LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question Which are major benefits of identifying the critical path? Correct Answer Your Answer It identifies activities to be given preference in allocation of resources. , It helps to exercise "control by exception". , It helps to identify the set of activities and events which are critical and as such must be carefully controlled and monitored It helps to identify the set of activities and events which are critical and as such must be carefully controlled and monitored , It identifies activities to be given preference in allocation of resources. , It helps to exercise "control by exception". Select The Blank Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL . Correct Answer Rectangular Your Answer Bell Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Lot Tolerance Percentage Defective Multiple Choice Single Answer Question Why method study should precede work measurement? Correct Answer Time for a job can be accessed accurately only after standardizing the method Your Answer Time for a job can be accessed accurately only after standardizing the method Select The Blank Question Correct Answer The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies. Reconditioning Your Answer Reconditioning Multiple Choice Single Answer Question Which of the following is the most popular technique for Project Production? Correct Answer PERT & CPM Your Answer Break Even Analysis True/False Question In case of backward pass computation, the latest event time of the end event equals to the earliest event time minus duration of that activity. Correct Answer False Your Answer True Match The Following Question Correct Answer Your Answer Draining and refilling of oil reserviors of plunger pump Yearly Hourly Parts lubricated with oil nipple Daily Weekly Tools and slideways two to three times a day Six monthly Table lubrication Weekly two to three times a day Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Answer Unexpected Your Answer Unexpected Multiple Choice Single Answer Question What is expected from stores department after they receive the stores issue order from dispatcher? Correct Answer Keep material ready for issue to shop when authorized Your Answer Keep material ready for issue to shop when authorized True/False Question Every network does not necessarily have a critical path. Correct Answer False Your Answer False Multiple Choice Multiple Answer Question Which are the subfactors of community facilities or social infrastructure? Correct Answer Accomodation , Educational , Entertainment Your Answer Accomodation , Labour laws , Educational , Entertainment Multiple Choice Single Answer Question One of the following is not a gross material Correct Answer cotton Your Answer Coal Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Answer Lot Tolerance Percentage Defective Your Answer Producer's risk Multiple Choice Multiple Answer Question Which of the following are types of non-destructive testing? Correct Answer Visual Testing , Eddy current , Magnetic flow detectors Your Answer Visual Testing , Eddy current , Magnetic flow detectors Multiple Choice Multiple Answer Question Which of the following are steps to identify the critical path in a small network? Correct Answer Compare the durations of all paths to identify the longest path. , Sum up the durations of activities along each path. , Enumerate all paths in the network and list down activities on each path. Your Answer Sum up the durations of activities along each path. , Find out the shortest path among all paths. , Enumerate all paths in the network and list down activities on each path. , Compare the durations of all paths to identify the longest path. Multiple Choice Multiple Answer Question Which of the following factors affect the quality control function? Correct Answer Quality of workmanship , Production aids , Manufacturing facilities Your Answer Quality of workmanship , Production aids , Competitive prices , Manufacturing facilities True/False Question The plotting of activities - critical, non-critical and dummy activities- is strictly according to their precedence relationship. Correct Answer True Your Answer True True/False Question Process layout is also called line layout Correct Answer False Your Answer True Multiple Choice Multiple Answer Question Which of the following three methods used to select the qualified supplier? Correct Answer By vendor plant surveys , By reputation , By experience Your Answer By vendor plant surveys , By reputation , By the perofrmance of first lot , By experience Multiple Choice Single Answer Question Which kind of relationship exists between those activities which can be carried out simultaneously and both activities require definite time to finish? Correct Answer Concurrent activities Your Answer Concurrent activities Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Necessity Your Answer Necessity True/False Question Quality can not be inspected into a product, it must be manufactured into it by the supplier. Correct Answer True Your Answer True Multiple Choice Single Answer Question What do you mean by the preventive maintenance by using five human senses? Correct Answer Preventive inspection Your Answer Manual inspection Multiple Choice Single Answer Question What do you mean by design