Part One ITEM No.7 REPORT OF THE STRATEGIC DIRECTOR OF CUSTOMER & SUPPORT SERVICES TO THE: BUDGET & AUDIT SCRUTINY - AUDIT SUB COMMITTEE ON Monday, 12th September2005 TITLE: ENERGY MANAGEMENT ACTIVITY JUNE TO AUGUST 2005 EXECUTIVE SUMMARY: The purpose of this report is to inform members of the energy audit activity undertaken by Audit & Risk Management Unit for the period June to August 2005 inclusive. BACKGROUND DOCUMENTS: None (Available for public inspection) ASSESSMENT OF RISK: Energy Audit activities form an integral part of the City Council’s Risk Management Strategy aimed at giving assurance regarding the management of the City Council’s key business risks. SOURCE OF FUNDING: Existing revenue budget COMMENTS OF THE STRATEGIC DIRECTOR OF CUSTOMER AND SUPPORT SERVICES (or his representative): 1. LEGAL IMPLICATIONS Provided by: Deputy Director of Customer & Support Services and City Solicitor 2. FINANCIAL IMPLICATIONS consultation with Head of Finance Provided by: Ongoing PROPERTY (if applicable): N/A HUMAN RESOURCES (if applicable): CONTACT OFFICER: Jim Gosney – Energy Manager 0161 793 3472 WARD (S) TO WHICH REPORT RELATE (S): N/A KEY COUNCIL POLICIES: Environmental Strategy DETAILS: See attached report 2 Energy Audit activities undertaken during the period June to August 2005 are detailed as follows: 1. ENERGY AUDITS Implemented Energy Savings, through purchasing, tariff analysis and water audits amount £11,693.33 to date. Refunds for the amount of £173,575.90 to date, have also been achieved and cheques from the various suppliers are being received. We are pleased to report that audits have been conducted at Lewis Street Primary School, Christ Church Primary School, all the Youth Centres, The Limes, White Meadows, The Withies and Brynheys EPH’s, and all the Libraries. The Recommendation summaries for the reports issued are attached in Appendix A. 2. MANCHESTER GREEN REVOLUTION The New Climate Agenda Climate change is the greatest environmental threat facing humankind today and each new temperature high, freak flooding incident or recordbreaking storm reminds us just how serious the impacts of climate change could be if ignored; it is a sobering fact that more people each year are displaced by the forces of nature, than by armed conflict or economic necessity. As a result, a broad political consensus, strengthened now by the ratification of the Kyoto Protocol and the decision by the Prime Minister Tony Blair to put climate change at the top of the G8 and EU agendas, is driving nations, businesses, households, and cities to take tangible steps to cut their greenhouse gas emissions dramatically. Manchester: Knowledge Capital In parallel, the focus of economic thinking across the United Kingdom and Europe is increasingly turning to innovation and entrepreneuralism as the key drivers for growth in the 21st Century; it is the knowledge economy that offers a buoyant future for business, particularly for the former powerhouse of industry, Manchester. A Green Energy Revolution Now Manchester: Knowledge Capital (M:KC) is leading a partnership including the local authorities of the Manchester city region and the regional sustainable development advocate, Sustainability Northwest (SNW) to bring about a 'green energy revolution' that will use the knowledge economy of the city region to convince businesses, large organisations and households –literally everyone – across Manchester 3 to play their part in radically reducing their emissions of CO2 and other greenhouse gases. The Revolution's Road Map Following a scoping study by SNW, which as been passed by the M:KC Board, a detailed study has been commissioned to examine the feasibility of implementing a broad, bold and pioneering programme of projects, initiatives and developments that will reduce Manchester's greenhouse gas emissions in innovative, practical and significant ways. It will also address the potential for economic benefits through cost savings and supply chain development. The contract for this study ahs been awarded to a consortium led by Addagy Limited and comprising Arup (engineers and architects), Creative Concern (communications) and Sheppard Robson (architects and planners). The study, managed for M:KC by SNW, started in March 2005 and is scheduled to last for seven months, finishing with a major stakeholder event this autumn. Project Phases The project involves two phases: Phase 1 The development and screening of ideas, including those identified during the scoping