Part 1 (Open to the Public) ITEM NO. 10

advertisement
Part 1 (Open to the Public)
ITEM NO. 10
Report of the Chief Executive and Strategic Director of Housing and Planning
To Regeneration Initiatives Cabinet Working Group
on 19th February 2007
TITLE: Update on Regeneration Projects and Programmes
RECOMMENDATIONS: That the report is noted.
EXECUTIVE SUMMARY: This report provides a summary update on key regeneration
programmes and projects. It outlines progress against milestones and highlights emerging
issues.
BACKGROUND DOCUMENTS: (Available for public inspection)
Making the vision real; Salford's Community Plan for 2006 - 2016
Regenerating a Great City, Salford's Neighbourhood Renewal Strategy
ASSESSMENT OF RISK:
Risk is assessed and addressed within individual projects and programmes.
SOURCE OF FUNDING: Key funding sources are identified throughout the report. Current
applications for funding are also indicated in the report.
COMMENTS OF THE STRATEGIC DIRECTOR OF CUSTOMER AND SUPPORT
SERVICES (or his representative):
1. LEGAL IMPLICATIONS
Provided by: n/a
2. FINANCIAL IMPLICATIONS Provided by: n/a
PROPERTY: n/a
HUMAN RESOURCES: n/a
CONTACT OFFICER:
Cath Inchbold, Assistant Head of Service, Regeneration Strategy and Co-ordination,
0161 793 3796
John Bentley, Regeneration Strategy and Co-ordination, 0161 793 3449
WARD(S) TO WHICH REPORT RELATE(S): All
1
KEY COUNCIL POLICIES:
Making the vision real; Salford's Community Plan for 2006 - 2016
Regenerating a Great City, Salford's Neighbourhood Renewal Strategy
DETAILS:
Information in this report is set out according to Community Committee Areas. It also
includes a range of programmes which facilitate much of the investment.
Area
Project
Page No
Claremont & Weaste
7
Weaste Renewal Area
8
Claremont Weaste Neighbourhood Plan
9
Eccles New Road Renewal Area
10
Building Schools for the Future
11
East Salford
12 - 13
Higher Broughton - Homeswap to new build
14
Higher Broughton - Broughton Green Development
15
Higher Broughton - Community Hub
15
Broughton Renewal Area
16
Lower Broughton
17
Chapel Street - Adelphi Media Quarter
18
Chapel Street - Springfield Lane
19
Charlestown & Lower Kersal NDC
20
Salford Science and Innovation Forum
21
Duchy and Pendlebury Renewal Area
22
Eccles
23
Liverpool Road Regeneration
24
A57 Strategy
25
Eccles Town centre
26
Magistrate Court & Justice Centre Initiative
27
Building Schools for the Future
28
Irlam & Cadished
29
Barton - Red City Development
30
Barton - Port Salford
30
Chat Moss Visioning
31
Liverpool Road Corridor
32
A57 Strategy
33
Building Schools for the Future
34
Little Hulton & Walkden
35
Ashton Field Site
36
2
Cutacre Mining
37
Walkden Town centre
38
Building Schools for the Future
39
Ordsall & Langworthy
40 - 42
Chapel Street - Salford Central Station
43
Manchester Bury and Bolton Canal - Phase 1
44
Chapel Street - Greengate
45
Ordsall Development
46
Pendleton Area Action Plan
47
Northern Housing Challenge Fund Proposal
48
Proposed Tesco Development
49
Seedley Village - Seedley & Langworthy
50
Salford Quays - Clippers Quay/ Michigan Avenue
51
mediacity:uk
52
Development of an Academy
53
Swinton
54
Lower Irwell Valley Improvement Area (LIVIA)
55
Swinton Town Centre
56
Agecroft Commerce Park
57
Building Schools for the Future
58
Worsley & Boothstown
59
Salford Forest park/ Manchester Race Course
60
Building Schools for the Future
61
Programme
Page no
HMRF
62
NRF
63
NDC
64
North West Objective 2 - Priority 2
65
North West Objective 2 - Priority 2
66
North West Objective 2 - Priority 3
67
Fairshares Transforming Your Space
68
SHIFT
69
LIFT
70
URC
71
SSCF
72
Building Schools for the Future
73
SRB 5
73
Irwell City Park
74
Salford West Regeneration Framework
75
3
Summary of Key Issues
Key developments that have occurred over the past six weeks within the following areas :
Project
Key Developments
The BBC Trust confirmed plans to move to Salford Quays, following the
announcement of the licence fee settlement on 18/01/07.
mediacity:uk
Pre planning application discussions are on-going regarding phase 1
reserve matters application, to be submitted shortly.
BSF
Outline planning permission granted for Oasis City Academy, Walkden
High school and Irlam & Cadished community high school at Planning
Panel on 01/02/07.
Salford West
SRF
A draft Salford West SRF futures report was produced in January 2007.
The second round of consultation has been scheduled for early March
2007.
Irwell City Park
The preliminary masterplan was presented to members of the ICP Board
22/01/07.
Agecroft
Commerce
Park
PZ Cussons have been granted planning permission to construct a £15m
factory which will be their UK headquarters for manufacturing. This will
take up the largest plot of land on Agecroft Phase III.
The consultation phase commenced with discussions at both Political
Executives and both Community Committees.
A57 Strategy
Urban Vision outlined draft ideas for options at the joint management /
project team meeting (19/01/07).
Pendleton
Area Action
Plan
Consultation on preferred options is deferred until May 2007, due to
feedback from GONW, the options being redrafted and the delay in the
PFI announcement.
DCLG announced PFI 5th round placements on 21/12/06. Pendleton will
share £200million with North Tyneside. The exact figures are not yet
known.
Granada Irwell
Lands
It is understood that Granada's landholdings on either side of the River
Irwell are being marketed, based on a masterplan prepared on behalf of
the landowners. This excludes the Granada land within the Middlewood
area, for which a separate planning application has been received. It is
understood that the mix of uses proposed is commercial/office (on the
Manchester side, an extension of Spinningfields south) and residential
(including on the Salford side). There has been no formal consultation
with the City Council thus far.
Croal Irwell
Regional Park
Discussions are scheduled with NWDA regarding Croal Irwell Regional
Park.
4
Project
Eccles new
Road Renewal
Area
Key Developments
The General Vesting Declaration for the 2 CPO’s on Bridson Street and
Nelson Street were both sealed on 17/11/06. It is expected that the
Council will have taken legal possession of any outstanding properties by
February 2007, enabling demolition to proceed.
The decision around the CPO of the Top Streets area is still expected to
be received in the early months of 2007.
Higher
Broughton
The new houses on Vincent Street for homeswap have now been
handed over and families have moved in. A positive press article recently
appeared in the MEN.
Work has started on site for the next affordable housing development of
52 units at Devonshire Square. The development agreement is now in
place. The units are expected to be ready for occupation in about 12
months.
Broughton Green - Around 30 properties are now occupied on the
Broughton Green site and around 80 houses have been completed. A
further 90 are under construction.
Parks For
People
Ordsall &
Langworthy
Six parks in Salford West have been identified, in the Parks for People
strategy, as requiring improvement works to bring the parks up to the
required standards by 2011:
- Cadished Park masterplan is to go before Cabinet for adoption in April
2007.
- Eccles Recreation Ground masterplan is to go before Cabinet for
adoption in April 2007.
- Parr Fold Park contractors on site. A revenue bid has been submitted to
Council to secure a ranger post.
- Peel Park masterplan to go before Cabinet for adoption in April 2007.
- Prince's Park contractors are on site and will achieve the District Park
standard by March 31st 2007.
- Victoria Park achieved the District Park standard and has gained the
nationally recognized Green Flag standard.
The consultation work carried out by TPAS, as independent community
advisors, has been completed for Seedley South. TPAS have produced
their final report, which was presented to a briefing session of the
Seedley & Langworthy Partnership Board on 22/01/07 (it will be formally
presented to the Board on 05/03/07). A newsletter confirming the
outcomes of the consultation has been drafted by TPAS with input from
the Leader and the HMR team.
Whilst there is agreement within the community for the need to provide
greater choice of homes in the area, the scale of demolition emerging
from the consultation is considerably less than originally anticipated.
There is an overriding need for the council to demonstrate that it has
listened to the community whilst exploring ways of achieving a careful
balance between the needs to secure transformation and a more robust
redevelopment opportunity for the private sector and the need to retain
and invest in more existing homes.
The HMR team is currently examining the case to extend the scale of
demolition in the area from that put forward by the community through
5
Project
Key Developments
the neighbourhood planning process.
Consultation with members took place on 02/02/07. A draft report will go
to informal Lead Member briefing confirming the recommendations for
investments in housing in Seedley South on 15/03/07.
Lower
Broughton
74 residents received a provisional offer on 20/12/06. 38 residents
accepted their offer of a new property in the first phase of the
redevelopment. An all day drop-in session was held on 21/12/06 at the
Information Centre to give residents the opportunity to provisionally
accept the offer and discuss any issues they may have regarding the
new properties.
Initial discussions are commencing regarding future phases.
Barton
Strategic Site
Port Salford - The Highways Agency holding direction now extends until
21st May 2007, allowing them more time to assess the highway modelling
and implications.
Greengate
The final Exchange Greengate Planning Guidance was adopted by
Council on 17/01/07.
Three major planning applications are due at Planning Panel in early
March 2007.
An application for the public realm submitted to Manchester City Council
has still to be registered. It is anticipated that the application will be
registered in February/ March and determined by April 2007.
Weaste
Renewal Area
Weaste Phase 5 block improvement scheme commenced on site
08/01/07. The anticipated completion date is the end of August 2007.
12 recent alleygate schemes along Weaste Lane and Tootal Road are
now complete and awaiting completion of snagging inspections.
NDC
Lower Kersal Health Centre launched, January 2007.
Manchester
Bury Bolton
Canal
The final design is complete and British Waterways have issued tenders
for the main engineering works with a return date in Jan 2007. The start
on site is delayed pending land acquisition from Granada. All partners
are now working to achieve the completion of the land agreement.
Outputs however are still at risk.
Irlam Railway
Station
GMPTE are in the process of putting a programme of works together
focussing on improving security and real time information. This should be
completed by April 2007, with works expected to start late 2007/ early
2008.
Shops Review
A shops review has been completed by Urban Vision. A report on the
shops review findings is due to go to Housing Lead Member late March/
early April 2007.
6
Claremont and Weaste
Claremont Weaste Neigbourhood Plan


Areas of change and opportunity were discussed at the advisory group meeting held on
22/01/07.
Initial key issues findings were discussed at the advisory group meeting held on 30/11/06.
Weaste Renewal Area


Weaste Phase 5 block improvement scheme commenced on site on 08/01/07. The scheme,
which is being delivered by Seddons, incorporates 52 properties and will continue the
improvement works along the Weaste Lane and Tootal Road corridors. The anticipated
completion date is the end of August 2007.
12 recent alleygate schemes along Weaste Lane and Tootal Road are now complete and
awaiting completion of snagging inspections.
Buile Hill Hall



Wilkinson Corporation was named as the preferred development partner for the Buile Hill
Mansion site in November 2006.
The mansion will be developed into a hotel, conference and function venue.
Proposals are now being worked up to be submitted as a planning application. If successful
this will enable the sale of the site to Wilkinson Corporation.
Eccles New Road Renewal Area


The General Vesting Declaration for the 2 CPO’s on Bridson Street and Nelson Street were
both sealed on 17/11/06. It is expected that the Council will have taken legal possession of
any outstanding properties by February 2007, enabling demolition to proceed.
The former Weaste bus depot is currently being redeveloped by private developers into
apartments for private sale.
Building Schools for the Future


