GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 GLAST Mission Large Area Telescope Project Gamma-ray Large Area Space Telescope Project Status March 31, 2004 Lowell A. Klaisner, Project Manager Stanford Linear Accelerator Center klaisner@slac.stanford.edu rev. 13 1 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Introduction • The transition to the first flight units has had the expected challenges and impacts – The LAT team is effectively stepping up to solve problems • Producing flight hardware – First tower integrated with the grid this fiscal year – Tight, success-oriented schedule • We will see risk to the instrument delivery date until we have established a production rate history – Plan has 9 weeks float to delivery for observatory integration • Overall project contingency is OK – Project is 65% complete – Contingency is 29% of cost to go • Funding in the current fiscal year is an issue – All funding for FY04 is allocated rev. 13 2 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 GLAST MISSION SUMMARY •Objective: Larger field of view (FOV), higher sensitivity, and broader energy detection range than any previously flown gamma-ray mission. •Mission Duration: 5 yrs (10 yr Goal) •Orbit: 565 km Circular, 28.5° Inclination •Launch Date: February 2007 •Launch Vehicle:Delta 2920H-10 •Launch Site: Kennedy Space Center rev. 13 3 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 GLAST Observatory LAT GBM NaI Sensors LAT Radiators Solar Array GBM BGO Sensors +Z Spacecraft +Y +X rev. 13 4 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Instrument Structure Anti Coincidence Detector 16 Tracker Modules Grid 16 Calorimeter Modules Electronics Modules Radiators Mass Power rev. 13 3000 Kg 650 Watts 5 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 LAT Organization Chart Collaboration Science Team Principal Investigator P. Michelson Instrument Scientist S. Ritz EPO L. Cominsky Instrument Science Performance S. Ritz Senior Science Advisory Committee N. Gehrels Project Manager L. Klaisner D. Horn J. Martin D. Nicholson, Admin Instrument Advisory Committee S. Kahn Deputy for Systems D. Horn Project Controls T. Boysen Design Integration & Analysis M. Nordby Mission Assurance D. Marsh Electrical Integration G. Haller Manufacturing Eng. J. Clinton System Engineering P. Hascall Integration &Test E. Bloom TKR R. Johnson CAL N. Johnson rev. 13 ACD D. Thompson Mechanical M. Campell DAQ & FSW G. Haller ISOC W. Craig (acting) D. Lung, Deputy SAS R. Dubois 6 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Partner Contributions to LAT • Tracker (TKR) - Italy (ASI/INFN): provide Si-strip detectors & assemble & test TKR modules Tracker - Japan: provide Si-strip detectors & oversee detector production - SU-SLAC & UCSC (USA): provide Si-strip detectors, front-end electronics, cable plant, components • Calorimeter (CAL) - IN2P3 (France): mechanical structure - Sweden: CsI xtals & acceptance testing - NRL (USA): Fabricate, assemble and test CAL modules • Anticoincidence Detector (ACD) • - GSFC (USA) Fabricate, assemble and test the ACD including micrometeoriod shield / thermal blanket • Data Acquisition System (DAQ) - SU-SLAC & NRL (USA): Data acquisition hardware & flight software • Mechanical/Thermal System - SU-SLAC (USA): provide LAT Grid, thermal radiators, heat pipes & ancillaries LAT Integration & Test - SU-SLAC (USA): assembly & test of LAT • - NRL (USA): instrument-level environmental tests rev. 13 ACD e+ e– Grid Calorimeter All partners contributing to science analysis preparations: software, science simulations 7 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 International agreements • • MoAs between Stanford Univ-SLAC and: – INFN, ASI, Italy pending signature – IN2P3, France; NRL revised & signed – CEA/DSM/DAPNIA, France; NRL revised & signed – Royal Inst. of Technology & Stockholm Univ., Sweden; NRL signed – Hiroshima Univ., ISAS & RIKEN, Japan; UCSC/SCIPP signed – NASA – Department Of Energy signed Agency level agreements – NASA – CNRS/IN2P3 Agreement pending; draft exchanged – NASA – CEA Agreement signed – NASA – ASI Agreement pending; draft exchanged – NASA – Japan draft sent to JAXA – NASA – Sweden draft in process rev. 13 8 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Budget, Cost, Funding, Performance 120 Actual Commitments Actual Costs Funding Earned Budget Planned Budget + Commitments Planned Budget $M 90 60 30 0 A M J J A S O N D J F M A M J J A S O N D J F MA M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F MA M J J FY00 rev. 13 FY01 FY02 FY03 FY04 FY05 9 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Cost and Schedule Variance 4.1 GLAST LAT PROJECT 4,000 2,000 0 1 month -2,000 CV -4,000 SV -6,000 -8,000 MAR03 APR03 MAY03 JUN03 JUL03 AUG03 SEP03 OCT03 NOV03 DEC03 JAN04 FEB04 BCWS 49,452 52,780 55,210 57,854 60,114 62,777 66,081 69,052 69,801 73,433 77,394 81,916 BCWP 46,114 49,627 51,835 54,564 56,229 58,348 60,548 62,648 69,724 73,353 76,574 80,742 ACWP 45,435 48,344 51,125 54,402 57,264 59,429 61,990 63,894 67,721 71,081 74,989 78,460 CV 679 1,283 710 162 -1,035 -1,081 -1,443 -1,246 2,003 2,271 1,585 2,281 SV -3,338 -3,152 -3,375 -3,290 -3,885 -4,428 -5,533 -6,404 -76 -80 -820 -1,175 rev. 13 10 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Contingency Analysis (K$) February 29, 2004 Baseline & Costs Funding Budget at complete Work Performed Cost to Go Percent complete Contingency Contingency/ Cost to Go rev. 13 $136,830 $124,383 $80,742 $43,641 65% $12,447 29% 11 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 GLAST Mission Office Support in FY04 • The GLAST mission management and the LAT project management identified areas were additional manpower would help assure that the project meet its goals. The mission office added funds to the project for this additional staff. – Integration and Test Staff $ 523K – Tracker Staff $ 738K – Performance and Safety Assurance $ 973K – Flight Software Staff $ 747K Total $2,981K • In addition, the mission office added funds to support the costs associated with the following CCB actions: – ACD Mechanical Materials and Support $ 195K – ACD Photomultiplier Anomaly Resolution $ 299K – ACD Base Electronics Assembly $ 222K – ISIS Scope Change $ 94K Total $ 810K Total funds added $3,791K • Also, the Mission Office has provided technical support – Thermal Engineering – EMI/EMC Engineering – Tracker and ACD Management – Mechanical Analysis rev. 13 12 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 History of the Budget at Complete Since Rebaseline Budget at Complete Delta Budget at Complete 130,000 14,000 125,000 12,000 10,000 120,000 8,000 K$ K$ 115,000 6,000 110,000 4,000 105,000 2,000 Mar-04 (Projected) Feb-04 Jan-04 Dec-03 Nov-03 Oct-03 -2,000 