GLAST LAT Project Gamma-ray Large Area Space Telescope Monthly Status Meeting September 1, 2005 Project Status Overview Lowell Klaisner Project Manager GLAST-LAT Project 1 GLAST LAT Project Monthly Status Meeting September 1, 2005 LAT Schedule TKR A 2/4/05A TKR 14 9/23/05 ACD 8/13/05 Red Dates are Milestones CAL A 12/08/04A CAL 14 6/10/05A FSW Complete X-LAT Plate TEM/PS A 2/17/05A TEM/PS 14 9/2/05 FSW Formal Test Last Flight Hardware GRID Assembly 2/25/05A Install Twrs A-13 Install Tower 14 System Checkout 10/01/05 12/01/05 06/01/06 01/15/06 System Test Ship LAT Enviro Test LAT RFI Observ. Integration Launch 2007 2 GLAST LAT Project Monthly Status Meeting September 1, 2005 Funding FY05 and Prior FY06 FY07 Total NASA $110.3 DOE $45.0 DOE funded research scientists at SLAC $13.9 $5.0 $2.4 $10.2 $5.0 $2.5 $134.4 $55.0 $4.9 Total $194.3 Includes $30.5M in the Stanford University proposal that is under review 3 GLAST LAT Project Monthly Status Meeting September 1, 2005 Summary • • • • • • • • Anti-coincidence detector Complete Calorimeter Complete Tracker September – All flight modules fabricated Mechanical/ Thermal September – Radiators in the Thermal/Vac Chamber Flight Software November – FQT followed by a delta FQT Data Acquisition boxes December Instrument January, 2006 Issues – Tracker cables – DAQ boxes • Subsequent integration and test 4 GLAST LAT Project Monthly Status Meeting September 1, 2005 Module Schedule M/E July 2005 Grid 1st Module 2nd Module 3rd Module 4th Module 5th Module 6th Module 7th Module 8th Module 9th Module 10th Module 11th Module 12th Module 13th Module 14th Module 15th Module 16th Module ACD X-LAT Radiators Harness PDU GASU 1st EPU/SIU Last EPU/SIU FSW Cand Test Start FSW FQT Inst Global Items System Test LAT Arrives at NRL Sine Vibe EMI/EMC Test Acoustic Test TVAC Weight & CG Preship Review Ship LAT Forecast Dates and Float (working days) to "Ship Mech/ACD TKR CAL 11/08/04A 02/04/05A - 12/08/04A 02/24/05A - 01/14/05A 05/10/05A - 01/14/05A 05/10/05A - 01/14/05A 05/10/05A - 01/14/05A 06/09/05A - 02/22/05A 06/09/05A - 02/22/05A 08/01/05 4 04/25/05A 09/02/05 41 04/25/05A 09/08/05 40 04/25/05A 09/12/05 40 05/25/05A 09/14/05 41 05/25/05A 09/14/05 44 05/25/05A 09/21/05 42 05/25/05A 09/21/05 45 06/10/05A 09/23/05 46 06/10/05A 08/17/05 1 07/22/05A 09/13/05 108 LAT" ELEC - I&T 02/17/05A 03/09/05A 05/19/05A 05/19/05A 06/02/05A 06/06/05A 06/06/05A 07/22/05A 07/22/05A 07/22/05A 8/5/2005A 8/5/2005A 8/5/2005A 08/12/05 08/12/05 08/12/05 69 72 75 08/30/05 10/18/05 10/12/05 11/22/05 12/20/05 06/14/05A 09/09/05 23 39 44 15 0 11 04/07/05A 04/13/05A 05/27/05A 05/31/05A 06/08/05A 06/27/05A 08/08/05 08/08/05 09/06/05 09/09/05 09/13/05 09/15/05 09/15/05 09/22/05 09/26/05 09/26/05 2 2 41 40 40 41 44 42 46 46 12/21/05 01/26/06 01/30/06 02/24/06 03/17/06 03/28/06 05/24/06 05/26/06 05/27/06 05/28/06 0 0 0 0 0 0 0 0 0 0 5 GLAST LAT Project Monthly Status Meeting September 1, 2005 Current Critical Path to Ship LAT to Spectrum Astro Elex: LCB/CPS/BP Fab for Flight 10/14/05 PrePreEnvironmental