Considerations when introducing new equipment into the LHC M.Gallilee CERN, CH-1211, Geneva 23, Switzerland INTRODUCTION AND GOAL This is a summary of the approval process required for the implementation of new vacuum chambers and equipment in the LHC. A rigorous approval process is required, with a final approval granted at the LHC Machine Committee (LMC). Reduction in diameter of the central vacuum chambers will allow for better Physics data and detector accuracy. The requested changes need a full machine study in order to ensure that they are compatible with both the current LHC and the future HL-LHC and that the most possible flexibility is given for future run conditions. EXAMPLES OF PAST STUDIES Pictures courtesy of ATLAS Pictures courtesy of CMS CMS reduction of central vacuum chamber inner diameter from 58 mm to 43.4 mm and ATLAS reduction from 58 mm to 47 mm inner diameter. Figures 1 and 2 show simplified diagrams of the changes. 7 Figure 1: New CMS Chamber—6.2 m in length, minimum inner diameter 43.4 mm, 0.8 mm wall Figure 2: New ATLAS Chamber—7.3 m in length, inner diameter 47 mm, 0.8 mm wall APPROVAL PROCESS EXAMPLE OF CAVERN MOVEMENTS FOR STABILITY TOLERANCES The approval process considers all areas where the new object may affect the performance of the machine. The experimental caverns have been measured at regular intervals. Floor Stability ATLAS Floor Stability Aug 03 – Dec 10 (graphique) Machine Protection A23-7 Background E-Cloud A17-14 1.5 1 Aperture approval with LMC Deep References 0.5 A11+5 MOVEMENTS IN MM Impedance Heating Positioning Tolerances Stability Tolerances A22-15 A17+8 Collimation A11-5 B0+8 B0+5 B0-5 B0-9 C23+10 C23+5 C23-7 (Sector layout now defined) 10-Dec Jun-09 Dec. 08 July 08 0 Febr 08 Aug 07 March 07 Aug 06 March 06 Nov-05 Oct 05 Aug 05 March 05 Oct-04 Sep-04 Dynamic Vacuum June 04 Aperture for n1 value March 04 C22-15 Aug 03 Mechanical Tolerances A23+5 2 Injection Optics & Beam Dump New Diameter Beam Pipe A23+10 FLOOR STABILITY : CUMULATIVE MOVEMENTS AUGUST 03 - DEC 10 C17+8 C17-14 C12-5 -0.5 C12+5 Data courtesy of Dirk Mergelkuhl and Vitali Batusov: CERN Static Vacuum 7 Data courtesy of Antje Behrens: CERN EXAMPLE OF VACUUM ANALYSIS EXAMPLE OF IMPEDANCE CALCULATION EXAMPLE OF TOLERANCES OLD AND NEW EXAMPLE OF APERTURE CALCULATION (N1 σ) More accurate tolerances have lead to an increase in the available physical aperture for the beam. 2011 Design Value Tolerances ATLAS CENTRAL CHAMBER CMS CENTRAL CHAMBER Composition of beampipe radius (mm) Mechanical Construction and Assembly 1.95 1.15 Installation Survey 2.6 at 2 sigma (95.4%) 1.6 at 2 sigma (95.4%) Cavern Stability 0.5/year 0.5/year Stability Margin 0 2.3 Sum of Tolerances 7.05 (for 5 years between alignments) 6.55 (for 3 years between alignments) Chamber Radius 23.5 21.7 Aperture (Radius-Tolerance Sum) 16.45 15.15 CONCLUSION In conclusion it has been shown that the approval of a new LHC element is a non-trivial process and many items must be considered before the final go-ahead can be given for installation. ACKNOWLEDGEMENTS The author would like to thank the CERN LEB working group for the material which has been used to form the basis of this poster presentation. Technology Department 28th October – 9th November 2012