Document 16046198

advertisement
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
True/False
Question
Flow process charts do record movements as well as visual
pictures.
Correct Answer False
Your Answer
False
True/False
Question
The OC curve is based on the assumption that if the lot is large
in comparison to the sample, the probabilities of the OC curve
will follow a poisson distribution.
Correct Answer False
Your Answer
True
Multiple Choice Single Answer
Question
The ratio of output to input of a production system is commonly
known as
Correct Answer Productivity
Your Answer
Productivity
Multiple Choice Multiple Answer
Question
Order preparation process for products manufatured to order
requires following documents
Correct Answer Sales Order , Work order , Shop order
Your Answer
Work order , Purchase order
Select The Blank
Question
The ________ is the maintenance work initiated on a result of
knowledge of the condition of an item from routine or continuous
checking.
Correct Answer Condition monitoring
Your Answer
Preventive maintenance
Match The Following
Question
Correct Answer
Scheduling of interrelated Critical Path Analysis
activities of small projects
with consideration of
uncertainty of duration of
Your Answer
Critical Path Analysis
activities.
Two machines &
Johnson's Two Machine
processing time depends Algorithm
on sequence of job
loading
Johnson's Two Machine
Algorithm
Sufficient orders and
resonable choice of
machines
Index Method
Index Method
Time relationship between Critical Ratio Scheduling
when a product is required
and when it can be made
available
Time series
Select The Blank
Question
Production control work is ________ in case of floor inspection
as compared with the centralised inspection.
Correct Answer easier
Your Answer
easier
Match The Following
Question
Correct Answer
Your Answer
When to inspect
Stages of inspection
Specification
What to inspect
Specification
Standard
How to inspect
Inspection devices
Tools & Jigs
How much to inspect
Sampling or cent percent Stages of inspection
inspection
Multiple Choice Single Answer
Question
Material Planning is an integral part of
Correct Answer Production Planning
Your Answer
Process Planning
Select The Blank
Question
An Ideal OC curve is ________ shaped curve that accpets all
the lots with quality equal to or better than AQL .
Correct Answer Rectangular
Your Answer
Rectangular
Multiple Choice Single Answer
Question
Technique of Value Engineering can be effectively employed in
design of a product to
Correct Answer To meet the intended function at lowest cost
Your Answer
Reduce lead time
Multiple Choice Single Answer
Question
Material control function of PPC is concerned with
Correct Answer Preparation of material estimates
Your Answer
Preparation of material estimates
Multiple Choice Single Answer
Question
Main objective of a good plant layout is
Correct Answer Reduce material handling cost
Your Answer
Reduce material handling cost
True/False
Question
In case of X bar-R charts, statistical limits are calculated from
averages of samples of n (4,5,…) instead of single sample of
large size to reduce the spread of natural variability.
Correct Answer True
Your Answer
True
Multiple Choice Multiple Answer
Question
Which of the following is not the characteristic of Project
Production?
Correct Answer Continuous flow of material , Highly mechanised material
handling , Virtually zero manufacturing cycle time
Your Answer
Fixed position layout , Virtually zero manufacturing cycle time
Multiple Choice Single Answer
Question
A good plant layout helps in
Correct Answer Reducing handling costs
Your Answer
Reducing handling costs
Multiple Choice Single Answer
Question
Inadequate production capacity ultimately leads to
Correct Answer Poor Customer Service
Your Answer
Low Productivity
Select The Blank
Question
Production Planning is a centralised activity which includes
functions such as ________
Correct Answer Scheduling
Your Answer
Scheduling
Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of
making any product/s is called
Correct Answer Factory
Your Answer
Factory
Multiple Choice Multiple Answer
Question
What are the uses of the instruction manual provided by the
manufacturer of a machine?
Correct Answer It gives instructions regarding installation and operation of the
equipment , It contains note on common troubles with causes
and remedies for troubleshooting , It enlists points, frequency
and type of lubrication
Your Answer
It gives instructions regarding installation and operation of the
equipment , It contains note on common troubles with causes
and remedies for troubleshooting
Multiple Choice Multiple Answer
Question
MRP utilises the following information
Correct Answer Master production schedule , Product structure , Lead time for
procurement/manufacturing
Your Answer
Master production schedule , Product structure , Lead time for
procurement/manufacturing
Select The Blank
Question
A good maintenance system is not a luxary but a ________.