Sep-03 95,000 Aug-03 0 Jul-03 100,000 SepDecFebOct-03 Nov-03 Jan-04 03 03 04 Aug03 With 0 0 0 0 11,767 0 3,940 939 -241 Without 0 0 0 0 11,767 0 959 939 569 Month Month BAC rev. 13 Mar04 (Proje Jul-03 BAC w/o Manpower increase & MPS change 13 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 BAC projections to end of project • Contingency available – 29% of cost to go $12,447K $140,000 Jul-05, $135,535 $135,000 Allocation of project contingency since rebaselining – Between the end of July 03 and the end of February 04 • Earned value $24,513K • Allocation of cont. $ 4,879K • Percentage 20% Jul-05, $133,111 Feb-04, $124,383 $125,000 Jul-03, $119,504 $120,000 $115,000 $110,000 Mar-03, $107,482 $105,000 $100,000 May-02, $99,973 BAC (20%) BAC $697 per month $95,000 • Rate of Allocation over the last 7 months – $697K per month – Projection at this rate for the remaining 16 months $11,152K • Cost risk will decline as project matures rev. 13 $90,000 M ay Au 02 gN 02 ov -0 Fe 2 bM 03 ay Au 03 gN 03 ov -0 Fe 3 bM 04 ay Au 04 gN 04 ov -0 Fe 4 bM 05 ay -0 5 • Rebaseline $130,000 14 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 FY04 Cash Flow As of February Report March Actions* Transfer of MPS Tax Current projection At the Costs $111,024 $810 ($801) $111,033 end of FY04 Funding Difference $110,600 ($424) $1,310 $500 ($801) $0 $111,109 $76 * Mission office moved $500K of LAT funding from FY 05 to FY04 • • Planned costs March through September – Project additional funds needed on FY04 • At $697K per month • At 20 % of costs (recent experience) • At 29% of costs (rate for the remainder) $29,108K $ 4,182K $ 5,821K $ 8,441K Mitigation – Move activities into FY05 – $5,000 Bridge available from Stanford University – Mission office move NASA funding forward, if available rev. 13 15 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Potential Liens Tracker Flight Nanoconnectors Tracker Bias Circuit Redesign/Refab Tracker MCMs and Source Inspection DAQ Additional ACTEL Parts, FPGAs DAQ Front End Simulator DAQ Global Trigger/GASU Board Wiring DAQ TEM Engineering Models Lockheed Martin Phase II Increase ACD ASIC delay Additional MGSE items for I&T Extend QA support for Tracker Tracker GTRC v7 cycle Calorimeter increased TVAC Testing Japanese Funding Total rev. 13 FY04 $95 $66 $348 $253 $329 $260 $400 $656 $400 $132 $90 $160 $50 TBD $3,239 16 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 LAT Schedule TKR A 07/02/04 07/28/04 TKR 14 12/21/04 01/25/05 ACD 11/03/04 01/03/05 CAL A 07/09/04 CAL 14 12/2/04 DAQ 11/01/04 01/11/05 01/21/05 TEM/PS 14 10/05/04 01/07/05 X-LAT 08/12/04 08/12/04 FSW Formal Test 02/18/05 02/18/05 Install Twrs 1-13 13 wks Install Tower 14 1 wk Install Gbl Items 6 wks 08/12/04 07/12/04 08/13/04 TEM/PS A 05/12/04 08/02/04 GRID Assembly 06/11/04 07/22/04 Install Twrs A&B 8 wks 2 Tower CPT 3 wks 01/04/05 01/28/05 Feb. 2004 Data FSW Complete 12/13/04 12/15/04 01/10/05 02/04/05 02/23/05 03/18/05 05/11/05 06/07/05 System Test 11 wks 10/31/05 10/31/05 Float 9 wks Ship LAT 1 wk Enviro Test 15 wks Float 4 wks LAT RFI Observ. Integration Launch 02/07 5 Weeks Dates Nov, 03 Current rev. 13 Pre-Test / CD-4 Review 07/14/05 Pre-Ship Review 12/01/05 Color Code Subsystem I&T Test Mission 17 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 LAT Critical Path Tracker Bottom Tray Parts 4/9/04 (0) Integrate ACD 3/15/05 (0) Assemble