Feb 8, 2007 GLAST LAT Project GLAST Large Area Telescope Gamma-ray Large Area Space Telescope LAT Observatory PER Stanford Linear Accelerator Center NCRs and Waivers 1 Feb 8, 2007 GLAST LAT Project LAT Environmental Test Flow 5/14/06 System Commissioning/ System Test Shipment 5/08/06 3 days 5/20/06 Offload & Set-up LAT CPT Sine Vibe 5 days 5 days 9 days PER 5/25/06 Install Radiator s 3 days EMI/EMC Test 6/14/06 11 days Acoustic Test 6/24/06 7 days 7/1/06 7/05/06 7/29/06 Pre TV 7/5/06 T- Bal T- Cycle 43 days NCRs and Waivers 9/07/06 CPT 3 days Remove Radiator s 2 days Weight & CG Pack and Ship 9/12/06 2 days 2 days PSR 9/15/06 9/18/06 Arrival SASS 2 Feb 8, 2007 GLAST LAT Project Post delivery items • Post delivery CPT successfully completed • FSW load B0.6.12, B0.6.13, B0.6.14, B0.6.15 and B0.7.0 and regression test successfully completed • LAT mechanically integrated to spacecraft • LAT Inrush measurements completed • LAT functional test completed • FSW load B0.8.0, B0.8.1 and B0.8.2 and regression test successfully completed • LAT to Spacecraft interface characterization test completed • FSW load B0.9.0 successfully completed and regression test in process NCRs and Waivers 3 Feb 8, 2007 GLAST LAT Project Unit Run Time • These unit run times (in hours) start after the LAT was completely integrated and cover through the completion of the CPT after TV – Does not include integration testing – Does not include unit testing Config No. SIU-P 1 2 3 4 5 6 7 8 9 1441 0 74 0 0 31 0 0 24 1570 LAT UNITS ON SIU-R GASU-P GASU-R EPU-P0 EPU-P1 EPU-R Towers 0 1742 0 47 54 0 5 5 0 1441 0 0 0 54 31 5 0 0 1853 NCRs and Waivers 1531 0 1742 74 47 0 0 0 5 24 1892 1441 0 74 47 54 0 5 0 24 1645 1441 1742 74 0 0 31 0 5 24 3317 0 1742 0 47 54 31 5 5 0 1884 1441 1742 74 47 54 31 5 5 24 3423 ACD 1441 1742 74 47 54 31 5 5 24 3423 ACD HV1 1441 0 74 0 0 31 0 5 0 1551 ACD HV2 0 1742 0 47 54 0 5 0 24 1873 PDU-P PDU-R 1441 0 74 47 0 0 5 0 0 0 1742 0 0 54 31 0 5 24 1567 1856 4 Feb 8, 2007 GLAST LAT Project Status of NCRs Promoted to QARs NCR Corresponding QAR Description Resolution 880, 881, 902, 948, 949 1196-4894 EPU, SIU Reboots CND, See Reboot Presentation 942 1196-4895 +X, -X LAT blanket replacement and final closeout Close post TV at final closeout 946 1196-4876 ACD FREE board 5 power up CND, No repeat at Observatory 855, 894 1196-4894 LATC verify and dump errors CND, No repeat at Observatory NCRs and Waivers 5 GLAST LAT Project Feb 8, 2007 Significant NCRs/QARs at GD • Issue – NCR 992 - Tracker tower 10 layer 0 readout via left side impaired • Investigation – Problem tracked to a communication problem in the interface between a GTRC and associated GTFE 0 which resulted in readout of stale data • Resolution – GTFE can be read out through an alternate path (to the right instead of to the left) – Register settings modified to read out this layer from the right side • In-orbit impacts – No impact in current condition – If right side readout becomes impaired, would lose 1 layer of 576 – not a significant impact NCRs and Waivers 6 Feb 8, 2007 GLAST LAT Project Documentation Status • • RFAs from previous reviews – See Systems Engineering Web site for dPDR, PDR, and CDR RFA closures • http://wwwglast.slac.stanford.edu/systemengineering/RFAS/RFAS.ht m – PER RFAs all closed – PSR RFAs all closed • Well, almost. Still have thermal report (in signoff) Waivers approved (details follow) NOTE: have 2 to work closure, one is in SC court NCRs and Waivers 7 GLAST LAT Project Feb 8, 2007 LAT Level Verification Status • • Overview – A total of 458 Level 2B and Level 3 reqts were identified for sell-off • 452 reqts at the LAT level • 6 reqts at the Observatory level Current Status – 319 approved by NASA <goal is to make this 409 by PER> – 34 in review cycle <will work with Mark, some will be moved to post build 1> – 50 TV related, just submitted <will work with Mark> – 6 compression related, FQT completed and just submitted <will work with Mark> – 43 GRB related, will close when FSW is completed – 6 to be closed at Observatory test (e.g. shock, 4 TV cycles) NCRs and Waivers 8 Feb 8, 2007 GLAST LAT Project LAT Waivers (1/3) CCR # 433-0311 433-0356 433-0357 433-0358 433-0360 Title Description Status DC Voltage Tolerance LAT is required to tolerate 0-40V DC. Due to MOSFET switches at power feed inputs, LAT can tolerate minimum 15V, excluding transient events. Approved Test Point Short Circuit Isolation LAT is required to operate within spec if any test point is shorted to ground. A shorted external clock select pin would render the redundant GASU inoperable. Approved DC Voltage Tolerance #2 LAT required to tolerate 0-40V DC. After a voltage drop analysis, it was found that the TEM MOSFET switches would receive too low a voltage with the DAQ feed voltage at 15V. To operate the TEM's safely, the input voltage needs to be 18.5V minimum. Approved GTFE TID LAT is required to perform TID testing on all GTFE ASIC lots. The final two lots were not tested since previous lots exhibited such large margins. Approved Tracker Environmental Test With Non-Flt or Missing Cables Several tracker towers went through environmental test with a subset of missing or non-flight flex cables. The replacement flight cables were not subjected to component-level vibe and will not see twelve tvac cycles. Approved NCRs and Waivers 9 Feb 8, 2007 GLAST LAT Project LAT Waivers (2/3) CCR # Title Description Status 24AWG STD Strength Cu High strength Cu alloy is required for 24AWG wire. LAT uses standard strength Cu wire. As reported by the LAT PCB, standard strength 24AWG wire has been used on previous NASA projects with GSFC’s approval with no compromise to product reliability. Approved 433-0362 J-STD vs NASA STD LAT circuit card assemblies uses J-STD-001 as the workmanship