NGAO Team Meeting Management Peter Wizinowich March 19, 2009 Presentation Sequence / Schedule • • • Build-to-Cost (B2C) Review Results B2C Design Changes Preliminary Design Status vs SDR Plan – Why? • Next Steps 2 1st Draft B2C Reviewer Report Good Job!! B2C study has been an extremely efficient, cooperative, and productive response to the SSC’s request Compelling Science • Preserved science cases seem very compelling • Committee finds elimination in wide-field, d-IFU capability tolerable • Science cost/benefits analysis shows that B2C changes preserve (and sometimes improve) excellence of narrow-field science 4 Credible Technical Approach • • • Technical approach is a sound simplification of SDR concept Science instrument concept now needs to catch up We would like to understand… – – – – – Cost of additional instrument feeds Cost tradeoff between combined and separate imager + IFS More detailed study of imager capabilities and requirements (multiple plate scale?) Potential performance (and future upgrades) for shorter wavelengths below 800 nm Cost of implementing a fixed pupil mode 5 Credible Contingency • • Good bottoms-up approach to computing contingency Committee recognizes some persistent uncertainties – – – • Functional contingency options should be developed if cost contingency remains uncertain – – • Laser operating in a variable gravity environment (pending results of ESO Preliminary design studies) MEMS (pending demonstration of 64x64 device) RTC? (recommend revisiting NFIRAOS comparison Develop a risk register, with decision points, and track it at each review Possible examples include laser power, order of MEMS, phased introduction of tip/tilt sensors and PAS lasers Lab Integration / Test Schedule may also need greater contingency (pending development of schedule) 6 Unsolicited Advice • Phased approach should be considered for the PDR – Can sky coverage capability be phased? – Can Strehl ratio (e.g. laser power) be phased? • • Can a unique science phase space be defined for KNGAO relative to TMT (not JWST)? More importantly, KNGAO is ready to proceed to PDR completion at the $60M cap 7 NGAO System Architecture Key AO Elements: • Configurable laser tomography • Closed loop LGS AO for low order correction over a wide field • Narrow field MOAO (open loop) for high Strehl science, NIR TT correction & ensquared energy X 8 Revised NGAO System Architecture Key Changes: 1. No wide field science instrument • Fixed narrow field tomography • TT sharpening with single LGS AO • 75W instead of 100W • Narrow field relay not reflected 2. Cooled AO enclosure smaller 3. Lasers on elevation ring 4. Combined imager/IFU instrument & no OSIRIS 5. Only one TWFS 9 AO Design Changes Summary A. Architectural changes allowed by no deployable multi-IFS instrument 1. LGS asterism & WFS architecture 2. Narrow field relay location B. New design choices that don’t impact the requirements 1. Laser location 2. AO optics cooling enclosure C. Design choices with modest science implications 1. 2. 3. 4. Reduced field of view for the wide field relay (120” vs 150” dia.) Direct pick-off of TT stars Truth wavefront sensor (one visible instead of 1 vis & 1 NIR) Reduced priority on NGS AO science – Fixed sodium dichroic, no ADC for NGS WFS & fewer NGS WFS subaperture scales (2 vs 3) 5. No ADC implemented for LOWFS (but design for mechanical fit) 6. OSIRIS role replaced by new IFS 10 Science Instrument Design Changes • NGAO Proposal had three science instruments ($20M in FY06 $) – Deployable multi IFS instrument – NIR imager – Visible imager • For the SDR we included OSIRIS integration with NGAO • Science instrument design changes that impact the science capabilities – – – – – No deployable multi IFS instrument Addition of single channel NIR IFS Removal of OSIRIS (science capabilities covered by NIR IFS) No visible imager Extension of NIR imager & IFS to 800 nm 11 AO Optics Relay & Switchyard • 150” dia SDR FOV reduced to 120” with new assumptions Visible Imager focal plane Science Instrument OAP4 FSM NGS WFS TWFS focal plane LOWFS Boxes FSM NGS WFS OAP3 Tweeter DM OAP2 K-mirror