Tracker Towers A-12 11/26/04 (0) Integrate Tkr/Cal Towers 12-14 2/3/05 (0) Integrate Cross-LAT Plate 3/18/05 (0) System Test 6/6/05 (0) Integrate LATWide Electronics 2/25/05 (0) Ready for CD-4 and Pre-Environmental Test Review 6/7/05 (0) Completion Dates (baseline variance) rev. 13 18 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Threats to Schedule • Path to Integration and Test of Tower A – Completing detailed documentation – Getting fabrication contracts in place – Anomaly in qualification testing • Path to Integration and Test of the complete instrument – Achieving planned production rates – Execution of I&T plans – Rapid response to anomalies • Path to Environmental Test (CD-4) – Anomalies requiring de-integration – Rapid analysis of and response to anomalies rev. 13 19 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Level 1 and Level 2 Milestones Milestone Plan Float Level 1 Milestones – DOE/NASA Joint Oversight Group DOE Critical Decision (CD) 0 Approval CD-1 Approval CD-2 Approval CD-3 Approval Flight Grid Complete CD-4 Approval June 25, 2001 July 23, 2002 November 8, 2002 August 31, 2003 September 15, 2004 March 15, 2006 June 25, 2001 Actual July 23, 2002 Actual November 8, 2002 Actual August 31, 2003 Actual July 22, 2004 8 weeks June 7, 2005* 40 weeks Level 2 Milestones – Federal Project Managers Launch Balloon Flight Instrument Preliminary Design Review Instrument Critical Design Review Start LAT Integration Pre Environmental Test Review Instrument Pre-Ship Review August 1, 2001 January 8, 2002 May 16, 2003 August 24, 2004 July 14, 2005 December 1, 2005 August 1, 2001 January 8, 2002 May 16, 2003 August 2, 2004 June 7, 2005 October 1, 2005 Actual Actual Actual 3 weeks 5 weeks 9 weeks * The CD-4 Review is planned for June 7, 2005 and the CD-4 Approval will occur after validation by DOE. rev. 13 20 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Technical Status rev. 13 21 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Closed Issues • CDR/CD-3 – Loss of CNES funding • Successfully transferred work to the US • Funded at the rebaseline – ASICs • All flight ASICs are delivered • No unresolved problems – CAL-GRID joint • Added “Menning Plates” • Issue closed – Cross LAT plate thermal connection • Chose direct connection between DAQ boxes and plate • Issue closed • Rebaseline Review – Tracker bottom tray design • Design complete and parts in fabrication rev. 13 22 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Subsystem Status 1 • • • • Data Acquisition (SLAC) – Out for bid for the flight Tower Electronics Modules – Designs of all cards exist and prototypes in test – Flight Software peer review 2/26/04, monthly software demonstrations Tracker (UCSC, SLAC, INFN) – Production planning readiness workshop held in Italy – Thermal-Vacuum test of the engineering model complete – Flight production underway • Silicon ladders (30% complete), Multi Chip Modules, mid-trays, and bottom tray components – Need to complete the flight documentation and testing Mechanical (SLAC) – Flight GRID being machined Thermal (SLAC) – Flight heat pipes in fabrication (Lockheed Martin) rev. 13 23 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Subsystem Status 2 • Calorimeter (NRL, IN2P3) – Flight production well underway • • • • 80% of CsI crystals in hand • 25% of CDEs have been manufactured • Flight ASICs (~12,000) have