standard instead of NASA-STD8739.3. Approved 433-0367 Tracker Flex Cable and MCM Coupon Failures Several flex cables and MCM’s are installed on the LAT although they have failed coupons. Approved Radiator Sine Vibe The radiators will not be installed for LAT-level sine vibe test. Instead, the radiators were subjected to alternative tests, i.e. pull test, tap test, LAT-level acoustic test. Approved EMI Skirt Stay Clear Center EMI skirt pieces near SC-LAT flexures exceed the LAT stay-clear by 0.015” max. Approved VCHP CECM The VCHP feed violates the CECM requirement. The measured value is ~700mVp-p vs the requirement of 200mVp-p. Approved 433-0361 433-0368 433-0369 433-0374 NCRs and Waivers 10 Feb 8, 2007 GLAST LAT Project LAT Waivers (3/3) CCR # Title Description Status 446-0402 Keyed Test Point Connectors Test point connectors are not keyed. Approved 446-0403 Segregate Signal Types on Test Connectors JL-39 contains signals of different signal classes. Approved Cable Shield Termination Floating shields are not properly terminated per NASA-STD- 8739.4. Approved RS103 TKR Noise Occupancy Tracker noise occupancy exceeded its limit of 10-4 during RS 103 (vertical polarization) between 95101MHz. Approved 446-0411 446-0412 NCRs and Waivers 11 Feb 8, 2007 GLAST LAT Project SC-LAT ICD Waivers ICN # -095 -107 -109 Title Description Status LAT Grid Interface Hole Out-of-Tolerance Several grid interface hole locations are out of tolerance. Using the as-built LAT Grid and SC interface hole locations, the analysis shows the predicted forces to align the shear pins are small and a minimum of 0.007” exist between the bolts and holes in the flexures and mating should not be an issue. Approved Recessed Grid Bushings The +Y and –Y LAT grid interface hole bushings are recessed by 0.022” worst case. Stress analysis at the SC mount interface shows the margins of safety for ultimate and yield bearing strength is 7% which is acceptable. The margin of safety for pin bending is >200%. Approved SC Overvoltage Protection for LAT VCHP Feeds The SC does not limit the VCHP voltage to maximum 40V. This is not an issue since the voltage is limited to 55.3 V and the LAT can withstand up to 60V. Approved Waiver for use of inches instead of meters in SC model Approved -112 Thermal Units NCRs and Waivers 12 Feb 8, 2007 GLAST LAT Project SC-LAT ICD Waivers ICN # -115 -120 -124 Title Description Status LAT Radiator FOV Obstruction Two SC snubber brackets and two separation switches are located in front of the LAT radiators. Pending LAT Review LAT Radiator Venting The LAT radiators partially vent through the through cutouts near the Solar Array Launch Lock Struts and the Solar Array Drive Mechanism. The results of the GSFC analysis shows this is acceptable. Approved LAT Inrush Current The inrush current when the DAQ feed is enabled by the SC exceeds the requirement. LAT analysis shows no damage or degradation to LAT components. Pending SC Review NCRs and Waivers 13 Feb 8, 2007 GLAST LAT Project GLAST Large Area Telescope Gamma-ray Large Area Space Telescope Pre-Environmental Review LAT Instrument Performance J. Eric Grove Naval Research Lab LAT Commissioner NCRs and Waivers 14 Feb 8, 2007 GLAST LAT Project Introduction • Continuing to monitor LAT performance via CPT, LPT, and calibrations from Baseline forward through Observatory integration – CPT • Detector subsystems • Copper paths, interfaces – Calibrations • Detector subsystems • Performance baseline successfully established at SLAC prior to shipment – Successfully verified at NRL and GD – Awaiting pre-TV calibration… • Compare with presentation 05 (LAT Test Results) from LAT PSR NCRs and Waivers 15 Feb 8, 2007 GLAST LAT Project ACD Performance • Aliveness No change from LAT PSR – PHA • All channels are alive and calibrated – Veto • All channels are alive and can be set to flight thresholds – Exception: one channel that is not used in flight veto – CNO • All channels are alive and can be set to flight thresholds • Performance notes – None – ACD performance is quite stable, operating within spec NCRs and Waivers 16 Feb 8, 2007 GLAST LAT Project CAL Performance • Aliveness No change from LAT PSR – Spectroscopy • All channels are alive and calibrated – Trigger • All discriminators are alive and can be set to flight thresholds – Data suppression • All discriminators are alive and can be set to flight thresholds • Performance notes – Front-end noise • Four channels (out of 6144) out of family at room temp – No impact to flight performance – No open NCRs on CAL performance – CAL performance is stable, operating within spec NCRs and Waivers 17 Feb 8, 2007 GLAST LAT Project TKR Performance • • Aliveness – Data • Total bad channel count < 0.3%, within spec – TOT • All channels are alive and calibrated – Trigger • Discriminators in all GTFEs are alive and can be set to flight thresholds Performance notes – TKR “noise flares”: old issue, no change since PSR • Transient increase in noise occupancy – Noise occupancy and data volume are within spec – TKR meets science performance requirements. Not an issue. – “Bad strip” trending: no change since PSR • Strips not usable for triggering or tracking – No significant loss of strips since LAT PSR – TKR meets science performance requirements. Not an issue. – TKR tower 10 layer 0 readout via left side impaired: new issue • Layer can still be read out from right side – Loss of redundancy in 1 layer out of 576 – Not an issue for flight performance, no effect on science • NCR 992 is closed – See Hascall presentation NCRs and Waivers 18 Feb 8, 2007 GLAST LAT Project Summary • LAT detector status – Performance baseline successfully established at SLAC • Baseline CPT and Calibration completed and signed off – Post-environmental test performance