An information roadshow was held at Buile Hill Park Hall 09/10/06.
A proposal for closing All Hallows High and replacing it with a brand new school closer to the
inner city and closure of Hope High School and replacement by an Academy in Salford Quays
were announced.
7
CLAREMONT VILLAGE
Project: Weaste Renewal Area
Pledge: Enhancing Life
Area Covered
Claremont Village
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
Summary
To provide a strategic framework for the physical, social and economic
renewal of the neighbourhood; securing its long-term sustainability by
making the area a more attractive and safer place to live, more
desirable places to visit and more inviting areas for private sector
investment; building on a strong local identity and aspiration and
involving the communities and other stakeholders.
Priorities and Milestones
Timescales
Completion of alleygating scheme.
February 2007
Completion of Weaste phase 5 block improvements.
August 2007
Progress
Date
Weaste Phase 5 block improvement scheme started on site 08/01/0,
anticipated completion August 2007.
January 2007
Alleygate schemes complete and snagging inspections ongoing.
Buile Hill Mansion presentations and assessment underway.
January 2007
On-going
Funding sources
Housing Capital Programme, HMRF and ERDF
Publicity to date
The new starts will offer an opportunity for good news stories in the
press.
8
Project: Claremont Weaste Neighbourhood plan
Pledge: Enhancing Life
Area Covered
Claremont, Weaste Community Committee Area
Lead Officer
Mike Arnold, Housing and Planning Directorate
Summary
To provide a strategic framework for the physical, social and economic
regeneration of the area.
Priorities and Milestones
Timescales
Neighbourhood Plan complete.
Winter 2007
Consultation on draft Neighbourhood Plan.
Summer 2007
Consultation on key issues for the area.
May 2007
Progress
Date
Areas of change and opportunity were discussed at the advisory group
meeting held on 22/01/07.
January 2007
Initial key issues findings were discussed at the advisory group meeting
held on 30/11/06.
December 2006
The baseline and issues report was discussed at the Advisory Group
meeting held on 30/11/06.
December 2006
Funding sources
SCC staff resources
Publicity to date
An information plan is being developed
9
Project: Eccles New Road Renewal Area
Pledge : Enhancing life in Salford
Area Covered
Enterprise Park/Quays
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
Summary
To provide a strategic framework for the physical, social and economic
renewal of areas’ neighbourhood; securing its long-term sustainability
by making the areas more attractive and safer places to live, more
desirable places to visit and more inviting areas for private sector
investment; building on a strong local identity and aspiration and
involving the communities and other stakeholders.
Priorities and Milestones
Timescales
Demolition of properties on Nelson Street/Bridson Street.
Progress
June 2007
Date
The General Vesting Declaration for the 2 CPO’s on Bridson Street and
Nelson Street were both sealed on 17/11/06. It is expected that the
Council will have taken legal possession of any outstanding properties
by February 2007, enabling demolition to proceed.
The former Weaste bus depot is currently being redeveloped by private
developers into apartments for private sale.
Two remaining owners are to relocate from Nelson Street/Bridson
Street. This is being closely monitored by members of the local area
team.
January 2007
January 2007
January 2007
Funding sources
Housing Capital Programme and HMRF
Publicity to date
Newsletter/ Claremont Weaste Community Committee
10
Project: Building Schools for the Future (BSF)
Pledge: Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Seedley
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
The BSF vision is to create buildings for the 21st century and to
provide choice and a greater range of services at each secondary
school. Supporting the vision is an investment of up to £110 million
from Government's BSF programme.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Progress
Date
The strategic Business Case was approved by Salford City Council and
submitted to DfES in November 2006.
December 2006
Consultation on draft proposals completed.
25/10/06
Information roadshow held at Buile Hill Park Hall.
09/10/06
A proposal for closing All Hallows High and replacing it with a brand
new school closer to the inner city announced in September.
Closure of Hope High School and replacement by Academy in Salford
Quays announced in July.
Funding sources
BSF
Publicity to date
Consultation information on SCC website.
Production of draft vision brochure.
11
September 2006
July 2006
East Salford
Higher Broughton
Broughton Green

Around 30 properties are now occupied on the Broughton Green site and around 80 houses have
been completed. A further 90 are under construction.
Homeswap to new build

The first families have now moved out of the Top Streets CPO area into their new homes on Vincent
Street. It is expected that most of the remaining houses will be occupied by the end of January
2007. So far residents have been very happy with their new homes and it is hoped that some
positive publicity will be possible during the early months of 2007 in local papers and in the housing
press.
Provision of New Playing Fields

Work is on-going relocating the sports pitches to the new site. These are completed in December
2006 and ready for grass seeding spring 2007. They will be available for use from spring 2008.
Top Streets CPO Area

A decision regarding the outcome of the Top Streets CPO is still expected to be received in the early
months of 2007. In the meantime the Council continues to acquire properties where possible by
agreement.
Devonshire/Bond Square

Work on this new development of 52 units has started on site and all development agreements are
in place between the Partnership, Contour Housing and the Council. Work is expected to take about
12 months. 11 units will be available to the Council for the purposes of relocation from the Top
Streets clearance area.
Community Hub


A partner contractor was appointed in November 2006. A planning application will be submitted
shortly. A costing exercise has been undertaken by Urban Vision. Revisions to the scheme and
revised costs, along with capital and revenue implications have been reported to and approved by
Lead Member.
Further local consultation needs to be undertaken with specific community groups.
Lower Broughton






74 residents received a provisional offer on 20/12/06. 38 residents accepted their offer of a new
property in the first phase of the redevelopment. An all day drop-in session was held on 21/12/06 at
the Information Centre to give residents the opportunity to provisionally accept the offer and discuss
any issues they may have regarding the new properties. Initial discussions are commencing
regarding future phases.
Invitations were sent to households to attend a all day session on 16/12/06 to encourage the
outstanding 36 households to provisionally sign up for their property. As at 19/12/06 approximately
90% of the offers have been accepted by residents.
5 private sales have been achieved prior to marketing commencing.
Officers undertook home visits to allow elderly and housebound residents the opportunity to sign up.
Consultation workshops for the Charter of Commitments for tenants living in Lower Broughton are
on-going. A workshop was held on 09/01/06 to consult and inform residents about Contour rents
and service charges.
The Lower Broughton Partnership Steering Group meeting was held on 29/01/07.
12
Chapel Street
Adelphi Media Quarter

The sale and acquisition of sites between Salford University and Salford City Council for Adelphi
Street, Meadow Road and the Irwell Valley campus is complete.
Springfield Lane

Urban Splash have advised that due to the need to undertake further design amendments/
refinements, the planning application will not now be submitted until late March 2007.
Charlestown and Lower Kersal
New Deal for Communities (NDC)



Lower Kersal Health Centre launched, January 2007.
19 Business Improvements Grants have been awarded since commencement of scheme.
Salford Sports Village received the 'Sports and Leisure Project of the Year' award at 2006 Building
and Engineering Awards.
Salford Science and Innovation Park



Early work has been undertaken to link Salford Science and Innovation Park with the Arc of
Opportunity.
NWDA have advised that the Northern Way bid ought to encompass other areas of expenditure and
not exclusively spend on ICT/Digital infrastructure.
Merger discussions between SCC, University of Salford and MSP are underway.
Claremont Village
Duchy and Pendlebury Renewal Area.




Duchy Bank housing development by SPACE ongoing (37 properties). These are due to be completed
October 2007.
February 2007 – Information update pack to be circulated to clearance area residents.
February 2007 – Second phase GVD to be executed on remaining 20 properties; residents have been
allocated new homes on the development site.
February 2007 – Selective demolition programme due to start in CPO area (on Minden Street).
13
BROUGHTON
Project: Higher Broughton Regeneration Initiative – Homeswap to new build
Pledge: Enhancing life in Salford
Area Covered
Higher Broughton Partnership area
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
Summary
This will provide access to new properties in the redevelopment for
owners living in the clearance area.
Priorities and Milestones
Timescales
Progress
Date
Devonshire Street works complete.
January 2007
The first 10 families have now moved out of the Top Streets CPO area
into their new homes on Vincent Street. It is expected that most of the
remaining houses will be occupied by the end of January 2007.
Planning approval granted for the new scheme on Devonshire Street
and work started on site in January 2007, subject to service diversions
and costs.
Funding sources
Publicity to date
January 2007
January 2007
 Housing Market Renewal Programme.
 Housing Capital Programme
 Higher Broughton Community Hub to be funded by unsupported
borrowing and receipts from the Partnership.
Press release on Homeswap at Vincent Street now being put together
for the MEN and the Salford Advertiser.
14
Project: Higher Broughton – Broughton Green Development and Related issues
Pledge: Enhancing life in Salford
Area Covered
Higher Broughton Partnership area
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
Summary
Maintain and support existing communities whilst seeking
opportunities for new development through a range of interventions.
Priorities and Milestones
Timescales
Decision on the CPO still outstanding.
Early 2007
Progress
Date
Devonshire Street started on site.
January 2007
Further sales are being generated on the Broughton Green
development following the Higher Broughton Partnership’s recent
success at the M.E.N. Residential Property awards.
January 2007
Around 30 properties are occupied on the Broughton Green site.
January 2007
The results of the Council’s formal review of the CPO strategy for the
Top Streets were approved by Lead Members for Housing and
Planning. The report indicates that residents are still broadly supportive
of the CPO action whilst landlords are opposed. Some refurbishment
options have also been developed, these went to the Lead Members for
comment during the same meeting. Residents have now been made
aware of the outcome of the Lead Member meetings and it is likely that
further detailed discussions will be held with residents looking for a
refurbished property. This will follow the outcome of the CPO public
inquiry decision being made known.
January 2007
Higher Broughton - Community Hub
A partner contractor was appointed in November 2006. A planning
application will be submitted shortly. A costing exercise has been
undertaken by Urban Vision. Revisions to the scheme and revised
December 2006
costs, along with capital and revenue implications have been reported
to and approved by Lead Member.
Further local consultation needs to be undertaken with specific
December 2006
community groups.
Community Hub report approved by Lead Member for Customer
02/10/06
Services.
Design plans with service users are progressing. A
consultation/information leaflet has been issued across Broughton with
October 2006
minimal response. Further discussions have been held with the local
Jewish Orthodox community.
Some consultation has been undertaken with potential service users
October 2006
and the community. More consultation will follow as appropriate.
Housing Market Renewal Fund 2006/07 Programme and Housing
Funding sources
Capital Programme.
Positive publicity is being lined up to maximise this opportunity at the
Publicity to date
appropriate time.
15
Project: Higher Broughton – Broughton Renewal Area
Pledge: Enhancing life in Salford
Area Covered
Broughton
Lead Officer
Jackie Crook, Housing & Planning
Summary
To develop and implement an action plan, in consultation with
residents and stakeholders, for the Broughton Renewal Area.
Renewal Area is bounded by Camp St to the South, the River Irwell to
the West, Bury New Road to the East and the Kersal border to the
North.
Priorities and Milestones
Timescales
Delivery of block improvements.
Nov 06 – April 07
Develop and implement alleygating scheme.
March 2007
Assemble Back Hamilton St site/ MSCA on Douglas St/ MSCA in
conjunction with Contour Housing in Rock and Hill St Area.
March 2007
Draft renewal action plan complete
October 2007
Progress
Date
Block improvements have been identified. Schedules for improvements
are under progress. Lead member approval received 15/12/06.
Developer partner has been appointed.
January 2007
Hamilton Street:
Planning approval received Oct 2006. Developer now on site.
January 2007
Site Assembly Hamilton Street:
Lead member approval to make CPO received 15/12/06. Pioneer
works acquired by voluntary agreement Dec 2006. CPO to acquire
remainder of site made on 15/01/07.
Yew Street:
Planning application now approved and currently awaiting confirmation
of funding.
January 2007
January 2007
MSCA Douglas Street:
Draft action plan presented to officer working group 27/11/07.
January 2007
MSCA Hill and Rock Street:
Draft action plan presented to officer working group 27/11/07.
Draft action plan presented to renewal area steering group 19/12/06.
The steering group are to feedback on plan during January 2007.
January 2007
Funding sources
Capital Programme, HMR
Publicity to date
Formal declaration notice – MEN and Salford Advertiser 18th May
2006
16
Project: Lower Broughton Regeneration
Pledge: Enhancing life in Salford
Area Covered
Lower Broughton
Lead Officer
Richard Wynne, Urban Vision
Summary
Regeneration of large area (150 acres) of public and private
residential and commercial / mixed use property.
Priorities and Milestones
Timescales
The first handover of properties is expected in March 2007.
March 2007
Demolition of Moss Street CPO houses to be completed by March
2007.
Contour and HMR consultation workshops to begin. The ongoing
workshops will inform and also consult with residents on issues such as
rent levels, tenancy agreements and anti social behaviour.
March 2007
April 2007
Progress
Date
5 private sales have been achieved prior to marketing commencing.
January 2007
74 residents received a provisional offer on 20/12/06. An all day drop-in
session was held on 21/12/06 at the Information Centre to give
residents the opportunity to provisionally accept the offer and discuss
any issues they may have regarding the new properties. 38 residents
accepted their offer of a new property in the first phase of the
redevelopment.
Invitations were sent to attend an all day session on 16/12/06 to
encourage the outstanding 36 to provisionally sign up for their property.
As at 19/12/06 approximately 90% of the offers have been accepted by
residents. Officers undertook home visits to allow elderly and
housebound residents the opportunity to sign up.
Initial discussions are commencing regarding the next phases.
January 2007
January 2007
January 2007
Consultation workshops for the Charter of Commitments for tenants
living in Lower Broughton are on-going. A workshop was held on
January 2007
09/01/06 to consult and inform residents about Contour rents and
service charges.
The next Lower Broughton Partnership Steering Group meeting will be
January 2007
held on 29/01/07.
First phase developments in progress with the first timber frames on
January 2007
site 17 January 2007.
Countryside Properties has erected an on site information centre. The
centre is situated on Muriel Street off Gt Clowes Street. The Information
December 2006
Centre will house a detailed model of the first phase of the
redevelopment and visitors will be able to watch a digital fly-through.
HMRF and Housing Capital Programme
Funding sources
Private
Publication of newsletters
Publicity to date
Advertising campaign planned by Countryside associated with Phase1
Advertising campaign to start January 2007
17
Project: Adelphi Media Quarter
Pledge: Encouraging learning, leisure and creativity in Salford
Area Covered
Chapel Street
Lead Officer
Richard Wynne, Urban Vision
Summary
Redevelopment of vacant land and outdated industrial properties
either side of Adelphi Street.
Priorities and Milestones
Timescales
Completion of Adelphi Street land transfer to the developer.
October 2006
Progress
Date
The sale and acquisition of sites between Salford University and Salford
City Council for Adelphi Street, Meadow Road and the Irwell Valley
campus have been completed.
January 2007
The two major schemes under discussion on Adelphi Street were the
Broadway Malayan scheme which was approved and the Vermont
scheme which was not approved, with a request made by planning
panel for amendments to the design.
January 2007
Adelphi planning guidance was approved by Lead Member.
Other private sector developers purchasing sites and securing planning
permission.
Issues about designs and finishes of the Adelphi Media Centre are
under discussion.
Funding sources
None directly
Publicity to date
n/a
18
19/05/06
Project: Springfield Lane
Pledge: Enhancing life in Salford/ Creating prosperity in Salford
Area Covered
Lead Officer
Summary
Chapel Street
Stephen Gwatkin, Urban Vision
Christine Duffin, Market Renewal Team, Housing and Planning
Redevelopment for residential and mixed use scheme with Urban
Splash
Priorities and Milestones
Timescales
Submit detailed planning permission for first phase of the development.
March/ April 2007
1st phase on site.
December 2007
Progress
Date
Urban Splash have advised that due to the need to undertake further
design amendments/ refinements, the planning application will not now
be submitted until the end March 2007.
The scheme is currently comprised of 450 apartments, 20,000 square
feet of commercial space on the lower levels of the apartment blocks,
an office building of approximately 50-70,000 square feet on the corner
of Trinity Way / Springfield Lane and 400 car parking spaces.
January 2007
January 2007
Funding sources
Private Sector, possible Public sector in relation to affordable housing
Publicity to date
Urban Splash coverage
19
Programme: Charlestown and Lower Kersal New Deal for Communities
Pledge: All 7
Area Covered
North Irwell Riverside
Lead Officer
Tim Field – NDC Chief Executive
Summary






