Gary Morton – October 2015 ESS Health & Safety Arrangements Construction Design and Management (CDM) Distribution: This document must be brought to the attention of all ESS managers, employees and contractors working in construction. Contents: 1.0 Introduction to the CDM 2015 Regulations 2.0 Summary of Duty Holder Responsibilities 3.0 CDM Notification Requirements 4.0 Client Duties 5.0 Designers Duties 5.1 6.0 Principal Designers Duties 6.1 7.0 Arrangements for Internal Design Development at Newcastle University Newcastle University Internal Arrangements for Principal Designer Contractors/Principal Contractors Duties 7.1 ESS Representatives Acting as Principal Contractor (small non notifiable projects eg decoration) Appendix 1 Construction Phase Plan Aide Memoir Appendix 2 Health and Safety File Template Appendix 3 Pre Construction Information Template Appendix 4 Designers Red, Amber and Green Lists, practical aides for designers on what to eliminate/avoid, and what to encourage. (Developed by HSE) Appendix 5 Principal Designer Letter of Appointment Appendix 6 Principal Designers Scope of Service Appendix 7 Principles of Prevention Industry Guidance (CITB Interactive Guidance Booklets) Client (Includes Clients Preconstruction Checklist) Designer (Includes Designers Red Amber Green Lists) Principal Designer Principal Contractor Contractor 1 Gary Morton – October 2015 1.0 Introduction to CDM 2015 Regulations The Construction (Design & Management) Regulations (CDM) are the main set of regulations for managing the health, safety and welfare in construction projects. CDM applies to all building and construction work and includes new build, demolition, refurbishment, extensions, conversions, repairs and maintenance. These revised regulations came into force on 6 April 2015. The ‘Approved Code of Practice’ for CDM 2007 was withdrawn on 6 April 2015 and replaced with Guidance. The new guidance is made up of five Parts: Part 1 Commencement, interpretation and application Part 2 Client duties Part 3 Health and safety duties and roles Part 4 General requirements for all construction sites Part 5 General Section Click here to download a copy of the Guidance 1.1 Construction Work Definition “Construction work” means the carrying out of any building, civil engineering or engineering construction work and includes: a the construction, alteration, conversion, fitting out, commissioning, renovation, repair, upkeep, redecoration or other maintenance (including cleaning which involves the use of water or an abrasive at high pressure, or the use of corrosive or toxic substances), de-commissioning, demolition or dismantling of a structure; b the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation (but not preconstruction archaeological investigations), and the clearance or preparation of the site or structure for use or occupation at its conclusion; c the assembly on site of prefabricated elements to form a structure or the disassembly on site of the prefabricated elements which, immediately before such disassembly, formed a structure; 2 Gary Morton – October 2015 2.0 d the removal of a structure, or of any product or waste resulting from demolition or dismantling of a structure, or from disassembly of prefabricated elements which immediately before such disassembly formed such a structure; e the installation, commissioning, maintenance, repair or removal of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to a structure, Summary of CDM Duty Holders Responsibilities CDM dutyholders* Who are they Clients are organisations or individuals for whom a construction project is carried out Summary of role/main duties Domestic clients are people who have construction work carried out on their own home, or the home of a family member that is not done as part of a business, whether for profit or not Domestic clients are in scope of CDM 2015, but their duties as a client are normally transferred to: The contractor, on a single contractor project or The principal contractor, on a project involving more than one contractor Designers are those, who as part of a business, prepare or modify designs for a building, product or system relating to construction work When preparing or modifying designs, to eliminate, reduce or control foreseeable risks that may arise during: Construction, and The maintenance and use of a building once it is built Principal designers** are designers appointed by the client in projects involving more than one contractor. They can be an organisation or an individual with sufficient knowledge, experience and ability to carry out the role Plan, manage, monitor and coordinate health and safety in the pre-construction phase of a project. This includes: Identifying, eliminating or controlling foreseeable risks Ensuring designers carry out their duties Make suitable arrangements for managing a project. This includes making sure: Other dutyholders are appointed Sufficient time and resources are allocated Relevant information is prepared and provided to other dutyholders The principal designer and principal contractor carry out their duties Welfare facilities are provided See paragraphs 23-52 for more guidance However, the domestic client can choose to have a written agreement with the principal designer to carry out the client duties. See paragraphs 53-56 for more guidance Provide information to other members of the project team to help them fulfil their duties. See paragraphs 72-93 for more guidance Prepare relevant information to the principal contractor to help them plan, manage, monitor and coordinate health and safety in the construction