study, involving wide stakeholder consultation. This phase will also address the issues of linking this initiative with related projects in the city region and drawing on the experiences of exemplar cities elsewhere in Europe. The outputs of this phase will be the shortlist of selected projects, with supporting details, and an overall communications plan aimed at stimulating the involvement of project champions. Phase 2 A detailed evaluation of the selected projects by leading specialists in the relevant fields covering management, technical, economic, timing, communications and funding issues together with sustainability and risk assessments. It will also address the overall strategy and plan for taking the Green Energy Revolution initiative forward, including the vision and aims, project phasing, management and organisation, communications, funding and measurement of results. The outputs will be individual project profiles and action plans, the final report and a presentation to stakeholders. The progress Summary for Phase 2 is attached as Appendix B. 4 3. AFFORDABLE WARMTH STRATEGY On 10 June 2005 Partners IN Salford launched the Affordable Warmth Strategy for the city. The Mayor and Mayoress of Salford welcomed over 75 guests, including many from community and voluntary groups, to the Digital World Centre to launch the strategy. The four key aims of the strategy are:1. To raise awareness and provide advice on energy efficiency and affordable warmth. 2. To establish partnership working and referral systems for vulnerable groups for affordable warmth. 3. To provide financial solutions for affordable warmth. 4. To improve the energy efficiency of the housing stock in Salford. An annual report on the progress on achieving the Strategy’s Key Aims will be published every spring, the first in 2006. It is planned that that report will contain details of the achievements of the strategy over the past 12 months and also feedback on how any ideas generated have been actioned. 5 APPENDIX A SUMMARY OF RECOMMENDATIONS Lewis Street Primary School No Cost Measures Consumption and C02 Reduction Ongoing Saving Refund £ 1. Transfer Electricity Supply to Scottish and Southern - £850.00 - 2. Introduce Good Housekeeping 10,033 kWh 4.31C02 £646.00 - 3. Turn off PC’s when not in use 3,679 kWh 1.582C02 £240.00 - 4. Remove Heating times for Sunday 27,916 kWh 5.31 C02- £394.00 - 5. Ensure water meter charges correct Low Cost Measures £12.00 £25.90 Consumption Reduction Saving £ Installation Payback Cost Period 1. Install Time Clocks on all DHW Heaters 8,562 kWh 3.682 C02 £553 £450 10 months 2. Install TRV’s 32,582 kWh 6.19 C02 £460 £600 16 months 3. Install Cistern Dams 51.5 m3 £88.34 £130.02 18 months 4. Install Urinal Controls 581.26 m3 £997.4 4 £675.45 8 months Saving Saving KWh £ Installati on Cost Payback Period 82,772kWh £4,210. 78 £1,855.4 7 5.3 months TOTALS 21.07 C02 632.76 m3 6 Christ Church Primary School No Cost Measures Saving Saving Saving KWh £ CO2 Tonne 1. Good housekeeping 5,850 £298 2.52 2. Reduce boiler temperature and remove obstacles front of radiators 13,745 £390 2.61 Low Cost Measures Saving Saving £ Install Cost CO2 Tonne Payback Period KWh 1. Timer controls on electric water heaters 5,850 £299 £200 2.52 0.7 years 2. Replace heating time clock 20,616 £585 £150 3.92 0.3 years 3. Replace cistermiser with PIR control 134m³ £230 £139.50 0.05 0.6 years 4. Install push taps 234m³ £401 £750 0.09 1.9 years 5. Install cistern dams 44m³ £76 £112.29 0.02 1.5 years CO2 Tonne Payback Period High Cost Measures Saving Saving KWh £ Install Cost 1. Convert electric to 15,000 gas heating in nursery £766 £5000 3.49 6.5 years 2. Convert oil to gas heating for main school 13,745 £1,603 £100,000 3.48 62.4 years Saving Saving KWh £ Install Cost CO2 Tonne Payback Period 74,806 £4,648 £106,351 .79 18.70 22.9 years Totals 7 Youth Centres No Cost Measures Site Recommendation Saving (kWh) Co2 (Tonne) Saving (£) Clifton Change electricity supplier Good Housekeeping 3,056 1.3 £519 £215 Oasis Re-set water heater time clocks Good Housekeeping Reset time clock and adjust TRVs 5,196 2,958 75,000 1.0 1.3 14.3 £492 £246 £1,116 North Salford Good Housekeeping 2,596 1.1 £165 Reset boiler time clocks 31,250 5.9 £465 Height Change electricity supplier Good Housekeeping Amendment of gas account Remove weekend boiler times 3,444 50,000 1.5 9.5 £370 £220 £437 £744 Ordsall Change electricity supplier Good Housekeeping 16,261 7.0 £1,460 £634 Greenheys Good Housekeeping 7,192 3.1 £367 Bridgewater Change of electricity supplier Better control of heating times 13,897 5.9 £868 £710 Eccles Change electricity supplier Better control of heating times 51,176 13.0 £269 £1,452 Irlam Change electricity supplier Correction of electricity rates Good Housekeeping 11,200 4.8 £1,508 £180 £438 Deans Road Change electricity supplier Boiler controls 76,000 14.4 £451 £1,245 Low Cost Measures Site Recommendation Cost North Air blower time Salford clock & TRVs Total £300 Saving (kWh) 6,250 Co2 Saving (Tonne) (£) 1.2 £93 £14,664 8 The Limes EPH No Cost Measures 1. 