Material Requirement Planning is very useful in following situations
Correct Answer Long Lead time for procurement , Several levels of assemblies in
product , Long manufacturing cycle
Your Answer
Long Lead time for procurement , Several levels of assemblies in
product , Long manufacturing cycle
Select The Blank
Question
The ________ is specified to indicate the maximum permissible
variability in the dimensions product or parts.
Correct Answer Tolerance
Your Answer
Standard
Select The Blank
Question
An ________ history card is the record of all repairs, replacements and
engineering changes carried out in the equipment during it's period of
service.
Correct Answer Equipment history card
Your Answer
Equipment history card
Multiple Choice Single Answer
Question
What can be the worst effect due to excessive vibration?
Correct Answer Breakdown
Your Answer
Breakdown
Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of making any
product/s is called
Correct Answer Factory
Your Answer
Factory
Multiple Choice Single Answer
Question
How dummy activities are shown in the time chart during project
scheduling?
Correct Answer Vertical lines
Your Answer
Vertical lines
Multiple Choice Single Answer
Question
Which of the following technique makes three time estimates for each
activity?
Correct Answer Project Evaluation & Review Technique
Your Answer
Project Evaluation & Review Technique
True/False
Question
Expediting action is necessary if the delays and interruptions are
abnormal and hence any subsequent delay is bound to extend the
promised delivery date.
Correct Answer True
Your Answer
True
Multiple Choice Multiple Answer
Question
Which features should be covered by the specifications of materials
while defining the qualitative requirement?
Correct Answer Material composition , Dimensions , Any heat treatment if required
Your Answer
Material composition , Dimensions , Any heat treatment if required
True/False
Question
Limit gauges are not useful when it is necessary to measure the exact
amount of variation.
Correct Answer True
Your Answer
False
Select The Blank
Question
The ________ is the defect level for which lots are regarded as bad
lots.
Correct Answer Lot Tolerance Percentage Defective
Your Answer
Lot Tolerance Percentage Defective
Multiple Choice Single Answer
Question
Technique of Value Engineering can be effectively employed in design
of a product to
Correct Answer To meet the intended function at lowest cost
Your Answer
Increase resourse utilization
Multiple Choice Single Answer
Question
What do you mean by the preventive maintenance by using five human
senses?
Correct Answer Preventive inspection
Your Answer
Sensitive inspection
Multiple Choice Multiple Answer
Question
Which of the following are typical examples of limit gauges?
Correct Answer Snap gauge , Plug gauge , Ring gauge
Your Answer
Snap gauge , Plug gauge , Ring gauge
Multiple Choice Multiple Answer
Question
Which are the major types of defects?
Correct Answer Minor , Major , Critical
Your Answer
Major , Critical
Match The Following
Question
Correct Answer
Your Answer
Emerson Efficiency Plan
Wage Payment
Facilities Planning
Craft
Facilities Planning
Production Scheduling
Work Sampling
Machine utilization
Sampling Inspection
Gantt Chart
Production Scheduling
Charting technique
Select The Blank
Question
The ________ is the maximum percentage defective that for the
purpose of sampling inspection can be considered satisfactory as a
process average.
Correct Answer Acceptable quality level
Your Answer
Acceptable quality level
Multiple Choice Single Answer
Question
A good plant layout helps in
Correct Answer Reducing handling costs
Your Answer
Reducing handling costs
Multiple Choice Multiple Answer
Question
Which of the following charts are used for the recording of data during
the method study?
Correct Answer Operation process chart , Multiple activity chart , Flow process chart
Your Answer
Operation process chart , Multiple activity chart , Flow process chart
Multiple Choice Single Answer
Question
What do you mean by the selection of the job for the method study on
the basis of manufacturing difficulties?
Correct Answer Technical consideration
Your Answer
Human consideration
True/False
Question
An activity can share the same tail event and same head event with any
other activity.
Correct Answer False
Your Answer
False
Select The Blank
Question
The ________ is the probability that a good lot will be rejected by the
sampling plan.
Correct Answer Producer's risk
Your Answer
Producer's risk
Multiple Choice Single Answer
Question
Inadequate production capacity ultimately leads to
Correct Answer Poor Customer Service
Your Answer
Poor Customer Service
True/False
Question
All activities must not be tied up into the network
Correct Answer False
Your Answer
True
Multiple Choice Single Answer
Question
Technique which can help an organization to reduce inventory is called
Correct Answer MRP
Your Answer
True/False
CPM
Question
Dust gets mixed with lubricants, forms an abrasive substance and
causes pre-mature failure of machinery.