phase. See paragraphs 94-115 for more guidance 3 Gary Morton – October 2015 Principal contractors are contractors appointed by the client to coordinate the construction phase of a project where it involves more than one contractor Plan, manage, monitor and coordinate health and safety in the construction phase of a project. This includes: Liaising with the client and principal designer Preparing the construction phase plan Organising cooperation between contractors and coordinating their work Ensure: Suitable site inductions are provided Reasonable steps are taken to prevent unauthorised access Works are consulted and engaged in securing their health and safety, and Welfare facilities are provided See paragraphs 110-146 for more guidance Contractors are those who do the actual construction work and can be either an individual or a company Plan, manage and monitor construction work under their control so that it is carried out without risks to health and safety For projects involving more than one contractor, coordinate their activities with others in the project team, in particular, comply with directions given to them by the principal designer or principal contractor For single-contractor projects, prepare a construction phase plan See paragraphs 147-179 for more guidance Workers are the people who work for or under the control of contractors on a construction site 3.0 The must: Be consulted about matters which affect their health, safety and welfare Take care of their own health and safety and others who may be affected by their actions Report anything they see which is likely to endanger either their own or others’ health and safety Cooperate with their employer, fellow works, contractors and other dutyholders CDM Notification Requirements Construction Projects are notifiable to the Health and Safety Executive when they are scheduled to: a Last longer than 30 working days and have more than 20 workers on site simultaneously at any point in the project; or when b Exceed 500 person days Note: a person day equates to an 8 hour shift. 4 Gary Morton – October 2015 3.1 Where a project is notifiable, the client must give notice in writing to the Health and Safety Executive as soon as is practicable before the construction phase begins. The Client is responsible for notifying projects to the Health and Safety Executive (as soon as practicable before construction work begins). In practice at Newcastle University the ESS Project Manager will inform the Client (budget holder) of their responsibilities as a named Duty Holder in the CDM Regulations and assist them in completing the F10 Notification form, click here to complete the online interactive form 3.2 The notice must contain the following particulars: 3.3 The notice additional requirements 3.4 The date of forwarding the notice. The precise address of the construction site. The name of the local authority where the construction site is located. A brief description of the project and the construction work that it entails. The following contact details of the client: name, address, telephone number and (if available) an email address. The following contact details of the principal designer: name, address, telephone number and (if available) an email address. The following contact details of the principal contractor: name, address, telephone number and (if available) an email address. The date planned for the start of the construction phase. The time allocated by the client under regulation 4(1) for the construction work. The planned duration of the construction phase. The estimated maximum number of people at work on the construction site. The planned number of companies working on the construction site. The name and address of any contractor already appointed. The name and address of any designer already appointed. A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations. The notice must be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work. Periodically update the notice as necessary. Retrospective Notifications eg project extension If a construction project is not notifiable at first, but there are subsequent changes to the scope of work so that it triggers the criteria for notification. The Client must then notify the work to the relevant enforcing authority as soon as possible. Note: The ESS Representative for the project will complete the retrospective notification with their University Client 5 Gary Morton – October 2015 4.0 Client Responsibilities The Client has one of the biggest influences over the way a project is ran and therefore they are accountable for the impact their approach has on the health and safety of those working on, or affected by the project. 4.01 4.1 The ESS Representative responsible for managing construction work must make the University Client aware of their responsibilities as a key duty holder in CDM. The client must then complete the Newcastle University CDM Client Form here (all projects including non-notifiable projects). Clients must make suitable arrangements for managing projects, including allocating sufficient time and other resources so that work can be carried out safely. Arrangements are suitable if they ensure that: a Construction work can be carried out, so far as is reasonably practicable, without risks to the health or safety of any person working on or otherwise affected by the project b Suitable welfare facilities are provided in respect of any person working on the project. c Clients must ensure that these arrangements are maintained and reviewed as necessary throughout the project. The ESS Representative for the project will monitor the adequacy of the contractors’ arrangements by ensuring the site is inspected in accordance with ESS Arrangements for Workplace Inspections and when attending site for routine progress meetings. d Clients must provide pre-construction information as soon as is practicable to every Designer and Contractor/Principal Contractor appointed, or being considered for appointment, to the project. Further to ensuring suitable arrangements are in place the Client is also responsible for ensuring all duty holders fulfil the requirements of their roll In practice the ESS Representative for the project is responsible for locating and providing preconstruction information on behalf of the Client. 