Part One ITEM NO.7

advertisement
Part One
ITEM NO.7
REPORT OF THE DIRECTOR OF CUSTOMER & SUPPORT SERVICES
TO THE: BUDGET & AUDIT SCRUTINY - AUDIT SUB COMMITTEE
ON Monday, 13th June, 2005
TITLE: REPORTS ISSUED MARCH TO MAY 2005
RECOMMENDATIONS:
Members are asked to note the contents of the report.
EXECUTIVE SUMMARY:
The purpose of this report is to inform members of the internal audit activity undertaken by
the Audit & Risk Management Unit for the period March 2005 to May 2005 inclusive.
BACKGROUND DOCUMENTS:
(Available for public inspection)
Various reports and working papers.
ASSESSMENT OF RISK:
Internal Audit projects are managed within the Unit’s risk based audit protocols aimed at
giving assurance regarding the management of the City Council’s key business risks.
SOURCE OF FUNDING:
Existing revenue budget.
COMMENTS OF THE STRATEGIC DIRECTOR OF CUSTOMER AND SUPPORT
SERVICES (or his representative):
1. LEGAL IMPLICATIONS
Customer & Support Services and City Solicitor
Provided by: Deputy Director of
2. FINANCIAL IMPLICATIONS
Provided by: Head of Finance
PROPERTY (if applicable): N/A
HUMAN RESOURCES (if applicable): N/A
CONTACT OFFICER:
Andrew Waine Audit Manager
Tel: 0161 793 3357
Email: andrew.waine@salford.gov.uk
WARD(S) TO WHICH REPORT RELATE(S): N/A
KEY COUNCIL POLICIES: N/A
DETAILS: See report attached.
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART
TWO
PART ONE X
Directorate
Children’s Services
Subject
Salford Consortium
Commencement
February 2005
Date
Report
Number
Issued Date
2535
March 2005
Scope
A policy of Post Implementation Review has been formalised by Internal Audit. The
review took the form of a follow-up visit, seeking to confirm that all the agreed
recommendations from the previous internal audit, report reference 2535/EDU/04
issued on the 14th June 2004, have been implemented.
Internal Auditor’s Opinion
Salford Consortium has made significant progress in implementing the
recommendations made within the original audit report. Our post implementation
review confirmed that the key concerns regarding quality of the learners’ files, and
the evidence on these files to support funding claimed for additional support, has
improved considerably.
Two minor recommendations had not been sufficiently implemented at the time of
this review. However in both instances, systems had been introduced and changes
have been agreed that will provide a greater level of control.
Original Main
Recommendations
The Administration Team’s list
of people in receipt of ALN/
ASN funding, should be
revised, updated, and
maintained on an ongoing
basis,
To ensure that all documents
on the file are updated as
appropriate, Key Workers,
possibly following the learners’
eight-weekly reviews, should
regularly review learners’ files.
Original
Management
Response
Agreed
Agreed
Implementation
Date
Immediately
Implemented
Agreed
31st August
2005
Current Position
Implemented
Implemented
2
Committee Summary
PART ONE
X
Directorate
Customer & Support Services
Subject
Payroll Review 2004-05
Commencement Date
PART TWO
August 2004
Report
Number
Issued Date
2698
March 2005
Scope
The objective of this review was to identify the risks and controls associated with the following processes:
 New starters and leavers
 Accuracy and integrity of employee records
 Deductions from pay and respective payments made to other Organisations
 Variations to pay
 Payroll processing and payroll accounts.
This years audit review also sought to confirm that the recommendations agreed in last years audit report
had been fully implemented.
Internal Auditor’s Opinion
Our review confirmed that the majority of the controls within Payroll are operating effectively and that the key
risks are adequately controlled.
However the review did highlight 14 areas requiring action to further enhance the control environment. The more
significant of these matters are:
 The use of exception reports to highlight potential errors or frauds should be extended to provide more
comprehensive control
 The current storage arrangements for paper based employee records do not provide adequate security in
respect of Data Protection and confidentiality
 There is insufficient documentation to confirm that the rates of overtime paid to some higher earners, in
excess of the National Salary Scale guidelines, are appropriate and authorised
 The checks that are required during the leavers’ process are not systematically controlled.
Whilst audit recognises that significant progress has been made since our last review with respect to
reconciliations, there are still some accounts that are not being reconciled with appropriate frequency, and there
are some small historic balances on a number of accounts that should be resolved.
Main Recommendations
Overtime should only be paid at a rate higher than scale point 31 when
such exceptions have been appropriately authorised and the reasoning
for the exception to the scale point 31 rule explained.
Additional exception reports should also be used to identify instances
where:
 An emergency tax code is used for more than six months
 Payments are in excess of 25% of their basic salary;
 Instances of duplicate bank account numbers exist, and
 There are duplicate names.
Plans should be implemented to have individual files for employees
stored within central cabinets that will be locked outside of the working
hours of the payroll section
In order to evidence that all the checks and tasks associated with
processing a leaver are completed, a single proforma leavers’ checklist
should be introduced, and circulated to the Outstationed Personnel
Teams.
Those accounts which are not yet reconciled on a regular basis, and any
accounts which when subject to monthly visual checks are found to have
a balance, should be formally reconciled and any unidentified balances
investigated. In addition, every effort should be made to resolve all
historic balances prior to year-end.
Management
Response
Agreed
Implementatio
n Date
01/08/2005
Agreed
01/08/2005
Agreed
01/05/2005
Agreed
01/07/2005
Agreed
31/03/2005
3
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE X
Directorate
Subject
PART TWO
Children’s Services
Report
Number
St Clements CE Primary School
Commencement
March 2005
Date
Issued Date
2552
March 2005
Scope
A policy of Post Implementation Review has been formalised by Internal Audit. The
review took the form of a follow-up visit, seeking to confirm that all the agreed
recommendations from the audit have been implemented.
Internal Auditor’s Opinion
Our Post Implementation Review found that eight of the eleven recommendations made in our original
report had been fully implemented.
Of those not fully implemented, we acknowledge that some action has been taken towards their
implementation. However, further action is still required to fully meet the requirements of the
recommendations made.
One more significant matter has yet to be fully resolved. The Pupil Savings account indicates a
difference, estimated to be around £225, between the amount saved and the amount available in the
bank and the cash in hand. Whilst some action has been taken to resolve this, the difference has not
yet been fully reconciled.
Original Main Recommendations
The school should immediately ensure that
sufficient funds are made available in the
Pupil Savings account to reimburse all
relevant individuals to the value of their
savings as recorded in the School Savings
Bank Registers.
The mandate signatories should be
reviewed on an annual basis, with
verification of the signatories being
approved by the school Governors and any
such verification should be minuted.
