CEE 463/663 – Traffic Engineering Fall 2006 Homework #1 Due: Tuesday, September 12, 2006 Problem 1: (Based on Problem 9-1 on Page 233 of the textbook) Consider the following spot speed data, collected from a freeway site operating under free-flow conditions (no congestion). Speed Group, mph 15-20 20-25 25-30 30-35 35-40 40-45 45-50 50-55 55-60 60-65 65-70 Number of vehicles observided 0 3 6 18 45 48 18 12 4 3 0 (a) Plot the frequency and cumulative frequency curves for these data. (b) Find and identify on the curves: median speed, modal speed, pace, percent vehicles in pace (c) Compute the mean and standard deviation of the speed distribution (d) What is the 95% confidence interval of the true mean speed (review basic statistics on how to calculate confidence intervals). (e) Based on the results of this study, a second is to be conducted to achieve a tolerance of ± 1.5 mph with 95% confidence. What sample size is needed? CEE 463/663 – Traffic Engineering Fall 2006 Problem 2. Traffic flow rates measured upstream of a freeway bottleneck (free of queues) are shown in the table below. Assume the freeway bottleneck has a capacity of 6400 vph. Calculate: (1) Traffic demand, Measured flow rate downstream of the bottleneck, and Delay during each interval. Indicate the units of each measure. (2) What is the maximum queue length during the hour? (3) Define the intervals when queue started and cleared. Interval, min 4:00-4:05 4:05-4:10 4:10-4:15 4:15-4:20 4:20-4:25 4:25-4:30 4:30-4:35 4:35-4:40 4:40-4:45 4:45-4:50 4:50-4:55 4:55-5:00 Flow Rate (vph) 5000 6000 6100 6400 6600 7000 6800 6200 5800 5400 5000 4800 Problem 3. Traffic volume counts were conducted at the intersection of Virginia Street/16th Street between 7:30 a.m. and 10:00 a.m. on a typical weekday in 2003. Determine the following: (a) The PHFs for both the entire intersection and the westbound approach. (b) Determine whether the intersection meets the MUTCD peak hour volume warrant. CEE 463/663 – Traffic Engineering TIME: DATE: PROJECT NO: to to 7:30 AM to 10:00 AM 2/27/2003 9:45 AM 9:30 AM J K INTERSECTION: N. Virginia/16th JURISDICTION: City of Reno PROJECT TITLE: PEAK HOUR PERIOD: 8:45 AM PEAK 15 MINUTE PERIOD: 9:15 AM N. Virginia Fall 2006 F D I H 16th N. Virginia N INTERSECTION PEAK HOUR FACTOR: RUNNING COUNTS Period End 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM 9:00 AM 9:15 AM 9:30 AM 9:45 AM 10:00 AM PERIOD COUNTS Period End 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM 9:00 AM 9:15 AM 9:30 AM 9:45 AM 10:00 AM HOURLY TOTALS Beginning At 7:30 AM 7:45 AM 8:00 AM 8:15 AM 8:30 AM 8:45 AM 9:00 AM . Left A N/A Eastbound Thru Right B C 16th Westbound Left Thru Right D E F 0 0 4 5 6 8 6 9 6 10 8 12 11 13 11 15 13 15 18 16 N. Virginia Northbound Left Thru Right G H I 129 4 219 12 309 30 405 43 494 47 609 55 757 61 883 71 980 74 1061 82 Left J 7 23 30 35 38 39 47 73 79 87 N. Virginia Southbound Thru Right K L 166 292 379 435 510 583 726 879 954 1033 TOTAL 306 555 762 933 1105 1306 1615 1932 2115 2297 A B C D 0 4 2 0 0 2 3 0 2 5 E F 0 5 3 1 1 2 1 2 0 1 G H 129 90 90 96 89 115 148 126 97 81 I 4 8 18 13 4 8 6 10 3 8 J 7 16 7 5 3 1 8 26 6 8 K 166 126 87 56 75 73 143 153 75 79 L TOTAL 306 249 207 171 172 201 309 317 183 182 A B C D 6 6 4 5 5 7 10 E F 9 10 7 5 6 5 4 G H 405 365 390 448 478 486 452 I 43 43 43 31 28 27 27 J 35 31 16 17 38 41 48 K 435 344 291 347 444 444 450 L TOTAL 933 799 751 853 999 1010 991