Building Communities
Crime and Community Safety
Education, Children and Young people
Physical Environment
Health
Business, Employment and Skills
Priorities and Milestones
First stage of Development at Kersal High.
Timescales
Winter 2006/07
Housing Improvements to commence Levens Street/Gerald Road.
New health investment strategy for local area to be produced.
Children and Young People’s Strategy produced.
Spring 2007
Spring 2007
Spring 2007
Progress
Lower Kersal Health Centre launched.
Date
January 2007
19 Business Improvements Grants have been awarded since
commencement of scheme.
January 2007
Salford Sports Village received the 'Sports and Leisure Project of the Year'
award at 2006 Building and Engineering Awards.
December 2006
The Intensive Neighbourhood Management Scheme was launched in
October 2006. This scheme will include a) practical actions, cleaner / safer
/ greener, b) making sure the community receives accurate information, c)
intensive support e.g. for isolated older people.
Phase 5 of Alleygating on site.
Publicity to date
December 2006
On-going
NDC newsletter
'In Bloom' coverage
20
Project: Salford Science and Innovation Forum
Pledge: Creating prosperity in Salford
Area Covered
North Irwell Riverside
Lead Officer
Matthew Lynn, Economic Development, Chief Executive Directorate
Salford Science Park encompasses the Salford Innovation Forum
Summary
(SIF) Building, Salford University Technology House and surrounding
business units to promote the growth of knowledge based industries.
Priorities and Milestones
Timescales
Linkage between Salford Science and Innovation Park and the Arc of
Opportunity to be complete.
March 2007
Completion of construction contract.
July 2007
Fit out stage completed and opening of building.
Dec 2007
Completion of Innovation Forum.
August 2008
Progress
Early work has been undertaken to link Salford Science and Innovation
Park with the Arc of Opportunity.
NWDA have advised that the Northern Way bid should encompass
other areas of expenditure and not exclusively spend on ICT/Digital
infrastructure.
Merger discussions between SCC, University of Salford and MSP are
underway.
Following an unsuccessful Northern Way Science Cities joint bid the
Salford Innovation forum project team has been asked to submit a bid
for the Salford Innovation Forum building in isolation. This will go to
NWDA early 2007.
The process of designing an Expression of Interest to appoint third
party operators to manage the Salford Innovation Park together with the
wider Science Park has been halted due to joint venture negotiations.
The Innovation Forum is on site with completion anticipated August
2008.
This is a URC priority project and features in the Manchester and part of
the Knowledge Capital ‘Arc of Opportunity’.
Funding sources
Publicity to date
£3.4m ERDF
£6.0m NWDA
£300K NDC
£0.56 Northern way Science City Fund
£9.7m Total capital costs
Press release January 2006
Press release October 2006
21
Date
January 2007
January 2007
January 2007
December 2006
December 2006
December 2006
Project: Duchy & Pendlebury Renewal Area
Pledge: Enhancing life in Salford
Area Covered
Claremont Village
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
To provide a strategic framework for the physical, social and economic
renewal of areas’ neighbourhood; securing its long-term sustainability
by making the areas more attractive and safer places to live, more
Summary
desirable places to visit and more inviting areas for private sector
investment; building on a strong local identity and aspiration and
involving the communities and other stakeholders.
Priorities and Milestones
Timescales
Selective demolition in CPO area.
March 2007
Decant final resident from Minden Street.
March 2007
Distribute resident information booklet.
March 2007
Agree final prices for new build properties with CPO residents.
Selective demolition start on site.
March 2007
Development brief for CPO area completed.
April 2007
First phase of residents move to Duchy Bank complete.
Progress
General Vested Declaration process complete.
Publicity to date
August 2007
Date
February 2007
Relocate remaining CPO area tenants.
Funding sources
March 2007
February 2007
Housing Capital Programme and HMRF
Newsletter updates
22
Eccles
Liverpool Road Regeneration

CCTV - All cameras and masts installed, site visit arranged for engineers 31/1/07 to address
operation problems with individual cameras.
A57 Strategy




Consultation phase commenced with discussions at both Political Executives and both
Community Committees.
Urban Vision outlined draft ideas for options at the joint management / project team meeting
(19/01/07).
Key stakeholders interviewed, January 2007.
Baseline analysis stage completed, January 2007.
Eccles Town Centre

LIFT site demolitions completed, October 2006. Work began on site in early January 2007.
Magistrates Court and Justice Centre Initiative



Gateway review due 30/01/07.
Outline planning permission was granted 03/08/06.
Indicative timetable now received from HMCS. Estimation of court opening summer 2010.
Building Schools for the Future



Information roadshow held at Salford Link Project 06/10/06.
Proposal for a new building at Wentworth High announced September 2006.
Proposal for refurbishing St Patrick's RC High announced September 2006.
Bridgewater Trail

Funding for completion of the Barton road section was approved in January 2007, with
completion expected March 2007.
Trafford Rectangle

A working group is being set up led by Trafford, including SCC and MCC, to look at how the
Trafford Rectangle will be dealt with in the Trafford core strategy.
23
Project: Liverpool Road Regeneration
Pledge: Creating prosperity in Salford
Area Covered
Eccles
Lead Officer
Ruth Shields, Economic Development, Chief Executive Directorate
Summary
To stem and turn around the decline of the Liverpool Road Corridor by
implementing a series of physical improvements. The challenge is not
simply to make regeneration happen, but to ensure that it builds long
term sustainability in every respect, economic, social and
environmental. This will involve balancing the retention of existing
communities, improving their social and economic prospects, with a
need to attract newcomers into the area.
Priorities and Milestones
Timescales
Shop Front Improvement Scheme completion.
On-going 2006 2007
Progress
Date
CCTV - All cameras and masts installed, site visit arranged for
engineers 31/1/07 to address operation problems with individual
cameras.
Shenton Homes Ltd purchased the former 'Talk of the North' site
(Sept/Oct 2006). The site has planning permission for 14 X 1 bed
apartments with car-parking. It is the intention of the new owners to
develop a four storey building comprising 23 apartments with a mixture
of 1\2 bedrooms.
Shop Front Improvement Scheme is ongoing, 3 completed, 2 are
ongoing, 3 are in development and there have been 4 expressions of
interest received.
Key Development Site – Crown Theatre, Church Street – progress
meeting with new owners (Engleford Limited). Confirmation received
that the company are in discussions with planning colleagues and
amending the planning application approved for the site. The
amendments will take into account the demolition and rebuild of the
EML building behind the Crown Theatre so that it becomes part of the
same scheme. The company have also secured a two year lease with
the owner of the land to the east of the Theatre to be used for additional
parking.
Initial discussions underway with Eccles and Salford Mosque Islamic
Society to discuss investment potential of properties owned by the
society.
Funding sources
NRF
2006/07 - £100,000
Capital budget
2006/07 - £180, 000
Publicity to date
Press Release in MEN re: Ministerial visit
24
January 2007
December 2006
December 2006
October 2006
Project: A57 Corridor Strategy
Pledge: Creating Prosperity in Salford
Area Covered
Eccles
Lead Officer
Stuart Kitchen, Assistant Director, Economic Development, Chief
Executive Directorate
Summary
Strategy to develop the Liverpool Road Corridor (A57).
Priorities and Milestones
Timescales
Baseline Audit and Preferred Options Report.
January 2007
Formal consultation phase planned for Feb 2007 comprising of:
1. Public consultation directly with the community
2. Formal event with key stakeholders
3. Online through www.salford.gov.uk
4. Promotional leaflet with consultation reply slip
Draft strategy and action plan circulated for comment.
February 2007
March 2007
Final strategy and action plan, presented to both Political Executives and
Community Committee’s.
March 2007
10 year strategy and action plan production.
March 2007 tbc
Progress
Date
Consultation phase commenced with discussions at both Political
Executives and both Community Committee’s.
January 2007
Urban Vision outlined draft ideas for options at the joint management /
project team meeting (19/01/07).
January 2007
Key stakeholders interviewed.
January 2007
Baseline analysis stage completed.
January 2007
Business survey comprising face to face interviews completed. 38% of
businesses along the corridor participated (140 businesses). The survey
highlighted the following issues of concern:
Crime and vandalism,
Appearance of area,
Litter / street cleaning and off street parking.
Urban Vision presented baseline review findings at management
meeting (19/12/06).
December 2006
December 2006
Funding sources
NRF £20k for commission
Plus additional for consultation phase, potential £6K
Publicity to date
Planned for Feb 2007 – web and PR leaflet
25
Project: Eccles Town Centre
Pledge: Creating prosperity in Salford
Area Covered
Eccles
Lead Officer
Richard Wynne, Urban Vision
Summary
Various interventions to promote or enhance the town centre.
Priorities and Milestones
Timescales
Eccles LIFT Centre open.
Spring 2008
Wilkinson store open.
March 2007
Progress
Date
Wilkinson have started shop fitting with the new store opening in March
2007.
January 2007
LIFT site demolitions completed October 2006. Work began on site in
January 2007.
January 2007
Magistrates Court is dependent upon Comprehensive Spending Review.
Funding sources
Publicity to date
Press coverage of Magistrate Court proposal.
26
Project: Magistrates Court and Justice Centre Initiative
Pledge: Enhancing life in Salford
Area Covered
Eccles
Lead Officer
Richard Wynne, Urban Vision
Confirmation of site for new courthouse at John William Street
Car parking solution will involve multi storey car parking.
Summary
Priorities and Milestones
HMCS & DCA approval through National Property Strategy.
Completion of Magistrates Court.
Date
January 2007
Indicative timetable now received from HMCS. Estimation of court
opening summer 2010.
Awaiting details of timetable from HMCS
December 2006
October 2006
Outline planning permission granted.
3rd August 2006
Cabinet has now agreed location of Court and car park as John William
Street, Eccles. An outline planning application has been submitted.
Negotiations for replacement car park and site transfer with HMCS.
Publicity to date
On -going
Earliest Jan 2008
Progress
Gateway review due 30/01/07.
Funding sources
Timescales
19th June 2006
On-going
Magistrates Court is dependent upon Comprehensive Spending
Review
Press coverage of Magistrate Court proposal
27
Project: Building Schools for the Future (BSF)
Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Eccles
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
BSF vision to create buildings for the 21st century and to provide
choice and a greater range of services at each secondary school.
Supporting the vision is an investment of up to £110 million from
Government's BSF programme.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Progress
Date
The strategic Business Case was approved by Salford City Council and
submitted to DfES in November 2006.
December 2006
Consultation on draft proposals completed.
25/10/06
Information roadshow held at Salford Link Project.
06/10/06
Proposal for a new building at Wentworth High announced.
Proposal for refurbishing St Patrick's RC High announced.
Funding sources
BSF
Publicity to date
Consultation information on SCC website
Production of draft vision brochure
28
September 2006
September 2006
Irlam & Cadishead
Barton Strategic Site
Red City Developments




This project will see the development of a 20,000 seat stadium with retail park.
Secretary of State gave approval to Salford Reds stadium development 03/11/06.
The applicant will now have to apply for the details of the scheme (reserved matters).
A development meeting has been held between SCC Economic Development and the Chief
Executive of Red City Developments Limited. Discussions currently centre around using
Section 106 monies to support pre employment training via the Salford Construction
partnership.
Port Salford


This is the development of a multi modal freight terminal; to include 2-berth port, rail freight
terminal, and 200,000 sq m warehousing.
The Highways Agency holding direction now extends until 21/05/07, allowing them more
time to assess the highway modelling and implications.
Chat Moss Visioning


This project examines the Mosslands area identifying sustainable future landuses.
A meeting is to be scheduled with Councillor Antrobus and Councillor Jones to discuss the
vision and next steps.
Liverpool Road Corridor


Public art preferred option presented to community committee January 2007.
Consultation was carried out at the Irlam Festival by artists commissioned to create public
artwork on a roundabout – this event was very well attended.
A57 Strategy
 Consultation phase commenced with discussions at both Political Executives and both
Community Committees.
 Urban Vision outlined draft ideas for options at the joint management / project team meeting
(19/01/07).
 Key stakeholders interviewed, January 2007.
 Baseline analysis stage completed, January 2007.
Building Schools for the Future


Outline planning permission granted for Irlam & Cadished community high school at
Planning Panel on 01/02/07.
Information roadshow held at Salford Link 06/10/06.
Irlam Railway Station

