Flow process charts do record movements as well as visual pictures.
Correct Answer
False
Your Answer
False
True/False
Question
Correct Answer
The OC curve is based on the assumption that if the lot is large in comparison to
the sample, the probabilities of the OC curve will follow a poisson distribution.
False
Your Answer
True
Multiple Choice Single Answer
Question
The ratio of output to input of a production system is commonly known as
Correct Answer
Productivity
Your Answer
Productivity
Multiple Choice Multiple Answer
Question
Order preparation process for products manufatured to order requires following
documents
Correct Answer
Sales Order , Work order , Shop order
Your Answer
Select The Blank
Question
Work order , Purchase order
Correct Answer
The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Condition monitoring
Your Answer
Preventive maintenance
Match The Following
Question
Correct Answer
Your Answer
Scheduling of interrelated
activities of small projects with
consideration of uncertainty of
duration of activities.
Critical Path Analysis
Critical Path Analysis
Two machines & processing time
depends on sequence of job
loading
Johnson's Two Machine Algorithm Johnson's Two Machine Algorithm
Sufficient orders and resonable
choice of machines
Index Method
Time relationship between when a Critical Ratio Scheduling
product is required and when it
can be made available
Index Method
Time series
Select The Blank
Question
Correct Answer
Production control work is ________ in case of floor inspection as compared with
the centralised inspection.
easier
Your Answer
easier
Match The Following
Question
Correct Answer
Your Answer
When to inspect
Stages of inspection
Specification
What to inspect
Specification
Standard
How to inspect
Inspection devices
Tools & Jigs
How much to inspect
Sampling or cent percent
inspection
Stages of inspection
Multiple Choice Single Answer
Question
Material Planning is an integral part of
Correct Answer
Production Planning
Your Answer
Process Planning
Select The Blank
Question
Correct Answer
An Ideal OC curve is ________ shaped curve that accpets all the lots with quality
equal to or better than AQL .
Rectangular
Your Answer
Rectangular
Multiple Choice Single Answer
Question
Technique of Value Engineering can be effectively employed in design of a product
to
Correct Answer
To meet the intended function at lowest cost
Your Answer
Reduce lead time
Multiple Choice Single Answer
Question
Material control function of PPC is concerned with
Correct Answer
Preparation of material estimates
Your Answer
Preparation of material estimates
Multiple Choice Single Answer
Question
Main objective of a good plant layout is
Correct Answer
Reduce material handling cost
Your Answer
True/False
Question
Reduce material handling cost
Correct Answer
In case of X bar-R charts, statistical limits are calculated from averages of samples
of n (4,5,…) instead of single sample of large size to reduce the spread of natural
variability.
True
Your Answer
True
Multiple Choice Multiple Answer
Question
Which of the following is not the characteristic of Project Production?
Correct Answer
Your Answer
Continuous flow of material , Highly mechanised material handling , Virtually zero
manufacturing cycle time
Fixed position layout , Virtually zero manufacturing cycle time
Multiple Choice Single Answer
Question
A good plant layout helps in
Correct Answer
Reducing handling costs
Your Answer
Reducing handling costs
Multiple Choice Single Answer
Question
Inadequate production capacity ultimately leads to
Correct Answer
Poor Customer Service
Your Answer
Low Productivity
Select The Blank
Question
Correct Answer
Production Planning is a centralised activity which includes functions such as
________
Scheduling
Your Answer
Scheduling
Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of making any product/s
is called
Correct Answer
Factory
Your Answer
Factory
Multiple Choice Multiple Answer
Question
What are the uses of the instruction manual provided by the manufacturer of a
machine?
Correct Answer
It gives instructions regarding installation and operation of the equipment , It
contains note on common troubles with causes and remedies for troubleshooting ,
It enlists points, frequency and type of lubrication
Your Answer
It gives instructions regarding installation and operation of the equipment , It
contains note on common troubles with causes and remedies for troubleshooting
Multiple Choice Multiple Answer
Question
MRP utilises the following information
Correct Answer
Your Answer
Select The Blank
Question
Master production schedule , Product structure , Lead time for
procurement/manufacturing
Master production schedule , Product structure , Lead time for
procurement/manufacturing
A good maintenance system is not a luxary but a ________.
Correct Answer
Necessity
Your Answer
Necessity
True/False
Question
Shape od an OC curve is a function of sample size and the acceptance number.