4.2 Appointing the Project Team Clients must ensure that: The health and safety competence of all appointments is assessed, in doing this ESS Use the assessment process identified in ESS Management of Contractors. 6 Gary Morton – October 2015 Appointments are made as soon as is practicable and in any event before construction work starts. (Until such time as appointments are made the Client takes on all duty holder responsibilities) Contractors/Principal Contractors/Principal Designers Where there is more than one contractor (company), or if it is reasonably foreseeable that there will be more than one contractor (company) on site during a project a Principal Contractor (PC) and Principal Designer (PD) must be appointed in writing. A Principal Designers letter of appointment can be found in Appendix 5 Failure to appoint a PC or PD will result in the Client taking on all PC/PD responsibilities/duties as identified in the Regulations. 4.3 Pre-Construction Information Pack The Client has the main duty for providing pre-construction information. This information relates to existing buildings and/or land and must be provided as soon as practicable to each Designer (including the PD) and Contractor (including the PC) who is bidding for, or already been appointed to work on the project. The ESS Representative for the project will assemble the Pre Construction Information Pack using the Pre Construction Information Template (see Appendix 3) 4.4 Construction phase Plan Clients must ensure that: Principal Contractors/Contractors have a suitably developed Construction Phase Plan on site before work is permitted to start. Note: The ESS representative responsible for the project will review the plan and only authorise work to start when they are satisfied that the plan is appropriate for managing risks arising from work on site. In practice the ESS representative responsible for the project will print their name, sign and date the 1st page of the plan as evidence that the plan has been reviewed and that authorisation to commence work has been given. Note: Digital Signatures will also suffice. This link will take you to HSE guidance on how to compile a Construction Phase Plan you will also find an aide memoir in Appendix 1 that can be used to check the content of Construction Phase Plans. 4.5 Health and Safety File Clients must ensure a Health and Safety File is produced. 7 Gary Morton – October 2015 Health and Safety Files are used to communicate key health and safety information about the completed project to those that are going to use the building/external estate or subsequently work on the building/external estate. The Principal Contractor; and the Principal Designer must prepare a Health and Safety file for the project, and must actively monitor the development of the file throughout the project. On completion of the project the Principal Designer will ensure the health and safety file is handed over to the Head of Maintenance (or Legislative Compliance and Contracts Manager) at Newcastle University and that a receipt for the file is received. Note: Health and Safety files must follow Newcastle University’s standard format. (See Appendix 2) 8 Gary Morton – October 2015 5.0 Designer Duties Designers must ensure the Client is aware of their duties under the CDM Regulations. When preparing or modifying a design the designer must take into account of the principles of prevention (appendix 7) and any pre-construction information to eliminate, so far as is reasonably practicable, foreseeable risks to the health or safety of any person: Carrying out or likely to be affected by construction work Maintaining or cleaning a structure Using a structure as a workplace If it is not possible to eliminate risks, the designer must, so far as is reasonably practicable: Take steps to reduce or, if that is not possible, control the risks through the subsequent design process Provide information about those risks to the principal designer Ensure appropriate information is included in the health and safety file. Designers must take all reasonable steps to provide, with the design, sufficient information about the design, construction or maintenance of the structure, to adequately assist the Client, other designers and contractors to comply with their duties under the CDM Regulations. 5.1 Arrangements for Internal Design Development at Newcastle University All persons carrying out Design Development at Newcastle University for projects relating to the Estate must ensure that the Principal Designer where appointed to the project is requested to review the design proposal prior to it being issued. 