The Governing body should approve the
scheme of financial delegation on an
annual basis. Any such agreement should
be minuted.
Security arrangements regarding visitors to
the School, at the school should be
enhanced
Original
Management
Response
Agreed
Agreed
Implementation
Date
Current Position
End of July 04
Not fully implemented
Agreed
Mid-June 04
Implemented
Agreed
Mid-June 04
Implemented
Agreed
01.06.04
Implemented
4
Committee Summary
PART ONE
X
Directorate
Customer and Support Services
Subject
Council Tax
PART TWO
Commencement
January 2005
Date
Issued Date
Report
Number
2672
March 2005
Scope
The Council Tax and Benefits Section is based within the Customer and Support Services
Directorate. It is responsible for the processing, billing and collection of Council Tax. A total number
of 92,586 Council Tax bills were issued in March 2004 and net collectable income for Salford City
Council was £63,895,246.
The Council Tax system is a key financial system for Salford City Council. It is also subject to
external scrutiny from the Audit Commission and therefore an annual review is required to ensure the
system is functioning effectively.
The agreed scope of the audit was to identify and evaluate the risks and controls associated with
Council Tax. Key risks being:
 Tax payers not charged
 Tax payers charged wrong amount
 Tax not collected
 Incorrect accounting
 System failure.
Internal Auditor’s Opinion
Overall, the audit testing undertaken confirmed that the Council Tax function is well controlled. The
majority of controls are operating effectively and key risks identified are adequately controlled.
However, a number of weaknesses were identified, the most significant of these were:
 A significant number of items had been posted to the suspense account that had not been
cleared, dating from 5 April 1993 to 8 December 2004
 A review of write-off procedures found that write-offs are not formally assessed to ensure only
appropriate accounts are written-off, prior to Committee authorisation.
Main Recommendations
Old items on the suspense account
should be investigated, monitored
and cleared.
To maximise the effectiveness of all
Council Tax reminder notices, the
format of all the reminder notices
should be reviewed and amended.
Management Response
Unidentified items are subject to prompt
investigation, monitoring and clearance. The 61
uncleared items mentioned are the residue of 3369
items that have found their way into Council Tax
suspense from the commencement of Council Tax in
April 1993. 32 items are DWP payments, which were
received without sufficient information for the PARIS
system to process, these items are currently being
looked at by the Recovery team and will therefore
remain in suspense for the time being. The balance
(29) items will be written off from the Council Tax
suspense account before the 31st March 2005.
The Special Projects Officer is currently reviewing
the wording of reminder notices.
Implementation
Date
31/3/2005
30/4/2005
5
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
PART TWO
St Paul’s CE Primary (Cross Lane)
Commencement
March 2005
Date
Issued Date
Report
Number
2582
April 2005
Scope
Internal Audit audited the School and issued report reference 2582/EDU/04 on the
29th July 2004.
A policy of Post Implementation Review has been formalised by Internal Audit. The
review took the form of a follow-up visit, seeking to confirm that all the agreed
recommendations from the previous audit have been implemented.
Internal Auditor’s Opinion
Seven out of the thirteen recommendations made in our original report have been
implemented as agreed. However, the remaining six recommendations have not
been satisfactorily implemented, including two higher priority matters requiring more
urgent attention:


The approval of the Governing Body for the Scheme of Financial Delegation has
not been recorded in the minutes of the respective meeting
The School inventory schedule is still incomplete and lacks the necessary detail
required.
Original Main
Recommendations
The school should create
an inventory record which
shows all items valued at
over £100.
The bank mandates
should be reviewed and
approved by the School
Governors on an annual
basis.
The scheme of financial
delegation should be
reviewed and approved
on an annual basis.
Original
Management
Response
Agreed
Agreed
Implementation
Date
End of the Spring
term, 2004.
Agreed
End of the
Autumn term,
2004.
Agreed
End of the
Autumn term,
2004.
Current Position
Not fully implemented. The
School has started to create
a paper-based inventory,
however it does not include
all the required information.
Implemented
Not fully implemented
The approval was not
recorded in the minutes of
the respective meeting.
6
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART
TWO
PART ONE
X
Directorate
Customer and Support Services
Subject
Payments and Receipts 2004/05
Commencement
March 2005
Date
Issued Date
Report
Number
2573
April 2005
Scope
PARIS interfaces with the Council’s Financial Systems and automatically allocates inbound transactions to
the correct funds, e.g. Saffron Rents, Council Tax / Benefits, and the SAP system. Items that are not
recognised by PARIS as belonging to a known fund are held in a suspense file in PARIS and these require
manual intervention to force processing.
Internal Audit reviewed the Payments and Receipts system and issued a report, reference 2573/CS/04 on
16th August 2004.
A policy of Post Implementation Review has been formalised by Internal Audit. A follow-up visit was
undertaken seeking to confirm that all the agreed recommendations from the previous audit have been
implemented.
Internal Auditor’s Opinion
The Post Implementation Review identified that three out of the four recommendations have been
appropriately implemented. The remaining recommendation had not been implemented as recommended in
the above audit report, however, satisfactory compensating controls are in place.
Agreed
Implementatio
n Date
Original Main
Recommendations
Original Management
Response
The notes on bills and
invoices, describing the
different methods of making
payments, should be revised
to advise customers to
obtain and retain a receipt as
evidence of payment.
All stakeholders will be
advised to amend their
bills and invoices to
reflect the message
that customers should
obtain a receipt at the
time of payment.
Immediate.
A new vetting procedure at
the recruitment stage is
being introduced. However,
it is not planned to include a
criminal record check. It is
recommended that the new
recruitment vetting process
be extended to include
criminal record checks.
This matter will be
referred to Personnel
as a matter of urgency
for their consideration.
(Personnel are
currently reviewing
similar changes to
Benefits recruitment).
Immediate
Current Position
Not implemented
The Section Leader (Cashiers) has
no direct control over bills / invoices
issued. Recent e-mail sent to all
Fund Managers requesting that they
should include “obtain receipt as
proof of payment” on all
documentation.
Note, when customer pays via Pay
Point, the receipt advises the
customer to retain the receipt for
proof of payment. Discussions will
be held with Alliance & Leicester (for
Post Office Ltd) to see if “retain
receipts as proof of payment” can
be added.
The current PARIS system allows
staff to trace payments.
Implemented
7
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Customer and Support Services
Subject
PART TWO
Report
Number
Treasury and Cash Management
Commencement
January 2005
Date
Issued Date
2690
February 2005
Scope
On an annual basis, an audit review of the Treasury Management (Loans and
Investments) process is undertaken by Internal Audit. The objective of the review is
to provide management with an independent appraisal of the adequacy of controls in
place over the key processes within the Treasury Management system. The review
was undertaken using information and transactions specific to the financial year
2004/05.