GMPTE are in the process of putting a programme of works together focussing on
improving security and real time information. This should be completed by April 2007, with
works expected to start late 2007/ early 2008.
29
Project: Barton Strategic Site
Pledge: Creating prosperity in Salford
Area Covered
Barton
Lead Officer
Martin Hodgson, Urban Vision
Summary
Salford Reds: 20,000 seat stadium with retail, hotel, fast food etc to
support the stadium use; and
Priorities and Milestones
Timescales
Site allocation in the Unitary Development Plan.
On-going
Progress
Date
A development meeting has been held between SCC Economic
Development and the Chief Executive of Red City Developments
Limited. Discussions currently centre around using Section 106 monies
to support pre employment training via the Salford Construction
partnership.
The developer is seeking to sign up key anchor tenants to make the
retail element of the scheme viable.
The developer will also be seeking NWDA assistance to offset the cost
of developing brownfield land.
The applicant will now have to apply for the details of the scheme
(reserved matters).
Secretary of State gave approval to Salford Reds stadium development
03/11/06.
January 2007
December 2006
03/11/06
Funding sources
Private
Publicity to date
Coverage of Salford Reds Stadium in MEN and Guardian
Area Covered
Barton
Lead Officer
Helen Ashworth, Urban Vision
Summary
Port Salford: multi modal freight terminal; to include 2-berth port, rail
freight terminal, and 200,000 sq m warehousing.
Priorities and Milestones
Timescales
Highways Agency pronouncement expected
21/05/07
Progress
Date
Highways Agency holding direction now extends until 21/05/07 to allow
more time to assess the highway modelling and implications.
2nd Supplementary Environmental Statement received. Additional
publicity and neighbour notification to be undertaken.
Assessment of the planning application and traffic issues being
investigated.
Funding sources
Private
Publicity to date
30
January 2006
September 2006
On-going
Project: Chat Moss Visioning
Pledge: Enhancing Life in Salford
Area Covered
Chat Moss (in Salford); Rixton and Risley Mosses (in Warrington) and
Astley Moss (in Wigan)
Lead Officer
Nick Lowther, Housing & Planning
To carry out an assessment of the Mossland project area to produce a
long term Vision that will promote the “best fit” for competing landuses
and establish sustainable landuse patterns with a view to:
-
Summary
-
-
understanding mossland habitat and landscape in order to
deliver maximum public benefit.
secure long term economic viability of mosslands based around
agriculture, establishment of local markets, specialist products
and creation of jobs for local people.
recognise unique potential of mossland to deliver rare and
significant amounts of mossland habitat of high biodiversity
value.
maximise value of mossland landscape as an accessible
leisure, health and local heritage resource for tourists, visitors
and local communities.
Priorities and Milestones
Timescales
Public Consultation on draft Vision.
Spring 2007
Progress
Date
A meeting is to be scheduled with Councillor Antrobus and Councillor
Jones to discuss the vision and next steps.
January 2007
The second draft of Chat Moss Vision was received mid December
2006 for consideration by the Mossland Action Group.
December 2006
Developing connections between Mossland Visioning and Salford West
Regeneration Strategy.
October 2006
Exploring future opportunities linked to the Greater Manchester Rural
Implementation Plan (part of Rural Development Plan for England),
coordinated by Manchester Enterprise, for future development of the
Mosslands Vision.
First draft was received. Comments have been returned for the second
draft.
Wigan MBC have contributed £10,000 towards the costs of the project
(thereby matching Salford City Council and Warrington Borough Council
contribution).
Funding sources
Salford City Council
Warrington DC
Countryside Agency
NWDA
NRF
Publicity to date
n/a
£10K
£10K
£5K
£10K
£5K
31
October 2006
September 2006
Project: Liverpool Road Corridor
Pledge: Creating prosperity in Salford
Area Covered
Irlam & Cadishead
Lead Officer
Ruth Shields, Economic Development Officer
Summary
To stem and turn around the decline of the Liverpool Road Corridor by
implementing a series of physical improvements. The challenge is not
simply to make regeneration happen, but to ensure that it builds long
term sustainability in every respect, economic, social and
environmental. This will involve balancing the retention of existing
communities, improving their social and economic prospects, with a
need to attract newcomers into the area.
Priorities and Milestones
Timescales
Completion of Public Art on Cadishead Way roundabout.
Review and further develop the Liverpool Road 1999-2009 Action Plan.
March 2007
March 2007
Progress
Date
Public art preferred option presented to community committee January
2007.
January 2007
A mailshot was circulated inviting local businesses to take part in a
consultation on the public art on a roundabout.
28/8/06
Artists commissioned to develop public art at Cadishead Way
Roundabout – the gateway to the corridor.
Funding sources
NRF 05/06 £45,000
NRF 06/07 £tbc
Publicity to date
32
Project: A57 Corridor Strategy
Pledge: Creating Prosperity in Salford
Area Covered
Irlam and Cadished
Lead Officer
Stuart Kitchen, Assistant Director, Economic Development, Chief
Executive Directorate
Summary
Strategy to develop the Liverpool Road Corridor (A57).
Priorities and Milestones
Timescales
Baseline Audit and Preferred Options Report.
January 2007
Formal consultation phase planned for Feb 2007 comprising of:
1. Public consultation directly with the community
2. Formal event with key stakeholders
3. Online through www.salford.gov.uk
4. Promotional leaflet with consultation reply slip
Draft strategy and action plan circulated for comment.
February 2007
March 2007
Final strategy and action plan, presented to both Political Executives and
Community Committee’s.
March 2007
10 year strategy and action plan production.
March 2007 tbc
Progress
Date
Consultation phase commenced with discussions at both Political
Executives and both Community Committee’s.
January 2007
Urban Vision outlined draft ideas for options at the joint management /
project team meeting (19/01/07).
January 2007
Key stakeholders interviewed.
January 2007
Baseline analysis stage completed.
January 2007
Business survey comprising face to face interviews completed. 38% of
businesses along the corridor participated (140 businesses). The survey
highlighted the following issues of concern:
Crime and vandalism,
Appearance of area,
Litter / street cleaning and off street parking.
Urban Vision presented baseline review findings at management
meeting (19/12/06).
December 2006
December 2006
Funding sources
NRF £20k for commission
Plus additional for consultation phase, potential £6K
Publicity to date
Planned for Feb 2007 – web and PR leaflet
33
Project: Building Schools for the Future
Pledge: Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Irlam and Cadished
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
BSF vision to create buildings for the 21st century and to provide
choice and a greater range of services at each secondary school.
Supporting the vision is an investment of up to £110 million from
Government's BSF programme.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Progress
Date
Outline planning permission granted for Irlam & Cadished community
high school at Planning Panel on 01/02/07.
February 2007
The strategic Business Case was approved by Salford City Council and
submitted to DfES in November 2006.
December 2006
Consultation on draft proposals completed.
25/10/06
Information road show held at Salford Link.
06/10/06
Proposal for refurbishing Irlam & Cadished High announced.
Funding sources
BSF
Publicity to date
Consultation information on SCC website
Production of draft vision brochure
34
September 2006
Little Hulton & Walkden
Ashton Fields Site



This project aims to develop a Film Village on the reclaimed site at Ashton Fields.
Assistant Director of Economic Development SCC briefed SCC leader on current situation
regarding Web Lighting and the Ashton Field site.
Discussions are ongoing with Web Lighting regarding the retention of their current operation in
Little Hulton.
Cutacre Site




This project will see a coal washing operation opening.
Discussions are on-going between UK Coal and Bolton MBC regarding the employment
potential of the site.
Archaeological works will begin at Wharton Hall during spring 2007.
During summer 2007 approximately 2ha of soil stripping will take place south of Cutacre tip.
Roe Green Loop

Phase 1 work on the 1km walkway between Spa Crescent and Mount Skip Lane commenced
at the end of September 2006. Work is expected to last 20 weeks. The cost of the first phase
is £250,000 and will be met by block 3 capital funding. The loop line will form part of the
national cycleway.
Walkden Town Centre



SCC have written to the owners of the former Kwik Save site to request plans for
redevelopment. The new owners replied in November formalising proposals and requesting
further discussions with SCC.
Building work on Walkden LIFT centre commenced November 2006.
Permission has been granted for residential development on the former cuemasters site on
Harriet Street.
Building Schools for the Future



Outline planning permission granted for Walkden High school at Planning Panel on 01/02/07.
Information roadshow held at Salford College 05/10/06.
Proposal to rebuild Walkden High and increase its capacity to 1500 pupils announced
September 2006.
35
Project: Ashton Field Site
Pledge: Creating prosperity in Salford
Area Covered
Little Hulton
Lead Officer
Mike Arnold, Planning Services
Summary
Development of a Film Village on the reclaimed site at Ashton Fields.
Priorities and Milestones
Timescales
Progress
Assistant Director of Economic Development SCC briefed SCC leader
on current situation regarding Web Lighting and the Ashton Field site.
Date
Discussions are ongoing with Web Lighting regarding the retention of
their current operation in Little Hulton.
Reclamation of the 7ha platform for industrial uses is complete.
Highway improvements to Ravenscraig Road are complete. Lambert
Smith Hampton are marketing the site to B1, B2 and B8 users.
Public open space works were completed November 2006.
Maintenance agreements are in place for the site to be maintained by
the Land Reclamation Trust.
Web Lighting’s new studio (C stage) is operational. Web have 61
employees directly employed in film making and related activities, which
rises to over 325 when film making is being undertaken on site.
Funding sources
NWDA/ EP
Publicity to date
36
January 2007
November 2006
November 2006
November 2006
Ongoing
Project: Cutacre Site
Pledge: Creating prosperity in Salford
Area Covered
Cutacre site, Little Hulton
Lead Officer
Anthony Stephenson, Urban Vision
Reclamation and restoration of the land, following coal extraction, for a
Summary
mixture of amenity, agriculture and woodland uses.
Priorities and Milestones
Timescales
Archaeological works will begin at Wharton Hall.
Spring 2007
Approximately 2ha of soil stripping will take place south of Cutacre tip.
Duration of programme.
4 years
Progress
Discussions are on-going between UK Coal and Bolton MBC regarding
the employment potential of the site.
Discussions regarding the provision of a bond to cover any restoration
costs of the site (if UK Coal collapse) are reaching a close between
SCC, Bolton MBC, Wigan MBC and UK Coal. The bond has been
agreed at £2.5million and the legal documents are now being prepared.
All pre-commencement conditions have been discharged and work is
commencing.
Funding sources
Publicity to date
Summer 2007
Date
January 2007
January 2007
On-going
Private funding
Liaison meetings with Ward Councillors and residents take place
every few months. Given the size of the site, it has been split into
areas A-H which will be worked as separate phases (some of which
overlap). These phases offer an opportunity for communication.
.
37
Project: Walkden Town Centre
Pledge: All
Area Covered
Walkden Town Centre
Lead Officer
Richard Wynne, Urban Vision
Summary
Various interventions to promote or enhance the town centre.
Priorities and Milestones
Timescales
Progress
SCC have written to the owners of the former Kwik Save site to request
plans for redevelopment. The new owners replied in November
formalising proposals and requesting further discussions with SCC.
Date
Building work on Walkden LIFT centre commenced.
Permission has been granted for residential development on the former
cuemasters site on Harriet Street.
Funding sources
Publicity to date
38
November 2006
November 2006
September 2006
Project: Building Schools for the Future (BSF)
Pledge: Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Little Hulton & Walkden
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
BSF vision to create buildings for the 21st century and to provide
choice and a greater range of services at each secondary school.
Supporting the vision is an investment of up to £110 million from
Government's BSF programme.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Progress
Date
Outline planning permission granted for Walkden High school at
Planning Panel on 01/02/07.
February 2007
The strategic Business Case was approved by Salford City Council and
submitted to DfES in November 2006.
December 2006
Consultation on draft proposals completed.
25/10/06
Information roadshow held at Salford College.
05/10/06
Proposal for expanding Walkden High School to 1,500 places to be
rebuilt on the current site.
Funding sources
BSF
Publicity to date
Consultation information on SCC website
Production of draft vision brochure
39
September 2006
Ordsall & Langworthy
Salford Central Station



Improvements to the station and approaches will provide a major transport interchange for
surrounding developments in Chapel Street and Manchester City Centre
Repair and restoration of the historic railway bridges was completed in November 2006.
The final Phase 1 design has been agreed and the various statutory approvals received. Phase 1
commenced on site on 04/12/06 and will be completed by September 2007.
Central Chapel Street

English Cities Fund (ECF) is developing a masterplan for the area as part of their evaluation of
development potential around the station. The masterplan will cover the area around the station,
extending West to Oldfield Road/Adelphi Street and North and South of Chapel street. ECF keen
that the masterplan be translated into informal planning guidance.
Manchester Bury and Bolton Canal


This project will restore the canal to navigation, instigating regeneration and development along its
length.
The final design is complete and British Waterways have issued tenders for the main engineering
works with a return date in Jan 2007. The start on site is delayed pending land acquisition from
Granada. All partners are now working to achieve the completion of the land agreement. Outputs
however are still at risk.
Ordsall Riverside

Ordsall Riverside area is facing significant development pressure, primarily for residential led high
density apartment schemes. This is at odds with both adopted planning policy and community
aspirations. In order to address these concerns the URC, working with the City Council, are
commissioning a masterplan to look at regeneration options for the Ordsall Riverside area. This
will include ongoing involvement of stakeholders in the area, including the community forum and
land owning stakeholders. Work on the masterplan should be complete by April 2007 and will form
the basis for the production of informal planning guidance for the area.
Crescent