Correct Answer
True
Your Answer
False
Multiple Choice Multiple Answer
Question
Which of the following can be subtypes of corrective maintenance?
Correct Answer
Shutdown Maintenance , Design-out Maintenance , Design-in Maintenance
Your Answer
Predictive Maintenance , Shutdown Maintenance
True/False
Question
Correct Answer
For p-chart, "Inspection by variables" is much faster than "Inspection by
attributes"
False
Your Answer
True
Multiple Choice Single Answer
Question
Site factors for plant location include
Correct Answer
Suitability of land
Your Answer
Suitability of land
Select The Blank
Question
Correct Answer
The ________ breakdowns usually cost more, partly due to damage done to the
adjustment components and partly due to emergency actions.
Unexpected
Your Answer
Partial
True/False
Question
Cent percent inspection is a must if the inspection is of destructive nature.
Correct Answer
False
Your Answer
False
True/False
Question
Correct Answer
Since value of p can never be positive, hence" if LCLp works out to be positive, it
is taken as zero."
False
Your Answer
True
Multiple Choice Single Answer
Question
Which varaible is taken along the abscissa or X axis?
Correct Answer
Time
Your Answer
Standard deviation
Multiple Choice Multiple Answer
Question
Which of the following are examples of specifications?
Correct Answer
Commercial standards , Assembly and testing instructions , Bill of material
Your Answer
Production schedule , Commercial standards , Assembly and testing instructions
Multiple Choice Multiple Answer
Question
Which of the following products should be produced by using mass production?
Correct Answer
Refrigerator , Tyre for automobile , Television Set
Your Answer
Refrigerator , Tyre for automobile , Television Set
Multiple Choice Single Answer
Question
Which of the following techniques is used by industrial engineering department to
obtain the utilisation index?
Correct Answer
Work Sampling Studies
Your Answer
True/False
Question
Method Study
An ideal OC curve is never possible only with cent percent inspection.
Correct Answer
False
Your Answer
False
Select The Blank
Question
The ________ is the probability that a bad lot will be accepted by the sampling
plan.
Correct Answer
Consumer's risk
Your Answer
Producer's risk
Select The Blank
Question
Correct Answer
The easiest way to bring the delayed job within the promised delivery time by
using extra shift or weekly holiday is ________.
Overtime working
Your Answer
Overtime working
True/False
Question
Correct Answer
The operator should not stop production if first piece is not approved by the
inspector.
False
Your Answer
False
Multiple Choice Single Answer
Question
The process of changing inputs into outputs thereby adding some value to entity
can be defined as
Correct Answer
Operation
Your Answer
Conversion
Multiple Choice Single Answer
Question
Which kind of relationship exists between those activities which can be carried out
simultaneously and both activities require definite time to finish?
Correct Answer
Concurrent activities
Your Answer
Concurrent activities
Multiple Choice Multiple Answer
Question
Which are different ways to show critical path in a network?
Correct Answer
Thick Line , Red Line , Double Line
Your Answer
Dotted line
Select The Blank
Question
Correct Answer
A ________helps to avoid crowding of jobs at a particular machine by change of
route of some of the jobs or by diverting work to other machine.
Control board
Your Answer
Control board
Multiple Choice Single Answer
Question
What do you understand by PERT ?
Correct Answer
Project Evaluation & Review Technique
Your Answer
Project Evaluation & Review Technique
Multiple Choice Multiple Answer
Question
Which of the following factors play important role while selecting or rejecting a
particular site from legislation and taxation point of view?
Correct Answer
Labour laws , Building codes , Policies regarding issue of licences
Your Answer
Labour laws , Policies regarding issue of licences
Multiple Choice Multiple Answer
Question
Which of the following concepts must be understood for the achievement of
quality?
Correct Answer
Quality of conformance , Purpose of product , Quality of design
Your Answer
Select The Blank
Question
Purpose of product , Process specifications , Quality of design
Correct Answer
The ________ is the probability that a good lot will be rejected by the sampling
plan.
Producer's risk
Your Answer
Producer's risk
Multiple Choice Single Answer
Question
What do you mean by the project duration for which the total cost is minimum?
Correct Answer
Optimum duration
Your Answer
Optimum duration
True/False
Question
Originating process of raw material influence Process Planning
Correct Answer
True
Your Answer
True