GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope Tracker Subsystem WBS 4.1.4 Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager rjohnson@scipp.ucsc.edu LAT-PR-01967 4.1.4 Tracker Overview 1 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Review Outline 1. Overview 2. Requirements summary 3. Design 4. Verification 5. Fabrication summary 6. Risks and Schedule 7. Appendix A: Requirements details 8. Appendix B: Fabrication details LAT-PR-01967 4.1.4 Tracker Overview 8 min 5 min 55 min 30 min 5 min 20 min 2 GLAST LAT Project LAT-PR-01967 CDR/CD-3 Review, May 12-15, 2003 4.1.4 Tracker Overview 3 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Design Overview • Stiff composite panels (>500 Hz) – Allows small gap between x-y SSD layers • Tungsten foils on panel bottom • SSDs on top & bottom faces • Electronics on panel edges – Minimizes the gap between towers (1.59 cm Si to Si) • Carbon-fiber walls for vertical support – Very stiff box structure – Passive cooling to tower base • Flexure attachment to Grid – Decouple from thermal expansion – Lowest frequency >150 Hz – Greatly reinforced attachment to the bottom tray. – Thermal straps couple sidewalls to the Grid (not shown) LAT-PR-01967 Multi-Chip Electronics Module (MCM) 19 Carbon-Fiber Tray Panels Carbon-Fiber Sidewalls (Aluminum covered) 2 mm gap CarbonFiber Wall Readout Cable Titanium Flexure 4.1.4 Tracker Overview Mounts 4 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Design Overview Close-up view of the interfaces on the bottom of a Tracker module. This interface has been substantially redesigned since the May ’02 random vibration tests of the prototype tower module, during which structural failures occurred in the carbon-carbon closeouts of the bottom tray. LAT-PR-01967 4.1.4 Tracker Overview 5 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker WBS & Interfaces Thermal Straps Interface Control Documents –Mechanical: LAT-SS-00138 –Electrical: LAT-SS-00176 LAT-PR-01967 4.1.4 Tracker Overview 6 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Organization Chart GLAST LAT IPO SLAC R. Johnson, UCSC Subsystem Manager H. Sadrozinski, UCSC Tracker Scientist T. Ohsugi, Hiroshima SSD Design, Testing, Procurement T. Borden, SLAC Mechanical-Thermal System Engineer J. Tice, SLAC I&T Supervision M. Goossens, Teledyne Manager, MCM assembly (Contractor) R. Bellazzini, INFN-Pisa Italian TKR Project Manager D. Nelson, SLAC Electronics System Engineer A. Brez, INFN-Pisa Development Engineer, Production Supervisor M. Sugizaki, UCSC Electronics Testing Nicolla Mazziotta, INFN-Bari Tracker Production Testing J. Olson, SLAC Readout-Controller ASIC Design E. Swensen, Hytec Mechanical Engineering Design (Contractor) LAT-PR-01967 E. Spencer, UCSC F.E. ASIC Design 4.1.4 Tracker Overview 7 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Peer Review and RFA’s • Significant Findings – Design maturity, qualification and verification planning are near CDR level, but still missing verification by EM testing. – The Tracker is near ready for manufacturing in some aspects, but other items need to wait until successful engineering model testing has been accomplished. • 39 RFA’s – We have responded to all 39 (see Tracker web page) – We have received comments back on 20 responses – 10 RFA’s were closed • 2 concerns – Lateness of EM tower environmental testing. • Bottom-tray and sidewall fabrication will start only when EM testing is complete. – Document status: IDD not released and only 50% of flight drawings released. • Some progress to show on this since the peer review. LAT-PR-01967 4.1.4 Tracker Overview 8 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Key Tracker Requirements • Tracker Level-3 requirements: LAT-SS-00017 • Tracker Level-4 requirements: LAT-SS-00134 & LAT-SS-00152 • Science Requirements that flow down to the Tracker design: – Effective Area – Field of View (aspect ratio) – Point Spread Function – Background Rejection – Dead Time • Low Power: <155 Watts for ~900,000 channels • Low Noise: occupancy <104 per trigger • High Rate: <10% dead time at 10 kHz • High Detection Efficiency: >98% • Mass: 510 kg allocated to Tracker (reserves held by IPO) LAT-PR-01967 4.1.4 Tracker Overview 9 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Mass Breakdown 1 Module 16 Modules Mechanical Structures 15.8 kg 252.9 kg Calculated Silicon-strip detectors 4.3 kg 68.8 kg Calculated Tungsten foils 9.2 kg 147.0 kg Calculated Electronics and cabling 2.2 kg 35.8 kg Measured Thermal straps 0.3 kg 4.2 kg Calculated Total 31.8 kg 508.7 kg • See LAT-TD-00177 for a much more detailed breakdown. • Check on the mass of the tray, from two EM prototypes: • Std tray without W, no SSDs, no MCMs: 52010 g meas., 550 g calc. • Std tray with W, no SSDs, no MCMs: 83010 g meas., 821 g calc. LAT-PR-01967 4.1.4 Tracker Overview 10 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Drawing Status • A link to the Tracker drawing tree can be found on the Tracker web site. • There are 87 drawings for the Tracker flight hardware. • No new drawings are needed. • 14 drawings are still being worked. • 73 drawings are released. LAT-PR-01967 4.1.4 Tracker Overview 11 GLAST LAT Project LAT-PR-01967 CDR/CD-3 Review, May 12-15, 2003 4.1.4 Tracker Overview 12 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Design Requirements: Grid Motion • Tracker-to-Grid Maximum Interface Distortion – Superimposed on MECO design limit loads – NOT superimposed on vibration analysis or testing Flexure Location 0° Midside Flexure +45° Corner Flexure +90° Midside Flexure +135° Midside Flexure -180° Midside Flexure -135° Midside Flexure -90° Midside Flexure -45° Midside Flexure Displacements Radial (µm) Vertical (µm) 46 93 81 165 14 91 -60 24 -29 0 20 0 0 0 -11 13 Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. LAT-PR-01967 4.1.4 Tracker Overview 13 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Design Requirements: Flexure Loads • Corner Flexure Maximum Design Limit Loads – Maximum from two CLA cycles Load Direction Shear Tension Compression Flexure Design Limit Loads (N) 1003 1277 1277 Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. • Side Flexure Maximum Design Limit Loads – Maximum from two CLA cycles Load Direction Shear Tension Compression Flexure Design Limit Loads (N) 2266 391 391 Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. LAT-PR-01967 4.1.4 Tracker Overview 14 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Design Requirements: Sine Vibe Frequency (Hz) Acceptance Test Levels 5 to 6.2 Thrust 6.2 to 50 Lateral 5 to 50 Axis Test Levels Sweep Rate 1.27 cm (0.5 in.) double amplitude 1.0 g (zero to peak) 0.7 g (zero to peak) 4 oct/min N/A 4 oct/min Proto-Flight Qualification Test Levels 5 to 7.4 1.27 cm (0.5 in.) double amplitude Thrust 7.4 to 50 1.4 g (zero to peak) 5 to 6.2 1.27 cm (0.5 in.) double amplitude Lateral 6.2 to 50 1.0 g (zero to peak) 4 oct/min 4 oct/min Qualification Test Levels 5 to 7.4 1.27 cm (0.5 in.) double amplitude 2 oct/min Thrust 7.4 to 50 1.4 g (zero to peak) 5 to 6.2 1.27 cm (0.5 in.) double amplitude 2 oct/min Lateral 6.2 to 50 1.0 g (zero to peak) Source: LAT-SS-00788-01-D4, “LAT Environmental Specification,” 15 Nov 2002. LAT-PR-01967 4.1.4 Tracker Overview 15 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Design Requirements: Random Vibe • GEVS Minimum Workmanship applied along all three axes independently Acceleration Spectral Density Function 20 80 500 2000 Overall 1.000 Acc & Qual ASD Test Level (G2/Hz) 0.01 0.04 0.04 0.01 6.8 Grms 0.100 ASD (G 2/Hz) Frequency (Hz) 0.010 0.001 10 100 1000 10000 Frequency (Hz) Source: GEVS-SE Rev A, “General Environmental Verification Specification for STS & ELV Payloads, Subsystems, and Components,” June 1996, Section 2.4.2.5. LAT-PR-01967 4.1.4 Tracker Overview 16 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Design Requirements: Dynamic Clearance • Maintain positive clearance between adjacent TKR tower modules (tower-to-tower collisions) (Source: Tracker-LAT ICD) – Maintain minimum allocation of 1.5 mm for dynamic response of towers (design gap between towers is 2.5 mm) • After fabrication/assembly tolerances, alignment, EMI shielding, static response, & thermal distortion are considered – Maximum dynamic response goal <145 µm RMS (acceptance) • Assumes adjacent towers are out-of-phase • Maintain positive clearance between adjacent trays (tray-to-tray collisions) – Maintain minimum clearance of 2 mm between adjacent trays • Silicon-to-silicon clearance – Minimum frequency goal of 500 Hz • Fixed base boundary conditions at tray attachment locations • Assumes adjacent trays are out-of-phase LAT-PR-01967 4.1.4 Tracker Overview 17 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Design Requirements: Quasi-Static Loads • Static-Equivalent Accelerations Launch Event Design Lift-Off/ 1 MECO 0.2 6.8 2 Accept3 Qual 3 Unit 3.7 6.8 4.6 8.5 g g Lateral Axial Transonic 2.34 4.43 Rot X/Y 20.2 rad/s Rot Z Scale Factor 20.2 rad/s2 2 1.25 Source (1) “Summary of the GLAST Preliminary CLA Results,” Farhad Tahmasebi, 11 Dec 2001. (2) 433-IRD-0001, “Large Area