Working with the City Council and other public sector / land owning stakeholders, the URC have
commissioned a masterplan to look at regeneration options for the Crescent area.
The masterplan will be complete by April 2007 and will also look at calming of the A6, at the
Crescent, potential for the creation of a new ‘University Square’ and restoration of the Manchester
Bolton Bury Canal through the area.
Greengate



The final Exchange Greengate Planning Guidance was adopted by Council on 17/01/07.
Three planning applications for Exchange Greengate were submitted in September 2006 – these
include two applications for mixed use development submitted by ASK and ASK/Network Rail and
an application for the primary public realm submitted by Central Salford. These applications are
currently being considered with a decision likely in March 2007.
An application for the public realm submitted to Manchester City Council has still to be registered.
It is anticipated that the application will be registered in February/ March and determined by April
2007.
40
Crescent Railway Station




Work has started with GMPTE, Network Rail, the University and Central Salford URC on options for
the future of Salford Crescent station. The station is currently working beyond its design capacity
and there are safety concerns at peak hours due to overcrowding of platforms.
The work will look at short term measures and longer term solutions (which could include relocation
of the station to a less constrained site.
Of more urgent concern is the introduction of new rolling stock by certain train operators – from
December 2006 and more significantly from May 2007. The net effect is that instead of 2 x 5 car
trains stopping per hour on one route, that will change to 1 x 3 car train per hour from December
2006. Further changes seem likely from May 2007.
This is a concern because it will result in fewer / smaller trains stopping at Salford Crescent (which
is already overcrowded). A mix of 3 and 6 car train sets will replace existing 5 car sets. Salford
Crescent Station can currently accept trains of up to 5 cars only. Lengthening platforms is not
possible without significant track relaying / signal changes, which cannot be implemented in the
immediate future.
Middlewood

Planning permission was granted in December 2006. The completion of 1st phase of the MBBC is
important for the delivery of Middlewood.
Pendleton

Enabling works for LIFT in progress ,October 2006.
Pendleton Area Action Plan
 Consultation on preferred options deferred until May 2007, due to feedback from GONW, the
options being redrafted, and the delay in the PFI announcement.
 DCLG announced PFI 5th round placements on 21/12/06. Pendleton will share £200million with
North Tyneside. The exact figures are not yet known.
Proposed TESCO adjacent to Shopping City



A steering meeting between Tesco /Prime Commercial Properties and SCC/URC/GMPTE took
place on 17/01/07. Further monthly meetings are scheduled.
A response from Tesco/ Gubbay to the action plan is expected shortly. A planning application is
expected to be submitted in May 2007. Many items are still to be resolved, but good progress is
being made on a number of fronts. In addition to the steering group a development approach team
is to be established to drive resolution of practical issues.
The timescales for delivery of the foodstore are being hampered by the school site swap (LEA - RC
Diocese), with potential vacant possession of the foodstore site now likely to be summer 2010.
Options to see if this date can be brought forward are being looked at but the outlook is not positive.
A note for the Leader of Council and Lead Members is to be produced for definitive guidance.
Northern Housing Challenge Fund Proposal


Great Places and SCC submitted a proposal to the Northern Housing Challenge Fund on the
15/09/06.
A decision by the Project Board on priorities is anticipated in the spring of 2007, although it is
possible this may be delayed until the summer. Successful proposals will then be worked up in more
detail . If successful spend would start in 2008/2009.
41
Seedley Village






Block improvements for West of Seedley Park Road phases 3 and 4 and Seedley West phase 3
have been completed. 183 homes were improved.
The Langworthy Hotel and adjacent land is currently being marketed with a deadline for receipt of
expressions of interest set for 26/01/07. The Seedley and Langworthy Partnership Board and the
Council consider this to be a good opportunity for a high quality mixed-use scheme in a particularly
prominent location along Langworthy Road. A selection panel including key partners and
stakeholders will review and shortlist submissions in January 2007.
Renovation works are currently on-going to improve 10 properties for Homeswap purposes on
Cooperative St.
Current scheme on site to improve 13 shops on Langworthy Road (195 -219), due for completion
May 2007.
Work has commenced on site on the refurbishment of Chimney Pot Park. Completion is scheduled
for April 2007. A celebration event is being planned for July 2007.
Construction of a mixed use scheme including a church (Emmanuel Church) community facilities
and 22 apartments is due to commence on site in spring 2007.
Salford Quays
Clippers Quay

Outline planning application approved by Planning Panel on 01/02/07 for the demolition of the
former cinema and erection of 654 residential units and 7,212m 2 of commercial floor space.
Michigan Avenue

Planning Panel granted planning permission on 01/02/07 for the erection of four 26-storey buildings
comprising of 1036 apartments and 58,475 sq.ft. of commercial space.
mediacity:uk





Considerable progress is being made on bringing the development forward.
Informal planning guidance approved January 2007.
Pre planning application discussions are on-going regarding phase 1 reserve matters application, to
be submitted in February 2007.
Letter from BBC Director General offering £200K towards next design phase has been received.
A strategic agreement is under negotiation between all partners.
Development of an Academy


Outline planning permission granted for Oasis City Academy at Planning Panel on 01/02/07.
Proposal to move Hope High to Salford Quays as an Academy were announced July 2006.
Ordsall