5.3 To aid Designers when assessing risks associated with design Red Amber and Green lists are provided in Appendix 4 6.0 Principal Designers (PD) Duties Principal Designers Must: Liaise with the Principal Contractor for the duration of their appointment. Hold regular progress meetings with the Principal Contractor. Share information on anything that could affect the project with the Principal Contractor, in particular: Information required for the development of the Construction Phase Plan Risks which have not been eliminated in the designs and the means to be used to reduce or control risks Safety critical design information 9 Gary Morton – October 2015 6.1 Newcastle University Internal Arrangements for Principal Designer Newcastle University Estate Support Service will maintain access to the necessary key competencies, skills and experience ‘in house (or with assistance from consultants) that enables the ‘Organisation’ to fulfil the role of ‘Principal Designer’. Important: While an individual may be required to ‘lead’ on the Principal Designer role collating pre-construction information, monitoring the progress of the Health and Safety File, reviewing designs it is essential that the designated lead recognises the limitations of their own competency and seeks the knowledge, skills and experience from colleagues/consultants as necessary. In practice this means having colleagues from ESS/OHSS/or specialist review design proposals/drawings and providing advice/comments. 7.0 Contractors/Principal Contractors Duties A Principal Contractor must be appointed in writing and fulfil all duties as identified below when there is more than one contractor (company) working on a project at the same time. This is regardless of the duration of the works or whether or not the project triggers HSE Notification requirements. Note: Principal Designer must also be appointed. The principal contractor must plan, manage and monitor the construction phase and coordinate matters relating to health and safety to ensure that, so far as is reasonably practicable, construction work is carried out without risks to health or safety, this includes: When assessing and managing work take account of the principles of prevention (Appendix 7) Liaising with the Client, Principal Designer and Designer Preparing a Construction Phase Health and Safety Plan Working with the Principal Designer to provide the Health and Safety File Assessing the competence of subcontractors, plan, organise and coordinate the work they do and ensure they cooperate with one another Providing suitable site inductions taking into account Newcastle University’s induction procedures Provide adequate supervision and monitor the health and safety performance of all employed on the site Ensure adequate resources are afforded to the project Ensuring the site is secure and unauthorised access is prevented Consulting with all workers regarding matters that affect their health and safety Providing suitable and adequate welfare provision 7.1 ESS Representatives Acting as Principal Contractor In some instances ESS Representatives (Maintenance/Improvements Team Operatives) may take on the role of Principal Contractor coordinating small scale, short duration low risk jobs(these jobs must not trigger the HSE Notification Requirements) . In all such cases 10 Gary Morton – October 2015 the ESS representative will risk assess the project and take advice from their line manager prior to commencement of work. Arrangements For Construction Phase Health and Safety Plan The ESS Representative will create a file that will be used to hold all documents relating to the project including: A scope of works A programme for the work Ensure all contractors have been inducted as per ESS Contractor Induction requirements and that a local site specific induction has been carried out (page 20 in the induction booklet) Provide all contractors with site specific information about hazards present at the work location eg asbestos pre refurbishment survey/mechanical and electrical plans Identify a suitable location for welfare facilities and site storage Collate and review all subcontractors risk assessments/method statements/COSHH assessments etc Alternatively you may use this template produced by HSE Construction Phase Plan for small projects (CDM 2015) - CIS80 Maintenance Team Client Arrangements The Head of Maintenance as the strategic budget holder will be named as client for all such works. 11 Gary Morton – October 2015 Appendix 1 Construction Phase Plan - Aide Memoir Format and Content Important Construction Phase Plans are required for all construction work involving more than one contractor (company). Employer and Design Team information and requirements as contained within the PreConstruction Information must be fully taken into account in the preparation of the Construction Phase Plan. This must be submitted to the Client (ESS Representative for the project) for consideration. Only when the ESS Representative is satisfied that the plan has sufficient information contained within it to ensure the health and safety of those carrying out the work, and/or those that could be affected by the work, will the plan be accepted and the start of work approved. The ESS Representative for the project will then sign and date the 1st page of the plan as proof the plan has been approved. No works shall commence until the Contractor has received confirmation that the plans content has been approved by the Client (ESS Representative). The following items are those to be included (as necessary), within the Construction Phase Plan. Construction Phase Plan Content Introduction Project Description Programme Health and Safety Policy (Statement of Intent only, not the entire document) Project Directory, including site team and responsibilities Health and Safety Objectives for the Project Means of Monitoring