Telescope (LAT) Instrument – Spacecraft Interface Requirements Document,” May, 2002. (3) “LAT Tracker Random Vibration Test Levels,” Farhad Tahmasebi, 27 Feb 2002. LAT-PR-01967 4.1.4 Tracker Overview 18 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Additional Requirements • Stay Clear Dimensions (Source: Tracker-LAT ICD) – Straightness ≤ 300 µm from top to bottom – Maximum outside dimensions (x & y) ≤ 371.7 mm – Maximum height ≤ 640 mm above grid surface • Launch Pressure (Source: LAT Environmental Specification) – Shall survive the time rate of change of pressure per the Delta II Payload Planner’s Guide, Section 4.2.1, Figure 4.2. – Extreme pressure conditions are experienced in the first 70 sec of fairing venting. • Venting (Source: Tracker-LAT ICD) – Sufficient venting of all TKR components is required to allow trapped gasses to release during launch. • EMI Shielding (Source: Tracker-LAT ICD) – Each TKR tower shall be covered on all 6 sides by at least 50 µm of aluminum electrically connected to the Grid. LAT-PR-01967 4.1.4 Tracker Overview 19 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Tray with Payload • The tray “payload” is bonded to the sandwich structure using epoxy, with the exception of the SSD bonding, which is done with silicone. – Silicone decouples the thermal/mechanical effects from the tray SSD’s BiasCircuit Structural Tray Panel Converter Foils BiasCircuit TMCM SSD’s LAT-PR-01967 4.1.4 Tracker Overview 20 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray Sandwich Structure • Lightweight 4 piece machined closeout frame, bonded to face sheets and core to form a sandwich structure Gr/CE Face Sheet C-C Structural Closeout Wall 1 lb/ft3 Aluminum Honeycomb Core LAT-PR-01967 Thermal Boss C-C MCM Closeout Wall 4.1.4 Tracker Overview 21 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray Vibration Testing • Thin-Converter Tray Vibration Test – Performed in Albuquerque, NM – Fixed boundary conditions at Sidewall attachment locations – Modal survey in Thrust direction – Random vibration test to GEVS general spec @ qualification level • LAT-PR-01967 Conclusions – Measured 710 Hz fundamental frequency vs. 711 Hz FEA – No indication of damage after qualification level (0dB) RV test – No indication of Carbon dusting after test 4.1.4 Tracker Overview 22 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray Vibration Testing (Con’t) • Thick-Converter Tray Vibration Test – Performed in Milan, Italy – Fixed boundary conditions at Sidewall attachment locations – Modal survey in Thrust direction – Random vibration test to GEVS general spec @ qualification level • LAT-PR-01967 Conclusions – Measured 580 Hz fundamental frequency vs. 518 Hz FEA – No indication of damage after qualification level (0dB) RV test 4.1.4 Tracker Overview 23 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Sidewall Mounting • All trays except bottom tray attachment – M2.5, CRES A286 fasteners – No metallic inserts in sidewall • Bottom tray attachment – M2.5 & M4, CRES A286 fasteners – Metallic top-hat design inserts in sidewall M4 Bottom Sidewall Section View of Bottom Tray Sidewall Inserts M4 M4 (M2.5 fasteners unless marked otherwise) LAT-PR-01967 4.1.4 Tracker Overview 24 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 1-yr Chronology of the Bottom Tray Break COI Joint Pull Tests Shake Final Design COI/Hytec Materials Testing Hytec Analysis & Design COI Reinforced Tray LAT-PR-01967 4.1.4 Tracker Overview 25 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Bottom Tray Closeout Walls • Bonded M55J/RS-3 internal frame for strength and stiffness • Machined C-C outside laminate for thermal transfer of MCM heat and machining of detail M55J/RS-3 Internal Frame C-C Outside Laminate MCM Closeout Wall Structural Closeout Wall Typical Closeout Wall Cross-Section (not to scale) Actual closeout wall blanks laid up at COI and ready for machining. LAT-PR-01967 4.1.4 Tracker Overview 26 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Corner Joint Details Pins (Reinforce Butt-Joint) Sandwich Structure w/ Reinforcement Brackets (Typ, 4 places) MCM Closeout Wall Bonded Butt-Joint Structural Closeout Wall LAT-PR-01967 Corner Reinforcement Bracket (Bonded) 4.1.4 Tracker Overview 27 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Corner Reinforcement Bracket • Machined Titanium Reinforcement Bracket – Strength & Stiffness Typical Machined Taper (Reduce Peel Stress) Sandwich Structure w/ Reinforcement Brackets (Typ, 4 places) Corner Block (Shear Reinforcement) Slots for M55J Closeouts (Bonded Interface) Inside View of Corner Reinforcement Bracket LAT-PR-01967 Corner Flexure Mounting Slot (Press Fit, 2 Pins, 1 Fastener) 4.1.4 Tracker Overview 28 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Bottom Tray with Payload • • SSDs are attached to top side only Tray payload is bonded to the sandwich structure using epoxy, with the exception of silicone used to bond SSD’s – Silicone decouples the thermal/mechanical effects from the tray below Bias-Circuit SSD’s Structural Tray LAT-PR-01967 TMCM 4.1.4 Tracker Overview 29 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Finite Element Modeling Element/Node Count Number Number Number Number Number Number of of of of of of Grids = BAR Elements = Spring Elements = Solid Elements = Plate Elements = Rigid Elements = 227653 1038 63316 120628 56442 219 Mass Properties of FEM Mass = 32.48 kg Center of Gravity Location: Xcg = -1.06E-5 m Ycg = -4.26E-7 m Zcg = 0.2623 m LAT-PR-01967 4.1.4 Tracker Overview 30 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Modal Analysis • Primary Modes with Mass Participation Factors Mass Participation Factors Mode # Frequency (Hz) T1 T2 T3 Mode Shape Description 1 182.1 0.2% 76.3% 0.0% Lateral Y - First Bending Mode 2 183.6 74.9% 0.2% 0.0% Lateral X - First Bending Mode 3 379.0 0.0% 0.0% 76.7% Axial Thrust Z 4 461.8 0.0% 0.0% 0.0% Torsional Z axis 5 462.5 - 496.9 0.0% 0.0% 0.0% SuperGlast Tray Bending Modes 9 527.2 0.0% 0.0% 0.3% Top Tray Bending Mode 10 548.0 - 549.5 0.0% 0.0% 0.0% Standard Tray Bending Modes 20 577.8 21.4% 0.0% 0.0% Lateral X - Second Bending Mode 21 580.1 0.0% 19.9% 0.0% Lateral Y - Second Bending Mode 22 661.4 0.0% 0.0% 1.6% 2nd/3rd Tray Bending Mode - In Phase 24 834.8 0.0% 0.0% 8.9% All Trays w/Bottom in Bending Mode - In Phase LAT-PR-01967 4.1.4 Tracker Overview 31 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower RV Analysis: Accelerations • Equivalent quasi-static accelerations from random vibration input Vibration Direction Input Levels 1 Sigma Grms CG Response 3 Sigma Grms CG Response Accept. Qual Qual Qual Lateral X 6.8 6.8 8.9 26.7 Lateral Y 6.8 6.8 9.0 27.0 Axial Z 6.8 6.8 12.0 36.0 Lateral 45XY* 6.8 6.8 8.9 26.6 * For Reference Only 19th Tray Response 20.0 18.0 Qual 16.0 14.0 10th Tray Response Grms 12.0 10.0 8.0 6.0 4.0 2.0 0.0 0 Bottom Tray Response LAT-PR-01967 0.15 0.3 Z Height (m) 4.1.4 Tracker Overview 0.45 0.6 32 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower RV Analysis: RMS Displacements Displacement Direction (µm) X Y Z RV in X (1RMS) 67 1 14 RV in Y (1RMS) 1 67 14 RV in Z (1RMS) 2 0 10 1.18 1.15 9.29 Min M.S. Tower RV in Y Responses 10.000 Qual Base Input 6.8 Grms Bottom Tray Response 7.7 Grms Tower CG Response 9.3 Grms 1.000 Acceleration (G^2/Hz) • Maximum RMS Response to Acceptance Level RV Input • Min MS is +1.15 Tower Tip Response 17.8 Grms 0.100 0.010 0.001 0.000 10.0 100.0 1000.0 Frequency (Hz) LAT-PR-01967 4.1.4 Tracker Overview 33 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray Finite Element Modeling • Tray FE models were constructed for all five tray types • Modal and random vibration analysis performed • Results are summarized in HTN102070-0005 Detailed HYTEC Tray FEM (Top, Thin-, No-Converter) Detailed INFN Tray FEM (Thick-Converter) LAT-PR-01967 4.1.4 Tracker Overview 34 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 FE Modal Analysis Results Tray Description Top Tray Thin-Converter Tray Thick-Converter Tray No-Converter Tray Bottom Tray Frequencies (Hz) Without Payload With Payload Stiffness Effects Stiffness Effects 569 584 N/A 718 767 673 711 518 764 788 • Fixed Base Boundary Conditions – Simply supported at sidewall attachment locations • Payload stiffness effects include Tungsten and bias-circuits – Silicon applied as mass only Typical 1st Mode Shape of the Thin-Converter Tray LAT-PR-01967 4.1.4 Tracker Overview 35 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Bottom Tray Finite Element Modeling • Fidelity of FEM is sufficient to calculate stresses • Analysis is done in the tower configuration • Static analysis is used to estimate stresses during design phase – Equivalent static accelerations calculated to simulate 3σ random vibe environment • Random-Vibe Analysis is used to calculated RMS stresses to finalize design LAT-PR-01967 4.1.4 Tracker Overview 36 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Analysis FS, MUF & MS Requirements • Factors-of-Safety on Static & Random Vibration Loads/Stresses Applied to Design Levels – Metallic Structures1 • Ultimate Design Factors-of-Safety = 1.4 • Yield Design Factors-of-Safety = 1.25 – Composite/Bonded Structures2 • Ultimate Design Factors-of-Safety = 1.5 – Qualification Test Factor1,2 = 1.4 • Model Uncertainty Factor (MUF) – MUF applied to analysis = 1.15 • Previous prototype testing and model validation/verification • Margins-of-Safety – Margin-of-Safety Equation = Sallowable/(FS * Smax) – 1 – All Margins must be above 0.00 Reference: NASA-STD-5001 1) Table I, Section 5.1.1 2) Table III, Section 5.1.3 LAT-PR-01967 4.1.4 Tracker Overview 37 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Bottom Tray Minimum Margins: Tension Zero Compression LAT-PR-01967 4.1.4 Tracker Overview 38 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Side Wall & Screw Margins of Safety • Insert MS is calculated using the interaction of the vertical and lateral loads Basic Interaction Eqn: MS LAT-PR-01967 1 1 Where: Rx 2 Ry 2 Ri i allowable 4.1.4 Tracker Overview Tension Zero Compression 39 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray’s 2-19 Minimum Margins (Bottom Tray Not Shown) Tension Zero Compression LAT-PR-01967 4.1.4 Tracker Overview 40 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Flexure-to-Grid Attachment Configuration • • • • • 8-Flexure Configuration – 4 in each corner – 4 along each side Allows radial distortion of grid due to thermal input Material: 6Al-4V Titanium, Annealed Tapered 3-Blade Design Center stiffener to increase critical buckling LAT-PR-01967 4.1.4 Tracker Overview 41 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Flexure Margins Corner Flexures: Load Case Interface Design Loads Liftoff & Transonic MECO + Grid Distortion Random Vibration Loads RV Loads along 45 Axis Grid Thermal Distortion Margin-of-Safety Ultimate Yield 0.29 0.33 0.90 0.96 1.02 1.09 0.22 0.26 0.27 0.32 0.51 0.56 von Mises Stresses from Normal Load Note: All Margin calculations include fabrication tolerances Side Flexures: Load Case Interface Design Loads Liftoff & Transonic MECO + Grid Distortion Random Vibration Loads RV Loads along 45 Axis Grid Thermal Distortion Margin-of-Safety Ultimate Yield 0.25 0.29 0.93 0.99 1.05 1.11 0.41 0.46 0.42 0.47 0.42 0.47 Note: All Margin calculations include fabrication tolerances LAT-PR-01967 4.1.4 Tracker Overview 42 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Heat Strap Analysis: Stress Analysis • Maximum load case is the lateral random vibration – Shear deformation shown below • Minimum Margin-of-Safety is +0.52 Von Mises Stresses High Medium Low LAT-PR-01967 4.1.4 Tracker Overview 43 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Thermal Design Requirements • Tracker Temperature Requirements – Maximum heat load = 10.2 W – Maximum Temperature of SSDs = 30°C • Tracker Temperature Limits: State Qualification Acceptance Test Operating Low Temp Limits (°C) -30 -20 -15 High Temp Limits +50 +30 +30 Survival (°C) Low = -30 High = +50 N/A Source: LAT-SS-00778-01-D4, “LAT Environmental Specification,” 15 Nov 2002. LAT-PR-01967 4.1.4 Tracker Overview 44 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Thermal Design Overview • 16 identical towers (19 trays each) – 10.2W (hot) and 8.7W (cold) per tower, located on MCM boards – Primary heat path is from MCM closeouts on each tray to high conductivity walls (K13D), down walls to Grid through copper heat straps • • • • 2.55 W per strap (hot) RTV interface at Tracker Bolted (dry) at Grid Interface Delta T is <3°C cables – High emissivity external surfaces (black paint) promote radiation between towers and from towers to ACD LAT-PR-01967 4.1.4 Tracker Overview 45 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Electronics Cooling • Low IC power density (20 MHz clock): – GTFE chip: 7.8 mW for 0.33 cm2 0.024 W/ cm2 – GTRC chip: 32 mW for 0.12 cm2 0.26 W/cm2 • Total MCM power of 0.25 W is spread by the PWB over about 100 cm2 along the tray edge 2.4 mW/cm2. The 8-layer board has several full copper planes to spread the heat. • The MCM is bonded to the carbon-carbon closeout with epoxy. • The carbon-carbon carries the heat to the sidewall through a 20 cm long boss and 10 fasteners into the tower sidewalls. • SSDs stay below 30°C operational. The ICs will be only a few degrees warmer. LAT-PR-01967 4.1.4 Tracker Overview 46 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Thermal Model +Z • SINDA/TSS Model – 82 Nodes/Tower, 1312 total • Trays are lumped into groups per tower – – – – – – Top tray Top 5 Standard Trays Bottom 6 Standard trays Heavy Trays Standard No Converter trays Bottom Tray 8 13 4 0 9 5 1 14 10 6 2 11 15 7 3 • Each Tray Group consists of 1 Tray node, 4 closeout nodes (Q input), 8 wall nodes • Copper strap interface to Grid nodes LAT-PR-01967 +Y 12 +X 4.1.4 Tracker Overview 47 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Thermal Simulation Results – Hot • Steady State Temperatures – Max DT up wall is 6°C (7°C including entire tower) – Max Temp, +24°C °C Steady State Temperatures +Z +Y 15 0 • Located at Bay 5, Top 5 Std Closeout Trays • Transient Temperatures – Max Tracker Transient, +24°C W 167.4 -20.1 -147.4 0.0 Energy Balance Tracker Dissipation to ACD to Grid SUM LAT-PR-01967 +X Internal View 4.1.4 Tracker Overview 48 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Thermal Simulation Results – Hot °C • Simulate complete failure of the GridTower interface (copper straps) in the center tower (Bay 5). • DT steady state increase is 4.4°C – Max Temp is now +28.4°C LAT-PR-01967 Bay 4 Bay 5 4.1.4 Tracker Overview Bay 6 49 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Thermal Results - Survival • Minimum Tracker Survival Temperature is –24 °C Tracker Bay 5 Survival Temperatures over 5 Orbits 0 0 50 100 150 200 250 300 350 400 450 500 Temperature, C -5 -10 -15 -20 Top Tray -25 Time over 5 orbits, min LAT-PR-01967 4.1.4 Tracker Overview 50 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Electronics Design • The major challenges: – Low power: <168 W of conditioned power • Less than 0.29 W per MCM or 190 W/channel • The flight design achieves 0.25 W per MCM! – Low noise occupancy: (noise trigger rate <500 Hz) • The trigger requires occupancy less than 5/100,000 ch/trigger • Readout and onboard processing requires <1/10,000 ch/trigger • The beam-test/balloon flight tracker achieved much better… – Compact packaging: bring signals around the tray corner – Manufacturing and QC: 884,736 channels, >98% functional – Reliability: design, redundancy, testing • Implementation: 2 ASIC designs and chip-on-board technology. • Reliability: – Redundant readout and control paths. – Redundant power paths. – Protection against power shorts. LAT-PR-01967 4.1.4 Tracker Overview 51 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Readout Architecture Emphasis on compactness, minimum of wiring, and redundancy: • • • • Serial, LVDS readout and control lines on flat flex-circuit cables. Either of the two communications cables can fail without affecting the other. Two readout and control paths for every 64-channel front-end chip. Any single chip can fail without preventing the readout of any other. 24 64-channel amplifier-discriminator chips for each detector layer • Trigger output = OR of all 1536 channels in a layer. LAT-PR-01967 GTRC Control signal flow GTRC Control signal flow GTRC • Read command moves data into 1 of 2 GTRC buffers. • Token moves data from GTRCs to TEM. GT FE GT FE GTRC Nine detector layers are read out on each side of each tower. GTRC GTRC 9-99 8509A22 Data flow to FPGA on DAQ TEM board. 2 readout controller chips for each layer 4.1.4 Tracker Overview Data flow to FPGA on DAQ TEM board. 52 Control signal flow • Upon trigger (6-fold coincidence) data are latched into a 4event-deep buffer in each front-end chip. Data flow GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 A2 A1 A0 NSDATA_IN A3 TREQ_IN LEFT GTFE RD_IN NTREQ GTRC CTRLREG TACKB NSCMD SCMD_OUT A2 A1 A0 CLKB RESETB NSDATA_IN A3 NTOKEN_OUT NRESET TOKEN CLK NSDATA NTACK TREQ_IN LEFT GTFE RD_IN NTREQ GTRC CTRLREG TACKB NSCMD SCMD_OUT CLK NRESET NSDATA NTACK TOKEN • Block diagram of the ends of two readout layers and their connections to the TEM – Clock, Command, Trigger, and Reset are bussed to the GTRC chips – Token and Data daisy-chain up and down the 9 layers – Each layers sends its Layer-OR directly to the TEM – The TEM communicates only with the GTRC chips, always by serial LVDS. – The GTRC communicates with 24 GTFE chips on the MCM. NTOKEN_OUT Tracker Readout Architecture CLKB RESETO RESETB TEM LAT-PR-01967 4.1.4 Tracker Overview 53 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 MCM Readout Module Configuration • • • • • • • 8-layer polyimide PWB Top edge thickened and machined to a 0.80 SSD mm radius Kapton Bias 1-layer flex circuit (“pitch adapter”) bonded Circuit Tray Structure over the radius Fully encapsulated wire bonds Conformal coating 2 Omnetics nano connectors Adhesive Steel alignment pins + adhesive GTRC, 1 of 2 Pitch-adapter flex bonded over radius ASIC MCM PWB GTFE, 1 of 24 359.0mm 24.58mm 18.0mm Connector, 1 of 2 Grounding Screws 3 Total LAT-PR-01967 Mounting Screws, 1 of 8 4.1.4 Tracker Overview 54 