Correct Answer True
Your Answer
True
Multiple Choice Multiple Answer
Question
Which of the following situations demand the technical consideration
while selecting a job for method study?
Correct Answer Jobs having inconsistent quality , Operations inviting frequent requests
from supervisors for relaxation in allowed time because of variations in
materials and tool performance , Jobs in which too many man-hours are
spend in checking and rechecking work
Your Answer
Jobs having inconsistent quality , Operations inviting frequent requests
from supervisors for relaxation in allowed time because of variations in
materials and tool performance , Jobs in which too many man-hours are
spend in checking and rechecking work
Multiple Choice Multiple Answer
Question
Which of the following are examples of attributes?
Correct Answer Cracks , Burrs , Texture
Your Answer
Cracks , Hardness , Burrs
Select The Blank
Question
In case of an OC curve, the risk of rejecting a good quality lot may vary
between ________.
Correct Answer 0.01 to 10%
Your Answer
0.01 to 10%
Select The Blank
Question
The ________ must ensure that the product satisfy the functional
requirements of it's usage.
Correct Answer Quality of design
Your Answer
Quality of inspection
True/False
Question
Delay in completion of projects result in unwelcome additions to the
fixed manufacturing expenses.
Correct Answer True
Your Answer
True
Multiple Choice Multiple Answer
Question
Which of the following activities are used while recording for method
study?
Correct Answer Delay , Operation , Inspection
Your Answer
Delay , Operation , Inspection
True/False
Question
Root cause of most of the breakdowns is failure of the lubrication
system.
Correct Answer True
Your Answer
True
Select The Blank
Question
The term ________ emplies the foregone profit due to inability of
company to produce.
Correct Answer Opportunity cost
Your Answer
Opportunity cost
True/False
Question
Latest finishing date is the latest event time of the tail event.
Correct Answer False
Your Answer
False
Multiple Choice Multiple Answer
Question
What is the basic minimum requirement for those who are responsible
for the quality of design?
Correct Answer In depth knowledge about alternative materials and manufacturing
processes , access to latest technology and production process
adopted by industries in the developed market , Continuous effort in
product development
Your Answer
In depth knowledge about alternative materials and manufacturing
processes , access to latest technology and production process
adopted by industries in the developed market , Continuous effort in
product development
True/False
Question
If the firm has adopted elaborate planned maintenance system, there is
no chance of any unplanned maintenance work.
Correct Answer False
Your Answer
False
Multiple Choice Multiple Answer
Question
Which of the following is not the characteristic of Project Production?
Correct Answer Continuous flow of material , Highly mechanised material handling ,
Virtually zero manufacturing cycle time
Your Answer
Continuous flow of material , Highly mechanised material handling ,
Virtually zero manufacturing cycle time
Multiple Choice Single Answer
Question
Which document is used for returning the surplus material?
Correct Answer Stores Return Note
Your Answer
Stores Return Note
Select The Blank
Question
Work study is also called ________ study
Correct Answer Time and Motion
Your Answer
Time and Motion
Match The Following
Question
Correct Answer
Your Answer
Factor Analysis
Method to evaluate layouts
Method to evaluate layouts
Minimization of production
delays
Objective of good layout
Objective of good layout
Maximum visibility
Principles of good layout
Principles of good layout
Scale model
Layout analysis
Layout analysis
Multiple Choice Single Answer
Question
The process of changing inputs into outputs thereby adding some value
to entity can be defined as
Correct Answer Operation
Your Answer
Operation
Multiple Choice Single Answer
Question
What does the additional cost incurred to reduce the duration of an
activity by one unit of time represent?
Correct Answer Activity cost slope
Your Answer
Activity time slope
Select The Blank
Question
Production control work is ________ in case of floor inspection as
compared with the centralised inspection.
Correct Answer easier
Your Answer
easier
Select The Blank
Question
One detachable ticket is prepared for each ________.
Correct Answer Operation
Your Answer
Operation
Multiple Choice Single Answer
Question
The ratio of output to input of a production system is commonly known
as
Correct Answer Productivity
Your Answer
Productivity
Multiple Choice Single Answer
Question
Which of the following policies is advisable in case of low product
variety and large volumes?
Correct Answer Low Skilled Labour & Special Purpose Machines
Your Answer
Low Skilled Labour & Special Purpose Machines