Performance Scope of Work 12 Gary Morton – October 2015 Significant risks as identified Project Arrangements Access/Egress Security/Signage Waste disposal Deliveries and material storage Welfare/facilities i.e. (toilets, washrooms, changing and drying facilities, hot and cold running water, the ability to heat food and boil water) First Aid Emergency Procedures Power and water provision Parking Personal protective equipment (PPE) Temporary works Electrical works-temporary supplies-isolation procedures Testing procedures Sequence of works/programme Permits to work Induction procedure Workforce consultation Liaison Design changes Subcontractor selection 13 Gary Morton – October 2015 Subcontractor information dissemination procedures Risk control ‘Toolbox Talks' Monitoring and consultation procedures Risk, CoSHH, Noise and Manual Handling Assessments as applicable. (Added when produced and throughout the contract period). Method Statements for all major elements. These to include, where relevant, but not be limited to: Temporary works : façade retention; shoring- heavy timber ; steel frames; hoarding; scaffold; formwork etc; Waste removal; Existing services- especially buried; Building fabric cleaning [ any method ]; Major glass/window removal; Asbestos removalencapsulation; Dismantling and removal of materials Lifting Operations including hoists gin-wheels and cranage; Emergency Contacts: name/ contacting details Site Rules[To take into account the] Fire /emergency plan[ Must not compromise any existing arrangements] 14 Gary Morton – October 2015 15 Gary Morton – October 2015 Appendix 2 Estate Support Service Health and Safety File Template 16 Gary Morton – October 2015 1. Introduction The Principal Designer as one of their duties is responsible for the collation and final preparation of the Health & Safety File. The format will be developed around the following requirements. Information for the file should be provided throughout the duration of the construction phase and not left until practical completion. Information for the File is to be provided in electronic format only (3 copies) with drawings to be provided in PDF and CAD versions. The University model for the Health & Safety File incorporates the O&M information and is required to be site specific and provide only that information applicable to the project, not manufactures catalogues and the like. It is recommended that the principal contractor and design team make themselves familiar with format and the need to assimilate information throughout the design and construction phase in order to present the completed file to the client at the end of the construction phase of the specific phase of the works. The layout and content for the section of O&M information should comply with all sections of BISRIA BG1/2007 see below for the proposed Health and Safety File Format This File provides an executive summary of the significant health and safety information relating to this project. This information will be passed to the client upon completion of the construction stage of the project (or as soon as practicable thereafter). The File and the information referred to within it aim to assist any persons involved in later use, maintenance, future construction work and eventual deconstruction. 2. Duties of the Client It is the duty of the client, to contribute, and provide information for the Health and Safety File; It is the duty of the client to keep and maintain the Health and Safety File for future reference and make available to those required to carry out work on the structure; It is the duty of the client to pass the Health and Safety File on to any other person who acquires an interest in the structure. 3. Format The documentation has been supplied in the following format: No hard copy/copies of information. 3 CD Read Only format as a record of the completed structure and 1 DVD RW in a format which will allow the information to be modified and take into account future works. 4. General Note Whereas certain basic information must always be included, in order to manage the size of this file, reference has been made to the location of relevant documents supplied by the Client, Designers and Principal Contractor. 17 Gary Morton – October 2015 1.0 General Information 1.1 Location Information 1.2 Description of the Works 18 Gary Morton – October 2015 1.3 Project Directory Project Sponsor/Client contact details Designer’s contact details Principal Contractor contact details Principal Designer Contact details Project Engineer/Project Surveyor Contact Details Stakeholders and Neighbours Contact Details Security Control and ESS Health and Safety Contact Details 1.4 General contract details, end of maintenance period date. 19 Gary Morton – October 2015 1.5 Consents - Building Regulation Approval; Fire Certificates; Practical Completion Certificate etc. 1.6 Health & Safety – Residual Risks and Hazards 1.7 Existing Surveys 1.8 Utilities and Services 1.9 Emergency Procedures 1.10 Cleaning and Maintenance 2.0 Building Fabric and Structure 20 Gary Morton – October 2015 2.1 Elemental Breakdown (Common Arrangement of Work Sections) Methods and materials which present residual risk in respect of cleaning, maintenance, modification or demolition 2.2 Structural Design 2.3 Fire Safety Strategy 3.0 Building Services (The following may be separate Files provided by the Specialist Subcontractors; each File to be broken down to cover each relevant building service/element.) 