GLAST LAT Project LAT Planning Meeting July 17th and 18th GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope I & T Input to LAT Planning Meeting July 17th and 18th Elliott Bloom SU-SLAC Subsystem Manager Brian Grist SU-SLAC Subsystem Engineer elliott@slac.stanford.edu, bgrist@slac.stanford.edu 650-926-2469 650-926-2998 4.1.9 - Integration and Test 1 GLAST LAT Project LAT Planning Meeting July 17th and 18th Key Milestone List to Delivery (Not Necessarily in Current PMCS) EM Plan, Procedures, EGSE and MGSE Complete 07/31/03 Receive CAL EM 08/08/03 Receive TKR mini-tower 08/22/03 EM Tower functional tests Complete 09/18/03 EM Tower Available for use by Flight Software 09/18/03 EM Calibration Complete 10/12/03 EM mechanical fit check using 1X4 Grid, TKR Mech tower, CAL 10/13/03 CAL EM at NRL Loading Doc; TKR mini-tower in Italian Customs 10/17/03 Support GSI Beam Test (CAL and TKR mini-tower) 11/14/03 All I&T Flight Techs on Staff (Mechanical and Electrical) 12/15/03 Flight Integration Training MGSE Ready 01/15/04 All Flight Integration Procedures Complete 02/15/04 All Flight Integration MGSE Complete with SDP 03/01/04 LAT Assembly Configuration EGSE Ready For Use 03/01/04 Integration Readiness Review 03/15/04 TKR A/B Available RFI 04/15/04 Grid Available RFI 05/20/04 CAL A/B Available RFI 05/20/04 4.1.9 - Integration and Test 2 LAT Planning Meeting July 17th and 18th GLAST LAT Project Multi-Tower EGSE (9/15/03) EGSE Crate ACD or Sensor Simulator CPU GASU WAN LCB 28 V Supply VME AEM Central Database EBM TEMs Firewall GEM Online Workstation CAL, TKR or Sensor Simulator T&DF System (LAT) 4.1.9 - Integration and Test SLAC EGSE 3 LAT Planning Meeting July 17th and 18th GLAST LAT Project Single Tower EGSE Configuration (GSI test) Online Workstation Subsystem (or simulator) CPU • Commanding • Telemetry • Monitoring AEM/TEM • Hardware Drivers LAT-COMM •External Trigger DC Power • Test Exec • Configuration • Commanding • Telemetry • Event Processing • Monitoring • Visualization • Data base • Message logger • Alerts • Electronic log Main Dataflow Ethernet Central Database WAN Back door debug RS-232 Ethernet Ethernet Router and Firewall VME Chassis External Hardware Subsystem/simulator Electronics/Online 4.1.9 - Integration and Test 4 LAT Planning Meeting July 17th and 18th GLAST LAT Project Key Milestone List to Delivery After Start of Flight I&T (Not in Current PMCS) Start Tower A/B Installation/Test Start Tower 1/2 Installation/Test Start Tower 13/14 Installation/Test Finish Tower Installation/Test Finish Installation of ACD/ELEX/X-LAT Flight Configuration Ready for System Test Complete System Test LAT Shipped for Environmental Testing Environmental Testing Complete LAT RFI 4.1.9 - Integration and Test 05/20/04 07/01/04 10/28/04 11/11/04 12/23/04 12/23/04 04/21/05 07/21/05 11/03/05 12/01/05 5 LAT Planning Meeting July 17th and 18th GLAST LAT Project ACD or Sensor Simulator GASU SIU Spacecraft simulator CPU Discretes 1553 1553 LCB 28 V Supply Central Database SSR AEM EBM GEM 3 EPUs TEMs Test Point on LAT EMI Skirt LAT Firewall CPU LCB CAL, TKR or Sensor Simulator WAN LAT Assembly Configuration (3/1/04) Online Workstation EGSE Crate CPU LCB SLAC EGSE 4.1.9 - Integration and Test 6 LAT Planning Meeting July 17th and 18th GLAST LAT Project ACD GASU SIU Spacecraft simulator CPU Discretes 1553 1553 LCB 28 V Supply AEM WAN Complete Flight Unit Configuration & CU (12/24/04) Central Database SSR EBM GEM 3 EPUs LCB TEMs Test Point on LAT EMI Skirt CAL, TKR Firewall CPU Online Workstation EGSE Crate CPU LCB LAT SLAC EGSE 4.1.9 - Integration and Test 7 GLAST LAT Project LAT Planning Meeting July 17th and 18th Interdependencies • Dependent on deliveries from all subsystems to be able to do the core of our work. – EM CAL & TKR mini-tower deliveries. – EM GASU and flight software support from ELX. – All Flight Hardware and Software. – MGSE FEM Analysis • Budget for I&T Flight Electronic Techs and the hiring of those techs (4 full time people starting 12/15/03) is currently the responsibility of ELX. I&T will schedule the work for these Techs. • System engineering test plans are required as input to I&T test plans and resulting procedures. • Mission level EGSE decisions can impact I&T EGSE schedule and budget. 