Environmental Test Review Review Test 2/6/06 1/26/06 Elex: SIU/EPU Box 1-5 Integration 12/20/05 Environmental Test 5/26/06 Integrate LATWide Electronics 12/21/05 Ship LAT to Spectrum Astro 5/28/06 System Test 1/25/06 Float 0 days 6 GLAST LAT Project Monthly Status Meeting September 1, 2005 Current Critical Path to Ship LAT to Spectrum Astro ● 1st critical path: Electronics SIU/EPU Components for Installation of LAT-wide Electronics 0 days float to Ship LAT to Spectrum Astro ● 2nd critical path: Completion, Delivery to SLAC and RFI to I&T of the ACD 3 days float to Ship LAT to Spectrum Astro ● 3rd critical path: Flight Software Validation & Installation on LAT 11 days float to Ship LAT to Spectrum Astro 7 GLAST LAT Project Monthly Status Meeting September 1, 2005 Level 1-2 Milestone List AV Activity ID ND Activity Descr iption AV : Ear lyBaseline Finish Finish -2m Var -1m Var BslnBaseline Float VarChange Finish Ear ly Finish FY 02 FY 03 FY 04 FY 05 FY 06 DOE/NASA Joint Oversight Group (Level 1) 1M1P000000 DOE Critical Decision (CD) 0 Approval 06/25/01A 0 0 0 06/25/01A 1M1P000010 CD-1 Approval 07/23/02A 0 0 0 07/23/02A 1M1P000020 CD-2 Approval 11/08/02A 0 0 0 11/08/02A 1M1P000030 CD-3 Approval 09/03/03A 0 0 0 09/03/03A 1M1P000060 Flight GRID Complete 11/08/04A 0 0 0 11/08/04A 1M1P000040 CD-4 Approval 03/15/06* 0 0 0 03/15/06* DOE/NASA Federal Project Managers (Level 2) 1M1BF00000 Launch Balloon Flight 08/01/01A 0 0 0 08/01/01A 1M1000100 Instrument Preliminary Design Review 01/08/02A 0 0 0 01/08/02A 1M1000110 I-CDR (Critical Design Review) 05/16/03A 0 0 0 05/16/03A 1M1000740 Start LAT Integration 03/23/05 -5 -5 -5 03/30/05A 1M1000700 Pre Environmental Testing Review 12/20/05 -27 -10 -20 01/26/06 1M1000120 PSR-(Instrument Pre-Ship Review) 04/18/06 -18 -18 -28 05/26/06 Run Date 08/19/05 08:49 Data Date 08/01/05 GLAST LAT PR OJ EC T Le ve l 1& &2 Milest ones LT-T1: Level 1 & & 2 Milestones FL-T1: Level 1 & & 2 Milestones Sheet 1 © Primavera Systems, Inc. 8 GLAST LAT Project 4.1. LAT Level3 Milestone 3 Milestones Count Level Monthly Status Meeting September 1, 2005 120 80 60 40 Plan 20 Actual Forecast MAY06 APR06 MAR06 FEB06 JAN06 DEC05 NOV05 OCT05 SEP05 AUG05 JUL05 JUN05 MAY05 APR05 MAR05 0 FEB05 Milestones 100 9 GLAST LAT Project Monthly Status Meeting September 1, 2005 Level 3 Milestones Completed in July 2005 AV Activity ID ND Activity Descr iption AV : Ear lyBaseline Finish Finish BslnBaseline Float VarChange Finish Ear ly Finish JU N FY 05 JU L AU G SE P Instrument Project Office (Level 3) 4.1.6 ACD 6 1M1001000 9 ACD Test Scripts (from ACD to I&T) 03/15/05* -91 07/22/05A 4.1.7 Electronics 7 1M79001080 9 Flight TEMAssy 6: Elec to I&T 05/27/05 -38 07/22/05A 7 1M79001090 9 Flight TEMAssy 7: Elec to I&T 06/06/05 -33 07/22/05A 7 1M79001100 9 Flight TEMAssy 8: Elec to I&T 06/13/05 -28 07/22/05A 7 1M79002080 9 Flight TEMPSAssy 6: Elec to I&T 05/27/05 -38 07/22/05A 7 1M79002090 9 Flight TEMPSAssy 7: Elec to I&T 06/06/05 -33 07/22/05A 7 1M79002100 9 Flight TEMPSAssy 8: Elec to