAL and TKR
– TKR ~ 200
– CAL ~ 256
– ACD ~ 388
» ~844 x 200 Hz x 86400 s x 1 days = 0.014 Tbytes
• 1 week (24 h/day) at horizontal orientation
– 7 days – Baseline GND calibration prior to NRL
– TKR ~ 200
– CAL ~ 256
– ACD ~ 388
» ~844 x 200 Hz x 86400 s x 7 days = 0.101 Tbytes
E. do Couto e Silva
12/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
SVAC runs: Data Volume during I&T at SLAC
•
•
•
•
•
•
•
•
•
SVAC Day 1 (during I&T)
SVAC Day 2 (during I&T)
Long Runs Vertical: Muon Gain
Long Runs Vertical: Zero Sup.
Long Runs Vertical: Flight Config
Long Runs Vertical: ACD Calib
Long Runs Horizontal
E2E tests (see Gary’s list)
VG data taking (TBD)
•
Total of raw LDF data
09 days
09 days
10 days
02 days
02 days
01 days
07 days
05 days
03 days
0.18 Tbytes
0.72 Tbytes
0.22 Tbytes
1.35 Tbytes
0.03 Tbytes
0.01 Tbytes
0.10 Tbytes
0.10 Tbytes
0.05 Tbytes
~ 3 Tbytes
» The number above was rounded up
•
Total after offline processing (x 2.5)
•
•
If ACD zero suppression is ON we reduce raw data volume by ~ 0.3 Tbytes
About 4000 raw files of ~ 500 MB size to search and analyze so we depend
strongly on the elog database for searching runs.
No reprocessing is assumed !
•
E. do Couto e Silva
~ 7.5 Tbytes
13/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Questions to be addressed
•
Need similar data volume estimation ASAP for all other tests if I&T
wants to ask SAS to provide support. Otherwise I&T should work out
how to get more disks on it own.
•
Does the volume of non zero suppressed data poses a challenge for
data transfer?
• DMZ and local storage in Clean room PC
•
Can the network and/or LATTE handle data throughput?
– It gets worse with the E2E high trigger rate tests
•
Are there changes expected when we have FSW available?
– Calibration scripts and commanding
– Data reduction
– Retrieval of register configuration information
– Data taking Time
– Does the runs database(elog) need to be modified?
E. do Couto e Silva
14/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Back up slides from Gary
for E2E Test using particle sources
E. do Couto e Silva
15/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
Event Sizes
Zero Supp (=Nominal Trigger Message)
Zero Supp, All 4 ranges
No Zero Supp
No Zero Supp, All 4 ranges
~250 bytes
~450
~6,400
~25,000
Max to SIIS (Space Craft Instr Interface Sys) ~ 5 Mbytes/sec
High Rate, No Zero Supp
= 10 K events/sec x 6.4 Kbytes/event
= 64 Mbytes/sec
Prescale the trigger?
– No, want to exercise the electronics !
Software Filter (in DAQ) ?– Yes
1) to get below
5 Mbytes/sec
2) to get below ~150 Kbytes/sec so 1 hr file <500 Mbytes
E. do Couto e Silva
16/13
GLAST LAT Project
SE Test Planning meeting October 4, 2004
E2E Data Volume
• Software Filter (TBD) keep 1 hour run File Sizes < 500 Mbytes
– Prescales Ext Trigs before writing to disk
– Prescales all Trigs in non-zero supp data
– Prescales all Trigs for high rate Cal Trigs, Am241 data
• E2E Particle Data volume generated at SLAC by I+T
– Individual Tests
87 runs x .5 Gb
~ 44 Gbytes
– Daily Trending
30 days x 1 hr x .5 Gb ~ 15 Gb
– Monthly Long Run 1 month x 24 hr x .5 Gb ~ 12 Gb
• E2E Data volume generated at Thermal Vac by I+T
– ~1/2 x Individual Tests
~ 22 Gb
• Total data volume = 100 – 1000 Gb (depends on software
filtering decisions)
E. do Couto e Silva
17/13
Download