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Pitch Adapter • 1-layer Kapton flex circuit • Ni + Au plating for wire bonding • Precision tooling holes (not shown) • Circuit & traces are trimmed to length after bonding to the PWB Bias HV ASIC Side SSD Side (228 m pitch) “ground” LAT-PR-01967 4.1.4 Tracker Overview 55 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Prototype Electronics Performance • See LAT-TD-1090. Reviewed at TKR ASIC review Dec 6, 2002. • Analog tests with “mini-MCM” plus full-length ladder (384 channels) – Gain and noise from charge-inject/threshold scans – Noise measurements from trigger-rate threshold scans – Noise occupancy from random triggers – Noise injection from digital readout – Gain versus number of channels pulsed – Pulse shapes and Time-Over-Threshold • Functional tests with full MCMs (no SSDs attached) – All digital functionality – Power consumption – Voltage and timing margins – DAC calibrations – Thermal cycling • Radiation Testing: TID, SEU, and SEL done on prototype ICs. LAT-PR-01967 4.1.4 Tracker Overview 56 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Measured MCM Power Consumption AVDDA 1.5 V AVDDB 2.5 V No Clock 77.4 mW 39.3 mW 20 MHz 77.4 mW 39.3 mW DVDD 2.5 V address 5 82.8 mW 134.3 mW MCM Power (W) 138.5 mW Allocation MCM Address > 0 0.251 MCM Address = 0 0.255 Tower 9.05 10.5 W 16 Towers 145 168 W LAT-PR-01967 DVDD 2.5 V address 0 4.1.4 Tracker Overview 57 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Results on the Flight ASICs • GTFE V-G3: 1 wafer was diced without prior probe testing: – 21 ICs were mounted on mini-MCMs and 72 on full-size MCMs – 91 out of 93 randomly selected (unscreened) chips worked 100%. – No evidence of the comparator instability that plagued the previous version (all 93 chips show nearly identical behavior, with stable Layer-OR outputs even at the minimum threshold setting). – The timing margin on the register read-back was corrected: • Chips on the full-size MCMs load and read correctly at VDD=2.5V up to 28 MHz (old versions fail at 23 MHz or less). • Chips also load and read correctly at VDD=2.25V and 20 MHz. – Two mini-MCMs were connected to full-size ladders. Noise performance is similar to the previous versions. • GTRC V-6: 1 wafer was diced without prior probe testing – Tested with probe card & test suite, as well as on mini-MCM and full MCM – All functionality is correct. – Timing margin improved: data readout works up to 30 MHz at 2.5V • >20 wafers have by now been tested with ~95% yield. LAT-PR-01967 4.1.4 Tracker Overview 58 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 EMI/EMC • Requirements document: 433-RQMT-005 • The Tracker will be well shielded: – All transmitted signals are LVDS and digital (very low radiation and excellent noise rejection). In addition, power and ground reference planes are always directly under or over the signal pairs. – Aluminum foil (over carbon-fiber) covering all 6 tower module sides. – Conductive tape around the corners to connect the sides. • SSD strips are the sensitive nodes, but – They are well shielded from any radiation. – Only a very local reference is needed (the amplifiers are millimeters from the strips with well identified, short current return paths). – The local grounding around the SSDs is critical for noise performance. • EM emissions will be tested from the qual unit, but we expect it to satisfy requirements easily (433-RQMT-0005). Preliminary measurements on the BTEM showed no measurable emission, even with the aluminum shielding walls removed. LAT-PR-01967 4.1.4 Tracker Overview 59 GLAST LAT Project LAT-PR-01967 CDR/CD-3 Review, May 12-15, 2003 4.1.4 Tracker Overview 60 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Engineering-Model Towers • Mini-Tower – 3 functional X-Y detector planes (3 X layers and 3 Y layers). – Develop and test tray assembly procedures with real electronics and detectors. – Test the readout electronics in a realistic environment. – Test the detector system with minimum-ionizing particles (cosmic rays). – Exercise the TEM based readout with multiple layers and multiple cables. – Platform for development of Tracker subsystem test procedures and software that will be needed for flight-module production. Carbon– Platform for I&T development. Fiber Wall • Full-size Structural/Thermal Tower – Full Form and Fit Tower – Flight design and materials for vibration testing – Full thermal dissipation for thermal-vacuum testing – Purpose is to develop the mechanical assembly processes and to validate the mechanical/thermal design. LAT-PR-01967 4.1.4 Tracker Overview 61 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Mini-Tower Al “grid” fixture LAT-PR-01967 4.1.4 Tracker Overview 62 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Mini-Tower Configuration • The essence: – 3 instrumented x,y silicon-strip detector planes – Each x,y plane is preceded by a thin tungsten foil (3% rad. len.) • The details: – 4 light composite panels supporting SSD ladders – 1 bottom tray with no SSD but with the mechanical interface to the grid • This is an older prototype tray refitted by COI with preliminary versions of the titanium reinforcement – 8 short versions of the readout cables – 8 MCMs (2 for each pair of readout cables) • The 2 lowest MCMs have no SSDs connected but are required in order to complete the data transmission circuit – Inexpensive aluminum walls • The status: – Presently assembled with prototype MCMs that are only partly functional, due to problems with the pitch adapter and prototype ASICs. – New MCMs with corrected pitch-adapter design and flight ASICs, plus new cables, are in production to refit the mini-tower in late May. LAT-PR-01967 4.1.4 Tracker Overview 63 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Extra Functional Tray • Another tray, instrumented on both sides with SSD and electronics, plus thin converter foils, is being assembled in Italy. This is in addition to the Mini-Tower. • This tray will undergo complete environmental testing to qualification levels, including – Random vibration: GEVS (LAT-TD-01004) – Thermal vacuum: 30C to +50C (LAT-TD-01037) • This will complement the environmental testing of the mechanicalthermal tower module, which will not include functional detectors and electronics. LAT-PR-01967 4.1.4 Tracker Overview 64 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Example EM Tray One of 5 functional trays built, using the first prototype MCMs and preproduction ASICs. Encapsulated ASICs Bias Circuit Handle for assembly fixtures MCM Thermal Boss Connector Saver LAT-PR-01967 4.1.4 Tracker Overview 65 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 EM Mini-Tower Under Test Eduardo Massimiliano Ric Selim Luca Mini-tower The mini tower effort has given the LAT collaboration, and specially the I&T group, the opportunity to build a team of collaborators across the following subsystems: ELX, I&T, TKR, and SAS. LAT-PR-01967 4.1.4 Tracker Overview 66 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Mini-Tower Test Status • All trays were tested individually with cosmic-ray events, using self triggering. Significant dead areas are present due to known problems in the pitch-adapters and ASICs of the first-generation MCM prototypes presently installed. • Register readout and charge-injection events are working with all 8 MCMs and 8 cables simultaneously in use. – This required more time than expected due to it being a learning experience, including much debugging of TEM firmware, our EGSE software scripts, and the cable layouts. – The front-end readout modules have been shown to function in accordance with their known condition prior to tower assembly. • We succeeded one week ago to self-trigger the mini-tower and observe cosmic-ray tracks. • Final quantitative mini-tower results will be obtained only after refitting with new MCMs and flight-version ASICs (in progress). LAT-PR-01967 4.1.4 Tracker Overview 67 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Leakage Currents The leakage current remains within specifications for all tested trays (no damage during assembly). TG001 Back leakage current 3500 Tray-lab The leakage current measured on full trays is in most cases lower than the sum of the single-ladder currents (but ladders were tested at 22º average temperature, while trays were tested at 17.5 º). 