been tested • All machined parts and 3 flight structures are complete Anti-Coincidence Detector (GSFC) – Flight scintillator detectors, phototube and electronic assemblies and the structure are in production Integration and Test (SLAC) – Facilities are ready to begin flight integration in August • Plan in place for support equipment and procurement started – I&T Kickoff held in March Instrument Science Operating Center (SLAC, SU, KIPEC, Collaboration) – Planning underway – Manager in place by end of Summer (Bill Craig, Acting) • Science Analysis Software (SLAC, Collaboration) – Initial suite of software tools in place – Highly successful Data Challenge 1 rev. 13 24 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Summary • No major outstanding technical issues – Analysis and testing continues • Producing flight hardware – One tower integrated in the grid this fiscal year – Tight, success-oriented schedule • Overall project contingency is OK – Project is 65% complete – Contingency is 29% of cost to go • Funding in the current fiscal year is an issue – All funding for FY04 is allocated • Continued strong support from NASA, DOE, and the Collaboration • A strong, talented and committed staff rev. 13 25 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Backup Slides rev. 13 26 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Cost Performance Report CAPW[3] Item (1) Current Period Actual Budgeted Cost Cost Variance Work Work Work Scheduled Performed Performed Schedule Cost (2) (3) (4) (5) (6) Cumulative to Date Actual Budgeted Cost Cost Variance Work Work Work Scheduled Performed Performed Schedule Cost (7) (8) (9) (10) (11) At Completion Latest Revised Budgeted Estimate Variance (12) (13) (14) 4.1.1 INSTRUMENT MANAGEMENT 442 442 545 0 -103 11,020 11,020 11,071 0 -51 15,945 15,945 0 4.1.2 SYSTEM ENGINEERING 139 139 179 0 -40 4,532 4,532 4,426 0 106 6,601 6,601 0 4.1.4 TRACKER 516 405 278 -112 127 11,386 10,952 11,143 -434 -190 14,698 14,698 0 95 131 753 36 -622 14,632 14,171 13,531 -462 640 22,103 22,103 0 347 208 322 -139 -114 11,750 11,235 10,799 -515 435 14,022 14,022 0 2,072 1,915 757 -157 1,158 11,472 11,912 11,352 440 560 20,350 20,350 0 4.1.8 MECHANICAL SYSTEMS 395 422 290 27 132 7,625 7,436 7,335 -189 101 13,478 13,478 0 4.1.9 INTEGRATION & TEST 240 234 210 -6 25 3,125 3,111 3,037 -14 74 7,373 7,373 0 4.1.A PERFORMANCE AND SAFETY ASSURANCE 133 133 73 0 61 1,447 1,447 1,140 0 307 2,469 2,469 0 3 3 17 0 -14 272 272 295 0 -24 328 328 0 4.1.C EDUCATION AND PUBLIC OUTREACH 64 60 61 -4 -1 1,438 1,437 1,260 -2 177 2,448 2,448 0 4.1.D SCIENCE ANALYSIS SOFTWARE 71 71 -12 0 84 1,892 1,892 1,747 0 145 3,243 3,243 0 4.1.E SUBORBITAL FLIGHT TEST 4 4 0 0 4 1,325 1,325 1,325 0 0 1,325 1,325 0 Gen. and Admin. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 124,383 124,383 0 12,447 12,447 0 136,830 136,830 0 4.1.5 CALORIMETER 4.1.6 ANTICOINCIDENCE DETECTOR 4.1.7 ELECTRONICS 4.1.B LAT INSTRUMENT SCIENCE OPERATIONS CENTER Undist. Budget Sub Total 4,522 4,167 3,471 -355 696 81,916 80,742 78,460 -1,175 2,281 Contingency Total 4,522 rev. 13 4,167 3,471 -355 696 81,916 80,742 78,460 -1,175 2,281 27 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Contingency Analysis Project Estimate (Escalated K$) WBS Item To Date To Go Cost* Cost Contingency Total Cost % Total Cost $ Plus Cont. 4.1.1 Instrument Management $ 11,020 $ 4,925 $ 