PART C Tender Submission Documents District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 1 of 35 PART C - FORM OF TENDER City of Surrey (the “Owner”) Contract Name: District Energy System Phase 2a: DPS, ETS and CBP Service Connections Reference No.: 1220-020-2015-001 TO OWNER: 1. WE, THE UNDERSIGNED: 1.1 have received and carefully reviewed all of the Tender Documents, including without limitation the Instructions to Tenderers, the Form of Tender, the Contract Documents, the Specifications and Drawings, City of Surrey’s Supplementary General Conditions, and the following Addenda: (Addenda, if any) 2. 3. 1.2 have full knowledge of the Place of the Work, and the Work required; and 1.3 have complied with the Instructions to Tenderers; and ACCORDINGLY WE HEREBY OFFER: 2.1 to perform and complete all the Work and to provide all the labour, equipment and material all as set out in the Tender Documents, in strict compliance with the Tender Documents; and 2.2 to achieve Substantial Performance of the Work on or before within ____________________________; and (work duration or date) 2.3 to do the Work for the price, which is the sum of the products of the actual quantities incorporated into the Work and the appropriate unit prices listed in Appendix 1, Schedule of Prices, plus any lump sums or specific prices and adjustment amounts as provided by the Contract Documents. For the purposes Tender comparison, our offer is to perform and complete the Work for the “Tender Price” as set out on Appendix 1 of this Form of Tender. Our Tender Price is based on the estimated quantities listed in the Schedule of Prices, and includes GST. WE CONFIRM: 3.1 that we understand and agree that the quantities as listed in the Schedule of Prices are estimated, and that the actual quantities may vary. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 2 of 35 PART C - FORM OF TENDER 4. WE CONFIRM: 4.1 that the following Appendices are attached to and form a part of this tender: 4.1.1 Appendix 1 – Schedule of Prices Appendix 2 – Preliminary Construction Schedule Appendix 3 – Key Personnel Appendix 4 – Tenderer’s Experience in Similar Work Appendix 5 – Subcontractors and Suppliers Appendix 6 – Bid Bond (*Please note, Schedules 1 through 3 (Incl.) of Part C – FORM OF TENDER are included for information purposes only and are not to be included with your Tender submission.) 5. WE AGREE: 5.1 that in consideration of $1, other good and valuable consideration paid by the Owner (the receipt of sufficiency of which is hereby acknowledged) we agree that this tender will be irrevocable and open for acceptance by the Owner for a period of 60 calendar days from the day following the Tender Closing Date and Tender Closing Time, even if the tender of another tenderer is accepted by the Owner. If within this period the Owner delivers a written notice (“Notice of Award”) by which the Owner accepts our tender, we will: 5.1.1 within 15 Working Days of receipt of the written Notice of Award deliver to the Owner: (a) a performance bond and a labour and material payment bond, each in the amount of 50% of the Contract Price, issued by a surety licensed to carry on the business of suretyship in the province of British Columbia, and in a form acceptable to the Owner; (b) a detailed Construction Schedule consistent with the preliminary construction schedule included in this Tender, which indicates the timing of the major activities of the Work and provides sufficient detail of the critical events and their inter-relationship to demonstrate the Work will be performed by the completion date stated in this Tender; (c) a detailed traffic management plan addressing vehicular and pedestrian movement, safety and access with specific detailing on methods, building and maintenance of temporary structures, signage and materials used to maintain the Place of the Work operations and access to staff and public users of the Place of the Work site; (d) a detailed Place of the Work site - specific safety and health plan addressing as a high-level overview the health and safety issues including, but not limited to hazards, mitigation measures, site District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 3 of 35 PART C - FORM OF TENDER orientations, safety meetings, first aid attendant requirements, and training requirements and record keeping; (e) a “clearance letter” indicating that the Tenderer is in WCB compliance; (f) a copy of a completed and signed certificate of insurance (in the form attached as a schedule to this Form of Tender) as specified in SGC11.6.1 indicating that all such insurance coverage is in place; (g) a valid City of Surrey Business License; and (h) copy the Owner on the “Notice of Project” as and when required under section 20.2 of the Occupational Health & Safety Regulation (BC Regulation 296/97). 6. 5.1.2 within 2 Days of receipt of written Notice to Proceed, or such longer time as may be otherwise specified in the Notice to Proceed, commence the Work; and 5.1.3 sign the Contract Documents. WE AGREE: 6.1 that, if we receive written Notice of Award of this Contract and, contrary to paragraph 5 of this Form of Tender, we: 6.1.1 fail or refuse to deliver the documents as specified by paragraph 5.1.1 of this Form of Tender; or 6.1.2 fail or refuse to commence the Work as required by the Notice to Proceed, then such failure or refusal will be deemed to be a refusal by us to enter into the Contract and the Owner may, on written notice to us, award the Contract to another party. We further agree that, as full compensation on account of damages suffered by the Owner because of such failure or refusal, the Bid Security shall be forfeited to the Owner, in an amount equal to the lesser of: 7. 