3000 Expected (sum of ladderscurrents) Leakage current (nA) 2500 2000 1500 1000 500 0 0 20 40 60 80 100 120 Bias Voltage (V) LAT-PR-01967 4.1.4 Tracker Overview 68 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Noise Trigger Rates • The noise trigger rate is monitored for each FE chip as a function of discriminator threshold. • Residual triggers at high threshold are due to cosmic rays. Threshold scan FE 21 100000 10000 OR of 64 Channels Counting rate (Hz) 1000 100 10 1 0,1 0,01 0 10 20 30 40 50 60 Threshold DAC LAT-PR-01967 4.1.4 Tracker Overview 69 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Cosmic Ray Triggers Event 1 Two example minitower cosmic-ray events obtained from self-triggering (the standard 3-in-arow trigger) Time-Over-Threshold: Event 2 ~ 10 s LAT-PR-01967 4.1.4 Tracker Overview 70 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 EM Tower Plan Synopsis • • • • • • • • May 15: May 27: June 13: June 24: July 8: July 22: August 5: August 15: LAT-PR-01967 M55J closeouts completed K13D sidewall panels completed Bottom tray fabricated Static load testing completed on bottom tray EM tower assembled Vibration testing completed Thermal-vacuum testing completed Deliver EM tower to I&T 4.1.4 Tracker Overview 71 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Test Matrix LAT-PR-01967 T T T M T T TQ TQ Vibe z-axis only Vibe & TV only 1 TQ T TQ TQ M T M T T M M M T T T TQ T T T TQ TQ Test 1 to destruction Vibe 5; z-axis only T TQ T T TQ TQ TQ TQ Comments TQ M TQ TQ Other Radiation T Thermal Cycle T Thermal Balance Burn-In T Thermal Vacuum Functional and Power Stacked Cosmic Ray Test EDS Compatibility (Grounding) T EMI/EMC Flight Tracker MCMs Tray panels Flight Bottom Trays Flight Tracker Std. Trays Flight Tracker Towers Interface Verification F F F F F TQ TQ Thermal Mass Properties C C C C S 4 38 36 19 1 TQ 18 A 1 A Electrical Pressure Profile Mini-MCMs (ASICs) Qualification MCMs QM Tracker MCMs Tray panels QM Bottom Tray QM Tracker Std. Trays QM Tracker Tower Acoustic Q Q Q Q Q Q Q Random Vibe + modal survey C C C C C C S 8 24 5 1 2 TQ 18 A 1 A Sinusoidal vibration+modal survey Component (ITEM) EM Tracker MCMs Tray panels Live trays EM Mini-Tower EM Bottom Tray EM Tracker Std. Trays EM Tracker Tower Sine Burst (static equivalent acc.) E E E E E E E Static Load Unit Type C C C C C C S Mechanical Quantity Assembly Level Hardware 2 for DPA Vibe z-axis only A 612 T 323 TA TA 17 TA T 306 T 17 TA TA TA M T Assembly Level Unit Type S= Subsystem F= Flight C= Component Q= Qual E= Engineering Model T T T T T T T T TQ TQ TQ T T T Vibe z-axis only T T T T QS QS T TA QS Verification Method: T= Test A= Analysis M= Measurement 4.1.4 Tracker Overview TA TA QS= Qual by Similarity TQ= Test, Qual Level TA= Test, Acceptance Level 72 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Static Proof Test of Bottom Tray Interface • Validate bottom tray and flexure design with static proof test in the lateral and vertical direction, scheduled for June ‘03 – Proof test to ±110% of Max expected load • Two bottom trays will be tested – 1 will be used in E/M RV test – 1 will be tested to failure • Static test goals – Measure interface stiffness – Proof test E/M bottom tray – Verify capability of bottom tray design – Verify flexure and heat strap design LAT-PR-01967 4.1.4 Tracker Overview {Sidewall not shown for clarity} 73 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Bottom Tray Test Configuration C.G. Reaction Point Tower Simulator Flight Equivalent Sidewalls (K13D2U/RS-3) Tray #2 Bottom Tray Heat Straps Flexures Grid Simulator Base Reaction Frame LAT-PR-01967 4.1.4 Tracker Overview 74 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Lateral Test Configuration Base Reaction into Granite Table Load Cell {Not Shown} Spring Assembly Reaction Frame {Outer Plate Not Shown} LAT-PR-01967 Reaction Shaft/Nut 4.1.4 Tracker Overview Displacement Probes 75 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Vertical Test Configuration Base Reaction into Granite Table {Not Shown} Reaction Shaft/Nut Spring Assembly Reaction Frame Load Cell LAT-PR-01967 Displacement Probes 4.1.4 Tracker Overview 76 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Panel Vibration Testing Tungsten side on the top Panels undergo acceptance vibration tests before mounting MCMs and ladders. Centrotecnica setup (Milan): - 1 LDS shake table - 2 fixtures - 9 read out channels Accelerometers: • Control: two mono-axial accelerometers positioned on two of the four L-shaped blocks TP1&TP2 • Fixture: three mono axial accelerometers placed on a corner on one of the four Lshaped block TP6 • Tray: one three-axial accelerometers in the middle of panel TP5 LAT-PR-01967 4.1.4 Tracker Overview 77 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Panel Vibration Levels Sine sweep Frequency range 20 2000 Hz Sweep rate 2 oct/min Maximum Amplitude 0.25 g0-pk Random vibration LAT-PR-01967 Frequency (Hz) ASD Acceptance Level (g2/Hz) ASD Qualification Level (g2/Hz) 20 0.01 0.01 20-50 +3 dB/oct +3 dB/oct 80-500 0.04 0.04 800-2000 -3 dB/oct -3 dB/oct 2000 0.01 0.01 Overall 6.8 grms 6.8 grms Duration 1 min/axis 2 min/axis 4.1.4 Tracker Overview 78 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Vibration Levels Low frequency sine sweep Random vibration High frequency sine sweep Frequency range 20 2000 Hz Sweep rate 2 oct/min Maximum Amplitude 0.25 g0-pk LAT-PR-01967 Frequency (Hz) ASD Acceptance Level (g2/Hz) ASD Qualification Level (g2/Hz) 20 0.01 0.01 20-50 +3 dB/oct +3 dB/oct 80-500 0.04 0.04 800-2000 -3 dB/oct -3 dB/oct 2000 0.01 0.01 Overall 6.8 grms 6.8 grms Duration 1 min/axis 2 min/axis 4.1.4 Tracker Overview 79 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Thermal Setup • Tower covered with a thermal blanket during T-V cycles. • The temperature of the plate onto which the tower is mounted is controlled. • During equilibrium the temperature is measured on all sides and at various heights throughout the tower. The tower has 16 thermistors in the readout cables at varying heights that can be acquired by using the TKR DAQ system. Additional thermocouples (TBR): 1.+Y sidewall center of the thermal boss of the tray number 1; 2.+X sidewall center of the of the tray number 1, on the center plane; 3.+Y sidewall center of the thermal boss of the tray number 19; 4.+X sidewall center of the of the tray number 19, on the center plane; 5.-X sidewall center of the thermal boss of the tray number 10; 6.-Y sidewall near the center of the tray number 10, on the center plane LAT-PR-01967 4.1.4 Tracker Overview 80 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray Thermal Levels Acceptance Qualification/Survival Temperature Range -20°C 35°C -30°C 60°C # of cycles 4 4 Temperature rate 20°C/hr 20°C/hr Pressure 1 atm T-C 1 atm T-C Duration @ T extreme 5 hr 5 hr Total Duration 62 + 2 hr 72 + 2 hr On orbit temperature range -15°C 30°C LAT-PR-01967 4.1.4 Tracker Overview 81 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower A Thermal Levels Thermal-Vacuum cycling/Qual level LAT-PR-01967 Ranges -30°C 50°C # of cycles 12 Temp. rate 20°C/hr Pressure 10-5 Torr Duration @ extreme 12 hr Total Duration 384 hr + stabilization @ T room 4.1.4 Tracker Overview 82 GLAST LAT Project LAT-PR-01967 CDR/CD-3 Review, May 12-15, 2003 4.1.4 Tracker Overview 83 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Production Overview Module Structure (walls, flexures, thermal-gasket, fasteners) Engineering: SLAC, Italy (Hytec) Procurement: SLAC, Italy SSD Procurement, Testing Japan, Italy, SLAC SSD Ladder Assembly Italy (G&A, Mipot) Tracker Module Assembly and Test Italy 10,368 2592 18 Tray Assembly and Test Italy (G&A, Mipot) 342 Electronics Design, Fabrication & Test UCSC, SLAC (Teledyne) Readout Cables UCSC, SLAC LAT-PR-01967 342 648 Composite Panel & Converters Engineering: SLAC, Italy (Hytec, COI) Procurement: Italy (Plyform) 4.1.4 Tracker Overview 84 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tracker Production Overview • SSD receiving & test (LAT-TD-00527). – At INFN institutes in Pisa and Perugia/Terni – 41% complete • Ladder fabrication (LAT-PS-00635). – Commercial vendors G&A and MIPOT in Italy – PRR’s completed last September (G&A) and in April (MIPOT) – 250 flight ladders assembled (about 10%) • MCM assembly (LAT-DS-01856). – Teledyne Electronic Technologies – Second prototype round is in progress • Tray panel fabrication (LAT-PS-01584). – Plyform S.R.L. in Italy – PRR held in April; some RFA’s needing closure • Tray assembly (LAT-PS-01801 and LAT-PS-01802). – G&A in Italy • Tower assembly (LAT-PS-01854 and LAT-PS-01855). – INFN Pisa • Environmental testing (LAT-TD-00155 and LAT-TD-01840). – Alenia Spazio in Rome LAT-PR-01967 4.1.4 Tracker Overview 85 GLAST LAT Project LAT-PR-01967 CDR/CD-3 Review, May 12-15, 2003 4.1.4 Tracker Overview 86 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 CCB Actions Affecting 4.1.4 TKR Change Request # Description Status LAT-XR-00883-01 Hytec Design Consulting Approved, $40K LAT-XR-01319-01 Procurement of Silicon Strip Detectors Approved, $387K* LAT-XR-01457-01 Bottom Tray Redesign Approved, $629K LAT-XR-01463-01 Assemble Flight Tray Panel Detail Breakdown Approved, $0K LAT-XR-01622-01 Delay of Silicon Strip Detectors Approved, $0K LAT-XR-01861-01 Hytek Design Support Approved, $0K LAT-XR-01752-02 SLAC/HEPL Labor Escalation Rate Changes Approved, -$17K *Directly offset by corresponding funding increase from Japan. LAT-PR-01967 4.1.4 Tracker Overview 87 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Key Deliverable Milestones Activity Description FY 04 FY 05 JAN FE B MAR AP R MAY JUN JUL AUG SE P OCT NOV DE C JAN FE B MAR AP R MAY JUN JUL AUG SE OCT P 4.1.4 Tracker T racker Modules A & B RFI ( for Calibration) T racker Modules 1 & 2 RFI ( for Calibration) Flight Tracker T ower 3, 4 RFI Flight Tracker T ower 5, 6 