rotator, upper level 25mm tweeter DM NIR Imager focal plane Fold down 140 mm Woofer DM Switchyard mirror LGS WFS 100 mm Woofer DM K-mirror OAP1, upper level OAP4 OAP3 LGS WFS focal plane OAP1 LOWFS/dIFS focal plane OAP2 12 Revised Cost Estimate Including all proposed cost reductions & new cost estimates: • Inflation assumption = 2.0% in FY09 & 3.5%/yr in FY10 to 15 NGAO System System Design Preliminary Design Detailed Design Full Scale Development Delivery & Commissioning Contingency (24%) NGAO Total = IFS Design Imager and IFS Instrument Contingency (10/30%) NGAO Instrument Total = Overall Total = Actuals ($k) Plan (Then-Year $k) FY07 FY08 FY09 FY10 FY11 FY12 FY13 739 495 214 1240 1492 1600 5500 978 400 500 7415 8715 739 739 709 709 1240 51 123 17 192 1432 466 1741 3014 3958 6000 10134 11729 229 78 443 4284 4264 486 67 1309 1279 146 739 5670 5544 632 4697 11670 15678 12361 FY14 FY15 5262 1764 3119 10145 1825 611 2436 12 4 15 10161 0 2436 Total 1234 2946 8078 22293 3589 8951 47090 358 9613 2822 12793 59883 13 Revised Cost Estimate AO Labor Hours Including all proposed cost reductions & new cost estimates: Labor Only Actuals (hrs) NGAO System FY07 FY08 FY09 Preliminary Design 2335 15000 Detailed Design Full Scale Development Delivery & Commissioning NGAO Total = 2335 15000 Plan (hrs) FY11 FY12 FY13 FY10 FY14 FY15 15872 12495 40000 19529 20000 40000 20336 16306 16306 28367 40000 39529 40000 36642 16306 Total 33207 72024 80336 32612 218179 NGAO Labor (excluding instruments) 45000 40000 Labor Hours 35000 30000 25000 20000 15000 10000 5000 0 FY09 FY10 FY11 FY12 Fiscal Year FY13 FY14 FY15 14 Cost Changes by WBS Labor hrs PY 4 4.1 4.2.1 4.2.2 4.2.3 4.2.4 4.2.5 4.2.6 4.2.7 4.2.8 4.2.9 4.2.10 4.3.1 4.3.2 4.3.3 4.4.1 4.4.2 4.4.3 4.4.4 4.4.5 4.4.6 4.4.7 4.4.8 4.5.1 4.5.2 4.6 AO System Development AO Enclosure 0 AO Support Structure 0 Rotator 0 Optical Relays 0 Optical Switchyard 2544 LGS Wavefront Sensor Assembly 994 NGS WFS / TWFS Assembly 952 Low Order Wavefront Sensor Assembly 0 Tip/Tilt Vibration Mitigation 0 Acquisition Cameras 0 Atmospheric Dispersion Correctors 864 Simulator 0 System Alignment Tools 0 Atmospheric Profiler 0 AO Controls Infrastructure 0 AO Sequencer 0 Motion Control SW 1500 Device Control SW 0 Motion Control Electronics 0 Non-RTC Electronics 0 Lab I&T System 0 Acquisition, Guiding, and Offloading Control 0 Real-time Control Processor 0 DM's and Tip/Tilt Stages 0 AO System Lab I&T 0 0.0 0.0 0.0 0.0 1.4 0.6 0.5 0.0 0.0 0.0 0.5 0.0 0.0 0.0 0.0 0.0 0.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 $k Trips Labor Non-labor Travel Conting 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 149 66 55 0 0 0 42 0 0 0 0 0 80 0 0 0 0 0 0 0 0 150 0 0 0 191 327 80 55 0 0 0 0 0 0 0 0 0 0 74 0 0 0 126 -225 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Total 27 0 0 0 102 170 30 24 0 0 11 0 0 0 0 0 30 0 28 0 0 0 35 -45 0 Use largest change as an example of cost spreadsheet 177 0 0 0 442 562 165 79 0 0 53 0 0 0 0 0 110 0 102 0 0 0 162 -270 0 B2 C2+ A1 C3,C4 C3 C4,C5+ A1,C2 A1,C2 A1 C1, MEMS 15 Cost Changes by WBS Labor hrs PY $k Trips Labor Non-labor Travel Conting 5 5.1 5.2 5.3 5.4 5.5 5.6 Laser System Development Laser Enclosure Laser Laser Launch Facility Laser Safety Systems Laser System Control Laser System Lab I&T 7 7.1 7.2 7.3 7.4 7.5 Labor $k hrs PY Trips Labor Non-labor Travel Conting Telescope & Summit Engineering Telescope Performance 0 0.0 0 0 0 0 0 Infrastructure Mods for AO 316 0.2 0 17 150 0 43 Infrastructure Mods for Laser 358 0.2 0 19 19 0 8 OSIRIS Modifications 1200 0.7 0 90 46 0 17 Interferometer and OHANA Mods 0 0.0 0 0 0 0 0 0 1526 0 0 0 400 0.0 0.8 0.0 0.0 0.0 0.2 0 8 0 0 0 0 0 144 0 0 0 24 0 -26 146 0 0 20 0 31 0 0 0 0 0 -614 47 0 0 12 Total 0 -465 193 A1 0 0 56 Total 0 211 B2 46 153 0 16 Preliminary Design Status vs SDR Plan • $3479k PD phase budget – – • Through Feb. ~21% complete vs 46% expected to be complete in SDR plan – • • $455k FY08, $2000k FY09, $1024k FY10, includes $449k of contingency 36,000 work hours This does not include science instrument design Through Jan. we have spent $437k or 14% of budget excluding