NGAO Management Update Peter Wizinowich NGAO Meeting #11 November 5, 2007 Project Reports • 4th & 5th reports submitted to Directors on 9/19 & 11/2 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning • Emphasis during this report period has been on: – – – – – System architecture evaluation & selection (June – Aug.) Functional requirements (Aug. – Dec.) Subsystem design (Sept. – Dec.) Proposals to TSIP & ATI Plus: completion of two performance budgets, incorporation of additional atmospheric characterization data, & summary reports for the performance budgets & trade studies 2 System Design Milestones Requirements Performance Budgets + Trade Studies System Architecture + Functional Requirements Subsystem Design + Functional Requirements # MILESTONE DATE STATUS 1 SD SEMP Approved 10/9/06 Complete 2 SD phase contracts in place 10/27/06 Complete 3 Science Requirements Summary v1.0 Release 10/27/06 Complete 4 System Requirements Document (SRD) v1.0 Release 12/8/06 Complete 5 Performance Budgets Summary v1.0 Release 6/15/07 Complete 6 SRD v2.0 Release 5/22/07 Nearly complete 7 Trade Studies Complete 6/22/07 Complete 8 SRD v3.0 Release 9/7/07 Not started 9 System Design Manual (SDM) v1.0 Release 9/21/07 Complete 10 Technical Risk Analysis V1.0 Release 9/21/07 Complete 11 Cost Review Complete 12/7/07 Some work as part of system architecture 12 SDM v2.0 Release 2/12/08 13 System Design Review Package Distributed 3/4/08 14 System Design Review 3/31/08 15 SDR Report & Project Planning Presentation at SSC meeting 4/14/08 Management Plan 4 milestones completed since June SSC meeting 3 Schedule & Budget Schedule: 53% of System Design Phase work complete through Oct. 4 Schedule & Budget Budget: 64% of System Design Phase budget ($730k) spent through Sept. – 92% of the $798k FY07 budget, excluding $20k contingency Plan needs to be reviewed to ensure deliverables complete for SDR NGAO: Cumulative % Cost & Work vs Month 70% Cumulative Total 60% 50% 40% 30% 20% % of budget 10% % of work 0% 1 3 5 7 9 11 Month (1 = Oct/06) 5 Schedule & Budget NGAO: Costs ($k) by Institution by Month 50.0 Costs ($k) 40.0 WMKO 30.0 COO 20.0 UCO SETI 10.0 0.0 1 3 5 7 9 11 Month (1 = Oct/06) 6 TSIP & ATI Proposals • $2M TSIP proposal for NGAO preliminary design submitted on Aug. 31 – – • $1.1M ATI proposal for deployable near-IR integral field spectrograph system design submitted on Nov. 1 – – • $2M request to fund ~70% of preliminary design Detailed schedule/budget to be determined during system design Proposed to ATI program because • Most complex NGAO instrument, with longest lead time • Advanced nature of key components made it suitable for ATI System design scheduled from May/08 to Dec/09 Proposal writing in both cases led by Adkins with support from WMKO management & NGAO EC 7 Design Teams • • • • • • AO opto-mechanical (Lead - Gavel) AO wavefront sensors (Velur) AO operational tools (Neyman) Laser facility (Chin) Controls (Johansson) Science operations (Le Mignant) • Work scope planning sheets (21) produced for all major design tasks – Define tasks, approach, inputs, products & personnel – Ensure agreement on scope – Some approvals are still pending 8 WSPS Status All but the following WSPS have been approved: • AO opto-mechanical – 3.2.1 AO system architecture • – 3.2.2 AO enclosure • – 3.2.3.12 PSF monitoring camera • Revision received, but effort has grown by 20h Controls (Johansson) – 3.2.4.1 & 2 Non RTC software & electronics • • Revisions requested AO operational tools – • Revisions requested 3.2.3 AO opto-mechanical • • ? Revisions recently received Science operations (Le Mignant) – 3.4.2.1 & 2 AO-Instrument operations architecture & optimization • Low priority since WSPSs for currently active WBS approved 9 Summary • Major milestones, except for science/system requirements, are being met • Good progress on functional requirements & database to maintain them • Schedule is starting to slip. – EC will be reviewing schedule & deliverables to ensure SDR is held on schedule & within budget 10