RFI Flight Tracker T ower 7, 8 RFI Flight Tracker T ower 9, 10 RFI Flight Tracker T ower 11, 12 RFI Flight Tracker T ower 13, 14 RFI Flight Tracker T ower 15, 16 RFI Run Date 04/21/03 15:05 Data Date 04/01/03 © Primavera Systems, Inc. LAT-PR-01967 G LA ST L A T PR OJ EC T A V: F loa t to Le ve l 3 M ile sto nes Forecast Baseline Product Available Date Forecast Baseline Integration Need Date LT-T7: Level 3 to AV :(tb) FL-D7 Integration Mil estones CDR AV : Up Triangle, L3: Down Triangl e 4.1.4 Tracker Overview Sheet 1 88 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 4.1.4 Work Flow Summary LAT-PR-01967 4.1.4 Tracker Overview 89 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 4.1.4 Work Flow Summary LAT-PR-01967 4.1.4 Tracker Overview 90 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 4.1.4 Work Flow Summary LAT-PR-01967 4.1.4 Tracker Overview 91 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Critical Path • Silicon Strip Detectors (SSD) – SSD Procurements • 8154 SSDs shipped from HPK by 5/31/03 • Balance of SSDs (3381) by 9/30/03 • TMCMs – From the present best-known schedule for delivery of flight EEE parts, SLAC will deliver the first set of TMCMs to Pisa 9/17/03. • Flight Tray Panel Fabrication – Tentatively begins in mid May, but some RFAs from the PRR and Peer Review are still being closed (note that the TMCMs are driving the schedule at present). LAT-PR-01967 4.1.4 Tracker Overview 92 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Budget, Cost Performance $M, Then-Year Dollars 12 8 4 Actual Commitments ACWP BCWP BCWS+ Planned Commitments BCWS 0 . . . . FY00 LAT-PR-01967 . . . . FY01 . . . . . . . . FY02 . . . . . . . . . . FY03 . . . . . . . . FY04 4.1.4 Tracker Overview . . . . . . . . FY05 93 . . GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Cost/Schedule Status • Status as of March 31, 2003: Item In k$ Budget at Complete 10,915 Budgeted Cost for Work Scheduled (a) 7,400 (a) Budgeted Cost for Work Performed (b) 6,716 (b) Actual Cost for Work Performed 6,630 Cost Variance 87 1.3% of (b) Schedule Variance -684 -9.2% of (a) The schedule variance mostly represents the cost of all the MCM production parts and materials, for which procurement was not completed in March as originally planned. LAT-PR-01967 4.1.4 Tracker Overview 94 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Risks TKR-1 • • • • • Risk Description: – Low Tracker MCM yield. Each MCM holds 26 ICs. The MCMs are tested before encapsulation, to allow for rework. However, rework is costly, and too much rework could make it impossible to hold the schedule and budget. We need it to be the exception, rather than the rule, but so far, in the EM run, rework involving IC replacement was needed on the majority of MCMs. Risk Mitigation: – Screening and handling procedures need to be improved according to the plan described here. Risk Impact Assessment: – Possible delay in tower assembly and increased labor cost at Teledyne. Risk Mitigation Implementation Plan: – 1. (Johnson, Sugizaki) Improve IC screening. The GTRC chips were not screened for the EM, some features of the GTFE were not screened, and the screening was at only 2 MHz due to technical problems. These systems will be improved and tested. An inker is being added to the probe station to remove human error in die sorting. We also may need to reject dice close to the wafer edge. (end March) 2. (Johnson, Ziegler) Improve IC handling. Detailed procedures are being written. (end March) 3. (Borden) Improve testing of the MCM PWB prior to assembly and again prior to die attach. (Mid April) 4. (Johnson, Sugizaki) Improve the MCM test software to speed up localization, of a bed IC. (June 1) 5. Improve IC design (done), especially to remove the G-chip oscillation problem. Current Status: – May 2, 2003: both probe cards were rebuilt and successfully tested, and the test software now tests 100% of functionality. The wafer testing procedures were completed, reviewed and released. The cleanroom has been upgraded and inspected. Flight wafers are under test, including automated inking of bad dice. The yield is excellent, and the known ASIC bugs, including the oscillation problem, have been demonstrated to be cured in the flight design. The lapping and dicing procedures were prepared by Clinton & Virmani, and we are preparing to dice 3 wafers under these specs and retest the assembly procedure at Teledyne on 10 MCMs (to be used to refit the mini-tower). LAT-PR-01967 4.1.4 Tracker Overview 95 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Risks TKR-2 • • • • • Risk Description: – MCM-SSD CTE mismatch. The Tracker MCMs and the SSDs are connected by wire bonds, which are to be encapsulated. This interface is not yet tested. Since it goes the full width of a tray, there is a risk of damage from movement during thermal cycling. Risk Mitigation: – The flight MCMs are to be fabricated in Polyimide instead of FR4, to lower the CTE (Aramid was considered but has other undesirable features). The encapsulation will be Nusil silicone, as in the ladders, which allows some movement with low stress. The interface needs to be tested on the EM. Risk Impact Assessment: – Critical Path Impact Risk Mitigation Implementation Plan: – Build a complete functional engineering-model tray by mid April(two MCMs) in addition to the ones in the mini-tower, and put it through full qualification-level thermal-vacuum testing. (May) Current Status: – May 2, 2003: The tray panel is in hand, as are the two MCMs and the ladders. The procedure for encapsulating these bonds is being tested first on some mechanical/thermal EM trays. At present the design is done and the dams for the adhesive are being made. LAT-PR-01967 4.1.4 Tracker Overview 96 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Risks TKR-3 • • • • • Risk Description: – Tray-panel fabrication start-up. Fabrication of tray panels at Plyform needs to start in early March (i.e. pre-CDR) unless the rate can be made to exceed current predictions. We have not yet seen a plan from Italy/Plyform on how to accomplish this, nor have we seen any documentation. Risk Mitigation: – SLAC assistance to Pisa in getting documentation and materials in place. Risk Impact Assessment: – Critical path impact Risk Mitigation Implementation Plan: – Acquire Carbon-Carbon material early from SLAC (done). Procure cores from SLAC (in progress). Tom Borden travel to Plyform in early February to assist with planning and documentation. Current Status: – May 2, 2003: 1. The cores were ordered and already received and shipped to Italy. 2. Tom Borden traveled to Italy and helped prepared a draft procedure document. 3. We received a detailed schedule from Pisa for the flight build. It shows that the tray panel fab can start in May instead of March and the electronics will still be the critical path. 4. The PRR for the panels was held at Plyform in March. Some issues need to be closed before start of flight production, particularly verification of the new plan to provide grounding of the core. LAT-PR-01967 4.1.4 Tracker Overview 97 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Risks TKR-4 • • • • • Risk Description: – Procurement of MCM components. MCM production at Teledyne needs to start soon to have MCMs ready to accept ASICs in late May. The design includes parts that are not yet approved but have 8week lead times (the connectors), parts for which we have been working for a long time for approval without complete closure (polyfuses), and parts for which we do not have agreement on fabrication specifications (the PWB and flex). Furthermore, our success rate at SLAC for procuring these items for the EM was poor. We need Teledyne on contract to help us handle these procurements. The LAT parts specialist to date has never made any contacts with Teledyne. Risk Mitigation: – Increase manpower at SLAC on these procurements. Contract with Teledyne to do all of the parts receiving. Risk Impact Assessment: – Critical path impact. Risk Mitigation Implementation Plan: – Have a meeting at Teledyne, including Nick Virmani, as soon as possible to iron out the contract and specifications to be used for MCM PWB and flex procurements and specifications to be used for MCM assembly. Action also needs to be taken on the Omnetics nano-connectors to get them approved for flight. Current Status: – May 2, 2003: 1. The meeting at Teledyne was held successfully, clarifying a lot of issues. 2. The Omnetics connectors were approved and are on order. 3. The HV caps and polyswitches were approved and are on order. 4. Final PWB and flex prototypes are in hand and being tested. 