The agreed scope of the audit was to identify and evaluate the risks and controls
associated with loans and investments. The key risks were identified as follows;
Inappropriate borrowing; Incorrect repayments; Incorrect accounting treatment;
Systems failure; Monitoring, review and reporting; Inappropriate investing; Loss of
investment/interest income; Incorrect accounting.
Internal Auditor’s Opinion
The audit testing undertaken confirmed that the Treasury Management function is
well controlled. All the controls that were tested were operating effectively and the
key risks are adequately mitigated, as a result no audit recommendations are
deemed necessary.
Main Recommendations
Management
Response
Implementation
Date
No recommendations made
8
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
All Souls RC Primary School
Commencement
March 2005
Date
PART TWO
Issued Date
Report
Number
2711
April 2005
Scope
The standard objectives of a school audit are to provide an independent appraisal of
the adequacy of controls in key functional processes that operate within the school:
 Financial Management;
 Financial Administration
 Asset Management
 Pupil Welfare
 Contracted/Traded Services.
Internal Auditor’s Opinion
The School is in a deficit budget position. The agreed deficit for 2003/04 was reported as £11,358 and
was originally forecasted to increase to £47,895 by the end of 2004/05. Tight control over expenditure
has resulted in the latest projections anticipating a lower deficit of £19,248 at year-end, which suggests
prudent financial management.
We found that adequate controls were in place in most of the areas reviewed. The audit did highlight a
number of areas requiring attention to enhance the control environment., which are noted below.
Main Recommendations
The Headteacher should carry out periodic spot-checks on the cash
prepared for banking
The Governing Body should approve the Scheme of Financial Delegation
on an annual basis.
The School should complete and maintain an inventory of all items
greater than £100 in value.
An independent person should annually audit the School Fund. The
resultant audit report and a summary of income and expenditure should
be presented to the Governing Body.
The School should renew its data protection registration at the earliest
opportunity.
The School should complete a new bank mandate and the signatories
should be approved by the Governing Body.
The School's accounts should be formally reconciled on a monthly basis.
The Secretary should be provided with training on the CIS and its
requirements which impact upon her role in processing orders and
invoices.
When orders are processed, the order forms should be signed and dated
by the authorising person e.g. the Headteacher or Deputy Headteacher.
When invoices are processed for payment, cheque signatories should
sign and date the invoice.
The Headteacher should document her strategy to meet the budget and
her reasoning for decisions taken. In order to ensure appropriate
management of the budget, these details should be reviewed by the
Governing Body or Finance Sub-Committee at each meeting.
Management
Response
Agreed
Implementati
on Date
01/04/05
Agreed
01/11/2005
Agreed
01/09/2005
Agreed
21/06/2005
Agreed
18/03/2005
Agreed
01/11/2005
Agreed
Agreed
01/06/2005
1/09/2005
Agreed
18/03/2005
Agreed
01/04/2005
9
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Customer and Support Services
Subject
Main Accounting System
PART TWO
Commencement
February 2005
Date
Issued Date
Report
Number
2684
April 2005
Scope
The Main Accounting System at Salford City Council is run on the SAP system. To
ensure all balances are accounted for within SAP, all other systems feed into SAP on
a regular basis. At the end of each financial year, SAP is utilised to produce Salford
City Council financial statements.
The objective of the review is to provide management with an independent appraisal
of the adequacy of the controls in place over the key processes within the Main
Accounting System. The review was undertaken using information and transactions
specific to the financial year 2004/05.
The results of the review are also subject to external scrutiny by the Audit
Commission. The Audit Commission also seek assurance that the key risks
associated with the Main Accounting System are adequately controlled and
functioning effectively.
The agreed scope of the audit was to identify and evaluate the risks:
 Opening balances not in agreement with the audited accounts
 Inaccurate reflection of the Authority’s financial position
 Main accounting system not in balance
 Incomplete / inaccurate transactions from feeder systems
 Unauthorised / erroneous transactions
 Balances not accurately accounted for.
Internal Auditor’s Opinion
Overall, the audit testing undertaken confirmed that the Main Accounting System is
well controlled. The majority of controls are operating effectively and the key risks
identified are adequately controlled.
However, a weakness was identified in the audit that related to payroll reconciliations
being incomplete. In addition, weaknesses were identified via a review undertaken by
Computer Audit of SAP Technical (Report ref 2646/CS/04), none of which were
considered to present a high risk.
Main Recommendations
Management Response
The outstanding payroll
reconciliations should be
completed and action taken
on the unidentified items.
Payroll control accounts were
identified twelve months ago
warranting further investigation. A
dedicated resource was applied and
reconciliations completed for most
accounts. Of the remaining two, one
is now complete and the other close
to completion. Decisions on
unidentified items are planned during
final accounts process.
Implementation
Date
31/5/2005
10
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
PART TWO
Report
Number
Brentnall Primary School
Commencement
April 2005
Date
Issued Date
2727
April 2005
Scope
To provide an independent appraisal of the existing controls in key functional
processes operating within the school.
Internal Auditor’s Opinion
We are of the opinion that the school has adequate controls in place, which are
generally operating effectively in most of the areas reviewed.
However, the review did identify areas where improvements are needed to the
control environment. The most significant areas identified are as follows:
 The requirement to establish a Register of Business Interests
 Approval of the Scheme of Financial Delegation
 Independent review of trip records.
Main Recommendations
The Governing Body should establish a
Register of Business Interests, which
should be completed for the Headteacher,
all members of the Governing Body and
their partners.
Once a school trip has taken place the
balance sheet on the Trips Check List
should be fully completed for transparency.
The Headteacher should sign the sheet to
verify his review and approval.
The Scheme of Financial Delegation should
be approved by the Governing Body on an
annual basis and this should be
documented officially within the minutes of
the Governing Body meeting.
Management
Response
Agreed
Implementation
Date
14.6.2005
Agreed
30.4.2005
Agreed
18.4.2005
11
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
St Luke’s RC Primary School
Commencement
March 2005
Date
PART TWO
Report
Number
Issued Date
2702
May 2005
Scope
The standard scope and objectives of schools’ audits have been determined to
provide an independent appraisal of the adequacy of controls in key functional
processes that operate within a school. These include financial management;
financial administration; asset management; pupil welfare; and contracted/traded
services.
The School has experienced financial difficulties in recent years although savings
have been made which have alleviated the situation. The School has recently
received Head Room Funding, which has almost eliminated the budget deficit.
Internal Auditor’s Opinion
We are of the opinion that the School achieves a high standard of administration,
despite recent difficulties in respect of staffing levels and has adequate measures in
place to control the majority of risks within the key processes examined.