6.1.3 the face value of the Bid Security; and 6.1.4 the amount by which our Tender Price is less than the amount for which the Owner contracts with another party to perform the Work. Our Address is as follows: District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 4 of 35 PART C - FORM OF TENDER Phone: ____ ______ - ________ Fax: ____ ______ - ________ E-mail: _____________________ Attention: This Tender is executed this ________ day of _________________, 201_. Contractor: (Full Legal Name of Corporation, Partnership or Individual) (Authorized Signatory and Corporate Seal) (Authorized Signatory) District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 5 of 35 PART C - FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Contract Name: District Energy System Phase 2a: DPS, ETS and CBP Service Connections Reference No.: 1220-020-2015-001 From Tenderer: _______________________________________________________ Company name The Tender Price to complete all of the Work is apportioned in accordance with the following table. The prices shown in each of the numbered rows of the table shall include (i) all labour, material and other costs, (ii) overhead and profit, (iii) PST, and (iv) all other taxes, duties, assessments, charges and fees, except for GST. GST shall be shown separately on the row provided therefor. Note: Prices must be PST-inclusive. Only GST is to be shown as a separate line item. Table A: Schedule of Prices Item Description of Work Unit Est. Qty. 1. GENERAL 1.1 Bonding and Insurance L.S. - 1.2 Mobilization/Demobilization L.S. - 1.3 Traffic & Pedestrian Management Survey O&M Manuals and Record Drawings L.S. - L.S. - 1.4 Unit Price Amount Subtotal Items 1.1 to 1.4 2. SITE WORK 2.1 Site Preparation Trenching, Bedding & Import Backfill (1.2 - 1.8 m Depth) lin.m 335 a) 75 mm dia Piping lin.m 0 b) 100 mm dia Piping lin.m 0 c) 150 mm dia Piping lin.m 6 d) 300 mm dia Piping Trenching, Bedding & Import Backfill (1.8 - 2.4 m Depth) lin.m 303 a) 75 mm dia Piping lin.m 5 b) 100 mm dia Piping lin.m 0 c) 150 mm dia Piping lin.m 16 d) 300 mm dia Piping lin.m 5 a) Concrete Sidewalk / Pavement lin.m 4 b) Asphalt Road Repair lin.m 319 c) Concrete Curb and Gutter lin.m 0 2.2 2.3 2.4 Site Restoration District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 6 of 35 PART C - FORM OF TENDER d) Soft Surface Landscape lin.m 13 2.5 D.E.S. Manhole ea 2 2.6 Utilities Crossing ea 0 2.7 Watermain Replacement ea 0 2.8 Air Release Valve Assembly ea 2 2.9 100 mm dia. Sanitary Sewer L.S. - 2.10 25 mm dia. Water Service L.S. - 2.11 CBP Concrete Pad (Optional) L.S. - 2.12 Electrical duct bank L.S. - 2.13 Fencing & Gates L.S. - 2.14 Logstor Material Handling L.S. - a) DWG C02-C-101 L.S. - b) DWG C02-C-102 L.S. - L.S. - 15.2 c) DWG C02-C-103 Connections to Containerized Boiler Plant L.S. - 15.3 Testing & Commissioning of DES L.S. - 15.4 Leak Detection L.S. - 15.5 Pre-stressing L.S. - 15.6 ETS Work a) DWG C02-P-03 L.S. - b) DWG C02-P-04 Subtotal Items 15.1 to 15.6 Inclusive L.S. - Subtotal Items 2.1 to 2.14 Inclusive 15. MECHANICAL 15.1 D.E.S. Piping and Valve System 16. ELECTRICAL & CONTROLS 16.1 Concord Phase 1 Building L.S. - 16.2 L.S. - 16.3 Concord Phase 2 Building Connection to Central Control Station L.S. - 17. INDETERMINATE ITEMS 17.1 Trench Over Excavation Removal of Existing Abandoned Utilities m3 50 lin.m 20 Additional Mass Concrete m3 5 Removal of Buried Concrete Supply, Placement and Compaction of Additional Fill Material as Requested by the Engineer m3 5 tonne 50 Controlled Density Fill m3 10 Trench Rock Removal m3 5 17.2 17.3 17.4 17.5 17.6 17.7 District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 7 of 35 PART C - FORM OF TENDER 17.8 Dritherm m3 5 17.9 Tree and Root Mass Removal Subtotal Items 17.1 to 17.9 Inclusive ea 3 18. CASH ALLOWANCE 18.1 Supply of pre-insulated pipes L.S. L.S. - $450,000 18.2 Unknown Utilities L.S. L.S. - $50,000 Subtotal Items 1 to 18 Inclusive GST @ 5% TOTAL TENDER PRICE District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 8 of 35 FORM OF TENDER 1.1 Description of Payment Items .1 Work set out in the Schedule of Quantities and Prices shall include, but not be limited by, the following brief descriptions: PART 1 - GENERAL 1.1 Bonding and Insurance This item shall include all costs for bonding and insurance for the complete Contract. Payment will be made at the lump sum price tendered in the Schedule of Quantities and Prices on the first progress payment subsequent to submission of documentation of Bonding and Insurance coverage. The lump sum tender under this item shall not exceed 1% of the total tender price. 1.2 Mobilization and Demobilization This item shall include all costs for mobilization and demobilization associated with the Contractor's equipment, site facilities, and services including temporary access road for the work. Payment for mobilization and demobilization will be made at the lump sum price shown in the Tender Form. Fifty percent (50%) of the lump sum price will be paid on the first progress payment certificate due after the Contractor has established the operation and facilities specified, and received the Owner’s approval of the construction schedule. The remaining 50% will be paid upon completion of the contract, removal of equipment, and cleanup and site restoration of the work areas to the satisfaction of the Engineer. The lump sum bid under this item shall not exceed 3% of the total tender. 1.3 Traffic & Pedestrian Management This item shall include all cost to prepare a Traffic and Pedestrian Management Plan that covers the length of the Place of the Work. The Plan must be approved by the City prior to commencement of the Work. Cost should account for possible Plan revisions as requested by the City prior to final approval. This item also includes all costs for labour and equipment to implement the Traffic and Pedestrian Management Plan for the duration of the Work for all areas that it applies to. This includes coordination with, and notification to all applicable parties for lane or road closures. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 9 of 35 FORM OF TENDER Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. 1.4 Survey and Record Drawings This item shall include all costs for labour, materials and equipment to conduct: 1. Construction survey layout of all utilities to lines and grades as shown on drawings; and 2. Record survey of all as-built utility locations and elevations. Record survey information shall be provided to the Engineer in project datum in digital, CSV file (Northing, Easting, Elevation, Description) or AutoCAD DWG format. Information to include, but not limited to: Manholes, Building Penetration (Location and Elevation) Centerline inverts of standard benched manholes Finished lid/rim centerline elevation D.E.S. Pipe (Location, Invert Elevation, Finished Surface Grade) All mainline fittings, bends, tees, valves, end caps, etc… All service line fittings, bends, tees, valves, end caps, etc… General (Location and Elevation) Existing utilities locations and inverts at D.E.S. Pipe crossings Note: Construction Survey does not replace the requirement for the Contractor to maintain an accurate set of red-lined record drawings indicating all changes to the design. This item shall also include all costs for labor and material to submit: 1. Operation & Maintenance Manuals 2. As-Built Drawings / Record Drawings 3. ISO’s / welding maps Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. PART 2 - SITE WORK 2.1 Site Preparation This item shall include all costs for the completion of site work preparation for the D.E.S. piping installation. This shall include, but not be limited to, the clearing and grubbing of the site, removal of cleared and grubbed materials from site, and installation of temporary fencing. This shall also include asphalt and concrete saw cut as per the Drawings and Specifications. Payment will be made at the unit price tendered per lineal metre of prepared trench piping. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 10 of 35 FORM OF TENDER 2.2 a),b),c),d) Trenching, Bedding & Import Backfill (1.2 – 1.8 m) This item provides all compensation for all costs for excavation depth from 1.2 to 1.8 m of piping trenches, supply, place and compact bedding material and trench backfill. (For trenches to accommodate the D.E.S. Piping). The work includes but is not limited to: • Trench excavation • Disposal of excavated material • Supply, placement, and compaction of bedding material in the pipe zone • Approved trench backfill • Excavation for tee installation • Shoring and dewatering • Testing of bedding and backfill material • Support of existing structures and piping Payment will be made at the unit rate tendered for each lineal metre of piping trench. 2.3 a),b),c),d) Trenching, Bedding & Import Backfill (1.8 – 2.4 m) This item provides all compensation for all costs for excavation depth from 1.8 to 2.4 m of piping trenches, supply, place and compact bedding material and trench backfill. (For trenches to accommodate the D.E.S. Piping). The work includes but is not limited to: • Trench excavation • Disposal of excavated material • Supply, placement, and compaction of bedding material in the pipe zone • Approved trench backfill up to subgrade • Excavation for tee installation • Shoring and dewatering • Testing of bedding and backfill material • Support of existing structures and piping Payment will be made at the unit rate tendered for each lineal metre of piping trench. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 11 of 35 FORM OF TENDER 2.4 a),b),c),d) Site Restoration This item shall include all costs for re-instatement of existing sod, seed, topsoil, turf, asphalt, sidewalks and curb and gutters, in areas disturbed by construction to City of Surrey standards. This item shall also include all costs for sawcut removal of concrete and asphalt, replacement of base and subbase materials as detailed on the construction drawings, line painting if applicable and sidewalk and curb restoration. All waste debris shall be disposed of off-site. Restoration work covered under this item is limited to that which is a direct result of construction activities in the immediate vicinity of the proposed works. Any other area appurtenances, surface features, etc. that have been disturbed by the Contractor shall be restored to their original condition at the cost of the Contractor. Payment will be made at the unit rate tendered in the Schedule of Quantities and Prices. 2.5 D.E.S. Manhole This item provides compensation for all costs for supply, construction, and installation of concrete manholes as shown on the drawings t Payment will be made at the unit rate tendered in the Schedule of Quantities and Prices. 2.6 Utilities Crossing This item provides compensation for all costs for supply, preparation, and installation of Styrofoam and insulation providing minimum clearance between existing utilities or bedrock and the D.E.S. piping. Payment will be made at the unit rates tendered for each crossing requiring minimum clearance. 2.7 Watermain Replacement This item provides compensation for all costs for the relocation of existing watermain, to City of Surrey Standards, in direct conflict with the D.E.S. piping alignment. Payment will be made at the unit rate tendered in Schedule 1 for each relocation as directed by the Engineer. 2.8 Air Release Valve Assembly This item provides compensation for all costs for material and labour to supply and install air release valve manhole assembly including but not limited to precast District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 12 of 35 FORM OF TENDER manhole sections, lid, frame and cover, concrete blocks, and drain rock. The cost for valves, pipe tapping and related mechanical work shall be included in Part 15. Payment will be made at the unit rate tendered for each air valve assembly installed. 2.9 100-mm-diameter Sewer This item provides compensation for all costs for material and labour to supply and install 100-mm-diameter PVC sanitary sewer service as shown on the drawings and specifications, including but not limited to piping, fittings, couplings, equipment, cleanouts, inspection chambers, and all other additional work related to sanitary sewers and services. Payment will be made at the unit rate tendered for each lineal metre of piping installed. 2.10 25-mm-diameter Water Service This item provides compensation for all costs for material and labour to supply and install 25-mm-diameter water service as shown on the drawings and specifications, including but not limited to piping, valves, fittings, couplings, equipment, curb stop, connections to municipal utility and boiler plant, all other additional work related to water services. Payment will be made at the unit rate tendered for each lineal metre of piping installed. 2.11 CBP Concrete Pad and connections This item provides compensation for all costs for material and labour to supply and install the Containerized Boiler Plant concrete pad as shown in the drawings including all service connections not covered above. Payment will be made at of the lump sum price tendered in the Schedule of Quantities and Prices. 2.12 Electrical Duct Bank This item provides compensation for all costs for material and labour to supply and install the electrical duct bank connecting the BCHydro transformer to the Containerized Boiler Plant. This section covers supply of electrical cable and termination 2.13 Fencing & Gate This item provides compensation for all costs for material and labour to supply and install the fencing and gate as shown in the drawings i 2.14 Logstor Material Handling District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 13 of 35 FORM OF TENDER This item provides compensation for all costs for material and labour to coordinate, receive, inspect, handle and track all Logstor® material as stated in the Schedule of Quantities in Section 01220 Part 2 Payment will be made at of the lump sum price tendered in the Schedule of Quantities and Prices. PART 15 - MECHANICAL 15.1 a),b),c) D.E.S. Piping and Valve System This item provides compensation for all costs for mechanical works required in accordance with the drawings and specifications. This item shall include, but not be limited to, supply, preparation, and installation of D.E.S. piping, valves, equipment, pipe supports, fittings, couplings and all other additional work related to D.E.S. piping equipment. This item shall also include all x-ray testing of every D.E.S. piping weld. Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. 15.2 Connections to Containerized Boiler Plant This item provides compensation for all costs for materials and labour for all connections to the Containerized Boiler Plant as shown on the drawings including but not limited to D.E.S. piping, water service and sanitary services. Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. 15.3 Testing & Commissioning of D.E.S. This item provides compensation for all costs required to flush, test, and commission all D.E.S. piping system installed as per the Drawings and Specifications. Payment will be made at of the lump sum price tendered in the Schedule of Quantities and Prices. 15.4 Leak Detection This item provides compensation for all costs required for leak detection of the entire D.E.S. piping system installed. This will include the installation and wiring of the X1L in the Containerized Boiler Plant and the 1517 boxes in the two Phase 2a ETS only. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 14 of 35 FORM OF TENDER Payment will be made at of the lump sum price tendered in the Schedule of Quantities and Prices. 15.5 Pipe Pre-stressing This item provides compensation for costs required for renting and operation of an electrical pipe pre-stressing in accordance with manufacturer and supplier requirements and recommendations. 15.5 a),b) ETS Work This item provides compensation for all costs for mechanical works required in accordance with the drawings and specifications. This item shall include, but not be limited to, supply, preparation, and installation of piping, valves, equipment, pipe supports, fittings, couplings and all other additional work related to the ETS piping equipment. This item shall also include all x-ray testing and commissioning as per project specifications. Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. PART 16 - ELECTRICAL & CONTROLS 16.1 Concord Phase 1 Building This item provides compensation for all costs for electrical and controls works required in accordance with the drawings and specifications for Concord Phase 1 building. This item shall include, but not be limited to, supply and installation of all electrical and controls components and all other additional work to have a fully operational system as per the project specifications. Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. 16.2 Concord Phase 2 Building This item provides compensation for all costs for electrical and controls works required in accordance with the drawings and specifications for Concord Phase 2 building. This item shall include, but not be limited to, supply and installation of all electrical and controls components iand all other additional work to have a fully operational system as per the project specifications. Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. 16.3 Central Control Station District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 15 of 35 FORM OF TENDER This item provides compensation for all costs for electrical and controls works required in accordance with the drawings and specifications for connecting to the existing central control panel at City Hall. Payment will be made at the lump sum price quoted in the Schedule of Quantities and Prices. PART 17 - INDETERMINATE ITEMS All indeterminate items and the quantities identified in Schedule A may increase, decrease or not be used at all. No payment will be made if the work is not undertaken. 17.1 Trench Over Excavation This item provides compensation for all costs associated with vertical pipe trench over excavation in general as directed by the Engineer. The work includes but is not limited to: • Trench over excavation • Disposal of over excavated material • Additional fill material • Shoring and Dewatering • Testing of additional fill material Payment will be made at the unit rate tendered based on the fill volume determined in the field by the Engineer. 17.2 Removal of Existing Abandoned Utilities This item includes all costs for supply of all materials, equipment, labour, excavation and backfill to remove and dispose of existing abandoned utilities in conflict with the D.E.S. piping alignment as directed by the Engineer. This item shall also include the additional fill material to replace the abandoned utilities volume. Payment will be made at the unit rate tendered for each lineal metre of abandoned pipe removed. 17.3 Additional Mass Concrete as Requested by the Engineer This item shall include all costs for crude forming and placement of mass concrete as requested by the Engineer. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 16 of 35 FORM OF TENDER Payment will be made at the unit price quoted in the Schedule of Quantities and Prices for each cubic meter of concrete in place. Measurement will be based on truck volume as per dispatch slips certified by the Engineer. 17.4 Removal of Buried Concrete This item shall include all costs for supply of all materials, equipment, and labour for removal of buried concrete in conflict with the D.E.S. piping trench as directed by the Engineer. This item shall include, but not limited to saw cut and removal of concrete, disposal off site, and backfill with import material. Payment will be made at the unit price quoted in the Schedule of Quantities and Prices for each cubic meter of concrete removed. Measurement will be based on field measurement by the Engineer 17.5 Supply, Placement and Compaction of Additional Fill Material as Requested by the Engineer This item shall include all costs for supply, placement, and compaction of additional 75 mm minus free draining structural backfill material as requested by the Engineer. Payment will be made at the unit price quoted in the Schedule of Quantities and Prices. 17.6 Controlled Density Fill This item shall include all costs for forming, placing, finishing and curing of additional concrete density fill as requested by the Engineer. Payment will be made at the unit price quoted in the Schedule of Quantities and Prices for each cubic meter of concrete in place. Measurement will be based on truck volume as per dispatch slips certified by the Engineer. 