PART 1 ITEM NO.6a (OPEN TO THE PUBLIC) _________________________________________________________________________________________ REPORT OF THE STRATEGIC DIRECTOR ENVIRONMENT _________________________________________________________________________________________ TO THE LEAD MEMBER FOR ENVIRONMENT ON 23rd APRIL 2007 _________________________________________________________________________________________ TITLE: DRAINAGE IMPROVEMENTS – ORDSALL PARK _________________________________________________________________________________________ RECOMMENDATIONS: That the following quotation be accepted: £ 27,279 - received from Environmental Services DSO with regard to the undertaking of drainage and improvement works to the grass football pitch at Ordsall Park. _________________________________________________________________________________________ EXECUTIVE SUMMARY: _________________________________________________________________________________________ BACKGROUND DOCUMENTS: (available for public inspection) Detailed plans/drawings of the improvements _________________________________________________________________________________________ ASSESSMENT OF RISK: Low _________________________________________________________________________________________ THE SOURCE OF FUNDING IS: 2007-8 Approved Capital Programme (S106 commuted sum from planning ref: 42541) _________________________________________________________________________________________ LEGAL ADVICE OBTAINED: N/A, improvements are being carried out under existing Grounds Maintenance Contract _________________________________________________________________________________________ FINANCIAL ADVICE OBTAINED: Yes, _________________________________________________________________________________________ CONTACT OFFICER: Alan Rowley. Tel: 909 6500 _________________________________________________________________________________________ WARD(S) TO WHICH REPORT RELATE(S) Ordsall _________________________________________________________________________________________ KEY COUNCIL POLICIES: please delete those not appropriate Budget Monitoring Community Strategy Cultural Strategy Environmental Strategy Equalities Health Planning Strategy Procurement Policies Regeneration _________________________________________________________________________________________ DETAILS: A commuted sum of £88,000 has been agreed from the development of land bounded by Trafford Road, Ordsall Lane, Archie Street and Craven Drive for housing. The developer – Translloyd Ltd/Salford College/Salford City Council has made the following payments: Translloyd Salford College Salford City Council Total £23,500 £23,500 £41,000 £88,000 received 9/3/2005 received 9/3/2005 cost centre to be provided upon approval As stated within the legal agreement the commuted sum is to be used as follows: “provision of additional changing room accommodation in the Ordsall Recreation Centre that adjoins the site”. “the provision of drainage to the existing grass pitch at Ordsall Park”. The changing room provision has previously been completed and approval is now sought to improve the drainage to the existing grass pitch. Investigations have revealed that sand-slitting and reinforcement of the rootzone will provide a solution to the drainage problem. A quotation of £ 27,279 has been received from the Council’s existing Grounds Maintenance Contractor – Environmental Services DSO. A revenue budget for the maintenance of this pitch already exists and the improvement works will allow for a higher standard of maintenance to be achieved at no additional cost. The works are supported by the Ordsall & Langworthy Neighbourhood Management Team. It is anticipated that the improvements will assist the Council in the provision of a much needed facility and help to address the lack of opportunities currently available for local youths and football teams within Ordsall Park. _________________________________________________________________________________________ TENDER APPROVAL - PROFORMA For use in seeking the approval of the Lead Member for Customer and Support Services to proceed with a capital proposal REPORT TO LEAD MEMBER FOR CUSTOMER AND SUPPORT SERVICES Title of Scheme : Play Area Improvement Clowes Park, Higher Broughton Recommendations (please append report to Lead Member for Directorate only if preferred) Approval is given to proceed with the above Scheme Details (please append report to Lead Member for Directorate only if preferred) Please see attached report Tender Details (please append report to Lead Member for Directorate only if preferred) Please see attached report Estimated - Start Date : May 2007 Estimated - End Date : July 2007 FINANCIAL DETAILS Breakdown of Scheme Cost : 05/06 £000‘s 06/07 £000‘s Contract Other Capital Works Contingency Fees (Env. Services Project Design and Management) Other Total Cost 07/08 £000‘s Later £000‘s Total £000‘s 27 27 4 4 31 31 2007/08 only - Phasing of Capital Expenditure (£000‘s) Apr May 0 June 0 July 27 Aug 0 Sept 0 Oct 0 Nov Dec 0 0 Jan 0 Feb Mar 0 4 Note : The monthly cash flow above should be consistent with the contract start and end dates shown above and should allow for normal time lapses which will occur between work being done, claimed for, certified and paid, as well as retentions. Please consult your Capital Accountant if you need assistance with this or any other part of this proforma. Is Scheme In The Current Approved Capital Programme ? Funding Identified : 06/07 £000‘s Supported Borrowing Unsupported Borrowing (see note 1) Grant (Specify) Capital Receipts (S106 commuted sum) Other (Specify) Total Yes / No 07/08 £000‘s 08/09 £000‘s Later £000‘s Total £000‘s 31 31 31 31 Other Financial Implications Decision Lead Member Customer and Support Services Approved/Not Approved