Main Recommendations
The need for the School to work closely
with the Education Accountant to ensure
that future budget projections are suitably
devised and implemented.
An improvement in arrangements regarding
an independent review of trips and the
introduction of a comprehensive costing
sheet to be used at the conclusion of trips.
The requirement to bring the School’s
inventory record up-to-date and to ensure
that all significant items are recorded and
reviewed annually.
Management
Response
Agreed
Implementation
Date
29 May 2005.
Agreed
30 June 2005.
Agreed
27 May 2005.
12
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
PART TWO
Report
Number
St Paul’s C.E. Primary School
Commencement
April 2005
Date
Issued Date
2728
May 2005
Scope
The standard objectives of a school audit are to provide an independent appraisal of
the adequacy of controls in key functional processes that operate within the school,
such as:
 Financial Management
 Financial Administration
 Asset Management
 Pupil Welfare
 Contracted/Traded Services.
Internal Auditor’s Opinion
In our opinion the School is well run and receives strong support from its Governing
Body. The majority of the risks are well managed and its management team have
shown prudence in their financial planning and expenditure in order to manage the
current budget deficit. However, our review found a number of areas where the
control environment should be enhanced, the more significant of these were:
 The governance controls in place for the school fund are weak. The fund is not
independently reviewed on an annual basis, and a statement of account, detailing
income and expenditure, is not presented to the Governing Body
 The bank mandates for the School's two accounts are not up-to-date. Both
include a former member of staff
 All schools are required to register with the Information Commissionaire as data
controllers, however the School is not currently registered.
Main Recommendations
The school fund should be formally reconciled at least
quarterly and independently audited on an annual basis.
In addition, a statement of the fund's income and
expenditure should be provided to, and reviewed by, the
Governing Body annually.
The School's bank mandates should be updated. The
Governing Body should review and approve the
changes.
The School should compete its registration with the
Information Commissioner at the earliest possible
opportunity.
Management
Response
Agreed
Implementation
Date
01/07/2005
Agreed
01/06/2005
Agreed
01/06/2005
13
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART
TWO
PART ONE
X
Directorate
Children’s Services
Subject
Report
Number
Wentworth High School
Commencement
April 2005
Date
Issued Date
2585
May 2005
Scope
A policy of Post Implementation Review has been formalised by Internal Audit. The
review took the form of a follow-up visit, seeking to confirm that all the agreed
recommendations from the audit have been implemented.
Internal Auditor’s Opinion
Our Post Implementation Review found that the majority of the recommendations
made in our original report had been fully implemented.
Only those recommendations relating to the inventory record have not yet been fully
implemented, although significant progress has been made in this area and the
improvements achieved are in line with the timescale previously determined.
Original Main
Recommendations
An exercise should be
undertaken to bring the
School’s inventory records
up-to-date, along with an
improved system to ensure
that loaned items are
appropriately signed back
upon their return.
Staff should be vigilant to
ensure that the door to
the main entrance is kept
firmly closed.
Original
Management
Response
Agreed.
Agreed
Implementation
Date
Agreed.
Immediate.
End of summer
term 2004.
Current Position
On schedule for
implementation.
Implemented
14
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
St Luke’s CE Primary School
Commencement
March 2005
Date
PART TWO
Report
Number
Issued Date
2703
May 2005
Scope
The standard scope and objectives of school’s audits have been determined to
provide an independent appraisal of the adequacy of controls in key functional
processes that operate within a school. These include financial management;
financial administration; asset management; pupil welfare, and contracted/traded
services.
The current Headteacher will be retiring at the end of the summer term 2005, after
more than 20 year’s service at the School.
Internal Auditor’s Opinion
We are of the opinion that the School achieves a high standard of administration, and
has adequate measures in place to control the majority of risks within the key
processes examined.
Main Recommendations
The school should determine an
improvement to the security of the School’s
funds whilst participating in trips, by finding
an alternative to the use of presigned
cheques to pay for activities.
The need to undertake a review of the
records held in the STAR system to ensure
that records held are comprehensive and
up-to-date.
The requirement to ensure that the
inventory record is accurate and up-to-date
by undertaking an annual review.
The need for the Headteacher to ensure
that the Register of Interests is completed
promptly and retained on file for reference.
Management
Response
Agreed.
Implementation
Date
10 June 2005.
Agreed.
Already
implemented.
Agreed.
01 July 2005.
Agreed.
16 May 2005.
15
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Environmental Services
Subject
PART TWO
Report
Number
Waste Arisings
Commencement
February 2005
Date
Issued Date
2716
May 2005
Scope
The agreed scope of the review was to:
 Ascertain how waste from other sources is accounted for. This includes waste
from the Highways Department, New Prospect Housing, and other contractors.
 Benchmark Salford City Council with councils of a similar nature.
 Check the accuracy of the data from Greater Manchester Waste Disposal
Authority.
 Ensure that all waste is categorised as Household Waste Arisings.
Internal Auditor’s Opinion
Our review of the data provided by GMWDA highlighted a number of control
weaknesses that need to be addressed by management.
We are concerned that the City Council could not reconcile the recycled waste to the
claim, or the domestic waste arisings to the schedule of waste arisings provided by
GMWDA. Invoices for chargeable waste (Grounds Maintenance etc.) that do not
reconcile to the tonnage charged are paid without query.
Due to the number of anomalies within the system, we did not feel that it was
appropriate to benchmark the figures to other councils.
The reason for the increase in domestic waste arisings is difficult to ascertain due to
the weaknesses in the control environment .Based on the findings of the audit there
is every possibility that the errors highlighted are duplicated in the domestic waste
arising figures that are not controlled.
Main Recommendations
Internal Audit made 6 recommendations that
were considered to be high priority.
Management have accepted the findings and
have agreed to action them immediately.
Management
Response
All Agreed
Implementation
Date
April 2005
16
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
Lewis Street Primary School
Commencement
April 2005
Date
PART TWO
Report
Number
Issued Date
2717
May 2005
Scope
The standard scope and objectives of school’s audits have been determined to
provide an independent appraisal of the adequacy of controls in key functional
processes that operate within a school. These include financial management;
financial administration; asset management; pupil welfare, and contracted/traded
services.
Falling rolls at the School have resulted in the threat of closure or the potential
amalgamation with a neighbouring School, Christ Church CE, although a final
decision has not yet been taken. The current Headteacher will be retiring at the end
of the summer term 2005, and arrangements are in hand to appoint an Acting Head
until such time as a formal appointment is made in respect of a permanent
replacement.
Internal Auditor’s Opinion
We are of the opinion that the School achieves a high standard of administration, and
has adequate measures in place to control the majority of risks within the key
processes examined.