3.1 Electrical 3.2 Mechanical 3.3 Lifts 3.4 Specialist 3.5 Statutory Authorities; Incoming / outgoing services 3.6 Test Certificates 21 Gary Morton – October 2015 4.0 As Built Information (Drawings to be checked and marked as built) 4.1 Architects Drawings 4.2 Structural Drawings 4.3 Structural Safe Loads 4.4 Electrical Services Drawings 4.5 Mechanical Services Drawings 4.6 Plumbing Services Drawings 4.7 Specialist Services Drawings 4.8 Incoming Services & Utilities 4.9 Site Investigations and Surveys 4.10 Designers Risk Assessments/Considerations 22 Gary Morton – October 2015 4.11 Fabric & Finishes Layouts & Floor Plans 5.0 Health & Safety Generally 5.1 Construction Methods used 5.2 Materials used 5.3 Access Arrangements/ confined spaces 5.4 Location of drainage and terminations 5.5 Emergency procedures (including Fire escape strategy etc.) 5.6 Safe working loads 5.7 Residual Design Risk 5.8 General schedule and maintenance information; 23 Gary Morton – October 2015 6.0 Cleaning and user guide 6.1 User Guide Notes 6.2 Cleaning Instructions and Guide 6.3 Permit to Work Systems 6.4 Manufacturer’s Instructions The layout and content of the O & M’s should comply with all sections of BISRIA BG1/2007 Sections 2, 3 & 4. 1 electronic copy 24 Gary Morton – October 2015 Appendix 3 Estate Support Service Pre Construction Information Template 25 Gary Morton – October 2015 Contents 1.00 Description of Project 1 2.00 Clients Considerations and Site Rules 3.00 Environmental Restrictions and Existing On-Site Risks 4.00 Significant Design and Construction Hazards 26 Gary Morton – October 2015 1. Description of the Project 1.1 Location of the Project 1.2 Nature of the Project 1.3 Scope of Works 1.4 Project Dates Start Date: End Date: 1.5 Pre - Construction Information (Drawings, Surveys, Site Rules, Hazards etc) 27 Gary Morton – October 2015 1.6 Project Directory Project Sponsor/Client contact details Designer’s contact details Principal Contractor contact details Principal Designer Contact Details Project Engineer/Project Surveyor Contact Details Stakeholders and Neighbours Contact Details Security Control and ESS Health and Safety Contact Details 28 Gary Morton – October 2015 2. Client Considerations and Site Rules 2.1 Workplace Transport including access and parking restrictions 2.2 Client Permit to Work Systems 2.3 Fire Precautions 2.4 Emergency Procedures 2.5 Confined Spaces 2.6 Risk Assessment 2.7 Smoking restrictions 2.8 Environmental Restrictions and On Site Risks 2.9 Environmental Risks/Waste Disposal 2.10 Utility Services 2.11 Security 2.12 Work outside normal hours 2.13 Access to buildings 2.14 Newcastle University ESS Contractors Induction Booklet 3. Significant Design and Construction Risks 29 Gary Morton – October 2015 3.1 Design Risks Designers must be aware of their responsibilities in accordance with CDM – So far as is reasonably practicable risks arising through design and associated with the Buildability, Useability and Maintainability of a project should be; eliminated, reduced and or controlled 3.3 Summary of Significant Risks and Hazards associated with this project Asbestos containing materials Occupied Site High level access for construction and maintenance issues Manual handling and material distribution Working within existing and occupied buildings Traffic management Working on existing service installations Slips trips and falls Interface with existing private and public access routes Site Housekeeping and welfare arrangements Falls from height Access for future maintenance and subsequent life of the project Maintaining and providing escape and evacuation routes Work in Labs 4. Materials Requiring Special Precautions e.g. Radiation Appendix 4 Designers Red Amber Green Lists 30 Gary Morton – October 2015 Red Lists: Hazardous procedures, products and processes that should be eliminated from the project where possible • Lack of adequate pre-construction information, eg asbestos surveys, geology, obstructions, services, ground contamination etc. • Hand scabbling of concrete (‘stop ends’, etc); • Demolition by hand-held breakers of the top sections of concrete piles (pile cropping techniques are available); • The specification of fragile rooflights and roofing assemblies; • Processes giving rise to large quantities of dust (dry cutting, blasting etc.); • On-site spraying of harmful substances; • The specification of structural steelwork which is not purposely designed to accommodate safety nets; • Designing roof mounted services requiring access (for maintenance, etc), without provision for safe access (eg. barriers). • Glazing that cannot be accessed Safely, All glazing should be anticipated as requiring cleaning and replacement, so a safe system of access is essential. • Entrances, floors, ramps, stairs and escalators etc not specifically designed to avoid slips and trips during use and maintenance, including effect of rain water and spillages. • Design of environments involving adverse lighting, noise, vibration, temperature, wetness, humidity and draughts or chemical and/or biological conditions during use and maintenance operations. • Designs of structures that do not allow for fire containment during construction Amber Lists: Products, processes and procedures to be eliminated or reduced as far as possible and only specified/allowed if unavoidable. Including amber items would always lead to the provision of information to the Principal Contractor. 