Start on site on the first phase development (31 houses and 3 apartments on Taylorson Street)
commenced on 04/12/06. Completion is expected late 2007.
Proposals are being prepared for development of 260 dwellings at Hulton Street. A planning
application was submitted in February 2007.
Ordsall Hall lottery assessment visits are being carried out over Jan/Feb 2007. A decision from the
Heritage Lottery trustees on phase 1 is expected in March 2007.
The new primary school and Children’s Centre are on target for opening autumn 2007.
42
Project: Salford Central Station
Pledge: Creating prosperity in Salford
Area Covered
Chapel Street
Lead Officer
Peter Baker (Central Salford URC)
Summary
 To improve the station and its approaches
 To provide a major transport interchange for surrounding
development in Chapel Street and Manchester City Centre
Priorities and Milestones
Timescales
Phase 1 completed.
September 2007
Progress
Date
The final Phase 1 design has been agreed and the various statutory
approvals received. Phase 1 commenced on site on 04/12/06.
December 2006
Repair and restoration of the historic railway bridges was completed.
English Cities Fund (ECF) developing masterplan for the area as part of
their evaluation of development potential around the station. The
masterplan will cover the area around the station, extending west to
Oldfield Road/Adelphi Street and North and South of Chapel Street.
The ECF scheme will be presented to the URC board on 25/10/06.
URC board to take decision on ESF proposal 02/11/06.
Final phase 1 design agreed and various statutory approvals received.
Possible additional funding from Railway Heritage Trust for historic
conservation is still being investigated.
The English Cities Fund (ECF) have been given a 3 month exclusivity
agreement with the URC to explore the development of the wider area
around the station.
Funding sources
Phase 1: EDZ
£1,080,848
GMPTE £3,352,442
Publicity to date
43
November 2006
October 2006
October 2006
September 2006
Project: Restoration of Manchester, Bury & Bolton Canal (MBBC)
Pledge: Enhancing life in Salford
Line of the Canal from the River Irwell Trinity Way / Hampson St to
Clifton Junction (and on into Bury & Bolton)
Phase 1 Middlewood
David Evans, Housing and Planning Directorate
Lead Officer
Mark Jackson, British Waterways
To see the restoration of the canal to navigation, as a catalyst to
Summary
regeneration & redevelopment along its line.
Priorities and Milestones
Timescales
Start on site of phase 1.
Early 2007
Area Covered
Expected completion phase 1.
Late 2007
Securing NWDA approval to project outline for future phases of the
canal.
Progress
The final design is complete and British Waterways have issued tenders
for the main engineering works with a return date in Jan 2007. The start
on site is delayed pending land acquisition from Granada.
The acquisition of Granada land is with solicitors for completion. Subject
to completion of acquisition from Granada, a start on site is expected
early in 2007, with completion winter 2007. All partners are now working
to achieve the completion of the land agreement. Outputs however are
still at risk. This issue has become complicated by Granada linking
disposal to British Waterways with an acquisition they want from Salford
City Council and consequent implications.
Discussions required with British Waterways to consider the impact of
proposed budget cuts on the 2nd and future stages of MBBC. This is
continuing but is tied in with making a start on phase 1.
ERDF (EDZ) funding approved for phase 1 Middlewood but the start is
now delayed and is a cause for concern.
Funding sources
Phase 1
ERDF £2,039,362
NWDA £1,100,000
S106
£1,000,000
Private sector £1,000,000 (contribution of land)
Publicity to date
44
Post 2006
Date
January 2007
January 2007
On -going
Project: Greengate
Pledge: Enhancing life in Salford/ Creating prosperity in Salford
Area Covered
Chapel Street
Lead Officer
Peter Baker (Central Salford URC)
Summary
Redevelopment of vacant and underused land and industrial property in
Greengate to create a new mixed-use urban quarter at core of
conurbation. Key project within Central Salford URC’s Chapel
Street/The Crescent Transformation Area. Need to ensure links with
Irwell City Park, City Centre Transportation Strategy and Springfield
Lane site.
Priorities and Milestones
Timescales
Key planning permissions for public realm and next phases of private
sector development.
February/March
2007
English Partnerships (EP) property and economic appraisals
undertaken.
By March 2007
Acquisition and CPO strategy developed.
By March 2007
EP investment programme developed and approved.
By Spring 2007
Key acquisitions by EP (former Exchange Bus Station) and
ASK/Network Rail (Chapel Street frontage).
April 2007
Public realm application submitted to MCC to be determined
April 2007
Progress
Date
The final Exchange Greengate Planning Guidance was adopted by
Council on 17/01/07.
A formal outline planning application was received from BSE on
22/12/07
Three planning applications for Exchange Greengate were submitted in
September 2006 – these include two applications for mixed use
development submitted by ASK and ASK/Network Rail and an
application for the primary public realm submitted by Central Salford.
These applications are currently being considered with a decision likely
in February/March 2007.
An application for the public realm submitted to Manchester City
Council has still to be registered. Additional traffic information is
required and discussions between highway engineers are currently
taking place. It is anticipated that the application will be registered in
February and determined by April 2007.
Public realm scheme being appraised by EP. The former bus station
has been declared surplus by GMPTE. EP are now negotiating bus
station purchase with GMPTE. CPO under consideration.
CABE response to the public realm scheme and planning applications
now received – generally favourable comments.
Development proceeding on site - Abito, Dandara and Chestergate
Land Ltd schemes progressing well.
January 2007
January 2007
January 2007
January 2007
January 2007
December 2006
On -going
Network Rail/ ASK joint venture has not yet been formally signed.
Issue of power supply to be discussed as part of wider discussion with
United Utilities on infrastructure provision for Central Salford.
Funding sources
English Partnerships, Private Sector and SCC Section 106
Publicity to date
Positive publicity in local press and professional journals about various
planning applications and public realm proposals.
45
ORDSALL
Project: Ordsall Development
Pledge: Enhancing life in Salford
Area Covered
South Irwell Riverside
Lead Officer
Malcolm Sykes, Strategic Director Housing and Planning Directorate
Summary
Regeneration and development within the Ordsall estate.
Priorities and Milestones
Submission of planning application for second phase of framework
development.
Opening of new primary school.
Timescales
February 2007
Summer 2007
Progress
Construction of new primary school and children’s centre commenced
and on target for opening autumn 2007.
Construction of a further 750 new apartments, by Bellway, David
McLean Homes and Lowry Homes well advanced.
Development Proposal Notice for 260 new houses and apartments at
Hulton Street submitted for council approval. Planning application was
submitted n February 2007.
Ordsall Hall lottery assessment visits are being carried out over Jan/Feb
2007. A decision from the Heritage Lottery trustees on progression
through to Stage 2 is expected on 20/03/07.
Start on site on the first phase development (31 houses and 3
apartments on Taylorson Street) commenced on 04/12/06. Completion
due late 2007. 28 properties sold to date.
Date
On-going
On-going
January 2007
January 2007
December 2006
Planning permission for 437 apartments and 12,000ft2 offices on
Ordsall Lane granted to Countryside Properties.
December 2006
URC commissioned consultants to prepare master plan for Ordsall
Riverside in liaison with SCC Planning team.
December 2006
Public consultation, including 4 events staffed by the Council, PCT and
LPC Living held to determine local views on the need for shops and
public services and on sketch plans for the Radclyffe School and
District Centre sites. Results of questionnaires currently being
assessed.
October 2006
SCC and URC have convened a meeting with developers to discuss the
increasing development pressure on Ordsall Lane.
October 2006
Planning application submitted by Vanguard Textiles for mixed-use
development on existing employment site on Ordsall Lane.
September 2006
Funding sources
Publicity to date
Private sector-led development, predominantly on Council-owned
land. Infrastructure works funded from land values. Sources of gap
funding to be identified. Housing Capital Programme.
 Local press articles followings completion of development
agreement.
 Press releases issued in respect of recent consultation
event.
 Quarterly newsletter for local residents.
46
Project: Pendleton Area Action Plan
Pledge: Enhancing life in Salford
Area Covered
Pendleton Centre
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
Summary
To develop an Area Action Plan for the central Pendleton area.
Priorities and Milestones
Timescales
Consultation on Preferred Options for Pendleton Area Action Plan.
Develop outline business case for PFI.
May - June 2007
Summer - Winter
2007
Consultation on Draft Pendleton Area Action Plan.
June - July 2008
Public Examination into the Draft Pendleton Area Action Plan.
Selection of preferred PFI bidder.
January 2009
Winter - Spring
2010
Adoption of Pendleton Area Action Plan.
December 2009
Progress
Date
Consultation on preferred options is deferred until May 2007, due to
feedback from GONW, the options being redrafted, after the delay in
the PFI announcement.
DCLG announced on PFI 5th round placements on 21/12/06. Pendleton
will share £200million with North Tyneside. The exact figures are not
yet known.
Contractors for the LIFT project now on site and preparation work for
the new access route is underway.
Funding sources
Housing Capital Programme, Private, PFI credits
Publicity to date
Various, associated with AAP consultation.
MEN press coverage of PFI announcement Dec 06
47
January 2007
January 2007
Nov 2006
Project: Northern Housing Challenge Fund Proposal
Pledge: Enhancing Life/ Creating Prosperity
Area Covered
Pendleton
Lead Officer
Deborah MacDonald, Housing and Planning Directorate
Summary
This will deliver 300 units of shared equity accommodation, mainly
family housing with a development of live / work units. This will provide
training and employment opportunities in conjunction with Step 1 in
Salford construction training scheme.
Priorities and Milestones
Timescales
Decision by project board on successful projects.
Spring/Summer
2007
Work up proposal (This may be revised in light of delays to the
announcement of the successful proposals).
Oct 2006 - August
2007
Project start (This may be revised in light of delays to the
announcement of the successful proposals).
2008/09
Progress
Date
Great Places have advised that a decision by the Project Board on
priorities is anticipated in spring 2007, although this may be delayed
until summer 2007.
It is anticipated that the original timescales will be revised to reflect the
delay in the announcement of the successful proposals and that
proposals will be worked up in 2007. If successful, spend would start in
2008/09, although this may be later due to the delays highlighted
above.
Great Places and SCC submitted a proposal to the Northern Housing
Challenge Fund.
January 2007
15/09/06
Funding sources
Great Places £2.5M
Private Sector Partner Developer £2.5M
Housing Corporation £2.5M
Salford Council (land contribution)
Publicity to date
None. If successful on the programme, publicity can be generated.
48
Project: Proposed TESCO Development – Shopping City
Pledge: Creating prosperity in Salford/ Enhancing life in Salford
Area Covered
Land adjacent to Pendleton Way
Lead Officer
Peter Openshaw, Urban Vision
New food store to support the centre and enhance retail facilities in
Summary
the area.
Priorities and Milestones
Timescales
New Church on site.
February/ March
2007
Planning application to be submitted.
March 2007
Progress
Steering meeting between Tescos /Prime Commercial Properties and
SCC/URC/GMPTE took place on 17/01/07. Further monthly meetings
are scheduled.
A response from Tesco/ Gubbay to the action plan is expected shortly.
A planning application is expected to be submitted in May 2007. Many
items are still to be resolved, but good progress is being made on a
number of fronts. In addition to the steering group a development
approach team is to be established to drive the resolution of practical
issues.
The timescales for delivery of the foodstore are hampered by the school
site swap (LEA - RC Diocese), with potential vacant possession of the
foodstore site now likely to be summer 2010. Options to see if this date
can be brought forward are being looked at but the outlook is not
positive. A note for Leader of Council and Lead Members is to be
produced for definitive guidance.
The School Organizations Committee consideration of schools
proposals is expected in early 2007, which if approved will trigger a
CPO action on the Glendinning street site. Lead Member
Education/Cabinet approvals to proposals is now in place.
CPO action to now be taken forward.
Further steering meetings scheduled between February and May 2007
to drive matters to a conclusion.
The relocation church site has been assembled without a contested
CPO as all interests were acquired beforehand. Other off site works are
progressing well, but issues relating to school CPO need to be
resolved.
GMPTE have appointed consultants to undertake Business case
analysis of bus options associated with the closure of Pendleton way.
Detailed discussion has commenced in relation to the land and
financial transactions associated with the sale of the Pendleton way car
parks to enable the extension of the shopping centre to proceed.
Funding sources
Private
Publicity to date
49
Date
Monthly meetings
ongoing
Monthly meetings
ongoing
January 2007
January 2007
Monthly meetings
ongoing
Project: Seedley and Langworthy
Pledge: All 7
Area Covered
Seedley Village
Lead Officer
Gill Finlay, Housing and Planning Directorate
To create a sustainable neighbourhood of choice that offers a safe
Summary
and attractive place to live for the existing community and encourages
newcomers and private investment.
Priorities and Milestones
Timescales
Secure preferred developer for the Langworthy Hotel and adjoining
land.
End March 2007
Construction work to start on Langworthy Hotel site.
Spring 2007
Seedley South consultation to identify preferred option for neighborhood
regeneration to be completed by TPAS.
March 2007
Neighbourhood strategy for Seedley South to be in place.
March 2007
Shops Phase 2 Refurbishments Complete.
May 2007
Chimney Pot Park completion.
May 2007
Progress
Date
A marketing brief has been prepared for the Langworthy Hotel and
adjacent land with a deadline for receipt of expressions of interest set
January 2007
for 26/01/07. A selection panel including key partners and stakeholders
will review and shortlist submissions in January 2007.
131 Homeswaps now completed relocating owner-occupiers from
January 2007
clearance areas.
Current scheme on site to improve 13 shops on Langworthy Road, due
for completion May 2007. A marketing exercise is being planned to
January 2007
identify appropriate users for the empty units.
Work has commenced on site on the refurbishment of Chimney Pot
Park. Completion is scheduled for April 2007. A celebration event is
January 2007
being planned for July 2007.
Eight disabled adapted bungalows for rent are currently being
developed by Great Places Housing Group on Nadine Street. The units
January 2007
are due to be completed from February – April 2007.
Shops on the east side of Langworthy Road have been cleared as part
of site preparation for the construction of a mixed use scheme including January 2007
a church (Emmanuel Church), community facilities and 22 apartments.
Work continuing and good progress being made on Urban Splash
development. The first units for occupation are due to be ready in
January 2007
March 2007. Affordable housing to be delivered by FTBI; £5m
investment via EP.
Central Salford HMR team are preparing an information brochure for
residents to explain activities, responsibilities and contacts for
January 2007
clearance area management; due to be published February 2007.
The demolition of former shops at 132 - 174 Langworthy Road is
On-going
ongoing.
NWDA, ERDF, HMRF, English Partnerships and Housing Capital
Funding sources
Programme.
Chimney Pot Park press coverage
Publicity to date
Launch of US First Time Buyers Initiative in October 2006
In Bloom July 2006
50
Project: Clippers Quay/ Michigan Avenue
Pledge: Enhancing life in Salford/ Creating prosperity in Salford
Area Covered
Salford Quays – Clippers Quay
Lead Officer
Dave Jolley, Urban Vision
Summary
Mixed-use development.
Residential to comprise mix of dwelling types from 1 to 3 bed.
Strong design requirement – aim is landmark building.
Priorities and Milestones
Timescales
Clippers Quay to begin on site.
Late 2007
Progress
Date
Clippers Quay
Outline planning application approved by Planning Panel on 01/02/07
for the demolition of the former cinema and erection of 654 residential
units and 7,212m2 of commercial floor space.
February 2007
Michigan Avenue
Planning Panel granted planning permission on 01/02/07 for the
erection of four 26-storey buildings comprising of 1036 apartments and
58,475 sq.ft. of commercial space.
The new application was taken to Planning Panel, where considerable
reservations were raised about the mix of the scheme. The scheme is
being reviewed and will be taken to Planning Panel on 01/02/07.
The site has planning permission for a mixed use residential scheme of
600 units in two 21 storey and two 29 storey towers. New application
submitted for 1,100 units 16/10/06.
Funding sources
Private Sector
Publicity to date
51
February 2007
January 2007
16/10/06
Project: mediacity:uk
Pledge: Creating prosperity in Salford / Enhancing life in Salford
Area Covered
Lead Officer
Summary
Salford Quays – Dock 9
Cath Inchbold, Assistant Head of Service, Regeneration Strategy and
Co-ordination, Chief Executive Directorate
Proposed relocation, from London and Manchester, of key BBC
Departments such as Childrens', Sport and Radio Five Live and the
creation of a hub of media and creative industries with the BBC at its
heart, mediacity:uk.
BBC agreement to move up North is contingent upon the licence fee
settlement.
Priorities and Milestones
Timescales
Progress
Date
The BBC Trust confirmed plans to move to Salford Quays, following the
announcement of the licence fee settlement on 18/01/07.
January 2007
Considerable progress is being made on bringing the development
forward.
January 2007
Informal planning guidance approved January 2007.
January 2007
Pre planning application discussions are on-going regarding phase 1
reserve matters application, to be submitted in February 2007.
January 2007
Letter from BBC Director General offering £200K towards next design
phase has been received.
January 2007
A strategic framework agreement is under negotiation between all
partners, working to a 01/11/06 deadline.
October 2006
People Programme finalised with the BBC, to be included in the
strategic framework agreement.
October 2006
Funding sources
Publicity to date
BBC relocation local and national press coverage.
52
Project: Development of an Academy
Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Salford Quays
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
The Hope Academy proposal is not part of the BSF and will form a
separate consultation process.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Specific consultation process for Academy proposal to take place.
January 2007
Progress
Date
Outline planning permission granted for Oasis City Academy at
Planning Panel on 01/02/07.
February 2007
Expressions of interest approved by DfES.
September 2006
Information roadshow held at Ordsall Neighbourhood Office.
Proposal to move Hope High to Salford Quays as an Academy
announced.
Funding sources
DfES
Publicity to date
53
04/10/06
July 2006
Swinton
Swinton
Lower Irwell Valley Improvement Area (LIVIA)
 This project will assess and treat contaminated land, where possible returning it to soft-end
and recreational use. Over 200 hectares of land has been identified for reclamation in the
Irwell Valley.
 The Forestry Commission (FC) have commenced site management and maintenance.
Significant improvements are already visible.
 The FC are also securing the relevant permissions to deliver the first stage of capital
improvements with a value of almost £400k planned for spend in this financial year.
Swinton Town Centre



Discussions still proceeding with regards to the LIFT Centre.
Discussions being sought with Swinton shopping centre owners. A meeting is considered
essential and the shopping centre owners are being pressed for dates.
A residents parking scheme is to be considered for implementation, on an experimental
basis, following consultation.
Agecroft Commerce Park


This is a 16.5 hectares site, is owned by the Northwest Development Agency (NWDA) and
marketed by DTZ (Manchester Office).
PZ Cussons have been granted planning permission to construct a £15m factory which will
be their UK headquarters for manufacturing. This will take up the largest plot of land on
Agecroft Phase III.
Building Schools for the Future (BSF)