Main Recommendations
The need for the School to agree and
implement suitable recovery plans to
reduce and eliminate the budget deficit
within a specified timescale.
The requirement to reintroduce and
appropriately complete the official LEA
Finance Stamp and ensure that orders are
appropriately authorised.
The requirement to bring the School’s
inventory record up-to-date and to ensure
that all significant items are recorded
appropriately.
Management
Response
Agreed.
Implementation
Date
16 May 2005.
Agreed.
16 May 2005.
Agreed.
31 October
2005.
17
Committee Summary
PART ONE
X
Directorate
Education and Leisure
Subject
Salford Community Leisure
Commencement
April 2005
Date
PART TWO
Report
Number
Issued Date
2708
May 2005
Scope
Salford Community Leisure (SCL), on behalf of Salford City Council (SCC), provides and manages
sports and leisure services. Currently, a management agreement is in place between SCL and the
Directorate of Education and Leisure. However, this is expected to change in September 2005 and the
Directorate of Community Health & Social Care is expected to take over the management agreement
with SCL.
The review sought to ensure appropriate monitoring arrangements are in place and that SCL are
providing a value for money service.
The key risks were identified as:
 Management agreement is not authorised, monitored, and reported on a regular basis
 Quality of service and performance is not monitored and reported on a regular basis
 Inaccurate reflection of the Salford Community Leisure financial position.
Internal Auditor’s Opinion
Overall, the audit review undertaken confirmed that the monitoring arrangements between SCL and
SCC are well controlled. Two issues were identified, these were:
 Directorate of Community Health & Social Care will assume responsibility for the monitoring of the
management agreement with SCL in September 2005, and it is essential that a proper handover
period is planned.
 The current performance indicators in place do not enable SCL and SCC to measure accurately if
they are meeting their strategic aims.
Implementation
Main Recommendations
Management Response
Date
The Directorate of Community
The recruitment process for an Assistant
01/09/2005
Health and Social Care should
Director for Culture and Sport is about to
ensure a member of staff is
commence, with the intention of having a new
appointed prior to the handover, in
appointment in place by September 2005. If
order to familiarise themselves with
this is not achieved other arrangements will
the systems utilised by the current
be made to ensure a smooth transition of the
Directorate. This will ensure that
monitoring responsibility for SCL to the
there is a smooth handover and that Community, Health and Social Care
controls are retained when
Directorate.
monitoring the service and
performance of SCL.
The current working group should
The Audit Commission is currently reviewing
01/08/2005
ensure that the performance
the BVPIs for cultural services as part of its
indicators are designed to enable
work on CPA 2005 and is expected to make
SCC and SCL to measure the impact final decisions on the BVPIs for culture and
activities are having on particular
sport by July 2005. SCC proposes to use the
targets and if SCC and SCL are
PIs introduced by the Audit Commission as
meeting their strategic aims and
part of the suite of PIs it will utilise for the
goals.
performance management of SCL and will add
to these some local indicators, which the
working group is currently preparing.
18
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Children’s Services
Subject
PART TWO
Report
Number
St George’s CE Primary School
Commencement
April 2005
Date
Issued Date
2747
May 2005
Scope
The standard scope and objectives of schools’ audits have been determined to
provide an independent appraisal of the adequacy of controls in key functional
processes that operate within a school. These include:
 Financial management
 Financial administration
 Asset management
 Pupil welfare
 Contracted services.
Internal Auditor’s Opinion
The School maintains a high standard of administration although there is a recurring
theme in that checks undertaken are not always evidenced and therefore cannot be
substantiated.
Main Recommendations
The Governing Body should approve the
Scheme of Financial Delegation.
Information in relation to pupils held on
SIMS.net should be kept up-to-date and
reviewed periodically.
Management
Response
Agreed
Implementation
Date
29.6.05
Agreed
7.5.05
19
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Community, Health and Social Care
Subject
PART TWO
Strategy for care first (and related systems)
Commencement
October 2004
Date
Issued Date
Report
Number
2660
February 2005
Scope
The aim of the audit was to determine the degree of control over the following risk
areas:
 Development/ maintenance of the strategy
 Delivery of the strategy
 Meeting business needs
Internal Auditor’s Opinion
The audit has concluded that there was substantial awareness of the key risks likely
to affect the development and delivery of a strategy for Care First and related
systems. Controls were already in place and Directorate and System Support Unit
(SSU) management have recognised that these require enhancing, to manage the
effects of the Authority re-structure and the technological changes arising from the
need for practitioners to operate within a corporate, regional and national framework.
They also recognise that the controls will need to be established within the context of
the drive to align all systems and services with one or more of the Council’s seven
pledges. It should be noted that some controls were intended rather than actual, e.g.
the proposals for a Care First programme board, and considerable effort will be
needed over the coming months, to ensure that good overall and IT governance
processes are applied and then sustained.
Main Recommendations
A Care First strategy document should be
developed, for use by the proposed Care First
Programme Board. This could be an extract from
the overall ICT Strategy, but should be in an
appropriate format for the Board to use in
overseeing the development of Care First.
The governance processes for controlling the
strategy should be embedded within it or links
should be made into processes already
incorporated within the overall ICT strategy.
Management Response
Agreed.
Implementation
Date
April 2006
A Care First strategy
document will be presented to
the Care First programme
board.
A recommendation will be
made to the Care First
Programme board to review
this strategy to ensure that
the appropriate links are
made with the following ICT
strategies:
20



The Housing Services
Directorate
The Children’s Services
Directorate
The Community Health
and Social Care
Directorate
The strategy will be
developed cognoscente of the
list of items contained within
the appendix
The SSU and Principle Officer (MI and
Performance) should carefully monitor ongoing
developments relating to corporate records
management policies and systems.
The AGMA consultant to the DPA/FOI Steering
Group has highlighted a number of particular risks
relating to the development of electronic records
management systems (ERMS) and electronic
document management systems (EDMS)
potentially affecting AGMA authorities in general.
These should be borne in mind, when creating the
strategy for Care First.
Those risks which may be of most relevance are
as follows:
i) Care First specialists may interpret specific
terms e.g. “archiving”, differently to records
management specialists
ii) Corporate systems procured may fail to take
into account existing or proposed systems for
ERMS and EDMS related to Care First.
Conversely, Directorate systems could become
out of line with corporate systems
iii) There may be differing interpretations of
various records management standards, e.g.
BS15489 Records Management, E-Government
meta-data standard (E-GMS) and the National
Archives functional specification for ERMS/EDMS
iv) New systems and modules may be
implemented that have no records management
functionality or cannot integrate with corporate
ERMS/EDMS systems.