5. We are close to getting orders out for the remaining standard resistors and capacitors. The limiting schedule item is the HV cap, with delivery expected August 1. To gain back schedule, we will carry out the preproduction run of 36 boards (non-flight boards to deliver to the software group) using non-flight capacitors of the same type from the same vendor. LAT-PR-01967 4.1.4 Tracker Overview 98 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Appendix A LAT-PR-01967 4.1.4 Tracker Overview 99 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Documentation Status TKR Level-3 Specification LAT-SS-00017 TKR Interface Control Documents Mech: LAT-SS-00138 Elec: LAT-SS-00176 TKR Level-4 Specification Mech: LAT-SS-00134 Elec: LAT-SS-00152 Electronics Design Conceptual: LAT-SS-00168 GTFE ASIC: LAT-SS-00169 GTRC ASIC: LAT-SS-00170 MCM: LAT-SS-00171 GND & Shield: LAT-SS-00173 FMEA: LAT-TD-00178 LAT-PR-01967 Draft documents in italics Parts & Materials Mechanical: LAT-SS-00172 Electrical: LAT-SS-00179 Spares Plan: LAT-TD-01379 Procurement Specs SSD: LAT-DS-00011 Polyswitch: LAT-SS-01116 HV Cap: LAT-PS-1194 GTFE ASIC: LAT-PS-01201 GTRC ASIC: LAT-PS-01222 Flex cable: LAT-PS-01132 PWB: LAT-PS-01448 Fabrication Procedures Ladders: LAT-PS-00635 Tray panel: LAT-PS-01584 MCM: LAT-PS-01856 Trays: LAT-PS-01801/2 Towers: LAT-PS-01854 Test Plans & Procedures SSD: LAT-TD-00085/00527 Elec. Plan: LAT-TD-00153 ASIC probe: LAT-TD-01250 GTFE ASIC: LAT-TD-00247 GTRC ASIC: LAT-TD-00248 MCM: LAT-TD-00249 Radiation: LAT-PS-01325 Tray vibration: LAT-TD-00154 Tray thermal: LAT-TD-01839 Tower vibration: LAT-TD-00155 Tower thermal: LAT-TD-01840 4.1.4 Tracker Overview 100 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Requirements Flowdown • The flowdown shown in Foldout D of our NASA proposal is still valid. • Science Requirements that flow down to the Tracker design: – Effective Area – Field of View (aspect ratio) – Point Spread Function – Background Rejection – Dead Time • These Science Requirements flow down to the Tracker Level-3 Requirements, documented in LAT-SS-00017. • Other requirements are imposed by the IRD, the Tracker ICDs, and the LAT environmental specification, LAT-TD-00778. • The Tracker Level-4 Requirements documents specify our detailed requirements as they pertain to our specific design implementation. – Mechanical: LAT-SS-00134 – Electrical: LAT-SS-00152 LAT-PR-01967 4.1.4 Tracker Overview 101 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Key Tracker Requirements Parameter Requirement Actual Verification Power <155 W 148 W T,A Mass <510 kg 509 kg T Geometric active area >19,000 cm2 19,630 cm2 A Conversion efficiency >65% 65% A Converter-sensor spacing <3 mm 2.9 mm A Non-converter material (front) <35% 33% A <5% X0 5.1% X0 A 2-plane spatial resolution <0.2° 0.17° A Dead area <12% 11.2% A Hit efficiency >98% (>99% BTEM) T Aspect Ratio (FOV) <0.45 0.42 A <500 Hz (<10 Hz BTEM) T Effective area: Point Spread Function: Inter-tower material Trigger Noise Rate (Self Trigger) LAT-PR-01967 4.1.4 Tracker Overview 102 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Key Tracker Requirements Parameter Requirement Actual <0.25 ms <0.15 ms T Dead Time at 10 kHz trigger <10% <<10% by A A,T Noise Occupancy <104 (<105 BTEM) T Ionization Meas. (1 MIP vs 2 MIP) >2 >4 by A A,T Trigger Recovery Time Verification Radiation Hardness: see electronics design section. Reliability: see electronics design section and FMEA in LAT-TD-00178. Structural and Environmental (LAT-TD-00778): see mechanical design section. Contamination Control: LAT-MD-00404. Parts Control: LAT-MD-00099. EMI/EMC: 433-RQMT-0005: see electronics design section. LAT-PR-01967 4.1.4 Tracker Overview 103 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Appendix B LAT-PR-01967 4.1.4 Tracker Overview 104 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Parts & Materials • Two levels of controlling documentation: – LAT Level • LAT-DS-00405 LAT Mechanical Materials and Parts list • LAT-SS-00401 LAT EEE Parts Identification List • LAT-SS-00099 LAT EEE Parts Program Control Plan – Tracker Level • LAT-SS-00172 Tracker Mechanical Parts and Materials list • LAT-SS-00179 Tracker Electronics Parts list • LAT-TD-01379 LAT Tracker Parts and Components Spares Plan LAT-PR-01967 4.1.4 Tracker Overview 105 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Procurements • • • • • • • • • • • • • • In Progress SSDs: LAT-DS-00011 (~40%) Carbon-carbon bars (~50%) Aluminum cores (100%) Aluminum inserts Face-sheet material Tungsten foils ASICs (wafers 100%; testing & dicing in progress) – GTRC: LAT-PS-01222 – GTFE: LAT-PS-01201 HV caps: LAT-PS-01194 Polyswitches: LAT-SS-01116 QML SMT parts Nano connectors PWBs: LAT-DS-01448 Pitch-adapter flex EGSE & MGSE LAT-PR-01967 • • • • • • • • Starting Soon M55J material Sidewall material Tower fasteners Titanium flexures and brackets Thermal straps Bias circuits Flex-circuit cables: LAT-PS-01132 Micro-D connectors 4.1.4 Tracker Overview 106 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 TKR Silicon Strip Detectors • • GLAST has driven the 6” wafer technology: - Procurement spec: LAT-DS-00011 - Area: 8.95 cm x 8.95 cm - Thickness: 400 um, pitch 228 um GLAST - Very aggressive specs Cut-off (leakage currents, bad strips, dicing) 5261 SSDs received (by Peer Review date); “Skinny” 4304 tested; 165 reviewed; 38 rejected. “Skinny” GLAST Cut-of – SSD Testing Program: QA provisions: LAT-CR-00082. Testing at the manufacturer, Hamamatsu Photonics (HPK): • Detector IV and CV GLAST • Test for bad channels (opens, shorts, broken capacitors) Flight SSD Testing at INFN Pisa or INFN Perugia (LAT-TD-00527) • Measure alignment of the cut edges with the lithography • Repeat IV and CV curves (all SSDs) Lot testing (using test structures): Hiroshima University LAT-PR-01967 4.1.4 Tracker Overview 107 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Ladder Fabrication Flow • LAT ladder fabrication follows this block diagram (see LAT-PS-00635 and LAT-PS-00831 for details) WS1: Receiving and Inspection Storage WS2: SSD Edge Bonding WS5: Electrical Tests Storage WS6: Wire-Bond Encapsulation WS3: Metrology Storage WS7: Encapsulation Inspection Storage WS4: Wire Bonding WS8: Electrical Tests Storage WS9: Storage of Completed Ladders • Assembly at G&A Engineering (251 flight ladders produced) • Assembly at Mipot staring up (PRR completed in April) LAT-PR-01967 4.1.4 Tracker Overview 108 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 SSD Edge Bonding Ladder assembly tool alignment errors 100 90 m 80 • Fast AND precise manual method • 24 ladder assembly tools used in parallel • Very good ladder alignment obtained 70 60 50 40 30 20 10 0 -20 -15 -10 -5 0 5 10 15 m LAT-PR-01967 4.1.4 Tracker Overview 109 20 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Encapsulation Dam & Fill encapsulation Dam: Nusil CV-1142 Fill: Nusil CV-15-2500 Requirements: 1. Height <0.5mm 2. Lateral overflow <0.05mm 3. Coverage of all the bondings and pads Fast system to verify the encapsulation height LAT-PR-01967 4.1.4 Tracker Overview 110 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Electrical Tests: Results 2000 1800 Leakge current history Expected Post-encaps. 1600 current (nA) 1400 1200 1000 800 600 400 200 Depletion voltage 0 1142 ladder ID 1163 1183 1203 1224 1244 1266 70 ladder dep. V expected from SSD 60 50 The causes of problems 3 and 4 have been corrected, foreseen rejection rate ∼1% LAT-PR-01967 40 30 20 10 90 80 70 60 50 40 30 0 20 Electrical test results: 1. Ladder tested 251 2. Accepted 243 (97%) 3. Broken edge 4 4. Probe accident 1 5. Not understood 3 150 1121 140 1101 130 1076 120 1054 110 1034 100 1014 Depletion voltage (V) • Bad channels caused by bonding (coupling shorts)=0.016% (accepted limit 1%) • No broken or bad wire-bond connections 4.1.4 Tracker Overview 111 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Ladder Fabrication Conclusions • Ladder fabrication has been successfully started (9% of the ladders have been produced with a 97% yield; likely increase of the yield to 99%). • Electrical and dimensional ladder characteristics are well within specifications • The production rate is > 10 ladders/day in both assembly centers, which will work in parallel (G&A Engineering and Mipot), so there are no schedule issues with this process. LAT-PR-01967 4.1.4 Tracker Overview 112 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 MCM Assembly Overview • Parts and materials all approved and presently on order • Assembly at Teledyne Electronics Technologies (L.A.) – Right-angle-interconnect assembly • This is the only non-standard process. • The long, narrow shape of the board, with raised edge and large number of ICs, is also unusual and requires special care. – Connector mounting and soldering of SMT parts – Die attach – Wire bonding – Electronics testing – Wire-bond encapsulation – Conformal coating • SLAC – MCM acceptance testing and burn-in LAT-PR-01967 4.1.4 Tracker Overview 113 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Pitch Adapter Installation • • • • Custom tooling developed by Teledyne Electronic Technologies. Epoxy is screened onto the flex circuit. Tooling aligns the flex with the PWB and bends it around the radius. Another tool cuts both edges flush with the PWB. 1 3 2 LAT-PR-01967 4.1.4 Tracker Overview 114 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Detail of an EM MCM, at One End Polyswitch Nanonics Connector (will be Omnetics) Pitch-adapter flex circuit GTRC ASIC 90° radius Grounding screw hole GTFE ASIC Shown prior to wire-bond encapsulation and