4.1.9 - Integration and Test 8 GLAST LAT Project LAT Planning Meeting July 17th and 18th Flight Hardware Procurements • No flight hardware procured by I&T. All flight components come from a subsystem. 4.1.9 - Integration and Test 9 GLAST LAT Project LAT Planning Meeting July 17th and 18th Flight Hardware Manufacturing Plan Status • • • • • • • • • • • • • • • LAT-MD-01376 LAT-MD-01137 LAT-MD-01533 LAT-MD-00446 LAT-MD-01587 LAT-MD-01598 LAT-MD-01462 LAT-MD-01836 LAT-MD-01837 LAT-MD-01838 LAT-MD-00676 LAT-MD-01386 LAT-MD-01586 LAT-MD-01055 LAT-MD-00440 LAT Integration & Test Plan In Work LAT EM Test Plan In signoff EGSE Plan In revision SVAC Plan Released SVAC Test Plan Released LAT Weight and CG Test Plan Released MGSE Development Plan In signoff LAT Dynamics Test Performance Plan Draft in Cyberdocs LAT Thermal Test Performance Plan Draft in Cyberdocs LAT EMI Test Performance Plan Draft in Cyberdocs LAT Assembly Sequence In revision LAT Facilities Plan Released LAT Survey & Alignment Performance Plan In signoff LAT Electrical Test Performance plan Released LAT Particle Test Plan In signoff 4.1.9 - Integration and Test 10 GLAST LAT Project LAT Planning Meeting July 17th and 18th Engineering Model Testing Closure Status • I&T Tests of the TKR mini-tower were done and the results reported to the Engineering meeting at June 10 Engineering Meeting. Data is still being worked. • EM tower (CAL EM and TKR mini-tower) due in August to I&T • Complete EM Tower functional test by September 18th and then make available to Flight Software. • Complete EM Calibration by October 12th. • Need 1x4 Grid and TRK EM Mechanical tower a week before Mechanical fit check to assemble TRK EM into grid. • Perform a mechanical fit check using 1x4 Grid, TKR Mechanical Tower, and EM CAL on October 13th. • CAL EM on the NRL loading dock and the TKR mini-tower in Italian Customs by October 17th. • Support the GSI Beam Test, including the CAL and the TKR mini-tower (run Carbon in the daytime) November 14th – 24th. 4.1.9 - Integration and Test 11 GLAST LAT Project LAT Planning Meeting July 17th and 18th Open Flight Design Issues/ Status Trades • CAL-Grid interface design, impacts I&T MGSE, assembly, processes, and procedures. Design not completed. • Grid EMI Skirt design impacts I&T assembly, processes and procedures. Design not completed. • X-LAT plate design impacts I&T MGSE, assembly, processes and procedures. Design not completed. • Radiator interface and MGSE design impact I&T, assembly, processes and procedures. Design not completed. • Environmental test sensor requirements impact I&T assembly, processes and procedures. Requirements have not been finalized. • LAT pointing knowledge requirements are under review by the project. I&T test plans cannot be finalized until we know the final requirements. 4.1.9 - Integration and Test 12 LAT Planning Meeting July 17th and 18th GLAST LAT Project Cost/Schedule Status (May Month End) -2% variance -5% variance Cost Variance – GREEN Schedule Variance – YELLOW Beam test change request has been approved and has been incorporated for the June Report. The monthly Cost and Schedule Variances are trending negative 4.1.9 - Integration and Test 13 GLAST LAT Project LAT Planning Meeting July 17th and 18th Issues/Concerns/Suggestions/Risks • Late delivery to I&T of EM parts and EGSE software test scripts. Late delivery has delayed preparations for LAT, particularly in areas of IFCT and SVAC. Possible impact on EGSE. Part of EGSE/MGSE verification strategy depends on I&T EM program. • • • • • • • Finalization of all LAT test plan requirements is not complete post CDR. This is resulting in compressed schedule and potential increased cost for I&T. Current estimates are September for completing all test plans from the Design Team. Delivery of flight hardware to I&T may be late. I&T EGSE is proceeding with in-house developed test executive software. Change to another system for Observatory and/or IOC will require major cost change request. Spacecraft interface detail uncertainty. Environmental test fixtures. EGSE interface. MGSE handling fixtures. SIIS fidelity uncertainty. Delivery of flight hardware to I&T may be late. When will a decision be made about where to go for Environmental Testing? This will impact preparations and design of Vib and T/V fixtures. 4.1.9 - Integration and Test 14