The Principal Officer (MI &
Performance) performs the
Caldicott Guardian role and
heads the Caldicott steering
group and is also the
Directorate lead officer for
Freedom of Information. SSU
also have a representative on
this group and this forum will
provide the framework for
monitoring ongoing
developments relating to
corporate records
management policies and
systems.
Ongoing
21
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
Directorate
Subject
X
PART TWO
Children’s Services
SIMS/EMS Data Management
Commencement
November 2004
Date
Issued Date
Report
Number
2675
March 2005
Scope
The aim of the audit was to determine the degree of control over the following risk
areas:


Security and backup of SIMS*/EMS data
Impact of legislative, regulatory and policy requirements on the management of
SIMS*/EMS data, e.g. those arising from the Freedom of Information and Data
Protection Acts (FOIA and DPA respectively)
*In respect of SIMS, the audit only covered data once transferred from the schools to
the Directorate’s Storage Area Network (SAN) drive R, prior to import into EMS.
The audit focussed on the management of EMS data, but it is acknowledged that
many of the current legislative and policy requirements impacting on LEAs also affect
data not recorded on EMS. It should also be noted that the IT Net Desktop Services
Unit administer the SAN drives used by the Directorate, e.g. in terms of user/system
access, but a full review of their involvement was outside of the audit scope
It is likely that further audit work will be undertaken in respect of EMS data
management issues as part of the 2005/2006 audit plan.
Internal Auditor’s Opinion
The audit has concluded that the risks relating to the security and backup of SIMS
import/EMS data are reasonably well controlled. However, for greater assurance, the
EMS Co-ordinator needs to establish that the access levels on the various
administration user accounts are reasonable, including those enjoyed by Desktop
Services. There is also a need to enhance the user procedures relating to leavers
and job transfers.
Regarding legislation and policies impacting on the management of SIMS/EMS data,
much work is being done in Strategic Support to manage the issues relating to legal
compliance and policy adoption. However, there will need to be greater senior
management buy-in within the Directorate, in terms of providing resources and
sponsoring working groups, if the regulations and policies are to be properly
embedded within the context of such drivers as the E-Government targets,
collaborative working, best value, customer relationship management initiatives and
the seven pledges and sub pledges.
22
Main Recommendations
A review should be undertaken of user
accounts with access to the EMS-related
folders on the SAN R: drive and the SAN E:
drive containing the EMS database.
The review should establish for each
account:
i) If it is needed or whether the same
functions can be undertaken using
another account
ii) Whether the access permissions
within the account are set at the right
level for routine administration
functions, e.g. does “allow” need to be
switched on for Full Control, Modify,
Read & Execute, etc. *
iii) Whether Desktop Services access is
appropriate
Management
Response
This review is
currently underway
and the points noted
will be incorporated
into that review. The
result will be a
procedure for
assessing the
appropriate access
rights for individuals
and new users.
Implementation
Date
June 2005 for
implementation
before the next
school year.
The issue of desktop
services access will
be reviewed
separately under
discussion with
Corporate IT.
iii) That default passwords have been
changed for default accounts such as
System and Domain Admins.
*System administrators often reduce their
own access levels on certain user
accounts, in order to limit the amount of
damage an unauthorised user could cause.
A formalised system should be introduced
for identifying and administering EMS users
who leave the Directorate or transfer jobs
within the Directorate.
Work is ongoing with
Corporate IT to be
included in the loop
for closedown of
email and computer
access.
April 2005
Managers of each unit should be asked
which staff have a need to access the EMS
system and which modules they should be
using. As a complementary control, the
emailing function built into the EMS user
detail screens could be exploited, e.g. users
could be asked to confirm their post and
section/unit. Where no response is
received within a pre-determined period,
the user should be de-activated.
It is hoped to include
this user directory
function as part of
the above review
(F1)
June 2005
An Intranet-based access administration
system for starters and leavers is being
considered for inclusion within the
corporate Employee Portal, which is under
development within the E-Government
programme. This should be borne in mind
when devising a more formal system for
Noted.
Ongoing
23
EMS or, for example, EMS could be used
as a pilot system.
The number of failed password attempts
allowed at EMS log-on should be reduced
from ten to three.
Strategic Support should investigate the
options for obtaining appropriate knowledge
and/or advice in respect of the legislation,
e.g. Learning and Skills Act, Education Act,
Health Authorities Act, etc., impacting on
the sharing of data between the LEA and its
partners.
In the first instance
this will be reduced
to 5 with a review
later.
Discussions with
corporate Legal
team are to be
arranged with a view
to assessing the
implications of
legislation on data
sharing and storage
within the current
systems and
structures.
February 2005
March 2006
Possible options are:
i) Formally establishing whether there
is a representative within the
Authority’s legal team, already
specialising in these areas, who could
be periodically consulted
Opportunities for
sharing information
with other
directorates will be
explored.
ii) Establishing the level of knowledge
within the Community, Health and
Social Care directorate. A small jointworking group could be set up to
examine the key issues, which could
be a sub-group of an existing group,
e.g. one of those already meeting to
deal with Authority re-structure issues
iii) Investigating the possibility of using
an area approach to the issue, e.g. an
AGMA-funded consultant, or of using
existing legal services provided under
the AGMA Joint Services Delivery
initiative
Note: Recommendation F4 is offered to
provide independent support for any
ongoing actions in this area.
The resources situation should be reviewed
in respect of the workload of the Data
Validation Group and the following factors
taken into account:
i) New controls/procedures will need to
be embedded, to sustain the integrity of
EMS data, once the existing data has
been cleansed, in order that credible
management information can be
produced from EMS
ii) New EMS modules are due to be
Whilst it is
appreciated that the
EMS team is under
resourced and that
the validation of the
data and the roll out
of new modules is
being delayed, it
needs to be
understood that the
directorate is in a
September
2005
24
implemented, leading to an increase in
the amount of data recorded on EMS,
potentially adding to the existing
reliability problems
iii) Implementation of the Capita B2B
module will mean greater integration
between SIMS and EMS, but could
bring new data integrity risks.
iv) Priorities are changing in respect of
the management of EMS data, e.g. the
need to ensure data integrity is
becoming more pressing, as the extent
of data sharing initiatives widens.
A working group should be set up within the
Directorate (or an existing one identified), to
oversee compliance with corporate
policies/legislation, e.g. the FOIA,
appertaining to non-personal EMS data.
Regarding the specific issue of retention
and destruction schedules for EMS data,
consideration should be given to drawing
up schedules, pending the introduction of a
working group.
Note: To ensure consistency, such a
working group would also need to tackle the
issues for data not recorded on EMS.