2. Consumption & CO2/tonne Reduction Ongoing Saving Electricity- Reinforce Good Housekeeping 10,381 kWh £464 Gas- Reset Controller 28,329 kWh 4.464 Tonne 5.38 Low Cost Measures 1 £ £400 tonne £ Install Cost Payback Period £47 £210 29.6 months £70 £140 24 months £88.34 £59.1 10 months Saving Saving CO2 £ Install Cost Payback Period 11,454 kWh £511 £210 £470 £140 £88.34 £59.1 £1069. 34 £409.1 Introduce Low Energy Bulbs Saving Saving CO2 1,073 kWh 0.461 tonne 2 Install Time switch to Potterton Boiler 4957 kWh 0.942 tonne 3 Install cistern dams Summary 1 Electricity 51.48m³ 4.925 tonne 2 Gas 33,286 kWh 6.325 tonne 3 Water 51.48m³ 4. Totals 44,740 kWh 11.25 tonne 51.48 m3 4.6 months 9 White Meadows EPH 1. No Cost Measures 1. 2. Consumption & Ongoing Saving CO2/tonne Reduction £ Lighting – Good housekeeping. 13,212 kWh £623.50 Reset Thermostats on 8 cyls 11,931 kWh 5.68 tonne Low Cost Measures 5.13 tonne Saving Saving Install Cost Payback Period £540 £560 12.5 months Up to £2850 £5,000 21 months £74.95 £59.10 9.5 months Saving Saving CO2 £ Installati on Cost Payback Period 24,658 kWh £560 10.6 tonne £1,163. 50 275,631 kWh £3010 £5,000 £74.95 £59.10 £4248. 45 £5619.10 CO2 1 2 £160 Install Low Energy Bulbs 11,446 kWh Install Immersion Heaters Up to 263,700 kWh 4.922 tonne 50.1 tonne 3 Install cistern dams Summary 1 2 Electricity Gas 43.68 m³ 55.23 tonne 3 Water 43.68 m³ 4. Totals 300,199 kWh 65.84 tonne 43.68 m3 15.87 months 10 The Withies EPH 2. No Cost Measures 1. 2. Consumption & CO2 /tonne Reduction Ongoing Saving Electricity-Reinforce Good Housekeeping 11,003 kWh £ 426 Gas- Re-set time switches 80,373 kWh 3. Low Cost Measures 1. 2. £ 4.73 £ 1,135 15.27 Saving Saving £ Installati on Cost Payback Period CO2 Install Low Energy Bulbs in Main Lounge 1878 £84 £47 6.7 months Install New Jackets to two 13,040 £184 £160 10.4 months 0.81 2.48 Hot Water Cylinders 4. Summary 1 Electricity Saving Saving CO2 £ Installation Cost 12,881 kWh £507 £47 £1,135 £160 £1,624 £207 Payback Period 5.54 tonne 2 Gas 93,413 kWh 17.75 tonne 3. Totals 93,254 kWh 20.81 tonne 1.5 months 11 Brynheys EPH 5. No Cost Measures 1. 2. 3. Saving kWh Ongoing Saving CO2 tonnes £ Electricity- Reinforce Housekeeping 18126 £ 801.56 Gas- Reinforce Housekeeping 1996 Water- Reinforce Housekeeping 268 m3 6. Low Cost Measures 1. Install Low Energy Bulbs to reading lamps 7. Summary 1 Electricity 7.79 £36.23 0.38 £467.50 Saving Saving £ Installati on Cost Payback Period CO2 Tonne 1180 kWh £57.11 £40 8.4 months 0.51 Saving Saving CO2 Tonne £ Installation Cost 19306 kWh £858.67 £40 Payback Period 8.3 2 Gas 1996 kWh £36.23 0.38 3 Water 268 m3 4. Totals 21,302 kWh 8.68Tonne £467.50 £1362.40 £40 0.3 months 268 m3 12 Libraries No Cost Measures Site Recommendation Broadwalk Broughton Cadishead Eccles Height Irlam Walkden Winton Broughton Eccles Height Little Hulton Winton Walkden Worsley Co2 (Tonne) 3.23 3.29 2.15 7.25 2.26 11.24 2.80 7308 2,175 30m³ 3.14 0.94 Cost Saving (kWh) £3,000 28,574 Co2 (Tonn e) 5.43 £279.00 463m³ £793.70 £35.46 £250.00 £23.64 £100.00 £6,000 19.02m³ 57.60m³ 12.68m³ 23.04m³ 90,796 £139.50 362m³ £32.64 £98.84 £21.76 £39.54 £1,487.2 4 £621.71 £23.64 £200.00 £5.91 £50.00 £17.73 12.68m³ 46.08m³ 3.17m³ 11.52m³ 9.51m³ £21.76 £79.07 £5.44 £19.77 £16.32 £150.00 £150.00 17.28m³ 3,500 £29.65 £178.85 £50.00 £11.82 £100.00 £5,000 11.52m³ 6.34m³ 23.04m³ TBC Good Housekeeping Good Housekeeping Good Housekeeping Good Housekeeping Reset heater time switch Re-set boiler heating times Good Housekeeping Removal of off peak meters Good Housekeeping Good Housekeeping Reduce push tap operation time Low Cost Measures Site Recommendation Broadwalk Saving (kWh) 7,500 7,650 4,991 16,863 5,250 59,147 6,500 Upgrade heating control system Install 2 PIR urinal controls Install 6 cistern dams Install 10 push taps Install 4 cistern dams Install 4 push taps Upgrade heating control system Install 1 PIR urinal control Install 4 cistern dams Install 