I&T 06/13/05 -28 07/22/05A 9 X-LAT Thermal Plate RFI from Mech to I&T 04/20/05 -65 07/22/05A B Online FU S/W Final Release-I&T to ISOC 07/14/05 0 07/14/05A 4.1.8 Mechanical 8 1M941710 4.1.9 I&T 9 1M1001740 Run Date 08/19/05 08:51 Data Date 08/01/05 © Primavera Systems, Inc. GLAST LAT PR OJ EC T C omplet ed Lev el 3 Miles tones in Re porting Mont h Sort by Subsys tem LT-TB: Completed Level 3 by Subsystem FL-TB: Level 3 Milestones compl. l ast month Sheet 1 10 GLAST LAT Project Monthly Status Meeting September 1, 2005 Level 3 Milestones Completed in August 2005 AV Activity ID ND Activity Descr iption AV : Ear lyBaseline Finish Finish BslnBaseline Float VarChange Finish Ear ly Finish JU L FY 05 AU G SE P OC T Instrument Project Office (Level 3) 4.1.4 Tracker 4 1M1000261 9 Flight Tracker Tower 6 RFI 06/16/05 -31 08/01/05 9 ACD Flight Unit at SLAC, Tested/Inspected & RFI 07/15/05 -23 08/17/05 4.1.6 ACD 6 1M1000410 4.1.7 Electronics 7 1M79001110 9 Flight TEMAssy 9: Elec to I&T 06/20/05 -33 08/05/05 7 1M79001120 9 Flight TEMAssy 10: Elec to I&T 06/27/05 -28 08/05/05 7 1M79001130 9 Flight TEMAssy 11: Elec to I&T 07/05/05 -23 08/05/05 7 1M79001140 9 Flight TEMAssy 12: Elec to I&T 07/12/05 -18 08/05/05 7 1M79001150 9 Flight TEMAssy 13: Elec to I&T 07/19/05 -13 08/05/05 7 1M79002110 9 Flight TEMPSAssy 9: Elec to I&T 06/20/05 -33 08/05/05 7 1M79002120 9 Flight TEMPSAssy 10: Elec to I&T 06/27/05 -28 08/05/05 7 1M79002130 9 Flight TEMPSAssy 11: Elec to I&T 07/05/05 -23 08/05/05 7 1M79002140 9 Flight TEMPSAssy 12: Elec to I&T 07/12/05 -18 08/05/05 7 1M79002150 9 Flight TEMPSAssy 13: Elec to I&T 07/19/05 -13 08/05/05 7 1M79520 FSW Test Peer Review Complete 08/15/05 0 08/15/05 Run Date 08/26/05 15:52 Data Date 08/01/05 © Primavera Systems, Inc. GLAST LAT PR OJ EC T Le ve l 3 Mile stones C omplet ed in A ugust Sort by Subsys tem LT-T9: L3 MS Compl eted Curr Mo (tb) FL-T2: L3 Milestones Completed Current Month Sheet 1 11 GLAST LAT Project Monthly Status Meeting September 1, 2005 Level 3 Milestones Completed in August 2005 AV Activity ID ND 1M99030 9 Activity Descr iption AV : Ear lyBaseline Finish Finish BslnBaseline Float VarChange Finish Ear ly Finish JU L FY 05 AU G SE P OC T 4.1.9 I&T 9 Start 8 Tower Comprehensive Performance Test Run Date 08/26/05 15:52 Data Date 08/01/05 © Primavera Systems, Inc. 06/20/05 -33 GLAST LAT PR OJ EC T Le ve l 3 Mile stones C omplet ed in A ugust Sort by Subsys tem 08/05/05 LT-T9: L3 MS Compl eted Curr Mo (tb) FL-T2: L3 Milestones Completed Current Month Sheet 2 12 GLAST LAT Project Monthly Status Meeting September 1, 2005 CPR Level 3 Cost Performance Report - Work Breakdown Structure Contract Type/No: Contractor: Location: CAPW[3] Item (1) Project Name/No: Report Period: LAT 6/30/2005 7/31/2005 Cumulative to Date At Completion Actual Budgeted Cost Cost Variance Latest Work Work Work Revised Scheduled Performed Performed Schedule Cost Budgeted Estimate Variance (7) (8) (9) (10) (11) (12) (13) (14) Current Period Actual Budgeted Cost Cost Variance Work Work Work