The Strategic Support Unit should carefully
monitor ongoing developments relating to
corporate records management policies,
including the introduction of electronic
records management systems (ERMS).
Risks likely to be of relevance to EMS are
as follows:
i) IT and Education specialists may interpret
the term “archiving” differently to records
management specialists
ii) Directorate systems procured, e.g. EMS
modules, may be out of line with Corporate
systems procured for ERMS
iii) Directorate policies/standards relating to
EMS may become out of line with various
records management standards, e.g. ISO
15489, E-Government meta-data standard
(E-GMS) and the National Archives
functional specification for ERMS.
If a working group was set up or identified,
as recommended in F6, then the group
should manage the above risks.
state of change.
These
considerations will
be taken into
account and will be
addressed along
with the overall
reorganisation.
A strategy Group will
be set up with AD
representation and
Senior Managers
from within the
Directorate. They
will oversee the
compliance stated
but will also look at
the wider strategic
implications of EMS
(and SIMS)
April 2005
The Strategic group
above will be
supported by a
working group that
will be made up of
users and
‘champions’ of the
system.
September
2005
These issues will be
raised in both these
forums and with help
from the partnership
information officer
and contacts with
the corporate FOI
and DP teams the
issues will be
addressed.
25
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Community & Social services
Subject
PART TWO
Report
Number
NHS NET
Commencement
January 2005
Date
Issued Date
2679
April 2005
Scope
The audit will assess the degree of control over the key risks threatening the
management of NHS Net, in relation to the following aspects:
 Access Controls
 Data Security
 Availability of data
 Security and reliability of data transported
Internal Auditor’s Opinion
Access controls were adequate, but there was some question over whether they
complied with NHS requirements, investigation revealed that the NHS position was
shifting.
There was an issue concerning the maintenance of the access of leavers and
movers.
A project was outstanding to implement a new server to monitor firewall activity.
Non-disclosure agreements were issued, but procedures in place did not ensure they
were completed and returned prior to access being granted.
There are single points of failure, in that if a communications line into a building fails
then NHS systems will not be accessible.
Users are required to use a number of methods / products to access email
messages.
Stronger change control procedures are needed to meet NHS requirements.
There was a question about the security of email messages coming in from the NHS
to SCC staff.
Main Recommendations
Management Response
To ensure access to NHSnet systems, funding must
be obtained to implement strong two-factor
authentication.
Accepted, however
recent advice from the GMSHA
Deputy CIO is that
authentication requirement is
now at application level.
Funding will be sought to
address the authentication
requirements of the Registration
Authority.
Discussions have taken place
with the Directorates HR team.
A process of identifying leavers and movers should
be put in place and a process developed to ensure
Implementation
Date
9 Months
3 Months
August 2005
26
that access is maintained in a timely manner.
It is recognized that a corporate solution is being
developed although no delivery timescale has been
agreed.
The implementation of the firewall monitoring server
should be completed as soon as possible.
Procedures should also be put in place to ensure
that appropriate analysis is applied to the logs
generated.
Consideration should be given to introducing an
Intrusion Detection System on the SCC network to
give a greater strength in depth against the
possibility of unauthorised access.
Procedures should be developed to ensure that the
confidentiality and non-disclosure forms are signed
and returned before access to systems is allowed.
Agreed that a report will be
commissioned from the system
supplier to meet this
requirement.
Authorised previously by this
Directorate. We will continue to
liase with the IT services team to
completion.
Discussions will be held with
relevant parties to determine the
most effective analysis is applied
to the logs generated.
We have been advised by IT
Services that this
recommendation is “Already part
of other Audit reports and as
agreed with Audit, can be
consolidated into 1
recommendation covering
several audits”.
Accepted.
Discussions will be held with
relevant parties to determine
most effective procedure.
A business impact analysis should be carried out to
Network resilience is considered
determine if the lack of resilience for the NHSnet link as part of the ongoing
exposes the organization to significant risk.
implementation of the link.
It is accepted that a business
impact analysis should be
undertaken. Action will be taken
accordingly.
A review of the NHSnet connection configuration
Agreed
should be carried out, on at least annual basis to
A review process will also
ensure that SCC remains compliant with the code of determine the appropriate review
connection.
period (minimum annually)
In accordance with guidelines from NHSIA the Head
A process for approving changes
of Social Services or a nominated deputy should
to the NHSnet connection
approve changes to NHSnet connection
configuration has been agreed.
configuration.
Discussions should be entered into with NHS
partners regarding strengthening the security of data
Discussions have already taken
emailed from NHS to SCC. Options include:
place and are continuing with NHS

Routing traffic down the secure line
partners and SCC Corporate
services regarding strengthening

Encrypting emails
email security.
Additionally, SCC staff working from NHS premises
should be periodically reminded not to send
confidential e-mails / attachments from NHS
equipment to SCC due to the risk that the email may
be routed through the Internet.
2 Months
3 months /
August 2005
4 months
2 months
Done
3 Months
Agreed.
Periodic reminders will be given to
staff regarding the Corporate
Information Security Policy.
27
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
Customer and Support Services
Subject
Sx3 (Council Tax and Benefits replacement
system) Readiness. Phase two. UAT
Commencement
April 2005
Date
PART TWO
Issued Date
Report
Number
2732
May 2005
Scope
The aim of our review was to ascertain the level of readiness for go-live and to identify any
potential issues or risks that may prevent or delay the successful implementation of Sx3. In
order to produce timely reports and manageable work packages, we adopted a phased
approach. This summary refers to phase two of the work, which provides an opinion upon the
adequacy of the user acceptance testing. (UAT)
Internal Auditor’s Opinion
The UAT processes have been well designed and managed but the bulk of the business
process testing was carried out in August 2004 using early versions of the software and before
many of the bespoke services and reports had been delivered. Sx3 functionality has been
proven through its use by other councils and therefore the main risks lie with the bespoke
interface work and reports. User testing is continuing via weekly, half day familiarisation
sessions and modular tests of the bespoke work delivered but this cannot provide the end-to
end assurance of a full UAT using the latest version of the software and all the related
interfaces, batch schedules and reports. In their response to this audit, management have
confirmed that all key areas will be tested before go live. This is planned for week
commencing 6th June 2005 with go live following on 20th June which leaves only one week to
resolve and retest any issues.
Main Recommendations
The project board should arrange for a full
end-to-end test prior to go-live.
The project board should assess and agree
the responsibilities for the ownership,
security / integrity and maintenance of the
existing council tax and benefits
applications, following Sx3 go-live. This
could be considered as part of the related
work on systems management. (Audit
report 2729/CSS/2005.)
Management Response
End to end testing is covered
in part by the system testing
task which links in with the
testing of the batch schedule.