15,945 16% $ 780 $ 16,725 4.1.2 Systems Engineering $ 4,532 $ 2,069 $ 6,601 14% $ 280 $ 6,881 4.1.4 Tracker $ 10,952 $ 3,746 $ 14,698 18% $ 665 $ 15,363 4.1.5 Calorimeter $ 14,171 $ 7,932 $ 22,103 23% $ 1,785 $ 23,888 4.1.6 ACD $ 11,235 $ 2,788 $ 14,022 32% $ 888 $ 14,911 4.1.7 Electronics $ 11,912 $ 8,438 $ 20,350 20% $ 1,707 $ 22,057 4.1.8 Mechanical Systems $ 7,436 $ 6,042 $ 13,478 40% $ 2,435 $ 15,914 4.1.9 Instrument Integration & Test $ 3,111 $ 4,263 $ 7,373 34% $ 1,438 $ 8,811 4.1.A Performance & Safety Assurance $ 1,448 $ 1,022 $ 2,469 29% $ 301 $ 2,771 4.1.B Instrument Science Operations Center $ 272 $ 56 $ 328 12% $ 7 $ 334 4.1.C Education & Public Outreach $ 1,437 $ 1,012 $ 2,448 0% $ - $ 2,448 4.1.D Science Analysis Software $ 1,892 $ 1,350 $ 3,243 18% $ 236 $ 3,479 4.1.E Suborbital Flight Test** $ 1,325 $ - $ 1,325 0% $ - $ 1,325 Subtotal*** $ 80,742 $ 43,641 $ 124,383 Unallocated Contingency Total Project Estimate 25% $ 10,523 $ $ 80,742 $ 43,641 $ 124,383 1,924 29% $ 12,447 $ 134,906 $ 1,924 $ 136,830 *"To date cost" refers to cost through February 29, 2004. "To go cost" refers to cost after February 29, 2004. **4.1.E Suborbital Flight Test is completed. ***Total contingency for project calculated against remaining costs at risk. Costs not at risk are costs to date and 4.1.C E/PO. rev. 13 28 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 History of Cost Estimate WBS Item 4.1 4.1.1 4.1.2 4.1.4 4.1.5 4.1.6 4.1.7 4.1.8 4.1.9 4.1.A 4.1.B 4.1.C 4.1.D 4.1.E LAT Budget at Completion Instrument Management System Engineering Tracker Calorimeter Anticoincidence Detector Electronics, Data Acquisition, Flight Software Mechanical Systems Integration & Test Performance & Safety Assurance Instrument Science Operations Center Education & Public Outreach Science Analysis Software Suborbital Flight Test Baseline May-02 $99,973 11,602 4,647 9,877 17,348 10,280 15,738 11,850 6,654 2,180 2,552 2,598 3,328 1,321 LAT Project Baseline CDR/CD-3 Rebaseline Mar-03 Nov-03 $107,462 15,357 6,453 10,915 17,830 11,557 16,672 10,373 6,588 1,607 2,512 2,684 3,595 1,321 $119,504 15,502 6,588 13,595 22,648 13,870 18,733 13,384 6,384 1,486 326 2,448 3,220 1,321 Baseline Change Current Feb-04 May-02 to Feb-04 $124,383 15,945 6,601 14,698 22,103 14,022 20,350 13,478 7,373 2,469 328 2,448 3,243 1,325 $24,409 4,342 1,955 4,821 4,755 3,742 4,612 1,628 720 289 (2,224) (150) (86) 4 24.4% 37.4% 42.1% 48.8% 27.4% 36.4% 29.3% 13.7% 10.8% 13.3% -87.2% -5.8% -2.6% 0.3% 4.1 Budget at Completion NASA DOE Japan $99,973 67,818 31,156 1,000 $107,462 72,577 33,499 1,387 $119,504 80,447 37,863 1,194 $124,383 84,771 38,418 1,194 $24,409 16,953 7,262 194 24.4% 25.0% 23.3% 19.4% 4.1 Contingency NASA DOE Japan Contingency as % of Cost to Go $21,266 15,422 5,844 0 29% $14,251 10,749 3,501 0 24% $14,345 10,208 4,137 0 29% $12,447 8,865 3,582 0 29% ($8,819) (6,557) (2,262) 0 -41.5% -42.5% -38.7% 0.0% 4.1 Total Estimated Cost NASA DOE Japan $121,240 83,240 37,000 1,000 $121,713 83,326 37,000 1,387 $133,849 90,655 42,000 1,194 $136,830 93,636 42,000 1,194 $15,590 10,396 5,000 194 12.9% 12.5% 13.5% 19.4% rev. 13 29 GLAST Mission - LAT Project DOE/NASA Review, March 31, 2004 Planned Staffing 250 150 100 Included in BAC rev. 13 Contributed 30 Jul-05 Jun-05 May-05 Apr-05 Mar-05 Feb-05 Jan-05 Dec-04 Nov-04 Oct-04 Sep-04 Aug-04 Jul-04 Jun-04 May-04 0 Apr-04 50 Mar-04 FTEs 200