measured at NRL • Baseline performance confirmed • Pre-ship CPT and Calibration completed and signed off – Post-integration performance measured at GDC4 • Baseline functional performance confirmed • Awaiting pre-TV calibration – Integrated LAT is ready for Observatory environmental test NCRs and Waivers 19 Feb 8, 2007 GLAST LAT Project GLAST Large Area Telescope Gamma-ray Large Area Space Telescope Observatory IRR/PER LAT Flight Software Jana Thayer Stanford Linear Accelerator Center NCRs and Waivers 20 GLAST LAT Project Feb 8, 2007 FSW Configuration Summary • • Currently operating LAT with FSW B0-9-0 – Satisfies 95% of FSW requirements – Includes resolution to watchdog reboots – ~50 hours of run-time including regression testing with this build History of FSW updates since shipment to GD-AIS – 7/06: B0-6-9 • LAT shipped to GD-AIS with this build • Installed prior to LAT environmental test • Fulfills 143/183 FSW requirements – 9/06: B0-6-12 • Included 6 months of bug fixes, JIRAs accumulated during LAT environmental testing • Fulfills 173/183 requirements – 9/06 – 10/06: B0-6-13, B0-6-14, B0-6-15 • Bug fixes, addition of reboot diagnostics – 11/06: B0-7-0, B0-7-1 • Event data compression implemented – 1/07 – 2/07: B0-8-0, B0-8-1, B0-8-2 • RAD750 errata and other reboot related JIRAs addressed – 2/07: B0-9-0 • Event data compression bug fixes implemented NCRs and Waivers 21 Feb 8, 2007 GLAST LAT Project Plan forward • Build plan for B1-0-0 – Build contents: • Support for commands to test LAT-GBM interface • GRB detection algorithm • Fully address 183 of 183 requirements – Target build date: 4/23/07 – Target Delta-FQT-B: 4/30/07 – Upload to LAT: 5/1/07 (>1 month prior to Observatory TVAC) • Support Observatory I&T with critical FSW patches/bug fixes prior to launch as necessary • Onboard FSW updates prior to launch are approved by a program-level CCB NCRs and Waivers 22 Feb 8, 2007 GLAST LAT Project Requirement Validation • B0-9-0: 173/183 requirements verified at FQT on 4/13/06 and delta-FQT A on 8/14/06 • Outstanding requirements – GRB detection algorithm: B1-0-0 • 5.3.10.2.1 GRB Location Accuracy • 5.3.10.2.2 Modification of GRB criteria • 5.3.11.3.3 Process Attitude Data • 5.3.11.6 GRB Alert Message Latency • 5.3.11.7 LAT GRB Repoint Request Message to SC – FSW Standards (verified as part of B1-0-0 after GRB detection algorithm is implemented) • 5.4.1 System of Units (metric system) • 5.4.2.x Coordinate Systems (3 requirements) • 5.4.3 Resource Margin NCRs and Waivers 23 GLAST LAT Project Feb 8, 2007 Impact to environmental test of remaining GRB requirements • GRB detection algorithm only verifiable on FSW Testbed • GRB algorithm not required for TVAC or observatory test – No observatory environmental tests require the presence of GRB detection algorithm • Desirable to implement on LAT prior to TVAC: – GRB detection algorithm for performance baseline – Infrastructure to test remaining LAT-GBM interface requirements NCRs and Waivers 24 Feb 8, 2007 GLAST LAT Project B1-0-0 - Open JIRAs • None of the open issues are liens against PER • Outstanding JIRAs dealing with requirements – FSW-292 Implement GRB detection algorithm • JIRAs dealing with bug fixes, significant improvements to operations – FSW-808 Problem enabling periodic triggers – FSW-305 Summary/statistics telemetry stream needs to be created for on-board event processors – FSW-582 Capture of layer splits in LATC does not consider the FE mode registers NCRs and Waivers 25 Feb 8, 2007 GLAST LAT Project Summary • FSW fulfilling 173/183 requirements used throughout Observatory I&T • Spontaneous reboots addressed by B0-9-0 – Reboot problem had minimal impact on LAT and Observatory testing • Clear plan forward to complete FSW • No LAT FSW liens to observatory environmental test NCRs and Waivers 26 Feb 8, 2007 GLAST LAT Project GLAST Large Area Telescope Gamma-ray Large Area Space Telescope LAT Reset Resolution Team (RRT) March 28 , 2007 Summary Status Erik Andrews NCRs and Waivers 27 Feb 8, 2007 GLAST LAT Project RRT: Background • • • • During LAT Instrument Integration and Test, infrequent but unexplained processor resets were observed. While these were documented in NCRs, analysis determined they were not preventing progress on Instrument Integration and Test. Testing continued in parallel with reset analysis Subsequent to Instrument delivery and checkout at General Dynamics, the Project created a team to focus on, analyze and solve these resets. Goal: Resolve Resets – Four areas of emphasis: • Fishbone analysis to focus effort in specific technical domains • Use/Create Off-line Memory Dump Analysis tools to support investigation • Develop run-time instrumentation of the FSW to improve insight into processing • Review dumped data from existing resets – Set up collaboration website to support task. • Reboot summary and dump data are maintained on the ISOC / FSW Website: – http://confluence.slac.stanford.edu/display/ISOC/FSW • Operational Plan: Evolved process to handle reboots during observatory test – Memory dump procedure defined – FSW on call 24/7 to diagnose reboots – FRB On-call team identified. Process produced good results as used. • Phone #s distributed and available for operators NCRs and Waivers 28 Feb 8, 2007 GLAST LAT Project Root Cause Analysis • The RAD-750 contains a Thermal Assist Unit (TAU) which can be programmed in an interrupt or a polled mode. LAT decided to implement TAU in an interrupt mode. – • • • (Note: GLAST SC does not implement TAU, and consequently this is a non-issue.) The RAD-750 provides a Decrementer Register which provides an interrupt back to the system when the counter expires (reaches 0 and transitions to xffff ffff). Concurrent use of these two interrupts can cause unpredictable results. This