Information roadshow held at Swinton Civic Centre 02/10/06.
Proposal for closing the Swinton and Moorside High Schools and replacement with one new
school of 1,500 pupils announced September 2006.
Proposal to expand St Ambrose - Barlow to 900 places, to be refurbished on its existing
site, announced September 2006.
54
Project: Newlands - Lower Irwell Valley Improvement Area (LIVIA)
Pledge: Enhancing life in Salford
Area Covered
LIVIA area in Pendlebury
Lead Officer
Tim Jones, Housing and Planning Directorate
Over 200 hectares identified for reclamation in the Irwell Valley.
Site suffers from significant contamination from a wide range of past
industrial uses.
Summary
Focus of the programme will be to assess contamination, treat it
where possible and restore the land for soft-end and recreational after
uses.
Priorities and Milestones
Timescales
Identify and agree 3 year capital programme.
On approval
Current Coalfield funding to be complete.
March 2007
Progress
The Forestry Commission (FC) have commenced site management and
maintenance and significant improvements are already visible.
The FC are also securing the relevant permissions to deliver the first
stage of capital improvements with a value of almost £400k planned for
spend in this financial year.
The Forestry Commission approved a 99-year lease on Council land. It
was originally expected that they would enter in to a 20 year lease, as
Newlands funding secures management and maintenance funding for
20 years. However, the FC is prepared to enter in to the additional
period on an ‘at risk’ basis.
The Single Programme Proposal Form (SPPF) for £4.75 million has
been approved by the NWDA and up to £365,000 was released for
2006/07.
Coalfield Community Funding of £225k has been secured for the Clifton
area, directly linked to the Newlands work on the LIVIA site.
Groundwork Salford, Manchester and Trafford have taken lead
responsibility for the delivery of this programme on behalf of the
Council. Phase I of works at Queensmere Dam to support the work of
Swinton and Pendlebury Angling Club has been completed. Progress
being made on entrance features at Silverdale.
Date
December 2006
December 2006
09/10/06
September 2006
On-going
£4.75m approved over a 5 year period, Approximately £1.5m of this
will provide at least 15 years management and maintenance.
Approximately £0.5 m has already been spent on site investigation
work, planning, design, legal issues, consultation work etc.
Funding sources
Publicity to date
Match funding has been secured from a number of sources including:
- Coalfield Communities fund, Environment Agency landfill tax credits,
S106 agreements, council capital receipts, Home Office ‘Gate-It’
funding.
Need to ensure linkage with other major regeneration initiatives
including e.g. Manchester Bolton & Bury Canal restoration, Central
Salford and New Deal for Communities.
Coverage in MEN
55
Project: Swinton Town centre
Pledge: Enhancing life in Salford
Area Covered
Swinton
Lead Officer
Richard Wynne, Urban vision
Summary
Overall improvement of town centre
Priorities and Milestones
A meeting between Swinton Shopping Centre agents and the LIFT
Chief Executive took place to discuss LIFT options.
Discussions being sought with Swinton shopping centre owners. A
meeting is considered essential and the shopping centre owners are
being pressed for dates.
A residents parking scheme is to be considered for implementation, on
an experimental basis, following consultation.
Discussions still proceeding with regards to the LIFT Centre.
Timescales
February 2007
January 2007
January 2007
December 2006
Progress
Date
Former Police Station demolished.
June 2006
Funding sources
n/a
Publicity to date
n/a
56
Project: Agecroft Commerce Park
Pledge: Creating Prosperity in Salford
Area Covered
Swinton
Lead Officer
Matthew Lynn, Economic Development, Chief Executive Directorate
Lever in private sector development in to the site using NWDA
funding. Currently the site is cleared and made up of development
plots serviced by an access road constructed in 2005 by NWDA. In
Summary
planning policy terms the end use is for employment generation in
terms of B1 Business, B2 General Industrial or B8, which is storage or
distribution. The site is 16.5 hectares and is owned by the Northwest
Development Agency and marketed by DTZ (Manchester Office).
Priorities and Milestones
Timescales
Encourage investment and developer interest in Phase III, which will
mean that all phases are up to full occupancy and maximum economic
End 2007
capacity.
Progress
PZ Cussons have been granted planning permission to construct a
£15m factory which will be their UK headquarters for manufacturing.
The site will provide 7,200 sq metres of floor space for industrial use
together with 1,240 sq m of offices over two floors. This will take up the
largest plot of land on Agecroft Phase III.
Currently the site is cleared and made up of development plots serviced
by an access road.
Funding sources
NWDA and RSI
Publicity to date
Article in Manchester Evening News 11/01/07.
57
Date
January 2007
November 2006
Project: Building Schools for the Future (BSF)
Pledge: Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Swinton
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
BSF vision to create buildings for the 21st century and to provide
choice and a greater range of services at each secondary school.
Supporting the vision is an investment of up to £110 million from
Government's BSF programme.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Progress
Date
The strategic Business Case was approved by Salford City Council and
submitted to DfES in November 2006.
December 2006
Consultation on draft proposals completed.
25/10/06
Information roadshow held at Swinton Civic Centre.
02/10/06
Proposal for amalgamating The Swinton and Moorside High Schools in
to one new school of 1,500 pupils announced. Site options are being
investigated.
Proposal to expand St Ambrose - Barlow to 900 places, to be
refurbished on its existing site, announced.
Funding sources
BSF
Publicity to date
Consultation information on SCC website
Production of draft vision brochure
58
September 2006
September 2006
Worsley & Boothstown
Salford Forest Park/Manchester Race Course

A second planning application for an international race course/equestrian centre/forest park
visitors centre/hotel/golf course/eco village submitted (July 2004). Urban Vision is in the
process of undertaking a detailed assessment of the proposed development.
The Highways Agency now has a holding direction in place until the 24 th May 2007. This
directs that the Local Authority cannot grant planning permission. All technical matters will
need to be resolved before the application can be taken to the Planning and Transportation
Regulatory Panel with a recommendation.
Peel's consultants submitted Green Belt supporting evidence in October 2006. A difference
of view still exists but the application will proceed.


Building Schools for the Future


Information roadshow held at Salford College 05/10/06.
Proposal for closing St George's RC High announced September 2006.
Destination Worsley




Marketing materials are currently being produced, this is part of the three year marketing
strategy.
A brand development exercise is currently underway.
The last 'Destination Worsley' public forum was held in September 2006.
Worsley tourism forum have monthly meetings.
59
Project: Salford Forest Park/Manchester Race Course
Pledge:
Area Covered
Lead Officer
Summary
Worsley/Boothstown
Chris Findley (Housing and Planning Directorate)
Martin Hodgson/Helen Ashworth (Urban Vision)
The Masterplan for the site includes the provision of a racecourse
with floodlit all weather track and grandstand; an equestrian centre;
80 bed hotel; a golf course and clubhouse; a forest park centre
comprising timber initiative centre, woodland wildlife centre,
exhibition space, a demonstration eco-village, camping and
woodland play area
A network of footpath, riding trails and cycle paths are proposed
A number of new roads are proposed including a link to J13 of the
M60
Extensive landscaping, including ground remodelling, the creation of
water bodies and woodland is also proposed
Priorities and Milestones
Timescales
Highways Agency pronouncement expected.
24/05/07
Progress
Date
The Highways Agency now has a holding direction in place until the
24/05/07. This directs that the Local Authority cannot grant planning
permission. All technical matters will need to be resolved before the
application can be taken to the Planning and Transportation Regulatory
Panel with a recommendation.
Peel's consultants submitted Green Belt supporting evidence in October
2006. This is currently being assessed.
A second planning application for the international race
course/equestrian centre/forest park visitors centre/hotel/golf
course/eco village was submitted. Urban Vision is in the process of
undertaking a detailed assessment of the proposed development.
Funding sources
Private Sector
Publicity to date
60
January 2007
January 2007
July 2004
Project: Building Schools for the Future
Pledge: Pledge: A learning and creative City/ A city where children and young people are valued
Area Covered
Worsley
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Summary
BSF vision to create buildings for the 21st century and to provide
choice and a greater range of services at each secondary school.
Supporting the vision is an investment of up to £110 million from
Government's BSF programme.
Priorities and Milestones
Timescales
Submission of the outline business case.
February 2007
Progress
Date
The Strategic Business Case was approved by Salford City Council and
submitted to DfES in November 2006.
December 2006
Consultation on draft proposals completed.
25/10/06
Information roadshow held at Salford College.
05/10/06
Proposal for closing St George's RC High announced.
Funding sources
BSF
Publicity to date
Consultation information on SCC website
Production of draft vision brochure
61
September 2006
PROGRAMMES
Programme: Housing Market Renewal Fund
Area Covered
Central Salford
Lead Officer
Kevin Scarlett, Housing and Planning Directorate
Summary
This project is reversing a failing housing market. There are four major intervention
areas. These are NDC area, Seedley & Langworthy, Higher and Lower Broughton
Start Date
02/10/03
End Date
2013
Key Outputs
Output
Target 06/07
Actual Sept 2006
Homes constructed
46
0 (report year end)
Homes acquired
26
105
Houses assisted with relocation
97
23
Progress
Date
Audit Commission monitoring visit feedback received.
December 2006
Discussions on-going with DCLG regarding CPO forward commitments/ use of
capital receipts.
On-going
Expenditure
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
2,300,000
4,920,000
4,039,000
5,111,000
16,370,000
Actual Spend 2006/07
2,300,000
4,476,000
4,353,000
-
Total Approved Spend
06/07
16,370,000
Publicity to date
All linked to delivery of neighbourhood level programmes within each of 8
neighbourhoods across Central Salford.
Integrated secretariat team now includes Marketing and Communications post.
62
Programme: Neighbourhood Renewal Fund
Area Covered
Citywide with focus on 10% most deprived wards according to 2004 Index of
Multiple Deprivation (affecting 15 of the 20 wards in Salford - these being Little
Hulton/ Walkden North/ Swinton North/ Pendlebury/ Swinton South/ Winton/ Irlam/
Barton/ Eccles/ Weaste & Seedley/ Langworthy/ Ordsall/ Irwell Riverside/
Broughton/ Kersal)
Lead Officer
Alan Tomlinson, Policy and Improvement, Chief Executive Directorate
Summary
This programme aims at improving floor targets and closing the gap in the
following areas: Economic Development
 Lifelong Learning
 Children and Young People
 Health
 Crime
 Social Inclusion
 Living Environment
Start Date
April 2001
End Date
March 2008
Key Outputs *1
Q1 & Q2 2006/07
Number of people into employment (priority 2) - Jobshop Advice Network.
62
Number of people into employment (priority 1) - Jobshop Advice Network.
69
Number of people engaged - Jobshop Advice Network.
263
Number of personal loans - Tackling Financial Exclusion project.
61
Number of people receiving financial advice -Tackling Financial Exclusion.
36
Number of grant applications from young people - Youth Action project.
10
Number of community groups supported - SAYO & SPARKY projects.
8
Progress
Date
All projects have signed-off contract letters.
January 2007
Third Quarter spend reports received.
January 2007
Only 2 projects do not have signed contract letters.
November 2006
All but 6 projects have returned signed contract letters.
October 2006
Second Quarter spend reports received.
October 2006
First Quarter spend reports received.
July 2006
£152,460 was carried over from 2005/06 and is now allocated to 2006/07 projects.
April 2006
Expenditure
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
£500,000
£1,000,000
£3,500,000
£4,460,460
£9,457,535
Actual Spend 2006/07
£697,451
£2,814,132
£1,689,408 *2
Total approved spend
£9,457,535
£5,200,991
Publicity to date
*1 no change since previous report, final Quarter 3 data will not be available until the end of January 2007
following confirmation of outputs with project managers.
*2 final
Quarter 3 data will not be available until the end of January 2007 following confirmation of spend
with project managers.
63
Programme: New Deal for Communities
Area Covered
North Irwell Riverside
Lead Officer
Tim Field – NDC Chief Executive
Summary
This programme concentrates on delivering improvements in the
following areas:
Building Communities
Crime and Community Safety
Education, Children and Young people
Physical Environment
Health
Business, Employment and Skills
Start Date
April 2001
End Date
March 2011
Programme Projects

