17.7 Trench Rock Excavation This item provides compensation for the addition-al cost of removing and disposing of trench rock over that of earth excavation. Trench rock excavation shall include the excavation and disposal of all material which in the opinion of the Engineer requires for its removal either drilling and blasting, wedging, sledging, or breaking with a power operated hand tool. Rock excavation does not include the excavation of soft or disintegrated rock which can be removed with a handpick or power-operated excavation machine. NO payment will be considered for trench rock encountered in subgrade fill sections. Rock excavation shall also include the removal and disposal of boulders exceeding District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 17 of 35 FORM OF TENDER one (1) cubic metre in volume if within a trench section, or if exceeding two (2) cubic metres if within a road subgrade section, which lie wholly within the excavation and in the opinion of the Engineer interfere with the work. If an outcropping of bedrock protrudes into the excavation and a portion less than one (1) cubic metre in volume is removed by blasting, payment will be made for a minimum of one (1) cubic metre. Excavated rock shall be disposed of on-site at locations designated by the Engineer. Payment will be made for the volume of rock excavation at the unit rate tendered per cubic metre. 17.8 Dritherm This item shall include all costs for supply, formwork, and placement of Dritherm material as requested by the Engineer. Payment will be made at the unit price quoted in the Schedule of Quantities and Prices for each cubic meter of dritherm placed. Measurement will be based on field measurement by the Engineer. 17.9 Tree and Root Mass Removal This item provides compensation for all costs for material and labour to remove tree and root mass from the pipe trench where in conflict with the D.E.S. piping where indicated on the drawings and where instructed by the Engineer. Payment will be made at the unit rate tendered for each tree and root mass removed. PART 18 - CASH ALLOWANCE Refer to Division 00 for terms and conditions District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 18 of 35 FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Table B: Schedule of Values: LINE ITEM SECTION OF WORK PRICES 1. $ 2. $ 3. $ 4. $ 5. $ 6. $ 7. $ 8. $ 9. $ District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 19 of 35 PART C - FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Table C: List of Cash Allowances: This section of the specifications forms part of the Contract Documents and is to be read, interpreted and coordinated with all other parts. The Tenderer shall include in the Tender Price all Cash Allowances listed below, which allowances shall be expended in whole or in part as the Owner shall direct, the amount of the Contract sum being adjusted in conformity therewith. The Tenderer shall include in the Tender price for such sums for expenses, supervision, Overhead and profit as he deems proper on account of all Cash Allowances. No demands for expenses or profit other than those included in the Tender price will be allowed. These Cash Allowances – which do not include GST – may be increased, decreased or deleted from the Contract with no adjustments to the Contract other than the net amount of such a variation. The Owner reserves the right to place a Contract or Contracts, for any and all parts of items included in the cash allowances at its discretion. Cooperate & coordinate with other contractors as may be appointed by the Owner. Cash Allowances as listed in this section are to be carried by the Contractor and are in addition to the work detailed in other sections of the specifications and drawings. Description of Cash Allowance e.g. 1. Amounts The Contractor shall include in the Form of Tender the sum of all cash allowances listed below, which shall be expended in whole or in part as the Owner shall direct, the amount of the Contract sum being adjusted in conformity therewith. Include the following Cash Allowance amounts (which do not include GST): Description of Cash Allowance Amounts Supply of Logstor Piping $450,000 Unknown Utility Conflicts $50,000 District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 20 of 35 PART C - FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Table D: - Alternate Prices The undersigned hereby provides the following Alternates for addition to or deletions from the Work: line item amount ($) addition description of work/supply amount ($) deduction .1 $ $ .2 $ $ .3 $ $ .4 $ $ Include a detailed description of any proposed Optional Alternative Work Items in the spaces indicated above, including the associated effect on the Tender Price (excluding GST). Include any additional product sheets or other information necessary to describe the proposed Optional Alternative Work. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 21 of 35 PART C - FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Table E: Separate Optional Prices The following are our prices for the separate optional goods and services listed hereunder. Such separate optional goods and services and amounts are NOT included in our Tender Price. The separate optional prices are a deduction from or addition to the Tender Price and do not include GST. DO NOT state a revised Tender Price. Effect on Tender Price ($) (GST Excluded) LINE ITEM DESCRIPTION OF SEPARATE OPTIONAL PRICE ITEMS ADDITION DEDUCTION .1 $ $ .2 $ $ .3 $ $ .4 $ $ Include a detailed descrition of any proposed separate optional price items in the spaces indicated above, including the associated effect on the Tender Price (excluding GST). Include any additional product sheets or other information necessary to describe the proposed separate price items. NOTE: The financial evaluations will be based on the Tender Price, not including the effect of any separate price items. The above prices do not include GST. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 22 of 35 PART C - FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Table F: Contractors Current Own Forces Labour Rates Tenderers should provide force account labour rates in the table below for all labour categories that will be involved in the Work. The labour rates will remain firm for the term of the Contract and will be used by the Owner for the purpose of evaluating and valuing changes in the Work in the case of lump sum, or in case of force account valuation. The labour rates provided below are all inclusive and include without limitation, wages, taxes and assessments and benefits payable in accordance with applicable laws, mobilization and demobilization, supervision, administration, small tool rental, overhead and profit. For the purposes of the above, small tools are considered to be any tool worth $2,000 or less in new value. All other tools should be listed as equipment in the table under Table G below. STRAIGHT TIME/HR (GST Excluded) LABOUR CATEGORY OVERTIME RATE/HR (GST Excluded) .1 Site Superintendent / Site Project Manager $ $ .2 Foreman $ $ .3 Carpenter $ $ .4 Labourer / Helper $ $ .5 Plumber (BCTQ) $ $ .6 Apprentice (or experienced) $ $ .7 Electrician (BCTQ) $ $ .8 Apprentice (or experienced) $ $ District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 23 of 35 PART C - FORM OF TENDER APPENDIX 1 - SCHEDULE OF PRICES Table G: Equipment Rates Tenderers should provide equipment rates for all equipment that will be involved in the Work. The equipment rates will remain firm for the term of the Contract and will be used by the Owner for the purpose of evaluating and valuing changes in the Work in the case of lump sum, or in case of force account valuation. The rates provided below are all inclusive and include without limitation, operator, fuel, lubrication, service, maintenance, depreciation, mobilization and demobilization, overhead and profit. It is acknowledged by the Contractor that if any portion of an hour is spent in performing the Work on a force account basis, a pro-rated portion of the force account rate shall only be charged. CONSTRUCTION EQUIPMENT CLASSIFICATION HOURLY RATE (GST Excluded) SPECIFY MAKE & MODEL $ $ $ $ $ $ $ $ $ $ We confirm that the rates quoted above will remain in force until _________________, 201_. (Additional pages may be attached to this page. Each such additional page is to be clearly marked “ITT (state tender name and tender number), FORM OF TENDER – PART C.”) District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 24 of 35 PART C - FORM OF TENDER APPENDIX 2 - PRELIMINARY CONSTRUCTION SCHEDULE Contract Name: District Energy System Phase 2a: DPS, ETS and CBP Service Connections Reference No.: 1220-020-2015-001 From Tenderer: _______________________________________________________ Company name Tenderers should provide a preliminary Construction Schedule for the goods and services, including the range of start dates to which your firm is prepared to commit and anticipated completion dates. This preliminary Construction Schedule should work within the timeframes as may be outlined by the Owner. Any conflict in the two should be described. The Time Schedule should include a list of all anticipated meetings with the Owner and their locations. The Owner prefers the preliminary Construction Schedule to be provided as a Microsoft Project Gantt chart both in paper and electronically. Include a list of all assumptions used in developing the preliminary Construction Schedule for the goods and services as presented in Schedule A – Specifications of Goods and Scope of Services, but not limited to the following: • • • • • • • • • • Project Meetings Design Milestones Mobilization and Demobilization Construction/Installation Milestones Equipment and Material Procurement Training and Demonstration Periods Work Commencement Date Substantial Performance of the Work Date Total Performance of the Work Date Final Completion of the Goods and Services The schedule included may be on 11”x17” size sheets. Proposed Disposal Site: ________________________________________________ District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 25 of 35 PART C - FORM OF TENDER APPENDIX 3 – KEY PERSONNEL Contract Name: District Energy System Phase 2a: DPS, ETS and CBP Service Connections Reference No.: 1220-020-2015-001 From Tenderer: _______________________________________________________ Company name Identify the key personnel who will be responsible for the Work, together with a description of the responsibilities such personnel will have in the performance of the Work and a description of the relevant experience of such personnel, using a format similar to the following: Name: ________________________________________________________________ Responsibilities: ________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ Experience: ___________________________________________________________ ______________________________________________________________________ ______________________________________________________________________ District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 26 of 35 PART C – SCHEDULE 1 APPENDIX 4 – TENDERER’S EXPERIENCE IN SIMILAR WORK Contract Name: District Energy System Phase 2a: DPS, ETS and CBP Service Connections Reference No.: 1220-020-2015-001 From Tenderer: _______________________________________________________ Company name Year Completed Description of Contract For Whom Work Performed District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Value Page 27 of 35 PART C – SCHEDULE 1 APPENDIX 5 – SUBCONTRACTORS AND SUPPLIERS Contract Name: District Energy System Phase 2a: DPS, ETS and CBP Service Connections Reference No.: 1220-020-2015-001 From Tenderer: _______________________________________________________ Company name The Tenderer proposes to use the following Subcontractors and Suppliers for the divisions or sections of work / supply listed below. [Note: It is not necessary for Tenderer to list all Subcontractors and Suppliers that the Tenderer proposes to use – only those for the divisions or sections of work / supply as may be listed below.] The named Subcontractors and Suppliers will not be changed without the written approval of the Owner. Refer to GC 3.7 of the General Conditions as supplemented, modified and amended by the Supplementary General Conditions. description of work / supply name of Subcontractor / Supplier 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. The Owner reserves the right of approval for each of the Subcontractors and Suppliers. The Contractor will be given the opportunity to substitute an acceptable Subcontractor and Supplier, if necessary. District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 28 of 35 PART C – SCHEDULE 1 APPENDIX 6 – ATTACH BID BOND (PAGE INCLUDED HERE FOR REFERENCE ONLY) District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 29 of 35 PART C – SCHEDULE 1 District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 30 of 35 PART C – SCHEDULE 2 PRIME CONTRACTOR DESIGNATION LETTER OF UNDERSTANDING As per the requirements of the Workers’ Compensation Act Part 3, Division 3, Section 118 (1-3), which states: Coordination of multiple-employer workplaces 118 (1) In this section: “multiple-employer workplace” means a workplace where workers of 2 or more employers are working at the same time: “prime Contractor” means in relation to a multiple-employer workplace, (a) the directing Contractor, employer or other person who enters into a written