has manifested itself in corruption of machine registers (cache configurations, stored PC values), stack pointers, etc. Some of which lead to watchdog timeouts. – BAE has reproduced the error in their lab. Seen on LAT Instrument + Testbed Quoting from the MPC-750 User Manual (but not listed in any errata document): – For both the MPC750 and MPC755, no combination of the thermal assist unit, the decrementer register, and the performance monitor can be used at any one time. If exceptions for any two of these functional blocks are enabled together, multiple exceptions caused by any of these three blocks cause unpredictable results! NCRs and Waivers 29 Feb 8, 2007 GLAST LAT Project Summary Of Resets • Of the 36 total unexpected reboots on the LAT – The root cause of 26 have been determined and fixed (as of 0.8.2) – JIRA 863 • Fundamental root cause related to interrupt conflict on RAD750 • Problem Confirmed by BAE. To be documented as (inherited) erratum very soon – The remaining 10, while suspected that they’re resolved, root cause remains unconfirmed • Many are likely already fixed – Caused by new BAE erratum but unable to definitively confirm due to lack of data and inability to reproduce – FSW has matured since the reboots occurred • For any not already fixed, we’re in a dramatically improved position to determine root cause of any future reboots – Improved diagnostic capabilities in FSW 0.9.0 and beyond – Improved post-reboot processes in place to ensure all relevant data is captured • Plan forward is to gain confidence in solution with extensive run time. – Plan is to run and re-run LAT Functional and CPT tests in preparation for Observatory Testing. – Anticipate 200 – 250 hours of reset-free powered time on the LAT since ‘fix’ NCRs and Waivers 30 Feb 8, 2007 GLAST LAT Project Remaining Open Reboots ID NCR Open/Clo sed Unit Type of reboot LAT Activity Run Time (UTC) Build During primary to secondary transition 77013656 1/8/2007 B0-6-15+ intSeSuite: AcdSuite_AcdLongFunctional.xml 77013266 12/1/2006 13:45 B0-7-0 EPU1 Boottype=4, 0x200 (machine check) Exception Boottype=4, CPU Exception, PPC Vector 0x300 (DSI) LPA: LAT-20xCNONoPer_0.50hr 77012150 10/26/2006 13:33 B0-6-14 Open SIU0 Boottype=0, VxWorks kernel panic LCI: TkrNoiseAndGain_CPT 77011860 10/19/2006 5:16 B0-6-14 13 948-4 Open EPU2 LCI: calu_collect_ci_calibGen_103 77011727 10/17/2006 16:35 B0-6-13 11 902-3 Open EPU2 During LatReinit 77010681 9/27/2006 B0-6-12 10 902-2 Open EPU2 Boottype=0, VxWorks kernel panic Boottype=4, CPU exception, PPC Vector 0x300 (DSI) Boottype=4, CPU exception, PPC Vector 0x300 (DSI) During LatPowerOnTurbo 77010653 9/27/2006 B0-6-12 8 948-2 Open EPU2 Boottype=2, Checkstop, EMC Vector 5 LAT-22x_0.50hr muon run 77009297 8/29/2006 6:09 B0-6-9 5 902-1 Open EPU0 Boottype=4, CPU exception, PPC Vector 0x300 (DSI) Boottype=0, 77004380 5/7/2006 2:15:53 PST B0-6-8 2 880 Open SIU0 4/10/2006 15:40 B0-6-6 30 902-4 Open EPU0 26 949-4 Open SIU0 18 948-8 Open 14 949-3 Boottype=4, 0x300, exception During LatReinit, concurrent with main feed on command VxWorks reboot NCRs and Waivers TkrTotGain_SVC_500hz 31 Feb 8, 2007 GLAST LAT Project Plan for Observatory Test • Testing based on LAT CPT – Core set of tests run across environments – Includes calibration and other tests that are run only at initial and final ambient CPT • Two orbit test – Demonstrates concurrent SC, GBM and LAT operations for 2 orbits during each execution of the CPT • CPT and LPT definitions follow • Day in the life – Full up operational scenario NCRs and Waivers 32 Feb 8, 2007 GLAST LAT Project Observatory Level LAT CPT • A LAT CPT performs the following test cases across the 9 redundancy configurations and across environments Test Case Description L-OBS-00x LAT Power On L-OBS-00x LAT Power Off L-OBS-10x L-OBS-02x L-OBS-06x L-OBS-13x L-OBS-22x L-OBS-301 L-OBS-401 L-OBS-501 L-OBS-312 L-OBS-412 L-OBS-512 LAT Load Shed LAT Reinitialization SIU/EPU Hardware Functional LAT/Spacecraft Interface Test LAT Science Operations Demo LAT ACD CPT LAT CAL CPT LAT TKR CPT LAT ACD LPT LAT CAL LPT LAT TKR LPT Configs 1-9 6-91 1-91 1-4,6 1-2 1,2,4,5 1-6 1 1 1 2 2 2 1. LAT Power Off will be run only post FSW B1.0 delivery. • Tests in addition to the CPT are also run as required or at initial/final ambient test – For example, L-OBS-04x LAT FSW Upload and L-OBS-90x FSW File System Verification NCRs and Waivers 33 Feb 8, 2007 GLAST LAT Project Observatory Level LAT LPT • A LAT LPT performs the following test cases in redundancy configurations 1 & 2 Test Case L-OBS-00x L-OBS-10x L-OBS-13x L-OBS-22x L-OBS-31x L-OBS-41x L-OBS-51x NCRs and Waivers Description LAT Power On LAT Load Shed LAT/Spacecraft Interface Test LAT Science Operations Demo LAT ACD LPT LAT CAL LPT LAT TKR LPT Configs 1-2 1-2 1-2 1-2 1-2 1-2 1-2 34 Feb 8, 2007 GLAST LAT Project Conclusion • • • LAT subsystem level test program successfully completed No liens open which preclude entrance to environmental test LAT is ready for Observatory Environmental test NCRs and Waivers 35 Feb 8, 2007 GLAST LAT Project Backup Charts NCRs and Waivers 36 GLAST LAT Project Feb 8, 2007 LAT Performance Backup slides NCRs and Waivers 37 GLAST LAT Project Feb 8, 2007 TKR Performance: Noise Flares • • • • Issue – 8 (of 612) layers in 17 Trackers have shown infrequent, sporadic flares of increased noise occupancy. The 8 layers are uncorrelated. – The flares are correlated across channels in a given ladder, with many or all channels in the ladder firing at once. – There is no evidence that the problem was statistically worse in T/V than in atmosphere, but we cannot rule out a small effect. Analysis – Monitor in cosmic-ray data in FM-8 and in 16 towers. – The affected regions are fully ON and sensitive immediately before and after