POM assgn : Parmeet True/False Question

advertisement
POM assgn : Parmeet
True/False
Question
Objective of Work Study is to improve Productivity
Correct Answer True
Your Answer
True
True/False
Question
After goods have been manufactured, route sheets and operation layouts should not be
collected back.
Correct Answer False
Your Answer
False
Multiple Choice Single Answer
Question
How is the probability of acceptance in case of Acceptable Quality Level (AQL )?
Correct Answer Very high
Your Answer
Very high
True/False
Question
For p-chart, p bar is the ratio of total number of units inspected to the total number of
units defectives.
Correct Answer False
Your Answer
False
Select The Blank
Question
The ________ is specified to indicate the maximum permissible variability in the
dimensions product or parts.
Correct Answer Tolerance
Your Answer
Tolerance
Multiple Choice Single Answer
Question
Which varaible is taken along the abscissa or X axis?
Correct Answer Time
Your Answer
Time
Multiple Choice Single Answer
Question
Which kind of labour force is required in case of Jobbing Production?
Correct Answer Highly Skilled
Your Answer
Highly Skilled
Multiple Choice Multiple Answer
Question
Which are the general principles underlying probability aspects of project planning?
Correct Answer Statistically three time estimate of an activity conform to Beta distribution. , Expected
time divides the area under the curve into two equal parts. , Expected time of an
activity is located at one third of the distance between "m" and mid-range { (a+b)/2 }
away from the most likely time.
Your Answer
Statistically three time estimate of an activity conform to Beta distribution. , Expected
time divides the area under the curve into two equal parts. , Expected time of an
activity is located at one third of the distance between "m" and mid-range { (a+b)/2 }
away from the most likely time.
Select The Blank
Question
A ________ is another form of subcontracting.
Correct Answer Hiring capacity
Your Answer
Hiring capacity
Select The Blank
Question
The ________ pertain to the climatic conditions which the component , product or
material should withstand.
Correct Answer Environmental specifications
Your Answer
Environmental specifications
Match The Following
Question
Correct Answer
Your Answer
Bottom compartment of control
board
Bunch of work orders arranged in Bunch of work orders arranged in a
a sequence in which they are to
sequence in which they are to be
be processed.
processed.
Control board
Pictorial view of machine loading
activity
Pictorial view of machine loading
activity
Top compartment of control board Work order of item currently
being worked on the machine
Work order of item currently being
worked on the machine
Middle compartment of control
board
Work order of item to be processed
next on the machine
Work order of item to be
processed next on the machine
Select The Blank
Question
OC curve of ideal sampling plan suggests that all lots less than 3% defectives have the
probability of acceptance of ________.
Correct Answer One
Your Answer
One
Multiple Choice Single Answer
Question
Which is the right time to prepare stores issue order?
Correct Answer When route sheet is ready
Your Answer
When route sheet is ready
Multiple Choice Single Answer
Question
What is the reason of excessive friction between parts?
Correct Answer Improper or lack of lubrication
Your Answer
True/False
Question
Improper or lack of lubrication
Cellular layout is based on the concept of Group Technology
Correct Answer True
Your Answer
True
Multiple Choice Single Answer
Question
How does the control chart of statistical quality control helps the operating personnel?
Correct Answer Identify the presence of an assignable cause before it develops
Your Answer
Identify the presence of an assignable cause before it develops
Multiple Choice Multiple Answer
Question
Which are different ways to show critical path in a network?
Correct Answer Thick Line , Red Line , Double Line
Your Answer
Thick Line , Double Line
True/False
Question
The control chart for number of defectives is more convenient to make than control
chart for fraction defectives sincethe fugure of number of defectives units can be
directly taken from the inspection report.
Correct Answer True
Your Answer
True
Select The Blank
Question
The ________ is the maximum percentage defective that for the purpose of sampling
inspection can be considered satisfactory as a process average.
Correct Answer Acceptable quality level
Your Answer
Acceptable quality level
Multiple Choice Multiple Answer
Question
Order preparation process for products manufatured to order requires following
documents
Correct Answer Sales Order , Work order , Shop order
Your Answer
Sales Order , Work order , Shop order
Multiple Choice Single Answer
Question
The process of changing inputs into outputs thereby adding some value to entity can be
defined as
Correct Answer Operation
Your Answer
Operation
Multiple Choice Single Answer
Question
Any premise in which persons are employed for purpose of making any product/s is
called
Correct Answer Factory
Your Answer
Factory
Multiple Choice Single Answer
Question
Inherent Safety' is one of the principle of good layout. In context of layout, this can be
achieved by the following
Correct Answer Clear gangway, location of material and material handling system
Your Answer
Safety training
Match The Following
Question
Correct Answer
Your Answer
Toung
Sweet
Sweet
Eye
Crack
Crack
Nose
Burnout
Burnout
Ear
Impact
Impact
Multiple Choice Single Answer
Question
How much time does the dummy activity take?
