GLAST LAT Project Gamma-ray Large Area Space Telescope GLAST Large Area Telescope WBS 4.1.D SAS LAT Monthly Managerfest Richard Dubois LAT SAS Subsystem Manager LAT Monthly Apr 14 2004 - SAS 1 GLAST LAT Project March - April Accomplishments • • • • Flight Integration Support front and center – Current version of GlastRelease under test by I&T – System tests under construction; unit tests on LDFreader – Investigating bug/issues tracker to have in time to support config control of SAS tools – Working with Eduardo on delivery of calibration algorithms (end May) – Agreement from subsystems on update of geometry doc. – Calibration update user interface on track OPUS pipeline – Database updating code done – Now working on batch interface/monitoring – One week slip expected to 1st week May Refocused SciTools architecture design post DC1 – First iteration of architecture done – Developer walkthrough held last week Starting HEASARC Network Monitoring with SLAC Computing Center – Now identified machine inside HEASARC to do file transfer tests • Thanks to Al Vernacchio for intervention! – Will provide long term understanding of file transfer speeds and reliability – Ground Systems proposing FastCopy as commercial tool for transfer • We offered SLAC’s bbcp as an alternative to consider LAT Monthly Apr 14 2004 - SAS 2 GLAST LAT Project Getting to End of May • I&T stuff ready to try – Sim/recon, calib algs and infrastructure, pipeline • Investigating new technology for next iterations of major infrastructure products – Application servers; web services; Java; Enterprise Java Beans etc – In widespread commercial use; passed us by • SLAC data server • OPUS pipeline • Release Manager • System Tests – System tests are being used as proof of principle • “traditional” implementations of the others will be supported for I&T with transitions when sensible/transparent • Get bug/issues tracker in place • Initiate users windows server at SLAC LAT Monthly Apr 14 2004 - SAS 3 GLAST LAT Project Key Milestones End May – first delivery of SAS tool to I&T Early June – kickoff I&T Analysis Workshop Mid (?) July – 2nd Analysis workshop Aug 4 – ISOC CDR Aug 17-18 - GSDR September - first hardware data analysis Early 2005 – DC2 (depends on Flight Int work load) LAT Monthly Apr 14 2004 - SAS 4 GLAST LAT Project Issues & Concerns Delivery of calibration algorithms Working with subsystems to make sure an adequate set happens OPUS operating (have 3 weeks float to end May deadline) Should be plenty of float for actual hardware ScienceTools taking back seat; prep for DC2 will be harder if Flight Int takes significantly more resources Need to know what support is needed from SAS for NRL env testing; Spectrum Astro, KSFC. “Porta-farm”? Need to start ramping up compute resources at SLAC next FY Is there money? LAT Monthly Apr 14 2004 - SAS 5