a flare. This ruled out intermittent bias connections as a cause. – Even during flares, all recent runs still satisfy all noise specifications. – Study in FM-8 versus HV level and humidity: – Unfortunately, we could not get the problem to recur at all in FM-8, so we did not reach any conclusion. – Test at lower bias voltage (80 volts instead of 100 volts) still showed flares – Data taken during TV indicates no significant change under vacuum Resolution Plan – Continue to monitor the effects in 16-tower cosmic-ray data, especially in TV testing. Impacts on On-orbit performance – The observed noise is very far from a level that would have any impact at all on performance. An increase by much more than an order of magnitude, including spreading to other trays, would have to occur to begin to see impacts. (Overall, the TKR noise performance is phenomenally good!) NCRs and Waivers 38 GLAST LAT Project Feb 8, 2007 TKR Performance: Noise Flares • TKR “noise flares” – Transient increase in noise occupancy • Duration is minutes to hours • Little or no dependence on – Time (i.e. no increase in rate of occurrence) – Temperature – Bias voltage – LAT-average noise occupancy • Mean = 1.3×10-6 over JuneJuly muon runs – Including flaring episodes – Mean drops to ~5×10-7 when flaring is excluded • Worst 90-minute period = 1.5×10-5 Note: LAT occ = Layer occ / 576 NCRs and Waivers 39 Feb 8, 2007 GLAST LAT Project TKR Performance: Bad Strips • Three major categories: – Hot strips: unusually high occupancy • Historically anything >10-4 occupancy, but strips well above this level can still be useful and should not be masked unnecessarily! • Small numbers, with no trending issues. – Dead strips: do not respond to internal charge injection • Either a dead amplifier or a broken SSD strip connected to the amplifier (usually the latter). • Very small numbers, with no trending issues. – Disconnected strips: broken wire bond or trace between… • (a) ladder and amplifier, mostly due to MCM encapsulation debonding from silicone contamination, • or (b) SSDs within a ladder, due to Nusil encapsulation debonding in thermal cycles. • The majority of the bad strips are in early towers, and the delamination definitely propagates somewhat with time. – Can reattach/detach with temperature change NCRs and Waivers 40 Feb 8, 2007 GLAST LAT Project TKR Trending Disconnected Channel Trend 20 0 -20 • Bad channel trend – Trend is essentially flat – Total number of bad channels after LAT env test = 3400 Total number of TKR chans ~ 900,000 – Total number of bad channels is within spec • <0.3% of channels NCRs and Waivers ho t2 34 co ld Po 234 st -T VA C ld 1 co ns tra ho t1 -60 Test phase • Old figure to be updated -40 Pr line eTV AC 10 40 Ba se Old figure to be updated 60 r FS W 100 80 16 Tw 1000 ha nd -o f 16 f -T w r FS Ba W se Pr line eTV AC ho t1 tra ns co ld 1 ho t2 3 co 4 ld Po 23 4 st -T VA C Total number of bad channels 10000 Disc. channel increase from hand-off Bad Channel Trend TkrFMA TkrFMB TkrFM1 TkrFM2 TkrFM3 TkrFM5 TkrFM4 TkrFM6 TkrFM7 TkrFM9 TkrFM10 TkrFM11 TkrFM12 TkrFM13 TkrFM14 TkrFM15 Test phase • Bad channel trend – Total increment since LAT completion • +XX disconnected strips – Small increase in bad count during environmental test • <XX% increase 41 Feb 8, 2007 GLAST LAT Project TKR Bad Strips – Summary • • • The problem of encapsulation delamination has been well known and discussed for a long time, including the increase during Tracker TVAC testing, but the project elected to use the affected MCMs as-is because of 1. the adverse schedule and cost impact of redoing 1/3 of the MCM production 2. and the belief that future degradation would never reach a level at which the science would be compromised. Nothing is different today: – There is some evidence that the problem areas have expanded very slightly during LAT integration, but • It is impossible to be sure at any time what channels are really disconnected, because the wires in delamination regions often make electrical contact even when the mechanical bond is gone. Many channels of the channels that appeared to be new disconnects during LAT environmental test were observed to be disconnected during TKR TVAC testing. • No disconnected channels have appeared in previously unaffected regions of MCMs. We expected that the problem regions would expand during LAT environmental testing at a level comparable to Subsystem environmental testing. – Indeed this is what was observed – Degradation is insignificant with respect to science performance • LAT environmental test caused bad channel count to change from 0.3% to 0.3% • Expect Observatory environmental test to cause count to change from 0.3% to 0.4% or less NCRs and Waivers 42 Feb 8, 2007 GLAST LAT Project GLAST Large Area Telescope Gamma-ray Large Area Space Telescope LAT FSW Backup Stanford Linear Accelerator Center NCRs and Waivers 43 Feb 8, 2007 GLAST LAT Project B2-0-0 (post-launch) • Address FSW changes based on lessons learned in testing – FSW-562 Make sure that PIG's power sequence is still correct – FSW-287 Anti-flooding for MSG – FSW-271 Logical/physical descriptions – FSW-414 Add internal resources to PIG and eliminate the LEM_micr argument present in most function prototypes/ – FSW-419 If LSEC cannot encode an event, nothing is placed into the datagram. – FSW-280 CAL and ACD bias voltage settings – FSW-538 There is no way to ignore the AEM when the LATC_verify operation is performed. – FSW-791 High and low splits are not separately ignorable NCRs and Waivers 44 Feb 8, 2007 GLAST LAT Project Deferred • Summary – – – – – – – – – – – – – FSW-824 CLONE -Disable memory controller Maximum Bank Active Timeout (would require change to PBC) FSW-832 CLONE -Need unique access to all cache lines of LCB I/O buffers