8 push taps Install 1 cistern dams Install 2 push taps Install 3 cistern dams Install 6 push taps Install time control on electric water heater Install 2 cistern dams Install 4 push taps Convert from electric to gas heating 17.25 1.51 Saving (£) £383.25 £390.92 £245.60 £784.25 £268.28 £968.83 £332.15 £150.00 £373.44 £111.14 £51.48 Saving (£) £468.04 £19.77 £10.88 £39.54 TBC 13 Libraries cont’d…. High Cost Measures Site Recommendation Irlam Improve thermal insulation/fabrication Install 2 push taps Convert from oil to gas heating Convert from electric to gas heating Little Hulton Walkden Total Cost Saving Co2 (kWh) (Tonne) £15,000 35,000 6.65 Saving (£) £573.30 £50.00 £20,000 2.98 £19.77 £1,433 30.92 £2,700 £40,000 11.52m³ 15,709 £12,769.93 14 APPENDIX B MANCHESTER | THE GREEN ENERGY REVOLUTION Phase 2 - Progress Summary August 2005 1. Detailed Evaluation of Projects Progress has been made on all of the short-listed projects and initiatives – see summary in Appendix. Work has also commenced on the production of the project profiles – see working document on Bio diesel attached to this report. A number of the projects are being “fast tracked”: CO2 Pledge based on discussions between the Project Team. M:KC and SNW Wood Biomass project due to the strong support from the key stakeholders and interest from the local authorities Low Carbon Industrial Estates through an opportunity to submit a Carbon Trust bid Green Office Revolution since we have a strong project champion in Bruntwood and there is scope to link this into the Pledge. 2. Carbon Baseline Model The broad methodology has been developed and we are awaiting a date for a meeting with CATE and Rochdale to agree the details. 3. Behavioural Change Plan The main elements of the Plan are in place: Research methodology and sample questions awareness/attitude survey (We Know Who YOU Are) Design of visuals (Extreme Visual Pleasure) Identification of dissonance moments which will link into the Visible Messages initiative (Dissonance Jamming) for the A detailed plan for the overall Campaign is being developed. 4. Stakeholder Event on October 25th This was discussed at the AGMA Environmental Co-ordinators Forum meeting on 20th July and at a subsequent follow-up meeting. The Environmental Co-ordinators have now agreed that the meeting should focus mainly on their Carbon Management agenda. Time has been allowed in the morning session for a short up-date on the Green Energy Revolution and one of the breakout groups in the afternoon would be devoted to the M:GER. Our view is that this should focus on achievement of strong buy-in to the policy and planning initiatives, which we are progressing. Hence the meeting would not be suitable as a general stakeholder engagement event. Moreover, the Co-ordinators have decided 15 to postpone their event until November which is too late to fit into the M:GER programme. Hence, we recommend that we should go back to the original plan of holding an end-of-project event which will be supported by the local authorities. Manchester Town Hall, which was booked for the Local Authority Conference on October 25th, is still available and we are currently checking on the costs. We will discuss this at the Working Group meeting on 17th August. 5. Forward Programme Some delays have been experienced with the organisation of some of the meetings with key stakeholders due to the holidays. This may delay the finalisation of some of the profiles but this should not affect the final report date as set out in the Phase 2 Programme. 16 Table 1 - Phase 2 Project Progress Summary Project Title Greening the City Self-sufficient Streetscapes Manchester Aeolian Tower Common Health Hotel Hydrogen Demonstrator Building Progress Summary LA’s contacted to ascertain interest and identify areas/sites. Red Rose Forest and Trees for Cities contacted to review funding possibilities Identification of project champions underway. Cost estimates for installation and maintenance obtained Estimates of CO2 savings, environmental and social benefits Risks and barriers to implementation(technical, economic, planning, political) assessed Evidence of cost benefit analysis from actual projects - reports identified LA’s contacted to determine interest and commitment List of grant funding sources obtained e.g. Carbon Trust, EST etc. (see Funding Pot) Currently available technologies being identified e.g. Solar bus shelters Pilot projects being identified. Checking on activities in other UK e.g. Stoke and London