NGAO Management Update Peter Wizinowich NGAO Meeting #11

advertisement
NGAO Management
Update
Peter Wizinowich
NGAO Meeting #11
November 5, 2007
Project Reports
•
4th & 5th reports submitted to Directors on 9/19 & 11/2
http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning
•
Emphasis during this report period has been on:
–
–
–
–
–
System architecture evaluation & selection (June – Aug.)
Functional requirements (Aug. – Dec.)
Subsystem design (Sept. – Dec.)
Proposals to TSIP & ATI
Plus: completion of two performance budgets, incorporation of
additional atmospheric characterization data, & summary reports for
the performance budgets & trade studies
2
System
Design
Milestones
Requirements 
Performance Budgets +
Trade Studies 
System Architecture +
Functional Requirements 
Subsystem Design +
Functional Requirements 
#
MILESTONE
DATE
STATUS
1
SD SEMP Approved
10/9/06
Complete
2
SD phase contracts in place
10/27/06
Complete
3
Science Requirements Summary
v1.0 Release
10/27/06
Complete
4
System Requirements Document
(SRD) v1.0 Release
12/8/06
Complete
5
Performance Budgets Summary
v1.0 Release
6/15/07
Complete
6
SRD v2.0 Release
5/22/07
Nearly complete
7
Trade Studies Complete
6/22/07
Complete
8
SRD
v3.0 Release
9/7/07
Not started
9
System Design Manual (SDM)
v1.0 Release
9/21/07
Complete
10
Technical Risk Analysis
V1.0 Release
9/21/07
Complete
11
Cost Review Complete
12/7/07
Some work as part of
system architecture
12
SDM
v2.0 Release
2/12/08
13
System Design Review
Package Distributed
3/4/08
14
System Design Review
3/31/08
15
SDR Report & Project Planning
Presentation at SSC meeting
4/14/08
Management Plan
4 milestones completed
since June SSC meeting
3
Schedule & Budget
Schedule: 53% of System Design Phase work complete through Oct.
4
Schedule & Budget
Budget: 64% of System Design Phase budget ($730k) spent through Sept.
–
92% of the $798k FY07 budget, excluding $20k contingency
Plan needs to be reviewed to ensure deliverables complete for SDR
NGAO: Cumulative % Cost & Work vs Month
70%
Cumulative Total
60%
50%
40%
30%
20%
% of budget
10%
% of work
0%
1
3
5
7
9
11
Month (1 = Oct/06)
5
Schedule & Budget
NGAO: Costs ($k) by Institution by Month
50.0
Costs ($k)
40.0
WMKO
30.0
COO
20.0
UCO
SETI
10.0
0.0
1
3
5
7
9
11
Month (1 = Oct/06)
6
TSIP & ATI Proposals
•
$2M TSIP proposal for NGAO preliminary design submitted on Aug. 31
–
–
•
$1.1M ATI proposal for deployable near-IR integral field spectrograph
system design submitted on Nov. 1
–
–
•
$2M request to fund ~70% of preliminary design
Detailed schedule/budget to be determined during system design
Proposed to ATI program because
• Most complex NGAO instrument, with longest lead time
• Advanced nature of key components made it suitable for ATI
System design scheduled from May/08 to Dec/09
Proposal writing in both cases led by Adkins with support from WMKO
management & NGAO EC
7
Design Teams
•
•
•
•
•
•
AO opto-mechanical (Lead - Gavel)
AO wavefront sensors (Velur)
AO operational tools (Neyman)
Laser facility (Chin)
Controls (Johansson)
Science operations (Le Mignant)
•
Work scope planning sheets (21) produced for all
major design tasks
– Define tasks, approach, inputs, products & personnel
– Ensure agreement on scope
– Some approvals are still pending
8
WSPS Status
All but the following WSPS have been approved:
• AO opto-mechanical
–
3.2.1 AO system architecture
•
–
3.2.2 AO enclosure
•
–
3.2.3.12 PSF monitoring camera
•
Revision received, but effort has grown by 20h
Controls (Johansson)
–
3.2.4.1 & 2 Non RTC software & electronics
•
•
Revisions requested
AO operational tools
–
•
Revisions requested
3.2.3 AO opto-mechanical
•
•
?
Revisions recently received
Science operations (Le Mignant)
–
3.4.2.1 & 2 AO-Instrument operations architecture & optimization
•
Low priority since WSPSs for currently active WBS approved
9
Summary
• Major milestones, except for science/system
requirements, are being met
• Good progress on functional requirements & database to
maintain them
• Schedule is starting to slip.
– EC will be reviewing schedule & deliverables to ensure SDR is
held on schedule & within budget