31 Gary Morton – October 2015 • Internal manholes / inspection chambers in circulation areas; • External manholes in heavy used vehicle access zones; • The specification of “lip” details (i.e. trip hazards) at the tops of pre-cast concrete staircases; • The specification of shallow steps (i.e. risers) in external paved areas; • The specification of heavy building blocks i.e. those weighing > 20kgs; • Large and heavy glass panels; • The chasing out of concrete / brick / blockwork walls or floors for the installation of services; • The specification of heavy lintels (the use of slim metal or hollow concrete lintels being alternatives); • The specification of solvent-based paints and thinners, or isocyanates, particularly for use in confined areas; • Specification of curtain wall or panel systems without provision for the tying (or raking) of scaffolds; • Specification of blockwork walls >3.5 metres high using retarded mortar mixes. 32 Gary Morton – October 2015 Green Lists: Products, processes and procedures to be positively encouraged. • Adequate access for construction vehicles to minimise reversing requirements (oneway systems and turning radii); • Provision of adequate access and headroom for maintenance in plant rooms, and adequate provision for replacing heavy components; • Thoughtful location of of mechanical / electrical equipment, light fittings, security devices etc. to facilitate access and away from crowded areas; • The specification of concrete products with pre-cast fixings to avoid drilling; • Specify half board sizes for plasterboard sheets to make handling easier; • Early installation of permanent means of access, and prefabricated staircases with hand rails; • The provision of edge protection at permanent works where there is a forseeable risk of falls after handover; • Practical and safe methods of window cleaning (eg. from the inside); • Appointment of a Temporary Work Coordinator (BS 5975); • Off-site timber treatment if PPA- and CCA-based preservatives are used (Boron or copper salts can be used for cut ends on site). • Off site fabrication and prefabricated elements to minimize on site hazards. • Encourage the use of engineering controls to minimize the use of Personal Protective Equipment For further examples of safe design practice go to the Safety In Design webpages http://www.safetyindesign.org.uk/design-guides Appendix 5 33 Gary Morton – October 2015 Principal Designers Schedule of Services Project: Location: The summary of services below are requirements from the Duties placed on Principal Designers by the CDM Regulations. The Guidance to the Regulations will be used as further clarification as necessary. 1 Cooperate with any all persons working on the project or on sites adjacent to it. 2 Plan, manage and monitor the pre-construction phase arrange and facilitate health and safety design review meetings, take minutes and provide copies of minutes to all stakeholders including the Client and Design Team. 3 Produce a list of Pre- Construction Information required for the project and provide a copy to the Client. Receive and collate Pre-Construction Information and circulate copies to all Designers, Contractors/ Principal Contractors without delay. 4 Review all designs, produce a design risk register and circulate copies to the Client and Design Team. 5 Ensure that designers comply with their duties and apply the general principles of prevention 6 Identify and eliminate or control, so far as is reasonably practicable, foreseeable risks to the health and safety of any person o Carrying out or liable to be affected by construction work o Maintaining or cleaning a structure o Using a structure designed as a workplace. 8 Ensure all parties working on the Pre-Construction Phase cooperate with one another and report any issues should they arise to the Client at the earliest opportunity. 9 During the Construction Phase the Principal Designer will facilitate design review meetings with the Principal Contractor and all Designers involved in the ongoing design for the project 10 Lead on the preparation of the Health and Safety File (with assistance from the Principal Contractor) throughout the Construction Phase to ensure it is developed according to the works programme and reflects progress/changes on site. Ensure the Health and Safety File is prepared in accordance with Newcastle University format. 34 Gary Morton – October 2015 Ensure three copies of the Health and Safety File are provided to the Client at Practical Completion. 11 Assist the Principal Contractor in preparing the Construction Phase Plan by providing all information held that is relevant to the project including PreConstruction Information obtained from the Client and any information received from Designers. Signature …………….……. Principal Designer Date……………….. Signature …………………… Client Date………………. 35 Gary Morton – October 2015 Appendix 6 Principal Designer Scope of Service This scope of service has been prepared to outline the duties and outputs required by a Principal Designer Appointed by Newcastle University Estates Support Service. All staff and appointed consultants are to comply both with the requirements and spirit of the Construction (Design & Management) Regulations and associated guidance together with CDM 2015 ESS Arrangements. Feasibility Stage PD Appointment made at this early stage will allow an Initial Risk Register to be developed that includes reference to site-wide elements, the location of the scheme, and an identification of the key areas of risk that should be incorporated into concept design. This will also allow more accurate cost evaluation when conducting feasibility. Principal Designer Responsibilities Output Measure Receive and review preliminary information Meeting with Client to Notes of relating to the projects aims and objections discuss headline meetings objectives Where projects exceed the CDM