Correct Answer Zero Time
Your Answer
Zero Time
Select The Blank
Question
The ________ is the maintenance work initiated on a result of knowledge of the
condition of an item from routine or continuous checking.
Correct Answer Condition monitoring
Your Answer
Condition monitoring
Multiple Choice Single Answer
Question
What does tail of an arrow represent?
Correct Answer Start of an activity
Your Answer
Start of an activity
Select The Blank
Question
The ________ is the probability that a good lot will be rejected by the sampling plan.
Correct Answer Producer's risk
Your Answer
Producer's risk
Select The Blank
Question
The ________ is the probability that a bad lot will be accepted by the sampling plan.
Correct Answer Consumer's risk
Your Answer
Consumer's risk
Multiple Choice Multiple Answer
Question
Which of the following are the most suitable cases where we can use CPA as effective
technique of scheduling?
Correct Answer Overhauling of a CNC machine , Purchase and installation of a newly imported special
purpose machine , Design, production and testing of prototype of a fighter aircraft.
Your Answer
Overhauling of a CNC machine , Purchase and installation of a newly imported special
purpose machine , Design, production and testing of prototype of a fighter aircraft.
Multiple Choice Single Answer
Question
Which kind of relationship exists between those activities which can be carried out
simultaneously and both activities require definite time to finish?
Correct Answer Concurrent activities
Your Answer
Concurrent activities
Select The Blank
Question
The ________ are the definitions of the measurable as well as nonmeasurable
characteristics of the product.
Correct Answer Specifications
Your Answer
Specifications
Select The Blank
Question
Goods after final inspection should accompany ________to enable dispatch department
to identify and draw correct reference.
Correct Answer Forwarding note
Your Answer
True/False
Question
Forwarding note
The steeper the OC curve, the better is the discrimination between good and bad lots.
Correct Answer True
Your Answer
True
Multiple Choice Multiple Answer
Question
Which of the following are types of non-destructive testing?
Correct Answer Visual Testing , Eddy current , Magnetic flow detectors
Your Answer
Visual Testing , Eddy current , Magnetic flow detectors
Multiple Choice Multiple Answer
Question
Which are the different types of flow process charts used for method study?
Correct Answer Equipment type , Man type , Material type
Your Answer
Equipment type , Man type , Material type
Multiple Choice Single Answer
Question
Which photographic technique is used to record path of motions of the members of the
body during method study?
Correct Answer Cyclograph
Your Answer
Cyclograph
Multiple Choice Multiple Answer
Question
Which of the following is not the characteristic of Project Production?
Correct Answer Continuous flow of material , Highly mechanised material handling , Virtually zero
manufacturing cycle time
Your Answer
Continuous flow of material , Highly mechanised material handling , Virtually zero
manufacturing cycle time
True/False
Question
Use of accurate measuring instruments and better supervision for inspectors is not
possible in case of floor inspection as compared to centralised inspection system.
Correct Answer True
Your Answer
True
True/False
Question
Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature
failure of machinery.
Correct Answer True
Your Answer
True
Select The Blank
Question
The ________ is the watch dog which ensures that every element of production and
activities which could affect the quality of end product are regulated to the extent
desirable.
Correct Answer Quality control
Your Answer
Quality control
Multiple Choice Multiple Answer
Question
Which of the following aspects are essential to ensure quality of purchased items?
Correct Answer Defining right quality for the job , Vendor performance evaluation , Making sure that
suppliers understand the requirements
Your Answer
Defining right quality for the job , Vendor performance evaluation , Making sure that
suppliers understand the requirements
True/False
Question
Process Planning is concerned with decisions regarding requirement of machines and
manpower for meeting customer demand
Correct Answer False
Your Answer
True/False
Question
True
All activities lying on the non-critical paths must have total float and free float.
Correct Answer False
Your Answer
False
Multiple Choice Multiple Answer
Question
Which of the following method can be adopted to overcome the problem of rushing up a
job for it's timely completion?
Correct Answer Use of optimum speeds and feeds , Subcontracting , Job splitting
Your Answer
Use of optimum speeds and feeds , Subcontracting , Job splitting
Multiple Choice Single Answer
Question
Which of the following data is unnecessary for scheduling process?
Correct Answer Cost breakup of products
Your Answer
Cost breakup of products
Multiple Choice Multiple Answer
Question
Which of the following are the major steps of making of the X bar-R control chart?
Correct Answer Collection of data , Claculation of mean,range,grand average and mean range , Set up
control chart for average and calculate control limits of range chart
Your Answer
Collection of data , Claculation of mean,range,grand average and mean range , Set up
control chart for average and calculate control limits of range chart
Download