during hardware operation (would require change to PBC) FSW-875 IVV TIM 1635 - LAT FSW Boot Code (PBC): Duplication of APID definitions in header & source code files may lead to execution errors FSW-626 LATC dumps have unexpected GTFE masks on LATC verify error dumps only FSW-239 vxw_flight RTOS consitutent still has the serial console device enabled FSW-540 Addition of AEM/EBM memory relocation register control FSW-697 Set the range for all padded fields to 0-0 FSW-474 Sharpen the definition of the extended counters so that completely accurate bookkeeping can be done even when there are dropped datagrams FSW-689 Split LFSFILEID into device, directory, and file name FSW-724 QSEC does not update the event-time fields in the standard context correctly FSW-526 NCR 794, problem 6: Add debugging code to LCBD code to trace intermittent failure FSW-636 NCR 882: CPU should apply a reset to the LCB after it powers the GASU and before it checks the LCB for data presence FSW-753 ACD calibration PHA threshold is not being iterated NCRs and Waivers 45 Feb 8, 2007 GLAST LAT Project Unscheduled • Unscheduled JIRAs (jbt – JIRA to be updated, most can be scheduled) – FSW-790 Tracker calibration doesn't work correctly with uneven splits – schedule it for B2-0-0 – FSW-729 LATC verify error response – schedule it for B2-0-0 – FSW-703 Ensure all registers are set - survey – FSW-763 EFC IVV code issues - determine whether action is necessary – FSW-699 Create report to identify configuration files in use - survey – FSW-872 Illegal memory reference in LCBD after request list fetch error – schedule for B2-0-0 – FSW-876 Include LATC ignore file used as part of the run configuration data – schedule it (B1-0-0) – FSW-878 CLONE -After integration with the space craft, time tones do not seem to be properly updated (B1-0-0) – FSW-799 Decide on desired level of command execution verification, ability to determine commanded configuration changes – FSW-838 PPC compiler is treating a char as an unsigned quantity rather than a signed - survey NCRs and Waivers 46 Feb 8, 2007 GLAST LAT Project RRT Backup Charts NCRs and Waivers 47 Feb 8, 2007 GLAST LAT Project #2 NCR-880 • • • • • • • Type: 0, VxWorks reboot Date/Time: 4/10/2006 3:40:00 PM Unit: SIU-R (SIU0) FSW Build: B0-6-6 Activity: TkrTotGain_SVC_500hz (~20s after script start) Analysis – Either some application called the reboot() or sysToMonitor() functions (not likely at all), or the VxWorks kernel issued a panic exception. This is usually the caused by a "work queue overflow" in the kernel, which can mean an overflow of timer expirations or interrupts. – For these reboot types, the kernel should leave a short text string at address 0x0000fd00. It usually contains a very short, not very descriptive message such as "Kernel panic: work queue overflow". Unfortunately, this was not looked at after the reboot. Current status – Not enough evidence to determine if caused by new RAD750 erratum – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 48 Feb 8, 2007 GLAST LAT Project #5 NCR-902-1 • • • • • • • Type: 4, CPU exception, PPC Vector 0x300 (DSI) Date/Time: 5/7/2006 9:15:53 PM Unit: EPU0 FSW Build: B0-6-8 Activity: During LatReinit, concurrent with main feed on command Analysis – Exception was generated at the application level, either while the RTOS was initializing, while the SBC was running, or after the applications had been initialized and running. – DSI exception occurs when no higher priority exception exists and a data memory access cannot be performed. DSISR register indicates: • Exception was caused by the data address being out of bounds for our MMU setup (CPU DBAT registers). • Exception occurred on a load access – DAR register indicates data address which was issued to cause the exception is out of range for the memory mapping we have implemented – Address related to error = 0xffffffc3 – SSR0 register indicates the instruction which generated the exception was a "lwz" instruction near the end of the kernel function "taskUnlock()". – As with #10, #11, and #30, DSI exception addresses for #5 and #18 are 0x365c6c, but the memory addresses are small negative values rather than the prepainted stack contents value of 0xeeeeeeee Current status – Not enough evidence to determine if caused by new RAD750 erratum – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 49 Feb 8, 2007 GLAST LAT Project #8 NCR-948-2 • • • • • • • Type: 2, Checkstop, EMC Vector 5 Date/Time: 8/29/2006 6:09:00 AM Unit: EPU2 FSW Build: B0-6-9 Activity: LAT-22x_0.50hr muon run (77009297) Analysis – Boot tlm seen about 25 seconds after series of commands to reset LRS counters. LatReinit after reboot resulted in single bit error tlm, possibly not related to watchdog timer induced reboot Current status – Need to verify that CPU is in fact configured to take the Checkstop option rather than the Machine Check Exception option. – Need to make decision on the idea of catching these errors at the software level. All of these critical errors can be masked off from generating EMC Vector or Checkstop exceptions. In the cases where the error is masked, it will be reported instead as a CPU interrupt or exception, resulting in the execution of a software error handler. The advantages are the abilities to provide a more detailed report and to be reconfigurable. This must be weighed against the likelihood that the error is in fact critical, and an attempt to execute software further would fail. – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 50 Feb 8, 2007 GLAST LAT Project #10 NCR-902-2 • • • • • • • Type: 4, CPU exception, PPC Vector 0x300 (DSI) Date/Time: 9/27/2006 5:52:58 PM Unit: EPU2 FSW Build: B0-6-12 Activity: During LatPowerOnTurbo (77010653) Analysis – EPU2 took the exception during the