Existing initiatives with wind generation on towers e.g. CFS, Hilton Hotel Identification of an appropriate Manchester project where wind generation and viewing gallery may be incorporated e.g. in Oldham Discussions with BWEA, RIBA, MCC etc. about funding for an architectural competition Other consultants in Manchester contacted to identify developments. Potential technology solutions being reviewed. Research into case studies and accreditation schemes/initiatives undertaken (e.g. REST, Ecotel, Green Hotels and Green Leaf Hotel Program Research into international chains versus local “boutiques” Discussions with local developers/champions e.g. r.gen/Urban Splash, La Sande. Key design elements, environmental objectives and operational parameters identified. Review of hydrogen economy developments in UK and Europe undertaken Discussions with key regional stakeholders (e.g. Ineos Chlor, Air Products, Shell etc) Identification of funding sources (e.g. DTI, EU) Assessment of project options in transport and static applications. Project Title CO2 Pledge The Great Renewables Sale 1000 Homes Low Carbon Industrial Estates Manchester Green Office Campaign Progress Summary Development of the initiative to sign-up 10,000 Mancunians by end October including web site, promotional campaign and support package. Contact with a wide range of local organisations to obtain support for the initiative and to commit to involvement in securing staff pledges Contact with potential funders including Defra, EST, NWDA, GO-NW etc. Scope for financial incentives being investigated. Discussions with organisations operating similar schemes: Solar for London, Kirklees Council Identification of renewable energy suppliers and initial discussions with some of them e.g. Windsave Review of Clear Skies accredited installers in the NW (none in Greater Manchester) Initial discussions with EST/Clear Skies regarding funding Review of possible EEC funding e.g. British Gas Information on suitable meters and costs being obtained from 4 suppliers Contact with LAs to identify potential use in social housing – positive response from Tameside, Rochdale and Manchester. Links to the Pledge and funding options being assessed Identification of target estates/parks and project champions – Trafford Park and Portland Basin (Ashton) look most promising Details of business/property mix on target sites obtained and low carbon options being assessed. Opportunity for funding under current Carbon Trust programme (deadline 2nd September!) – could be used for Trafford Park project through the Trafford Park Business Forum (now part of Manchester Chamber of Commerce). Scope to put in a proposal being investigated with potential partners. Contact made with potential “host” organisations. Bruntwood have just embarked on an environmental campaign which includes a comprehensive energy plan and they are very keen to get involved in the M:GER Manchester University are also keen to be involved based on their major new build and refurbishment programme. GM Strategic Health Authority has been approached and they have also expressed interest in getting involved. Several local suppliers of energy efficiency products/technologies have been identified. Project Title Bio fuels Supply Chain Wood Biomass Initiative Circle of Wind Zero Emission Vehicle Parking Arc Of Opportunity Progress Summary Discussions with potential project champions – GMPTE, Manchester Airport keen to get involved. CFS also interested in being involved. Identification of other stakeholders i.e. suppliers of bio diesel and hybrid buses, bus operators Project costs/returns assessed and funding sources identified Examples from other cities obtained e.g. Portsmouth, Graz. Scope to link into local initiatives assessed e.g. inward investors, local bio diesel suppliers Initial project to focus on high bio diesel blends. Discussions with project champions for wood chip supply from wood waste – Hadfields and Red Rose Background research into wood waste arisings and equipment options Review of experience at Kingmead School LAs contacted to identify potential applications in public sector buildings e.g. schools, district-heating schemes, leisure centres. Funding sources being identified – current EU Framework 6 call for demonstration project a strong possibility. Wind speed assessment shows best sites along the northern stretch of the M61/M60/M62 between Wigan and Rochdale would be best – speeds not high enough along southern section of M60. Scope for link