NGAO Team Meeting Management Peter Wizinowich May 26, 2009 Presentation Sequence / Schedule • • Preliminary Design Status vs SDR Plan PD Replan Status – – – – • • Project Plan Personnel Plan Milestones (NGAO, Instruments, Proposals) Instruments Near Term Priorities PD Deliverables 2 Preliminary Design Status vs SDR Plan • $3479k PD phase budget – – • Through Apr. ~27% complete vs 57% expected to be complete in SDR plan – • • $455k FY08, $2000k FY09, $1024k FY10, includes $449k of contingency 36,000 work hours This does not include science instrument design Through Apr. we have spent $730k or 24% of budget excluding contingency versus 27% of work completed Why? – Unplanned tasks that have required management attention • • • • – Personnel availability • • – NFIRAOS cost comparison B2C guidance MRI & ATI proposals Addition of science instruments Departing or unavailable personnel (DLM, RF, JZ, MB) Less senior management than planned Unclear direction in some areas • Primarily because of B2C 3 4 Actual % complete through Apr/09 Replan Status • Replan nearly complete – Need to confirm COO personnel availability & revise appropriately – Need leads to confirm that schedule can be met • Would like to finalize plan this week – The plan will not be revised again during the PD • • We will doubtlessly need to make tactical adjustments However this is the plan we will be judged against for the remainder of the PD – We will begin reporting against this plan starting with the May report • We should be sure that what we said would be done in May is complete (do some tasks already need to be pushed out?) 5 MS Project Plan 6 MS Project Plan 7 MS Project Plan 8 MS Project Plan 9 MS Project Plan by Individual 10 Staffing Plan FY09 Plan (May-Sept) NGAO Imager IFS $ 160 $12,005 100 280 400 200 600 1740 500 320 400 40 1120 400 800 60 3640 $7,500 $39,952 $28,066 $12,712 $42,807 $9,220 $152,263 101 101 $47,590 $18,353 $33,111 $0 $37,517 $29,979 $56,983 $3,384 $226,916 80 80 66 58 27 $3,984 $3,504 FY10 Plan v16? (thru PDR) NGAO Imager IFS $ 192 $14,694 40 $2,911 300 $22,500 336 $48,902 480 $34,353 200 $12,966 720 $52,396 283 $26,238 2268 283 0 $214,960 500 140 400 960 450 655 60 3165 260 80 260 304 257 356 11 Total (wo/IFS) Hrs $ 381 $28,875 40 $2,911 400 $30,000 1031 $149,133 962 $68,172 415 $26,632 1669 $119,867 384 $35,458 5282 $461,049 Name Bouchez Brown Crepp Dekany Delacroix Hale Velur Weber Subtotal = $32,800 $34,401 $47,588 $3,452 $219,275 1616 1274 1013 40 4000 954 2483 204 11584 $154,797 $58,728 $84,515 $0 $133,485 $72,174 $177,076 $11,409 $692,182 Gavel Kupke Lockwood Macintosh McGrath Peck Reinig analyst Subtotal = $18,629 $15,733 370 315 $22,613 $19,237 Canfield Software Eng $48,542 $18,720 $33,773 NGAO Hrs Plan Avail.-Plan 342 10 40 0 400 0 932 -316 1268 -388 219 181 1550 -230 4751 -743 1014 448 726 40 2090 774 1383 120 6595 -14 12 74 0 -10 76 72 0 210 Instrument Hrs Plan Avail.-Plan 384 0 0 0 732 -312 732 -312 753 326 0 0 11 FY09 Plan (May-Sept) NGAO Imager IFS $ 41 312 79 $34,908 387 322 16 $49,725 Staffing Plan FY10 Plan v16? (thru PDR) NGAO Imager IFS $ 300 460 410 $76,659 900 355 230 $89,778 16 201 114 $14,731 $7,825 100 100 369 103 $7,293 $23,818 $7,593 100 500 20 20 351 150 52 860 200 $56,659 $15,039 175 $12,769 584 87 81 787 0 941 1 12 $1,167 $37,378 $1,400 $1,459 $29,406 $10,945 12 $42,613 $5,921 $5,512 $39,800 $0 $68,623 $37 180 85 884 80 950 20 480 $35,004 50 $3,646 350 100 66 381 $17,689 650 $17,074 $30,782 614 600 $41,656 $52,234 800 590 0 8815 $55,361 $52,391 $0 $713,941 187 30 16 760 634 282 $416,016 $12,495 $7,983 $46,440 $5,837 $70,665 $1,494 $26,034 $7,297 $4,816 234 5548 70 1163 16 1498 Total (wo/IFS) Hrs $ 1430 $142,916 1982 $140,770 1 $76 16 $1,167 946 $70,044 142 $9,751 20 $1,459 503 $29,406 150 $10,945 0 $0 0 $0 100 $7,293 2142 $139,406 530 $39,239 6 $491 175 $12,769 216 $14,239 684 $42,613 2 $139 269 $18,517 196 $13,495 1988 $101,430 82 $5,979 3170 $231,461 105 $7,718 17 $329 2 $85 843 $62,029 100 $7,297 125 $9,072 20 $956 234 $17,074 1087 $51,037 7 $268 1669 $114,263 2177 $187,676 0 $0 21132 $1,491,407 Name Adkins Bell Campbell Chan Chin Chock Cohen Conrad Devenot Doyle Grace Hess Johansson Johnson Kinoshita Kwok Le Mignant Lyke McBride Medeiros Mogensen Morrison Nance Neyman Panteleev Ragland Simmons Stalcup Stomski Summers Sung Tolleth Tyau Ward Wetherell Wizinowich Woillez Subtotal = NGAO Hrs Plan Avail.