GLAST LAT Project Mechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager 1 GLAST LAT Project Mechanical Systems SLAC Status 2 GLAST LAT Project Mechanical Systems Grid Qual Static Load Test • Hardware – Grid Box assembly is 99% complete – All GSFC and Spectrum provided hardware is on hand • Pre-Test (SLAC activities) • – Test Interface Plate (TIP) Assembly delayed due to personnel conflicts with ACD operations – in work now – Need to return Spectrums Interface plate by mid-Sept. – Shipping container for Grid 2 on TIP due 9/7/05 Test (NTS activity) – Component flexure test required to proof load flexures prior to integration with the Flight LAT on the Test Interface Plate has been added to NTS SOW • Test performed on TIP assembly prior to SLT • Flexure strain gages also characterized for LAT sine vibe testing – NTS has evaluated final load cases and additional test above and submitted delta cost proposal (+$XXK) which is still within original budget 3 GLAST LAT Project Mechanical Systems Grid Qual Static Load Test Schedule 4 GLAST LAT Project Mechanical Systems Drawing Release Plan • • 66 of 73 (90%) drawings released – 3 MLI drawings (in work) – 4 unreleased parts not needed until Radiator fit check Known drawing revisions 5 GLAST LAT Project Mechanical Systems Concerns • • Lockheed Martin - Radiator delivery schedule – See LM presentation Completion of Grid Thermal Control System hardware installation delay until Sep 05. – Will try to perform on a non-interference basis, but may impact LAT schedule. – Heater bonding fixture trials underway in I&T 6 GLAST LAT Project Mechanical Systems Open Flight Design Issues • • Radiator integration sequence – Coupon testing of repeated make & break of joint has been tested. Results were inconclusive due to test facility problems. – Test facility alternatives under investigation. – Disassembly facilitated by use of mold release agent – Baseline process used for LM Radiator thermal vacuum test set up Radiator vibration requirements – Sine vibration testing will not be performed at LM • Test options under investigation 7 GLAST LAT Project Mechanical Systems MECH Qualification Program Grid-Top Flange Heat Pipe bond process qual Grid Box Assy Static Load test Complete. Report released Planning in work. Perform on Grid #2 X-LAT Plate Thermal Vac test Complete less MRB on final results Radiator Variable Conductance Heat Passed burst test, heat Pipe new extrusion capacity test after charging Radiator Acoustic at LMMS Radiator Thermal Vacuum at LMMS TCS-Radiator Thermal Balance at LMMS Comp Sep 05 Comp Comp Comp Sep 05 Sep 05 8 GLAST LAT Project Gamma-ray Large Area Space Telescope Mechanical Systems Cost/Schedule Reports for 4.1.8 Mechanical Systems Presentation July 2005 Month End 9 GLAST LAT Project Mechanical Systems Level 3 Milestone Count 4 Plan Actual Forecast 3 2 SEP05 AUG05 JUL05 JUN05 APR05 MAR05 FEB05 0 JAN05 1 10 GLAST LAT Project WPNO Level 3 Milestone List Activity Description Baseline Finish -2m -1m Delta Bsln Var Var Var Early Finish Mechanical Systems 2005 2006 FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL 4.1.8 M echanical Flight Grid RFI-Mech to I&T 03/23/05 -5 -5 -5 03/30/05A X-LAT Thermal Plate RFI from Mech 04/20/05 -43 -65 -65 07/22/05A Radiators ready for I&T (from Mech 07/22/05 -12 -17 -36 09/13/05 Run Date 08/19/05 08:47 Data Date 08/01/05 © Pri mavera Systems, Inc. GLAST LAT PROJECT Level 3 Milestones Baseline Variance (Organized by Subsystem ) LT-DZ: Baseline Variance FL-D4: AV: Level 3 Milestones Report #10 Sheet 10 11 GLAST LAT Project Mechanical Systems Milestone Variance Explanation Radiator RFI -36 days • Schedule Impact – No impact to LAT schedule • Cost Impact – LM requested additional funds to complete Radiator testing – Discussions between GLAST, LM and GSFC were held 12 GLAST LAT Project Mechanical Systems Cost Report Reporting Category Cost Incurred During Month Actual Planned 4.1.8 MECHANICAL SYSTEMS 4.1.8.1 MANAGEMENT 4.1.8.2 RELIABILITY & QUALITY ASSURANCE 4.1.8.3 MECHANICAL SYSTEM DEVELOPMENT 4.1.8.4 THERMAL SYSTEMS DEVELOPMENT (LM) 4.1.8.5 THERMAL CONTROL SYSTEM (SLAC) 4.1.8.6 RADIATORS, HEAT PIPES, THERM TEST, X-LAT (LM) 4.1.8.7 GRID 4.1.8.8 FABRICATION, ASSEMBLY, AND TEST 4.1.8.9 LAT I&T SUPPORT CAPW[3]Totals: 484 0 0 0 24 -179 0 8 0 337 79 0 0 0 95 165 0 51 22 412 Cum. to Date Actual Planned 4,110 399 1,088 1,043 715 7,625 656 521 0 16,157 Unfilled Estimated Final Orders Cost Detail Balance of Contractor Contract Outstanding AUG05 SEP05 Contract Estimate Value Estimated Cost 3,709 393 1,088 1,043 741 7,737 640 709 90 16,151 85 0 0 0 108 59 0 235 13 500 77 0 0 0 79 54 0 3 1 215 -401 -6 0 0 26 112 -16 188 90 -6 3,871 393 1,088 1,043 929 7,851 640 947 104 16,866 3,871 393 1,088 1,043 929 7,851 640 947 104 16,866 216 0 0 0 83 0 0 134 432 13 GLAST LAT Project Mechanical Systems Cost Variance Explanation • • Why overrun/underrun? – LM has overrun their contract – Proceeding with Radiator testing while cost issue is being worked What will be done to correct? – Additional funding required 14 GLAST LAT Project Mechanical Systems FTE Report (DOE/NASA-funded only) 8.0 7.0 6.0 5.0 4.0 3.0 2.0 PLANNED 1.0 ACTUALS 0.0 5 P0 SE 5 G0 5 L0 5 N0 AU JU JU 05 AY M 5 R0 AP 05 AR M 5 B0 FE 15 GLAST LAT Project Mechanical Systems FTE Variance Explanation • • Why overrun/underrun? – Delay caused by late start of Grid Box #2 assembly work What is the impact? – Delay in Grid Static Load Test – No LAT impact 16