transition from primary to secondary boot. Consequently, the LSW trace had not started yet and does not contain any useful information. – #10, #11, and #30 all take a DSI exception at address 0x365c6c in VxWorks routine taskUnlock() while attempting to access memory at address 0xeeeeeeee during startup – #10, #11, and #30 show a saved link register (lr) value in “application 0” word of the PBC telemetry of 0x360d70 in VxWorks routine reschedule() – #10, #11, and #30 differ only in the task control block address for the active task and the saved stack addresses in the “application 1” and “application 2” words. These are identical in #10 and #11 but different in #30, probably corresponding to the fact that the first two crashes occurred while running B0-6-12 while the last one was B0-6-15+. Both of these builds employ the same V6-11-2 version of VxWorks, and thus have no change in the addresses of the VxWorks routines. Current status – Not enough evidence to determine if caused by new RAD750 erratum – Potentially eliminated with changes in the startup ordering in B0-8-0 – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 51 Feb 8, 2007 GLAST LAT Project #11 NCR-902-3 • • • • • • • Type: 4, CPU exception, PPC Vector 0x300 (DSI) Date/Time: 9/27/2006 11:35:00 PM Unit: EPU2 Activity: During LatReinit (77010681) FSW Build: B0-6-12 Analysis – EPU2 took the exception during the transition from primary to secondary boot. Consequently, the LSW trace had not started yet and does not contain any useful information. – Code tried to access invalid address in the RTOS portion of RAM, in the taskUnlock() function within the V6-11-2 vxw_flight image – #10, #11, and #30 all take a DSI exception at address 0x365c6c in VxWorks routine taskUnlock() while attempting to access memory at address 0xeeeeeeee during startup – #10, #11, and #30 show a saved link register (lr) value in “application 0” word of the PBC telemetry of 0x360d70 in VxWorks routine reschedule() – #10, #11, and #30 differ only in the task control block address for the active task and the saved stack addresses in the “application 1” and “application 2” words. These are identical in #10 and #11 but different in #30, probably corresponding to the fact that the first two crashes occurred while running B0-6-12 while the last one was B0-6-15+. Both of these builds employ the same V6-11-2 version of VxWorks, and thus have no change in the addresses of the VxWorks routines. Current status – Not enough evidence to determine if caused by new RAD750 erratum – Potentially eliminated with changes in the startup ordering in B0-8-0 – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur including • dump about 2K bytes starting about 256 bytes below the stack pointer value (assuming the 2K bytes would not attempt to read past the end of physical memory) NCRs and Waivers 52 Feb 8, 2007 GLAST LAT Project #13 NCR-948-4 • • • • • • Type: 0, VxWorks kernel panic Date/Time: 10/17/2006 4:35:34 PM Unit: EPU2 FSW Build: B0-6-14 (or 6-13 per jana?) Activity: LCI: calu_collect_ci_calibGen_103 (77011727) Analysis – Not a lost decrementer since no 520s dropout in housekeeping • Current status – Not enough evidence to determine if caused by new RAD750 erratum – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 53 Feb 8, 2007 GLAST LAT Project #14 NCR-949-3 • • • • • • Type: 0, VxWorks kernel panic Date/Time: 10/19/2006 5:16:08 AM Unit: SIU-R (SIU0) FSW Build: B0-6-14 Activity: LCI: TkrNoiseAndGain_CPT (77011860) Analysis – SIU was emitting normal SIU statistics housekeeping packets until about 4 seconds before boot telemetry was observed • Current status – Not enough evidence to determine if caused by new RAD750 erratum – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 54 Feb 8, 2007 GLAST LAT Project #18 NCR-948-8 • • • • • • • Type: 4, CPU Exception, PPC Vector 0x300 (DSI) Date/Time: 10/26/06 13:33 Unit: EPU1 FSW Build: B0-6-14 Activity: LPA: LAT-20xCNONoPer_0.50hr (77012150) Analysis – SRR0: 0x00365c6c Instruction that caused problem – SRR1: 0x0000b030 Assorted bits copied from MSR register – DAR: 0xffffffff Address the CPU was trying to access – DSISR: 0x40000000 Basically, memory access error – PCI Status 2 Reg: 0x02000000 – Mem Status Reg: 0x00000004 – Task ID: 0x07fef864 dLCBDevt – Application 0: 0x00a3ec08 Link register (calling routine) – Application 1: 0x07fef580 Stack pointer – Application 2: 0x07fef4c0 Exception pointer – Application 3: 0x00000000 (and so on to until application 7) – Consistent with a pointer walking backwards through memory – As with #10, #11, and #30, DSI exception addresses for #5 and #18 are 0x365c6c, but the memory addresses are small negative values rather than the prepainted stack contents value of 0xeeeeeeee Current status – Not enough evidence to determine if caused by new RAD750 erratum – Investigation at dead end – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 55 Feb 8, 2007 GLAST LAT Project #26 NCR-949-4 • • • • • • • Type: 4, Exception, 0x200 (not DSI) Date/Time: 2006-12-01 13:45:42 Unit: SIU0 FSW Build: B0-7-0 Activity: intSeSuite: AcdSuite_AcdLongFunctional.xml (77013266) Analysis – Received a bad pointer, wrote a word where it shouldn’t have, and bad things happened – The register is out on the PCI, which means that the value is byteswapped. The rogue value that’s written has zeroes in most and least significant bytes, so you can’t tell which direction to read the number from, left or right. Current status – Tracked via FSW-872, on agenda for next FSW CCB – Not enough evidence to determine if caused by new RAD750 erratum – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 56 Feb 8, 2007 GLAST LAT Project #30 NCR-902-4 • • • • • • • Type: 4, Exception, 0x300 (DSI) Date/Time: 2007-01-08 Unit: EPU0 FSW