As individual testing of
interfaces, reports and
documents are completed they
will be included in these tests.
All individual items may not be
included in the system testing
due to time constraints.
S. Fryer has had preliminary
discussions with I.T. Services
about the on-going use of the
in-house system and future
discussions will include these
issues.
Implementation Date
Batch schedule
testing started April
18th System testing
was due to
commence May 9th
but will now only run
for one week w/c
June 6th.
Complete
28
Committee Summary
PART ONE
X
Directorate
Customer and Support Services
Subject
Sx3 (Council Tax and Benefits replacement
system) Readiness. Phase one. Status
Commencement Date
PART TWO
April 2005
Issued Date
Report
Number
2721
May 2005
Scope
The aim of our review was to ascertain the level of readiness for go-live and to identify any potential issues or
risks that may prevent or delay the successful implementation of Sx3. In order to produce timely reports and
manageable work packages, we adopted a phased approach. This summary refers to phase one of the work,
which provides an overview of the current status of the development. Phase two will cover the user
acceptance testing and phase three the data migration and cutover.
Internal Auditor’s Opinion
The audit has concluded that the risks relating to SX3 readiness are reasonably well controlled by the project
manager but we are concerned that there is little assurance, at project board level, that the outstanding
developments, issues, risks, interfaces etc will be completed and solutions to problems found, in time for the
“go live”.
This was an interim report that has been prepared to flag up key risks in time for the 21st April project board
meeting. Some of our recommendations are made to provide guidance and advice in areas that are still
under review and others are made in order to obtain confirmation that any potential showstoppers have been
identified and are being managed.
Main Recommendations
The project board should ensure that all outstanding tasks, issues
and risks are prioritised, given owners, resource requirements and
achievable completion dates.
Implementati
on Date
Complete
Management Response
Agreed
The project board should assess the status of each reconciliation
and the likelihood of achieving a balance.
A decision should be taken as to which reconciliations are vital
prior to go live. Where reconciliation is unlikely to be achieved they
should assess the risks of accepting the SX3 balance in favour of
the existing totals.
Agreed. The errors in Cut 5
cannot be corrected and
tested before go live so the
system will go live with
known reconciliation
failures. These will be
investigated and corrected
in the live system.
The project board should assess the status of data cleansing and Low risk
the potential effects upon the integrity of SX3 should cleansing not No significant issues with
be completed prior to go live.
data cleansing
The project board should ensure that all interfaces are signed off This will be arranged for all
as accepted at an appropriate management level within the out feeds.
partner/stakeholder area.
The project manager should agree the priority levels allocated to Agreed
each interface to ensure that every vital interface will be available
at go live.
The project board should identify all outstanding testing and ensure Superseded by UAT report
that this can be effectively completed before go live?
(2732/CSS/05) One week
of end-end testing planned
for W/C 6th June
The project board should identify the resource and skill Ongoing. SH, SF and MV
requirements from now up until the backlog has been cleared and meet regularly to monitor
identify and action any potential conflicts for resources or progress and issues
bottlenecks of work.
29
10 June 05
Complete
30 May 05
Complete
10 June 05
Complete
AUDIT & RISK MANAGEMENT UNIT
Committee Summary
PART ONE
X
Directorate
CUSTOMER & SUPPORT SERVICES
Subject
PART TWO
Report
Number
FREEDOM OF INFORMATION ACT PIR
Commencement
January 2005
Date
Issued Date
2686
May 2005
Scope
The aim of the original audit was to determine the degree of control over the following
risk areas:
 Implementation and maintenance of the FOI Publication Scheme
 Receipt and processing of information requests
 Records management.
The aim of this post implementation review (PIR) was to ascertain progress on the
recommendations made in the audit report (ref. 2593/CS/04), issued in September
2004, and to comment on current issues relating to the implementation of the FOIA at
Salford.
Internal Auditor’s Opinion
The PIR has determined that the majority of the recommendations highlighted by the
original audit have been carried out and the level of effective control over risks has
been improved. It is acknowledged that progress has been made to improve the
overall management of the project through the introduction of some of the principles
of PRINCE 2. However, the lack of the use of formal risk/issues logs may affect the
continuity/reliability of the project in the event of key personnel being absent for a
protracted period or leaving the employ of the Authority. There is also a possibility
that some risks and issues will be missed or not managed properly. Three new
recommendations have been made relating to; the gathering and retention of
information in respect of credit/debit card payments; consideration as to whether or
not the Authority charges dispersement fees for information; and the development of
a corporate records management policy.
Main Recommendations
Assurance must be given that the
information gathered for the purpose of
enabling credit/debit card payments to be
made, is obtained and retained being
cognisant of the principles of the Data
Protection Act and credit card companies’
requirements e.g. the Payment Card
Industry (PCI) standard.
Audit recommends that advice on the
Implementation
Date
An e-mail was sent to the SG which
Actioned
included the following instruction.
This issue was also discussed at the
SG meeting 12.04.05.
Management Response
“Please note, if you take any card
details for processing payments, you
must retain ownership of the details
and shred immediately, once the
payment has been processed. Do
30
performing of a risk assessment in this
area should be sought from the Authority’s
Corporate Information Security Manager
not leave details with payment clerks.
Please do not delay in the
processing of these details and do
not leave details unattended at any
time”.
This instruction has subsequently
been superceded by the following
instruction, ‘Accepting Payments for
FOI Charges’, stating that the
method of payment for information is
(in order of preference) debit card;
credit card; cheque. Payment by
cash is not to be offered or
encouraged but can be
accommodated if absolutely
necessary. Enquirers are to be
referred onto Customer Services
cashiers who will deal with payments
by debit/credit cards. RFICs should
not take any card details. Cheques
should be sent by post and RFICs
should not take receipt of cheques.
Applicants must make an
appointment with a named officer
from the Cashier Team if they wish to
make payment by cash. RFIC’s must
not take cash payments.
The Authority should consider establishing
a policy whereby dispersement fees below
a threshold of £100, for example, are
waived.
The development of the Corporate
Records Management Policy should be
regarded as a high priority and the IO
should do what she feels is necessary to
ensure the policy is formulated
expeditiously. This may include more
involvement on the part of the Head of Law
and Administration to encourage
directorates to comply with relevant
deadlines set by the IO. Audit considers a
prompt appointment of a records
manager/archivist (as detailed in F6
above) will also provide the necessary help
and extra resource required in this area.
Already considered. It is thought that
charges of above £10 would
discourage frivolous requests. This is
within the parameters of the other
GM authorities
To re-consider if necessary.
A report is being prepared for
Directors Team re the appointment of
a records manager. It is anticipated
that a records manager will be in
place by the end of September 2005.
Actioned
September
2005.
31
Download