conformal coating. LAT-PR-01967 4.1.4 Tracker Overview 115 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 IC Wafer Procurement (Complete) • Vendor: The MOSIS Service of the USC ISI. – Checking of design files, including DRC on the layout – Subcontracting for fabrication of the masks (Dupont) – Subcontracting the wafer fabrication • HP/Agilent 0.5 m, 3-metal, epitaxial process (AMOS14TB) – Thorough electrical testing of process monitors on each wafer • MOSIS guarantees that the wafers meet the Agilent process specifications • MOSIS provides the test results in the form of e.g. physical transistor parameter, sheet resistance, etc. – Extraction of Spice model parameters for each wafer lot • BSIM3 V3.1 models for design verification, especially in case problems arise – Shipment of wafers to SLAC • LAT specifications: LAT-PS-1201 and LAT-PS-1222 (released) LAT-PR-01967 4.1.4 Tracker Overview 116 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 ASIC Screening • Procedures, QA provisions, and travelers: LAT-PS-1250 • Detailed descriptions of the test vectors: – LAT-TD-247 for the GTFE – LAT-TD-248 for the GTRC • Carried out in a cleanroom at UCSC – Conforms with the LAT contamination control plan (LAT-MD-404) – Conforms with ESD controls of NASA-STD-8739.7 – 100% testing of all functionality – GTFE performance testing • Results: – GTRC (9 wafers) 95% yield – GTFE (3 Wafers) 93% yield • Wafer lapping, dicing, inspection – LAT-PS-01321 LAT-PR-01967 4.1.4 Tracker Overview 117 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 MCM Functional Test • Complete functional before die encapsulation (LAT-TD-00249) – Test all register and memory locations – Test all I/O functions, including LVDS bias levels – Test all inter-chip communication – Check power consumption – Test all amplifiers by charge injection and test the trigger output – Test for excessive noise or instabilities • A non-functional IC can be replaced at this point, if necessary, but our goal is to avoid having to do that. Interface Card (with cover removed) VME with COM Card and ADC Frequency Counter PC MCM DUT LAT-PR-01967 Adjustable Clock 4.1.4 Tracker Overview 118 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Test and Burn-In • This work will be done in the SLAC clean room in Building 33. • The MCMs remain in their closed storage boxes throughout this procedure. • A functionality test is done to check that no damage occurred during encapsulation. • 9 MCMs are connected to a pair of special flex-circuit cables (1 is shown at right, with a repeater board). • 4 such cables pairs are installed in a climatic chamber. • 8 long cables attach to the repeater boards and exit the chamber, to connect with a TEM. • The 36 MCMs are thermal cycled through the required acceptance cycles. • The temperature is raised to 85°C for 186 hours for burn-in. During this time the electronics are continually exercised and tested. LAT-PR-01967 4.1.4 Tracker Overview 119 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 EM MCM-Assembly Experience • Several problems were encountered in the first iteration that limit the usefulness of the MCMs presently installed on the mini-tower. See LAT-TD-01495 for a listing of the issues and the lessons learned. • A second iteration of MCMs is presently in progress, to refit the minitower by the end of May: – Flight-version ASICs, 100% functional and wafer tested with greatly improved hardware/software. – Improved dicing, inspection, and handling of the wafers. – New pitch-adapter flex-circuit design, with alignment and breakage issues worked out of it (this was the biggest source of loss of functionality in the previous MCM design). – New iteration of the PWB, with small bugs worked out of the design and with a greatly improved backside insulating layer. • We are confident that we will reach the specified >98% workingchannels with the new mini-tower MCMs. LAT-PR-01967 4.1.4 Tracker Overview 120 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 MCM Assembly onto Trays MCM incoming test: • Read out tests • Noise level • Noisy channels • HV test MCM final test: • Read out tests • Noise level • Noisy channels • HV test Procedure doc: LAT-PS-01802 MCM assembly with adhesive • Scotchweld 2216 A/B gray • Adhesive thickness .1mm • Pattern of adhesive lines to avoid air trapping • Pins to align to the closeout • Area occupancy ∼50% ⇨ Δt≲0.10C • Wire bond to the bias circuit The tray is put into the storage/shipping box and delivered to G&A for assembly of ladders onto the tray. LAT-PR-01967 4.1.4 Tracker Overview 121 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 The Tray Storage Box • This robust aluminum box provides safe and clean storage & shipping. • The tray can be fully tested while inside the closed box, connecting the MCMs to a readout cable via the connector savers. Fixation screws Connector saver protections Connector savers LAT-PR-01967 4.1.4 Tracker Overview 122 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Assembly of Ladders onto Trays • All the assembly operations under C.M.M. • Glue spots deposited with automated dispenser • Microbonding with automated wedge bonder C.M.M. with touch head and optical head Ladders vacuum kept on the bridges Reference dowels Jig of ladders alignment Alignment micrometers Jig of tray alignment LAT-PR-01967 4.1.4 Tracker Overview 123 GLAST LAT Project Ladder positioning CDR/CD-3 Review, May 12-15, 2003 Assembly phases Tray positioning • 1 set of assembly tooling ready • 5 more sets in fabrication • Max assembly rate: 15 trays/week • Planned assembly rate: 10 trays/week Microbonding LAT-PR-01967 4.1.4 Tracker Overview 124 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 First results Requirements: • Alignment error < 40m • Planarity 100m TG02 dw Planarity glue pads 5mm cure time 6h 0.4 ladder alignemnt 4.5 =14m 4 0.3 3.5 Z (mm) 3 0.2 x=47 0.1 0 -0.1 0 100 200 300 400 2.5 x=231 2 x=404 1.5 1 0.5 30 20 25 10 15 5 0 -5 -1 0 -1 5 -2 0 -3 0 Y (mm) -2 5 0 -0.2 m • Alignment and planarity of the ladders are within specification with improvements still possible. • Tools in production will allow an assembly rate that matches well the test rate of the trays and towers. LAT-PR-01967 4.1.4 Tracker Overview 125 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray Cosmic-Ray Test • • • • • Tray acceptance test, burn-in (room temperature), and calibration 4 set-ups in Italy, each with TEM-based EGSE system Trays remain inside their protective boxes, connected by connector savers Full set of flight-like flex-circuit cables plus 8 extender cables for each setup Accumulate cosmic-ray data for about 1 week LAT-PR-01967 4.1.4 Tracker Overview 126 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tray/Tower Test: EGSE in Pisa Processor & COM Cards 28 V Power Mini-MCM (DUT) TEM Power Module LAT-PR-01967 4.1.4 Tracker Overview 127 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Module Assembly Flow See LAT-PS-01854 and LAT-PS-01855 and for details LAT-PR-01967 4.1.4 Tracker Overview 128 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Reference pins Fixation holes Safety pins LAT-PS-01854 Below: pre-engineering tower ready for transportation and tests. Cable opening Lift system • Tray assembly system successfully tested during the pre-engineering tower test (spring 2002) • Iteration of the fixture design is in progress for the EM tower LAT-PR-01967 Fixture 4.1.4 Tracker Overview 129 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Module Assembly • With the help of a reference system made with precise aluminum walls, the stack of the trays is fast, accurate, and safe. • Complete functional test of the tower electronic readout system before attaching each sidewall. • The sidewalls are then added. Each tray is referred to precision holes in the sidewalls, which provides good alignment without accumulate of errors. • The system has been tested. The errors were below the maximum allowable tolerance (0.3mm). The process is fast (<1 day to mount a tower). • The tower is a good cosmic-ray telescope. The cosmic rays flux allows a complete and deep understanding at the single-channel level in a short time (1 week). • The fixture design is presently under revision to improve safety features that are important to avoid SSD damage. LAT-PR-01967 4.1.4 Tracker Overview 130 GLAST LAT Project CDR/CD-3 Review, May 12-15, 2003 Tower Storage & Shipping • Documentation – LAT-SS-00778, LAT Environmental Specification – LAT-SS-00134, Tracker Level IV Specification – LAT-MD-00228, LAT Contamination Control Plan • Full performance testing before and after shipping (LAT-TD-00191) • Full as-built documentation delivered with Towers • Shipping Containers: – Double containment • Inner container attaches to vibration fixture – Aluminum rods at each corner of vibration fixture – Data logger attached to vibration fixture » Mechanical shock, temperature, humidity and pressure – Electronic readout cables secured under tower – Outer Container: high-density foam and high impact plastic • Storage in the inner container, in the clean room LAT-PR-01967 4.1.4 Tracker Overview 131