Build: B0-6-15+ Activity: During primary to secondary transition (77013656) Analysis – The task dLCBDevt took the exception while trying to access memory at 0xeeeeeeee – #10, #11, and #30 all take a DSI exception at address 0x365c6c in VxWorks routine taskUnlock() while attempting to access memory at address 0xeeeeeeee during startup – #10, #11, and #30 show a saved link register (lr) value in “application 0” word of the PBC telemetry of 0x360d70 in VxWorks routine reschedule() – #10, #11, and #30 differ only in the task control block address for the active task and the saved stack addresses in the “application 1” and “application 2” words. These are identical in #10 and #11 but different in #30, probably corresponding to the fact that the first two crashes occurred while running B0-6-12 while the last one was B0-6-15+. Both of these builds employ the same V6-11-2 version of VxWorks, and thus have no change in the addresses of the VxWorks routines. – Current suspicion is that the problem is related to a race condition when the first forwarded magic 7 packet arrives at the EPU before startup is completed Current status – Analyzing stack dump for the dLCBDevt task – Potentially eliminated with changes in the startup ordering in B0-8-0 – Procedures/Tools in place to gather additional data should this type of reboot recur NCRs and Waivers 57 Feb 8, 2007 GLAST LAT Project Abbreviated Fishbone (1/2) Cause Discussion/Rationale 1. Hardware failure induces reboot Identical pre-existing, intermittent or environmentally induced failure of isolated part or board in 5 independent processors is not a credible cause for reboots. Recommendation per F. Huegel. Not Credible 2. Software induced reboot Code has been designed to avoid this issue. Desk checking and static analysis tools affirm design. Very Unlikely Code analysis performed to eliminate potential memory overwrite errors, but see 2.2.1 Very Unlikely Potential for overwrite documented in FSW-823, FSW-831. Static code analysis tools utilized by IVV to check for unprotected memory writes. Issues found in JIRAs 834, 835 and resolved. Very Unlikely. 2.1. Operating system flaw 2.1.1. Priority inversion 2.1.2.OS does not provide memory protection 2.2. Status Application software bug 2.2.1. 2.2.1.1. Memory overwrite Generic overwrite 2.2.2. Interrupt locks Code has been designed to avoid this issue. Instrumentation implemented in 0.7.1 and 0.8.0 affirm design. Very Unlikely 2.2.3. Task exception Task exceptions have occurred. Three of the resets trace to task exceptions. However, could not cause watchdog timeouts, since the CPU handles the exception first (and resets). Task exceptions are handled in the exception vector. System designed to collect information on the task that attempted to execute illegally. This data is captured preserved. These resets, when they occur are captured and provide good insight into what's happened. Possible Where race conditions are a potential, system designed to sequence events thru use of semaphores. Instrumentation in 0.8.0 affirm implementation. Unlikely 2.2.4.Race Conditions NCRs and Waivers 58 Feb 8, 2007 GLAST LAT Project Abbreviated Fishbone (2/2) Cause Discussion/Rationale 3. Operations/environment Not a credible cause – environmental testing was successfully completed with no change to reboot rate during any environment. Recommendation per F. Huegel. 4. LAT FSW interacts with computer firmware/OS feature 4.1. Features documented in vendor errata sheets Status Not Credible General note: examined errata from vendor, including newly disclosed features. 4.1.1. Errata 15 LAT was susceptible, documented in FSW-820, FSW-821. BAE Recommended work-around implemented in Build 0.8.x, so now eliminated. Not Credible 4.1.2. Errata 24 LAT was susceptible, documented in FSW-822, FSW-824. BAE Recommended work-around implemented in Build 0.8.x, so now eliminated. Not Credible 4.2. 5. Undocumented and previously unknown errata In designing LAT LCB, believe we ran across undocumented errata on the BAE bridge. Believe that it is possible here as well. (This turns out to the be case, confirmed by BAE.) Possible EPU/SIU hardware design flaw 5.1. LCB FPGA error 5.1.1. LCB incorrectly writes memory NCRs and Waivers Writes to random areas in memory could cause an exception reboot, but very unlikely to cause a watchdog timer reboot since corrupted memory would be more likely to cause computation errors or exceptions rather than causing a process to hang. Very Unlikely 59 GLAST LAT Project Feb 8, 2007 Reset Analysis-related FSW changes • • Process: – All RRT recommended changes to FSW are being tracked in the JIRA system • This means Project-level approval for each/all JIRAs identified – BAE Undocumented RAD750 Errata • Identified conflict between decrementer interrupt and TAU interrupt (#xxx) – BAE Documented RAD750 board (Bridge) Errata Related • Erratum #15: Simultaneous Snoop with CPU Read Hang ( #820, #821, #823, #826 ) • Erratum #24: Memory Controller Max Bank Active Timeout Hang (JIRA #822, #824*, #832*) – [* = Clones in SIU/EPU boot code. Deferred.] – Desk Checking key sections of the code • Potential LRA command/response lists processing conflict with Erratum #15 (# 826 ) • Identified & recommended changes to package EDS (#831) – Augment LSW log entries • Correcting identified LSW flaws (#812, #813) • Add Stack Pointer and Watchdog timer values on each context switch (#829) • Add entry/exit from ISRs (#829) – SIU task exceptions during power-down (#833) • LCB getting corrupted data from the GASU when it powers down. Fix is approved for next build. – Unprotected/unchecked memory accesses (Identified by IVV tools) • JIRAs: #834, #835; #837 (in 0.9.0) NCRs and Waivers 60 – Diagnostic: Cache configuration configurable at boot time.