modifications made to reduce time and effort required in carrying out maintenance work ? Correct Answer Design-in Maintenance Your Answer Design-in Maintenance True/False Question A load chart specifies the work to be carried out by each person of company during shift hours. Correct Answer False Your Answer True Multiple Choice Single Answer Question Process type layout is suitable when Correct Answer there is wide variation in processing time of operations Your Answer there is wide variation in processing time of operations Multiple Choice Single Answer Question Where the ignorance towards the degradation of machine leads to? Correct Answer Eventual breakdown Your Answer Eventual breakdown True/False Question Dispatching function is not a part of Production Planning Correct Answer True Your Answer True Match The Following Question Correct Answer Your Answer First off inspection First piece produced after tool change First piece produced after tool change Critical operation inspection After whose no rework is possible Costlier operation Patrolling inspection Inspection at the place of actual production Inspection at the place of actual production Key operation inspection Costlier operation After whose no rework is possible Multiple Choice Multiple Answer Question Which three of the following options can be used to reduce the duration of activity during project crashing? Correct Answer Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries. Your Answer Allocating more manpower and machines than originally planned for. , Conduct work study for that activity , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries. Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Lot Tolerance Percentage Defective Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.10 to 10% True/False Question Three time estimates are transformed into expected time before using it into a network. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question What is indicated by the erratic pattern points falling above and below the control limits in the Xbar-R-control chart? Correct Answer Defects in materials , Poorly trained operators , Frequent adjustments of machines Your Answer Defects in materials , Poorly trained operators , Frequent adjustments of machines , Clogging of fixtures and holes Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Preventive maintenance Multiple Choice Single Answer Question Which kind of inspection is followed in case of process layout? Correct Answer First off inspection Your Answer Pilot inspection True/False Question Latest finishing date is the latest event time of the tail event. Correct Answer False Your Answer True Multiple Choice Multiple Answer Question Following are the commonly used factors considered for evaluation of layout in factor analysis method Correct Answer Flow of material , Equipment utilization , Working condition Your Answer Flow of information , Flow of material , Equipment utilization , Working condition Multiple Choice Multiple Answer Question Why graphical method of recording is preferred over the descriptive method during method study? Correct Answer It segregates effective part form ineffective parts , It reduces effort involved in writing , Critical examinations easier and more effective Your Answer It segregates effective part form ineffective parts , It reduces effort involved in writing , It improves morale of workers , Critical examinations easier and more effective Select The Blank Question OC curve of ideal sampling plan suggests that all lots less than 3% defectives have the probability of acceptance of ________. Correct Answer One Your Answer One True/False Question Floor inspection delays the identification of faults which can not be rectified immediately before large lots are spoiled. Correct Answer False Your Answer False Multiple Choice Single Answer Question Which kind of preventive inspection detects some defects in moving parts, internal cracks, and others , when machine is under preplanned shutdown? Correct Answer Internal inspection Your Answer Internal inspection Select The Blank Question Capacity decisions have a direct influence on performance of production system in respect of ________ Correct Answer Delivery performance Your Answer Delivery performance Multiple Choice Multiple Answer Question Which of the following are illustrations of inspection? Correct Answer Physical count of incoming material against the quantity mentioned in delivery challan , A dimensional check with measuring instrument , Visual check of burrs and finish Your Answer Physical count of incoming material against the quantity mentioned in delivery challan , A dimensional check with measuring instrument , Visual check of burrs and finish , Check the operator performance Multiple Choice Multiple Answer Question Which of the following variables which operate periodically are the reasons for the cyclic pattern depicting peaks and valleys during Xbar-R control chart? Correct Answer Wornout positions , Fatigue , Roller eccentricity Your Answer Wornout positions , Intentional mistakes by unsatisfied worker , Fatigue , Roller eccentricity Multiple Choice Single Answer Question Which portion of the perforated route sheet should be signed by the operator or supervisor? Correct Answer Lower portion Your Answer Top portion