contingency versus 18% of work completed Why? – Unplanned tasks that have required management attention • • • • – Personnel availability (only X of planned Y hrs spent) • • – NFIRAOS cost comparison B2C guidance MRI & ATI proposals Addition of science instruments Departing or unavailable personnel (DLM, RF, JZ, MB) Less senior management than planned Unclear direction in some areas • Primarily because of B2C 17 18 Actuals through Feb/09 19 Plan through Feb/09 Next Steps • Revise & complete requirements (SCRD, SRD & FRD) – • Produce a plan to get from now to the PDR – – – – • FRD process defined in next presentation Identify priorities & milestones Incorporate instrument design Include commitments from personnel & their management Begin with revision we had produced in Aug/08 prior to new B2C direction (MS project plan & KAON) Manage the plan (post B2C review) – – – – – Ensure tasks are defined & agreed on Systems engineering team needs to manage requirements & interfaces, & address systems issues to ensure tasks & process are well defined Task leads & teams need to manage their task to produce deliverables, meet requirements on schedule & within budget TSIP monthly reports to monitor progress & identify issues (technical, schedule, budget) Bi-monthly team video meetings with some face-to-face working meetings 20 Preliminary Design Objectives & Deliverables 1 • • • • Science Case Requirements Document Observing Operations Concept Document System Requirements Document Functional Requirements & Interface Control Document(s) – AO system, laser system, science operations tools, science instruments – Managed within Contour database • Preliminary Design Manual (the document to read to understand the design & performance of the NGAO facility – will start by generating TOC at sufficient level to define deliverables) – Flowdown of requirements to design – Solidworks & Zemax model(s) – Software design (RTC, non-RTC & science ops tools) – Performance Budget Reports (wavefront, EE, astrometry, contrast, …) – Science Performance Analysis Report • Science Instrument Design Manual 22 Preliminary Design Objectives & Deliverables 2 • Risk Assessment & Management Report • Systems Engineering Management Plan – – – – Project plan to completion, including a detailed schedule & budget Phased implementation option(s) Cost estimation Justification for any procurements during DD 23 NGAO SDR PD Milestones Year Month NGAO Project Milestone 2008 May 2008 October 2009 March 2009 April External Interface Document Release 1 2009 February Internal Interface Document Release 1 2009 May Software & Controls Architectures PD complete 2009 May LGS WFS Assembly PD complete 2009 June Laser vendor identified & contract ready 2009 June Optical relay/switchyard PD complete 2009 September RTC Processing Requirements complete 2009 November Laser Launch Facility PD complete 2009 December LOWFS Assembly PD complete 2010 February Preliminary Design phase begins Functional Requirements PD Release 1 April/09 Operations Concept Document Release 1 Preliminary Design Review April/09 Jan/10 April/10? 24 New NGAO PD Milestones? SDR Plan 2008 May 2009 March 2008 October 2009 Feb & Apr 2009 May 2009 June 2009 May 2009 September 2009 December 2009 November 2010 February Replan Dates? 2008 May 2008 November 2009 March 2009 March 2009 April 2009 May 2009 May 2009 June 2009 July 2009 August 2009 September 2009 December 2010 January 2010 February 2010 February 2010 April Milestone Preliminary Design phase begins NFIRAOS Cost Comparison Build-to-Cost Review Operations Concept Document Release 1 Laser Risk Reduction Contracts Issued Requirements PD Release 1 Interface Document Release 1 Software & Controls Architectures PD complete Optical relay/switchyard PD complete LGS WFS Assembly PD complete RTC Processing Requirements complete Laser Preliminary Designs complete LOWFS Assembly PD complete Laser Launch Facility PD complete NGAO IFU SD & Imager PD complete Preliminary Design Review 25 Instrument Development • Imager and IFS for ~800 nm to 2.4 µm 26 Imager PD Phase 27 Imager PD Phase 28 Imager PD Phase 29 IFS SD Phase 30