proposal with the Owner of that workplace to be the prime Contractor for the purposes of this Part, or (b) if there is no proposal referred to in paragraph (a), the Owner of the workplace. (2) The prime Contractor of a multiple-employer workplace must (a) ensure that the activities of employers, workers and other persons at the workplace relating to occupational health and safety are coordinated, and (b) do everything that is reasonably practicable to establish and maintain a system or process that will ensure compliance with this Part and the regulation in respect to the workplace. (3) Each employer of workers at a multiple-employer workplace must give to the prime Contractor the name of the person the employer has designated to supervise the employer’s workers at that workplace. By signing this Contract, the Contractor accepts all responsibilities of a Prime Contractor as outlined in the Workers’ Compensation Act, and WCB (OH&S Regulation). As a Contractor signing this Contract with the Owner, you are agreeing that your Company, Management staff, Supervisory staff and workers will comply with the Workers’ Compensation Board (WCB) Occupational Health and Safety Regulation and the Workers’ Compensation (WC) Act. Any WCB violation by the Prime Contractor may be considered a breach of Contract resulting in possible termination or suspension of the Contract and/or any other actions deemed appropriate at the discretion of the Owner. Any penalties, sanctions or additional costs levied against the Owner, as a result of the actions of the Prime Contractor are the responsibility of the Prime Contractor. I, the undersigned, acknowledge having read and understand the information above. By signing this Contract, I agree as a representative of the firm noted below, to accept all responsibilities of the Prime Contractor for this project. I fully understand and accept the responsibilities of the Prime Contractor designation in accordance with the Workers’ Compensation Act while contracted by the City of Surrey for the project as described in this Contract and will abide by all Workers’ Compensation Board Regulation requirements. Contract No: 1220-020-2015-001 Contract Name: _______________________________ Name of Contractor: _______________________________ Qualified Coordinator’s Name: _______________________________ Worksafe BC #: _______________________________ Signature of Authorized Representative: ___________________________________ District Energy System Phase 2a , Invitation To Tender No.: 1220-020-2015-001 Page 31 of 35 CONTRACTOR HEALTH & SAFETY EXPECTATIONS RESPONSIBILITY OF CONTRACTOR(S) The City of Surrey strives to maintain a safe work environment for employees and contractors and insists upon the enforcement of safe practices and procedures in all premises and in all work activities. It is essential that all contractors and their employees and sub-contractor(s) perform in the same manner. It is every employers and contractors responsibility to ensure that staff and public are protected from workplace hazards. As a contractor to the City of Surrey, you are expected to conform to the requirements of the Workers’ Compensation Act, the WCB Occupational Health and Safety Regulation and to all federal, provincial and local laws and regulations. The City of Surrey Building Owner, Project Manager, and the Manager, Occupational Health & Safety or designate have the authority to order an unsafe act to cease or to have an unsafe piece of equipment removed from the premises or, in extreme situations, to shut down a job entirely. Any City of Surrey Employee that observes a safety infraction by a contractor performing work for the City of Surrey should bring it to the attention of a manager immediately or Occupational Health & Safety (604-591-4131). The following information is provided as typical City of Surrey requirements, but does not relieve the contractor from complying with all applicable local, provincial and federal laws, regulations and bylaws. PERSONNEL 1. You are expected to inform your employees of any potential hazard in the workplace and advise of appropriate action to be taken should a hazard be found or a fire or accident occur. 2. Contractors will restrict persons invited on the premises to employees only. No families or friends are permitted. 3. The contractor will advise the City of any on-site accidents involving the contractor’s employees, or injuries to others caused by the contractor’s business. SAFETY MANAGEMENT SYSTEM 1. Contractors will ensure their employees utilize proper safety equipment and clothing as required for job site activities. 2. Contractors must follow and have on site proper written safe work procedures for hazardous work, e.g. Fall protection, confined space entry, hotwork, lockout, excavations and shoring, traffic management, etc. 3. Contractor must Identify workplace risk and implement suitable controls. 4. Contractor must provide safety training and education to staff and have training records available for review. 5. Contractor must have a health & safety program for its workers and sub-contractors 6. Contractor will provide appropriate First-Aid coverage for their workers and subcontractors. 7. Contractor must forward a weekly work task list prior to work commencement. 8. The qualified safety coordinator must participate in the City of Surrey OHS Orientation or attend the Prime Contractor’s Orientation. WORK AREAS –City Facilities No work by contractors shall occur in any area without prior consent of the City of Surrey Manager, Civic Facilities or his designated representative. Work during normal business hours of the City shall not create undue noise, smells or otherwise unduly disturb the work of City of Surrey staff or the public. If an activity requires that a disturbance is likely, the contractor shall whenever possible only do that work outside normal business hours. District Energy System Phase 2a, Invitation To Tender No.: 1220-020-2015-001 Page 32 of 35 All activities that create a hazard (i.e. work from a ladder, removal of a floor tile, emission of VOC’s, etc.) to persons outside the contractor’s supervision shall have warning devices, delineation or barriers, sealed spaces, etc. as would normally be required to protect any person from that hazard. SAFETY ATTITUDE Your safety record and attitude are important criteria used to judge your qualification for future bidding on solicitations with the City of Surrey. You can help ensure employee safety and your eligibility for future business with the City if you exhibit and practice a “Safe Work - Safe City” attitude. The City of Surrey is concerned about the health, safety