Scheduled Performed Performed Schedule Cost (2) (3) (4) (5) (6) 4.1.1 INSTRUMENT MANAGEMENT 299 299 365 0 -67 17,207 17,207 16,975 0 232 17,778 17,778 0 4.1.2 SYSTEM ENGINEERING 150 150 120 0 30 7,364 7,364 7,375 0 -12 7,647 7,647 0 4.1.4 TRACKER 352 419 367 67 53 21,279 20,670 20,290 -609 380 21,702 21,702 0 4.1.5 CALORIMETER 166 89 88 -77 1 22,223 22,121 21,554 -102 567 22,594 22,594 0 56 216 313 160 -97 17,818 17,767 17,668 -51 98 17,968 17,968 0 4.1.7 ELECTRONICS 434 486 663 53 -177 28,295 27,375 27,587 -919 -212 28,894 28,894 0 4.1.8 MECHANICAL SYSTEMS 412 386 337 -26 49 16,151 16,094 16,157 -57 -63 16,866 16,866 0 4.1.9 INTEGRATION & TEST 382 286 238 -96 47 8,411 8,272 7,953 -140 319 9,451 9,451 0 81 81 158 0 -77 3,668 3,668 3,803 0 -134 3,846 3,846 0 5 5 2 0 3 327 327 312 0 15 334 334 0 4.1.C EDUCATION AND PUBLIC OUTREACH 67 67 24 0 43 2,537 2,537 2,217 0 320 2,684 2,684 0 4.1.D SCIENCE ANALYSIS SOFTWARE 74 74 90 0 -16 2,782 2,782 2,692 0 90 2,936 2,936 0 4.1.E SUBORBITAL FLIGHT TEST 0 0 0 0 0 1,325 1,325 1,325 0 0 1,325 1,325 0 Gen. and Admin. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 154,025 154,025 0 1,784 1,784 0 155,809 155,809 0 4.1.6 ANTICOINCIDENCE DETECTOR 4.1.A PERFORMANCE AND SAFETY ASSURANCE 4.1.B LAT INSTRUMENT SCIENCE OPERATIONS CENTER Undist. Budget Sub Total 2,477 2,557 2,766 80 -209 149,385 147,508 145,909 -1,878 1,599 Contingency Total 2,477 2,557 2,766 80 -209 149,385 147,508 145,909 -1,878 1,599 13 GLAST LAT Project Monthly Status Meeting September 1, 2005 FTE 4.1 LATReport Project FTEs (DOE/NASA-funded only) 250.0 200.0 150.0 100.0 50.0 PLANNED ACTUALS 0.0 FEB05 MAR05 APR05 MAY05 JUN05 JUL05 AUG05 SEP05 14 GLAST LAT Project Monthly Status Meeting September 1, 2005 Performance Analysis WBS BAC BCWS BCWP ACWP SV $ CV $ % BCWS % BCWP % ACWP SPI Trend CPI Trend SPI CPI CPI Fcst CpiSpi Fcst 96.99 95.77 94.73 0.987 1.011 152,356 152,438 232 96.79 96.79 95.48 1.000 1.014 17,538 17,538 0 -12 96.29 96.29 96.45 1.000 0.998 7,659 7,659 20,290 -609 380 98.05 95.24 93.49 0.971 1.019 21,303 21,333 22,121 21,554 -102 567 98.35 97.90 95.40 0.995 1.026 22,016 22,018 17,818 17,767 17,668 -51 98 99.16 98.88 98.33 0.997 1.006 17,869 17,869 28,295 27,375 27,587 -919 -212 97.93 94.74 95.48 0.968 0.992 29,117 29,169 16,866 16,151 16,094 16,157 -57 -63 95.76 95.42 95.80 0.996 0.996 16,932 16,935 4.1.9 9,451 8,411 8,272 7,953 -140 319 88.99 87.52 84.15 0.983 1.040 9,087 9,106 10 4.1.A 3,846 3,668 3,668 3,803 0 -134 95.38 95.38 98.87 1.000 0.965 3,987 3,987 11 4.1.B 334 327 327 312 0 15 97.90 97.90 93.35 1.000 1.049 319 319 12 4.1.C 2,684 2,537 2,537 2,217 0 320 94.52 94.52 82.62 1.000 1.144 2,346 2,346 13 4.1.D 2,936 2,782 2,782 2,692 0 90 94.75 94.75 91.69 1.000 1.033 2,842 2,842 14 4.1.E 1,325 1,325 1,325 1,325 0 0 100.00 100.00 99.98 1.000 1.000 1,325 1,325 1 4.1 154,025 149,385 147,508 145,908 -1,878 1,599 2 4.1.1 17,778 17,207 17,207 16,975 0 3 4.1.2 7,647 7,364 7,364 7,375 4 4.1.4 21,702 21,279 20,670 5 4.1.5 22,594 22,223 6 4.1.6 17,968 7 4.1.7 28,894 8 4.1.8 9 