Correct Answer Necessity
Your Answer
Necessity
True/False
Question
Shape od an OC curve is a function of sample size and the
acceptance number.
Correct Answer True
Your Answer
False
Multiple Choice Multiple Answer
Question
Which of the following can be subtypes of corrective
maintenance?
Correct Answer Shutdown Maintenance , Design-out Maintenance , Design-in
Maintenance
Your Answer
Predictive Maintenance , Shutdown Maintenance
True/False
Question
For p-chart, "Inspection by variables" is much faster than
"Inspection by attributes"
Correct Answer False
Your Answer
True
Multiple Choice Single Answer
Question
Site factors for plant location include
Correct Answer Suitability of land
Your Answer
Suitability of land
Select The Blank
Question
The ________ breakdowns usually cost more, partly due to
damage done to the adjustment components and partly due to
emergency actions.
Correct Answer Unexpected
Your Answer
Partial
True/False
Question
Cent percent inspection is a must if the inspection is of
destructive nature.
Correct Answer False
Your Answer
False
True/False
Question
Since value of p can never be positive, hence" if LCLp works out
to be positive, it is taken as zero."
Correct Answer False
Your Answer
True
Multiple Choice Single Answer
Question
Which varaible is taken along the abscissa or X axis?
Correct Answer Time
Your Answer
Standard deviation
Multiple Choice Multiple Answer
Question
Which of the following are examples of specifications?
Correct Answer Commercial standards , Assembly and testing instructions , Bill
of material
Your Answer
Production schedule , Commercial standards , Assembly and
testing instructions
Multiple Choice Multiple Answer
Question
Which of the following products should be produced by using
mass production?
Correct Answer Refrigerator , Tyre for automobile , Television Set
Your Answer
Refrigerator , Tyre for automobile , Television Set
Multiple Choice Single Answer
Question
Which of the following techniques is used by industrial
engineering department to obtain the utilisation index?
Correct Answer Work Sampling Studies
Your Answer
Method Study
True/False
Question
An ideal OC curve is never possible only with cent percent
inspection.
Correct Answer False
Your Answer
False
Select The Blank
Question
The ________ is the probability that a bad lot will be accepted by
the sampling plan.
Correct Answer Consumer's risk
Your Answer
Producer's risk
Select The Blank
Question
The easiest way to bring the delayed job within the promised
delivery time by using extra shift or weekly holiday is ________.
Correct Answer Overtime working
Your Answer
Overtime working
True/False
Question
The operator should not stop production if first piece is not
approved by the inspector.
Correct Answer False
Your Answer
False
Multiple Choice Single Answer
Question
The process of changing inputs into outputs thereby adding
some value to entity can be defined as
Correct Answer Operation
Your Answer
Conversion
Multiple Choice Single Answer
Question
Which kind of relationship exists between those activities which
can be carried out simultaneously and both activities require
definite time to finish?
Correct Answer Concurrent activities
Your Answer
Concurrent activities
Multiple Choice Multiple Answer
Question
Which are different ways to show critical path in a network?
Correct Answer Thick Line , Red Line , Double Line
Your Answer
Dotted line
Select The Blank
Question
A ________helps to avoid crowding of jobs at a particular
machine by change of route of some of the jobs or by diverting
work to other machine.
Correct Answer Control board
Your Answer
Control board
Multiple Choice Single Answer
Question
What do you understand by PERT ?
Correct Answer Project Evaluation & Review Technique
Your Answer
Project Evaluation & Review Technique
Multiple Choice Multiple Answer
Question
Which of the following factors play important role while selecting
or rejecting a particular site from legislation and taxation point of
view?
Correct Answer Labour laws , Building codes , Policies regarding issue of
licences
Your Answer
Labour laws , Policies regarding issue of licences
Multiple Choice Multiple Answer
Question
Which of the following concepts must be understood for the
achievement of quality?
Correct Answer Quality of conformance , Purpose of product , Quality of design
Your Answer
Purpose of product , Process specifications , Quality of design
Select The Blank
Question
The ________ is the probability that a good lot will be rejected
by the sampling plan.
Correct Answer Producer's risk
Your Answer
Producer's risk
Multiple Choice Single Answer
Question
What do you mean by the project duration for which the total
cost is minimum?
Correct Answer Optimum duration
Your Answer
Optimum duration
True/False
Question
Originating process of raw material influence Process Planning
Correct Answer True
Your Answer
True
Download