Housing redevelopment in riverside locations
Kersal High
Remodelling and renewal of existing housing public and private estates.
Salford Innovation Park hub.
Supporting Schools
GEARS+ (Automotive project with Young People)
Burglary Reduction
Community Health Action Partnership
Alley gating.
Public realm improvements.
Pendleton Gateway.
CRASY sports development.
Targeted policing.
Business Support (special grants for expansion)
Shop Parade improvements
Summer Fun
Job Shop.
Key Outputs to date
Beneficiaries of community safety initiatives - 438
People gaining advice and guidance - 2,146
Residents entering education / training - 923
Progress
Date
See earlier NDC Project update
Expenditure
Q1
Q2
Q3
Q4
Total
Spend
Projected Spend 2006/07
1,663,621
1,566,157
1,944,939
2,711,486
7,099,548*
Actual Spend 2006/07
1,306,339
1,250,239
1,831,484
-
4,388,062
Total Approved Spend
06/07
£7.1 million
Publicity to date
NDC Newsletter
*The approval letter from GONW has been received and the grant amount was £7,099,548. The extra
£77K allocated initially has now been revised.
64
Programme: North West Objective 2 Programme Priority 2
‘Improving People & Communities’
Area Covered
Lead Officer
Summary
Start Date
Barton, Blackfriars, Broughton, Langworthy, Little Hulton, Ordsall, Pendleton,
Weaste and Seedley, Winton (Walkden North, transitional)
Dee Carroll, Regeneration Strategy and Co-ordination,
Chief Executive Directorate
To create local employment and enterprise opportunities, remove barriers to
participation and progression, improve employability and to increase
participation in the labour market, build the capacity and cohesiveness of
groups and communities and improve the local physical environment. This
will be delivered through 5 key themes:
 Developing Enterprise & Employment in Communities.
 Improving Access to Employment.
 Developing an Inclusive Information Society.
 Connecting Communities.
 Building Economically Sustainable Communities
End Date
January 2000
December 2008
Key Outputs
Q1 - Q3 2006/07
New premises (m²) -
1580
Community safety initiatives
107
People assisted towards employment
42,648
Actions
Date
Moneyline
On-going
Job Shop Plus
On- going
Langworthy Road improvements
August 2006
Salford Sports Village - opened
August 2006
SALT - established
1997 - On-going
Cornerstone - opened
March 2002
ICT in the community - established
March 2002
Expenditure (calendar year)
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
900,000
250,000
200,000
200,000
1,550,000
Actual Spend 2006/07
940,523
261,578
123,942
-
1,526,043
Total approved spend
Jan 2000 to March 2007
£21,761,831
Publicity to date
65
Programme: North West European Objective 2 Programme Priority 2
‘Manchester Salford Sustaining Neighbourhoods Initiative’
Area Covered
Lead Officer
Summary
Start Date
Central Salford wards
Dee Carroll, Regeneration Strategy and Co-ordination,
Chief Executive Directorate
The Programme seeks to support the process of transformation in a limited
number of Priority 2 wards surrounding the regional centre, maximising the
opportunity afforded to the area its designation as the first Housing Renewal
Pathfinder. The Action Plan seeks to utilise ERDF resources to add value to
the Housing Market Renewal in order to create sustainable neighbourhoods
through:
 Targeted streetscape and environmental enhancements
 Alleyway treatments and alley-gating
 Associated neighbourhood planning and ward co-ordination
End Date
October 2004
December 2008
Actions
Date
Community safety initiatives - 10
December 2008
Environmental initiatives - 10
December 2008
Neighbourhood Management application approved.
February 2006
Streetscape approved - work on site has started.
September 2005
Transportation Corridor Improvements approved - work on site has started.
October 2005
1st claims was submitted.
December 2005
Expenditure (calendar year)
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
1,430,742
90,000
513,492
418,704
£2,445,013
Actual Spend 2006/07
1,430,742
87,075
-
-
£1,517,817
Total approved spend
£2,300,000
Publicity to date
66
Programme: North West Objective 2 Programme –
Priority 3 ‘Irwell Corridor Economic Development Zones’
Area Covered
Lead Officer
Summary
Start Date
Blackfriars/Broughton
Dee Carroll, Regeneration Strategy and Co-ordination,
Chief Executive Directorate
To develop employment sites and realise the economic potential of natural,
built, cultural or industrial heritage assets to create significant number of jobs,
that are accessible to residents from ‘communities in need’. This will be
delivered through 3 themes:
 Developing Strategic Employment Opportunities.
 Maximising the economic potential of the Region’s Natural, Cultural
Assets.
 Connecting with communities in need.
December
End Date
January 2000
2008
Actions
Date
Phase 1 complete.
June 2007
Securing NWDA approval to project outline for future phases.
Post 2006
Awaiting planning consent.
October 2006
Phase 1 on site.
June 2006
Start on site phase 1.
May 2006
Agreement to Phase 1 scheme by GMPTE/City Council/Network Rail/SRA/Train
Operating Company.
2004
Manchester Bury Bolton (MBB) Canal - Opening of the first phase.
2004
Expenditure (calendar
year)
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
1,942,926
1,500,000
1,093,831
2,087,299
5,324,358
Actual Spend 2006/07
1,942,926
886,137
-
-
2,829 ,036
Total approved spend
£5.3 million
Publicity to date
67
Programme: Fairshares Transforming Your Space
Area Covered
Lead Officer
Summary
Start Date
City Wide
Sue Ford, Regeneration Strategy and Co-ordination Section
Chief Executive Directorate
Chimney Pot Park
Mandley Park
City Park and Play Activity in 5 parks
Strengthening Communities – improvements at 5 community centres
Ordsall Community Café
Oakwood Park
Beechfarm Playing Fields
Princes Park
End Date
August 2003
March 2007
Actions
Date
All projects to be complete.
31 March 2007
Chimney Pot Park – The lottery funded element of the scheme is now complete.
December 2006
Mandley Park – Completed and open to the public.
October 2005
Oakwood Park – Completed and open to the public.
Autumn 2006
Chimney Pot Park - Site investigations completed.
September 2006
o
St. Mary’s Park – Completed and open to the public.
March 2006
o
Albert Park – Completed and open to the public. Additional multi-games area
now installed and open.
Winton Park – Completed and open to the public. Sure Start contributed £85k to
the project.
o
Lightoaks Park – All works completed and open to the public.
o
Eccles Recreational Ground – Completed and open to the public. Additional
multi-games area now installed and open.
Ordsall Community Café phase one completed and open to the public. Funding
has been secured to complete the final phase of the refurbishment.
May 2005
July 2005
November 2005
Beechfarm Playing Fields – Completed and open to the public.
December 2005
June 2005
May 2005
Princes Park – Completed and open to the public. Additional access path now
completed.
Strengthening Communities – All five Community Centres are complete and
open to the public. The project is now financially complete.
May 2005
All completed
December 2004
Expenditure
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
40,000
90,000
145,000
146,736
£421,736
Actual Spend 2006/07
40,386
91,970
144,125
-
£276,481
Publicity to date
68
Programme: SHIFT (Salford’s Health Investment For Tomorrow)
Area Covered
Salford community and hospital NHS services
Lead Officer
Stephen Whittaker, Salford PCT
Hope Hospital Redevelopment in a £130 million PFI contract and a further
£35 million modernisation investment.
Summary
Start Date
Change Management & Delivery: Redesign of health services to provide
integrated primary and hospital care with services provided in the most
suitable location: in hospital, in the community or at home. Six project areas
are Planned Care, Unscheduled Care, Diagnostics, Children’s Services,
Long Term Conditions and Practice Based Commissioning
NHS National Programme for IT IN Salford (now NHS Connecting for Health)
IN Salford, An integrated NHS Workforce IN Salford
April 2002
End Date
Actions
Date
NHS CFH - Local NHS patient information records transfer to new
national system (NHS Care Record System – Salford Primary Care
Trust).
Intermediate Care Beds at Heartly Green Care Home commissioned,
aiming to reduce demand on Hope Hospital beds for patients in
rehabilitation.
Hope Hospital - Financial close and start of construction.
Electronic prescriptions IN Salford.
October 2006
Spring 2007
June 2007
NHS Connecting for Health (CFH) - Local NHS patient information
records transfer to new national system (NHS Care Record System Hope Hospital).
NHS CFH – Picture Archiving and Communication System (PACS) brings
digital X-rays and scans to Hope Hospital, replacing traditional plain film
X-ray.
Hope Hospital - Submit full business case.
June 2007
December 2006
Autumn 2006
Choose & Book system allowing patients to choose first outpatient
appointment introduced. Currently handling more than 90% of Salford GP
referrals with a 100% target for Spring 2007.
Hope Hospital - Consultation with stakeholders.
December 2006
Summer 2006
NHS Anticoagulation service introduced ‘community anticoagulation
clinics’ in Swinton, Walkden and Charlestown.
Publicity to date
February 2007
(complete)
SHIFT website updates www.shiftprogramme.co.uk
Choose & Book – local and regional publicity campaign
69
March 2006
Programme: LIFT
Area Covered
Lead Officer
Summary
Six Health and Social Care Centres across Salford
Alan Westwood, Strategic Director Customer Services and Support
Services
Provision of new community and health buildings
Charlestown
Lower Kersal
Walkden
Swinton
Pendleton
Eccles
Priorities and Milestones
Timescales
Financial close Swinton.
Early 2007
Decision on final location of Swinton LIFT centre.
March 2007
Walkden under construction - practical completion.
July 2008
Eccles under construction - practical completion.
July 2008
Pendleton under construction - practical completion.
Progress
November 2008
Date
Phase 1C financial close Eccles.
05/12/06
Laing O Rourke to commence building works on site at Pendleton,
Walkden and Eccles.
Lower Kersal complete.
November 2006
November 2006
Proposals for Swinton to be reviewed, subject to the outcome of the
sale of the shopping precinct.
Phase 1C financial close Pendleton & Walkden achieved.
Winter 2006/07
31/10/06
Funding sources
PCT / NHS
Publicity to date
Walkden / Pendleton Financial Close
SHIFT website updates www.shiftprogramme.co.uk
70
Programme: Urban Regeneration Company (URC) Development
Area Covered
Central Salford
Lead Officer
Cath Inchbold, Assistant Head of Service,
Regeneration Strategy and Co-ordination, Chief Executive Directorate
Summary
Key projects for the URC are:
Salford Central station area.
Chapel Street realignment, transformation.
Greengate
Pendleton
Irwell Corridor
BBC Relocation
Progress
Date
Vision & Regeneration framework supplement in Salford Advertiser
(18/01/07).
January 2007
Regeneration Director appointed.
December 2006
Measures to open up/ clear trees on the Meadows under
consideration.
SCC/URC monthly meetings now established.
Publicity to date
October 2006
On-going
BBC relocation covered nationally and locally
71
Programme: Safer Stronger Communities Fund (SSCF)
Area Covered
Little Hulton (super output areas E01005662/ E01005664/ E01005665),
Winton (super output areas E01005725/ E01005729/ E01005731)
Lead Officer
Alan Tomlinson, Policy and Improvement, Chief Executive’s
Start Date
April 2006
Summary
Delivery of a programme of projects for Little Hulton and Winton in
respect of the Neighbourhood Element and Cleaner, Safer, Greener
Element of SSCF
End Date
March 2008
Actions
Date
Programme of projects for 2007/08 to be drafted.
March 2007
Identified under spend re-allocated to substitute projects.
22/01/07
Second meeting of project deliverers group.
8/01/07
Amber rating achieved for SSCF Programme by GONW.
21/12/06
First meeting of project deliverers’ group.
18/12/06
6 monthly review of Agreement with GONW
14/12/ 06
Contingency options have been identified in case there is an under spend.
October 2006
Board approves further projects to the value of £71,975.
3/11/06
Further applications assessed by SSCF Officer Group.
13/10/06
Further applications submitted
9/10/06
Board approves programme of projects for Little Hulton and Winton.
03/10/06
Board approves bulk of programme subject to further information on many
projects.
20/07/06
GONW accepts Salford SSC Agreement.
07/07/06
Revised Agreement submitted to GONW.
26/06/06
Salford SSC Agreement submitted to GONW.
28/04/06
SSCF Partnership Board agrees quick win projects for Little Hulton
(£42,529 for 7 projects) and Winton (£122,975 for 7 projects), largely youth
and community safety focused.
Expenditure
Q1
Q2
Q3
Q4
Original projected
spend
0
10,000
343,200
1,029,600
Revised actual and
profile December 2006
0
10,631
226,038
1,107,371
0
10,631
207,262
1,164,907
Revised actual and
profile January 2007.
Total approved spend
2006/07
£1,382,800 - projects in Little Hulton and Winton.
Publicity to date
72
March/ April 2006
Total Spend
1,382,800
1,344,040
(38,760 under
spend)
1,389,702
(6,902 overspend)
Programme Title: Building Schools for the Future
Area Covered
City Wide
Lead Officer
Mike Hall, Assistant Director (Resources), Children's Services
Start Date
Jan 2006
Summary
BSF will invest up to £110 million in rebuilding and refurbishing
secondary schools across the city.
End Date
2021
Actions
Date
The Outline Business Case is under development for submission in
February/ March 2007.
March 2007
Three planning applications are due at Planning Panel in February
2007. If permission is granted additional work is required.
January 2007
Stakeholder consultation event held on 09/01/07.
January 2007
The strategic Business Case was approved by Salford City Council
and submitted to DfES in November 2006.
Outline planning applications were submitted for sample scheme
schools (Irlam & Cadished High, Walkden High and the Academy at
Salford Quays) 30/11/06.
Consultation exercise has been analysed and feedback was provided
to parents.
Publicity to date
December 2006
December 2006
December 2006
Consultation sessions being held across the city
Dedicated pages have been set up on the Council's web site
A consultation leaflet has been published and widely distributed
Programme: Single Regeneration Budget Round 5
Area Covered
Lead Officer
Summary
City Wide
Sue Ford, Regeneration Strategy and Co-ordination,
Chief Executive Directorate
SRB 5 programme has now finished.
End of scheme conference/ workshop to be held on completion of
Evaluation.
Actions
Date
Stakeholder end of scheme conference to take place on 19/02/07.
Final SRB5 evaluation report received.
February 2007
January 2006
Succession strategies in place for whole programme.
Ongoing
HMRF investment.
On-going
Expenditure
Q1
Q2
Q3
Q4
Total Spend
Projected Spend 2006/07
11,000
0
8,000
16,000
35,000
Actual Spend 2006/07
11,000
0
-
-
11,000
Total approved spend 06/07
35,000
Publicity to date
73
Programme - Irwell City Park (ICP) Living Landmarks Lottery Bid
Area Covered
Ordsall / Irwell Riverside
Lead Officer
Malcolm Sykes, Strategic Director of Housing and Planning
Summary
Preparation of stage 2 Living Landmarks BIG Lottery submission. The
submission is being prepared through a collaboration of Salford City
Council, Manchester City Council, Central Salford URC and Trafford
metropolitan Borough Council. The vision of Irwell City Park is to
restore the river Irwell as an important urban waterway and create a
new and exciting city park at the heart of the regional centre.
Priorities and Milestones
Timescales
Preparation and submission of final lottery application.
Preparation of marketing and communications strategy.
31/05/07
End March 2007
Progress
Date
Private sector stakeholder consultation event held at the Imperial War
Museum on 13/02/07.
February 2007
Public stakeholder consultation event held at the Peoples History
Museum on 12/02/07.
February 2007
Preliminary masterplan was presented to members of the ICP Board
22/01/07.
January 2007
A developer forum was held on 6/12/06.
December 2006
Stakeholder event was held at the Lowry 13/12/06.
13/12/06
Broadway Malyan appointed as design and technical consultants.
Start up meeting held with BIG Lottery representatives.
Amion and Buro 8 appointed as project managers for the ICP project.
November 2006
24/10/06
12/10/06
Funding sources
Living Landmarks development funding
Publicity to date
Press release following progress to stage 2 and launch of the
technical and design competition.
Dedicated pages have been set up on the Council's web site
74
Programme - Salford West Regeneration Framework
Area Covered
Lead Officer
Summary
Salford West area covers 13 wards (Cadished, Irlam, Winton, Barton,
Eccles, Boothstown & Ellenbrook, Worsley, Swinton North, Swinton
South, Pendlebury, Walkden North, Walkden South, Little Hulton).
Maura Carey, Group Leader, Regeneration Strategy and Coordination
Development of a Strategic Regeneration Framework and Action Plan
that will drive investment and regeneration across the area for the next
20 years.
Priorities and Milestones
Timescales
Final framework and action plan produced.
May 2007
Consultation on draft framework and action plan.
March 2007
Draft framework produced.
January - February
2007
Stakeholder workshops.
December 2006
Progress
Date
Draft Salford West SRF futures report produced.
January 2007
Consultation feedback report completed.
January 2007
Councillor and community representative workshop held on 11/12/06
and 13/12/06.
Private sector stakeholder workshop held on 08/12/06.
Strategic Stakeholder consultation workshop held on 07/12/06.
Draft baseline and issues report received 27/11/06.
Salford West Regeneration Framework briefing and tour.
Funding sources
Publicity to date
December 2006
December 2006
November 2006
16/11/06
NRF
Dedicated pages have been set up on the Council's web site.
Coverage in Community Committee newsletters.
Article in property magazine.
75
Download