LEGEND BAC: Budget At Complete BCWS: Budgeted Cost of Work Scheduled (to date) BCWP: Budgeted Cost of Work Performed (to date) ACWP: Actual Cost of Work Performed (to date) SV $: Schedule Variance = BCWP - BCWS CV $: Cost Variance = BCWP - ACWP SPI: Schedule Performance Index = BCWP/BCWS CPI: Cost Performance Index = BCWP/ACWP Cpi_Fcst: CPI (to date) EAC Forecast = BAC / CPI CpiSpi_Fcst: Combination CPI and SPI EAC Forecast = ACWP + (BAC - BCWP) / (CPI *SPI) % BCWS: Percent Scheduled = BCWS/BAC % BCWP: Percent Complete = BCWP/BAC % ACWP: Percent Spent = ACWP/BAC Worse than .85 Between .95 and 1.10 Between .85 and .95 Better than 1.10 SPI and CPI Change Thresholds 15 GLAST LAT Project Monthly Status Meeting September 1, 2005 Variance Analysis Elem ent : 4. 1 OTH ER PR OD Bull's -ey e C hart - As of : J U L 05 N am e: LAT BEH I N D SC H ED U LE,AH UN EAD D EROF C OST SC H ED U LE, U N D ER C OST 6. 0 4. 0 CV % CUM Percent of Dollars 2. 0 2 4 1 0 Current Month 3 0. 0 -2. 0 5 Feb05 -4. 0 -6. 0 BEH I N D SC H ED U LE, OVER AH EAD C OST OF SC H ED U LE, OVER C OST -6. 0 -4. 0 -2. 0 0. 0 2. 0 4. 0 SV % C U M Perc ent of D ollars 6. 0 8. 0 16 GLAST LAT Project Monthly Status Meeting September 1, 2005 Budget vs Actuals vs Performance DOE + NASA Project Expenditures 4.1 LAT Budget, Cost, Funding, Performance Actual Commitments ACWP Fund BCWP BCWS+ Planned Commitments BCWS 150 120 $M 90 60 30 0 A M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N D J F MA M J J A S O N D J F M A M J J A S O N D J F MA M J J A S FY00 FY01 FY02 FY03 FY04 FY05 17 GLAST LAT Project Monthly Status Meeting September 1, 2005 Cost Report Monthly Contractor Financial Management Report 31-Jul-05 Reporting Category Cost Incurred During Month Actual Planned Cum. to Date Actual Planned NASA form 533M Report for Month Ending: Approved OMB # 2700-001 7/31/2005 Unfilled Estimated Cost Estimated Final Orders Cost Detail Balance of Contractor Contract Outstanding AUG05 SEP05 Contract Estimate Value 4.1.1 INSTRUMENT MANAGEMENT 365 299 16,975 17,207 307 264 232 17,778 17,778 30 4.1.2 SYSTEM ENGINEERING 120 150 7,375 7,364 154 130 (12) 7,647 7,647 - 4.1.4 TRACKER 367 352 20,290 21,279 235 188 989 21,702 21,702 421 88 166 21,554 22,223 201 171 668 22,594 22,594 14 4.1.6 ANTICOINCIDENCE DETECTOR 313 56 17,668 17,818 50 100 149 17,968 17,968 78 4.1.7 ELECTRONICS 663 434 27,587 28,295 353 246 708 28,894 28,894 748 4.1.8 MECHANICAL SYSTEMS 337 412 16,157 16,151 500 215 (6) 16,866 16,866 432 4.1.9 INTEGRATION & TEST 238 382 7,953 8,411 291 749 458 9,451 9,451 63 4.1.A PERFORMANCE AND SAFETY ASSURANCE 158 81 3,803 3,668 93 85 (134) 3,846 3,846 1 2 5 312 327 5 2 15 334 334 - 4.1.C EDUCATION AND PUBLIC OUTREACH 24 67 2,217 2,537 77 70 320 2,684 2,684 212 4.1.D SCIENCE ANALYSIS SOFTWARE 90 74 2,692 2,782 80 75 90 2,936 2,936 136 - - 1,325 1,325 - - 0 1,325 1,325 - 2,766 2,477 145,909 149,385 2,344 2,296 3,477 154,025 154,025 2,133 4.1.5 CALORIMETER 4.1.B LAT INSTRUMENT SCIENCE OPERATIONS CENTER 4.1.E SUBORBITAL FLIGHT TEST Total 18