notification requirements ie 30 days and more than 20 persons on site simultaneously or 500 person days Review existing pre construction information and identify further information required to allow further planning to be effective F10 Notification submitted by Client Written copy received and hard copy filed Produce information register and outline risk register Liaise with Project Team to identify headline risks associated with project during feasibility. Communicate key risks to other Duty Holders within Project Team. Headline Project Risk Register developed Establish Design Coordination Meeting Schedule, list of attendees and terms of reference. Issue meeting schedule and TOR to all attendees Additional surveys identified and costs allocated Project Risk Register to be retained by Client Evidence of communication of initial risk register (e.g. risk workshop) Provide copy to Client Principal Designer Responsibilities As above Design Stage Output Measure 36 Gary Morton – October 2015 Review initial designs and produce findings report on adequacy of Fire, Health and Safety elements of the design Report/notes produced and issued to all project stakeholders Copy of report/notes retained by Client Principal Designer Responsibilities Ensure adequate liaison with other stakeholders to ensure designs are reflective of key Fire Health and Safety elements of their operational requirements Attendance Design Team Meetings Output Design Review Meeting (chaired by PD) Review of Design Access and Maintenance strategies Produce access and maintenance review report/notes and circulate to all key stakeholders. Any required actions agreed and allocated via Estate Support Service Design Risk Register (DRR) to be reissued as significant revisions occur Measure Minutes of Meeting to be forwarded to Client Number of meetings attended commensurate to the scope and complexity of the project. Formal schedule of attendance to be agreed and monitored. All identified actions to be closed out. Continue development of Project Design Risk Register to reflect design development Develop initial inventory of information required for H&S File. Input to design development Initial Index for Health Safety and Fire agreed and issued to all stakeholders. Report retained by Client. Latest version DRR to be retained by Client DRR to be reviewed at all Design Team Meetings. Index to be presented at PreStart meeting. 37 Gary Morton – October 2015 Pre Construction Prepare Pre-Construction Information (PCI) PCI Index and for tender and then use by Principal Folder Contractor (PC) Facilitate Risk Workshop liaising with Project Team and PC to identify key risks arising from Construction, Maintenance, Cleaning and Use Liaise with Client to agree performance monitoring strategy for Construction Phase. Update Project Risk Register following Risk Workshop PCI Index and Folder issued to Designers and PC and copy retained Client. PCI should be issued in sufficient time to allow the PC to effectively plan, resource and cost the project. Minutes of Risk Workshop should be reflected in the Risk Register being updated to incorporate additional construction risks. Establish, agree and monitor KPI’s based upon expectations. Health and Safety inspection plan agreed for each This to include a Pre-Start Site Check-up scheme in writing. and periodic health & safety monitoring by a Audits to be Client Representative. provided to CIR with any recommendations closed out On a monthly basis provide CDM Report Completion of given CIR to monitor identifying key activities, meetings attended proforma providing production of monthly and report of identification of potential report to CIR. report in line with design issues. agreed KPI’s and to retain completed proformas Attend Pre-Start Meeting and confirm that all Pre-Start Meeting PD input at pre-start key FHS considerations have been minutes. recorded in minutes. identified, eliminated or controlled so far as is reasonably practicable. Preparation and revision of H&S File with H&S File any File will have been PC and provide any information available to available commenced at Precommence population. Define H&S file. information Start (and confirmed as populated on an such in minutes) ongoing basis. Formally write to the CIR to confirm the Written Formal evidence of adequacy of the Construction Phase Plan Correspondence. CPP review and and the Pre-start Site Check-up. inspection retained by the CIR. 38 Gary Morton – October 2015 Appendix 7 Principles of Prevention These principles are a requirement of the Management Regulations and apply to all industries, including construction. They provide a framework to identify and implement measures to control risks on a construction project. The general principles of prevention are to: (a) Avoid risks; (b) Evaluate the risks which cannot be avoided; (c) Combat the risks at source; (d) Adapt the work to the individual, especially regarding the design of workplaces, the choice of work equipment and the choice of working and production methods, with a view, in particular, to alleviating monotonous work, work at a predetermined work rate and to reducing their effect on health; (e) Adapt to technical progress; (f) Replace the dangerous by the non-dangerous or the less dangerous; (g) Develop a coherent overall prevention policy which covers technology, organisation of work, working conditions, social relationships and the influence of factors relating to the working environment; (h) Give collective protective measures priority over individual protective measures; and (i) give appropriate instructions to employees. 39