-Plan 240 101 1164 123 0 0 0 0 810 -109 120 14 20 0 418 33 150 0 8 -8 4 -4 0 100 1403 -174 382 -79 0 0 160 15 0 0 654 30 0 0 263 4 130 36 1430 241 83 -3 1763 128 20 1 12 0 0 0 839 -9 100 0 116 0 0 0 0 0 750 281 0 0 1133 281 1306 -116 0 0 13478 885 Instrument Hrs Plan Avail.-Plan 1342 -81 921 2 16 0 100 16 0 0 1169 -222 80 170 12 3644 -131 New NGAO PD Milestones Replan Dates 2008 May 2008 November 2009 March 2009 May 2009 June 2009 July 2009 August 2009 August 2009 September 2009 October 2010 October 2009 December 2010 March 2010 March 2010 April Milestone Preliminary Design phase begins NFIRAOS Cost Comparison Build-to-Cost Review Laser Risk Reduction Contracts Issued Operations Concept Document Release 1 Requirements PD Release 1 Software & Controls Architectures PD complete Optical relay/switchyard PD complete LGS WFS Assembly PD complete RTC Software PD complete Laser Launch Facility PD complete Laser Preliminary Designs complete LOWFS Assembly PD complete NGAO IFU SD & Imager PD complete Preliminary Design Review 13 New NGAO PD Milestones Replan Dates 2009 August 2009 October 2009 December 2010 January 2010 March NGAO Instrument Milestones Imager Trade Studies complete Imager Optical Modeling complete IFS Trade Studies complete IFS Slicer Down Select complete NGAO IFU SD & Imager PD complete Replan Dates 2007 September 2008 November 2009 January 2009 August 2009 September NGAO Proposal Milestones TSIP: NGAO PD Proposal submitted ATI: IFS PD Proposal submitted MRI: K2 Center Launch Proposal submitted MRI-R2: NGAO Proposal(s) to be submitted TSIP: NGAO Proposal to be submitted 14 Instrumentation Plan • NGAO Imager and IFS combined plan – Incorporates anticipate ATI funded IFS work – Parallels remaining AO system preliminary design phase • NGAO imager PDR and IFS SDR at or before NGAO main PDR – Imager preliminary design phase • Baseline is single instrument (common dewar, etc.) • Will do trade study for imager and IFS separately – IFS system design phase • Slicer approach trade study and down select • Requirements for all IFS components – IFS preliminary design phase extends beyond NGAO PDR • Will start Imager detailed design at same time as AO DD phase • When IFS PD phase completes remaining work will be one plan 15 Major Instrumentation Activities • Imager – – – – Brief trade study period Initial optical design Optical modeling and preliminary optical design Preliminary mechanical, electronic, software designs • IFS – – – – Trade studies Development of slicer design approaches Evaluation of approaches Down select for lab prototyping in PD phase • Documentation – – – – Instrument system level requirements Instrument system design manual Instrument systems engineering management plan Design phase reports 16 Near Term Priorities • Finalize planning – – • Finalize requirements – – – – • Complete NGAO replan Complete Instrument plan & staffing Revise & complete 1st release of requirements (SCRD, SRD & FRD) Requirements flowdown Complete 1st release of Observing Operations Concept Document Complete 1st release of Interface Control Document Manage the plan – – – – – Ensure tasks are defined & agreed on Systems engineering team needs to manage requirements & interfaces, & address systems issues to ensure tasks & process are well defined Task leads & teams need to manage their task to produce deliverables, meet requirements on schedule & within budget TSIP monthly reports to monitor progress & identify issues (technical, schedule, budget) Bi-monthly team video meetings with some face-to-face working meetings 17 Preliminary Design Deliverables 1 • • • • Science Case Requirements Document Observing Operations Concept Document System Requirements Document Functional Requirements & Interface Control Document(s) – AO system, laser system, science operations tools, science instruments – Managed within Contour database • Preliminary Design Manual (the document to read to understand the design & performance of the NGAO facility – draft PDM posted) – Flowdown of requirements to design – Solidworks & Zemax model(s) – Software design (RTC, non-RTC & science ops tools) – Performance Budget Reports (wavefront, EE, astrometry, contrast, …) – Science Performance Analysis Report • Science Instrument Design Manual 19 Preliminary Design Deliverables 2 • Risk Assessment & Management Report • Systems Engineering Management Plan – – – – Project plan to completion, including a detailed schedule & budget Phased implementation option(s) Cost estimation Justification for any procurements during DD 20