into chemicals sites in the area through Chemicals Northwest. Contacts being made with LAs – Rochdale keen to be involved. Initial discussions with developers Contact has been made with the LAs to discuss the idea and to obtain feedback on the practicalities of implementation. Meeting being arranged with Roy Newton, Head of Local Transport Plan Team which brings together representatives from the 10 authorities, to discuss this and the other transport initiatives. Concern raised by Tameside over loss of revenue and by Trafford over high percentage of privately owned car parks in the Borough. Discussion with MCC/GMPTA regarding the links with developments along the Irwell Corridor and Salford Crescent/Chapel Street. Contact with Salford CC being arranged. Concerns about demand for a link between Salford and Manchester universities and the lack of benefits for the rest of GM. Project Title Making Journeys More Sustainable Visible Messages Across the City Green Energy Map The Big Green Energy Experiment Standard Sustainable Energy Policies Low Carbon Authorities Buying for a Low Carbon Future Progress Summary Discussion with MCC/GMPTA regarding the links with the current transport corridor partnerships. Potential to link this initiative into one or more of the four Phase 1 corridors based on the priority Metro link extensions and the Leigh-Salford-Manchester corridor which includes a guided bus-way proposal. Next step is to participate in one or more of the partnership meetings in September. Oxford Road corridor project being followed up with Faber Maunsell. Also scope for a project along the A56 (Altrincham – Manchester) being discussed with Tameside MBC Additional ideas being considered for the “toolkit” of initiatives include destination charging, clear zones, electric bikes, car pool/club schemes and distributed workspaces. This will link into the Behavioural Change Campaign under the Dissonance Jamming element. Details will be worked up once the overall campaign has been discussed and agreed with M:KC and SNW. Work has started on the identification of the main green energy developments and on the design of the map. Work on this will commence when the Behavioural Change campaign has been discussed and agreed. Good opportunity to harmonise policies across GM through the current work on Local Development Frameworks (LDFs) which can incorporate new Spatial Plans and new Planning Policies/Guidance. Information on current and proposed requirements for on-site renewables and higher energy efficiency standards is being gathered – 7 authorities have responded to date. Meeting with AGMA Strategic Planning Information Group being arranged. Interest in committing to a GM target for CO2 reductions being discussed with the LAs based on a process similar to the Carbon Trust’s Local Authority Carbon Management Programme in which 5 of the LAs are already involved. This will be a key theme at the Carbon Management Conference in the autumn. Positive feedback to-date but need to discuss details and common baselines. Approach could be extended to include the health authorities and this is being followed-up with the GMSHA. Information on current green procurement criteria has been obtained for 6 authorities and GMPTE. Others being chased-up. Feedback on initiative generally positive but some reservations e.g. commitment from senior levels in the LAs, implementation issues and lack of supplier capacity (especially local). Initial focus on purchase of energy and materials with high-embedded energy content. Project Title Greening the Schools Building Programme Green Energy Funding Pot Progress Summary This project was not short-listed at the end of Phase 1 but it has emerged as a key area under the Low Carbon Authorities initiative due to support from the LAs. Information on the schools building programme in each Authority and the relevant contacts is being collected. Feedback from Bury, Bolton, Manchester and Oldham to date. Links with the Wood Biomass project being established. Need to agree a common standard across AGMA e.g. Eco-Schools Very Good or BREEAM Excellent. Funding sources being investigated include EST, EEC and the concept of a fund based on encouraging individuals and organisations to make their activities/events carbon neutral (e.g. Climate Partners approach). The individual commitments would link into the Pledge initiative. Consideration is being given to the development of ESCO funded projects. List of grant funding is also being compiled.