and wellbeing of all employees and contractors. It is essential we maintain a healthy, safe and productive work environment. All Employees & Contractors: It is everyone responsibility to: know and comply with WCB regulations and follow established safe work procedures immediately report any work related injury to his/her supervisor; and to the city representative not remain on the work site while his/her ability to work is in any way impaired report unsafe acts and conditions to their supervisor correct unsafe conditions immediately whenever it is possible to do so take reasonable care to protect your health & safety and the health and safety of other persons who may be affected by your act’s or omissions at work An employee must refuse to work if continuing to do so would endanger the health and safety of the employee, fellow employees or others. The worker must immediately report the circumstances of the unsafe condition to his or her supervisor or manager. If the unsafe condition is not remedied or the issue is not resolved the Manager, Occupational Health & Safety must be contacted. GENERAL RULES 1. For all secured worksites, contracted workers are required to sign in and sign out each day 2. (Access cards may be issued – a worker may need to provide an Identification document (i.e. Driver’s License) in exchange). 3. Personal protective equipment, as determined by the City, through consultation with the Contractors Health and Safety Representatives must be worn when and where required. (Hard Hats, Safety Footwear, Safety Vests and Safety Glasses must be worn on active construction sites. Hearing Protection must be worn when noise levels are above 85dBA.) 4. Horseplay, gambling and the use of alcohol or narcotics will not be tolerated. 5. No Smoking within 7.5M of a City owned buildings door exits, windows and vents. 6. Report ALL injuries to your supervisor immediately and notify the City’s site representative. 7. Report any unsafe conditions, including someone under the influence or hazards, which may allow an injury to occur to you, a fellow worker, or others on the worksite. A common sense approach usually resolves the issue. District Energy System Phase 2a, Invitation To Tender No.: 1220-020-2015-001 Page 33 of 35 8. Report any property damage, regardless of how minor. 9. Restricted and controlled products will be labeled, used and stored in accordance with the associated regulations, e.g. WHMIS. Follow all procedural instructions when using or handling hazardous materials/controlled products and ensure that all containers of hazardous/controlled product materials are properly labelled and stored in designated areas. 10. Obey all posted signs and notices. Do not venture into areas that you are not authorized to enter. 11. Always use the correct posture when lifting and get assistance if the weight is excessive. 12. Do not work within the limits of approach to high voltage equipment. 13. If working at heights greater than 10 feet a Fall Protection system must be in place. The appropriate Fall Protection equipment must be worn at all times. 14. Housekeeping (Orderliness and good housekeeping are basic requirements and must be maintained at all times): a) Aisles are to be kept clear at all times. b) Individual work areas are to be kept clean and tidy. c) All materials, tools, products and equipment are to be kept in their designated areas. d) Liquid spills are to be cleaned up immediately to prevent slips and falls. e) Accumulation of oily rags, combustible refuse or similar fire hazards will not be tolerated. 15. a) b) c) Fire Prevention: Become familiar with Surroundings and emergency exit. Ensure aisles and exits are not blocked at any time. Anytime a fire extinguisher is used, report it immediately to your supervisor, so that it can be recharged. 16. Equipment Operation (Any equipment, which could create a hazard, must be maintained in good condition): a) Equipment must not be repaired, adjusted or operated unless by a "competent person" who understand the safe operating procedures. b) Always be aware of the use and location of the "EMERGENCY STOP" button, if equipment is so equipped, before using the equipment. c) Loose clothing, jewelry and long hair must be secured to prevent becoming entangled with equipment. d) The Operator must check all safety devices on equipment before operation. e) All equipment must be turned off and the appropriate "lock-out" procedure followed, prior to repairs, cleaning, adjustment or lubrication. f) Radio/Walkman/I-pod Head phones are not allowed to be worn during regular work operations. g) All ladders must be of an approved type and length. Unacceptable ladders must be removed immediately from the premises. h) All vehicles and equipment on City property must be kept in safe mechanical condition at all times, and be operated only by persons with a valid driver’s license and/or proper training and qualifications. i) Contractors will not operate any equipment, valves, switches, etc., which are part of the City’s operation, unless specific permission is received from the Department Representative. 17. Ground Disturbance –Every time you dig in the ground, with a shovel or mechanized equipment, you run the risk of loss of life or damage to property if you hit any of the many buried cables, conduits, gas or oil pipelines and/or other underground facilities that serve our city, BC One Call Must be called and a ticket obtained prior to commencing any ground disturbance activities. District Energy System Phase 2a, Invitation To Tender No.: 1220-020-2015-001 Page 34 of 35 Issued By: Date: Distributed: Occupational Health & Safety Section - Contractor Coordination Program Revised: January 14, 2014 Original: August 15, 2014 Via Email & Posted on Intranet: January 16, 2015 :August 15, 2014 This document does not replace the Workers’ Compensation Act or WorkSafeBC OH&S regulation. Each individual Contractor must have specific health and safety safe work rules and procedures that apply to their work tasks. Each Contractor must comply with the Workers’ Compensation Act and WorkSafeBC Occupational Health & Safety Regulation and to all federal, provincial and local laws and regulations. If a contractor is unable to comply they must bring this to the attention of their qualified safety representative and to the Prime Contractor safety representative immediately. Authorized Signature: _________________________________________ Name: Date: ____________________________________________ (Please Print) _____________________________________________ District Energy System Phase 2a, Invitation To Tender No.: 1220-020-2015-001 Page 35 of 35