Keck NGAO Project Replan: AO and Laser Systems Donald Gavel NGAO Team Meeting 6 April 25, 2007 Don Gavel: Keck NGAO meeting April 25, 2007 1 AO and Laser Systems Project Replan: Outline of Presentation • • • • Program plan overview Purpose and approach of the replan Key changes highlighted Feedback from the team on schedule & level of effort Don Gavel: Keck NGAO meeting April 25, 2007 2 AO and Laser System Program Overview • AO and Laser System Design phase follows the system engineering / trade studies phase • Inputs: Architecture Definitions, Study results, FRDs v.1 (June/July time frame) • Outputs: Contributions to System Design Manual & FRDs v.2 (= Conceptual Design or Proposal level => raising funding to build) Don Gavel: Keck NGAO meeting April 25, 2007 3 Purpose and Approach of the Replan • Problem: present plan is behind schedule. • Approach: given currrent status and lessons learned, adapt the plan to achieve key goals using the resources available • Play to people and institutional strengths • Streamline the work – fewer people at higher percentage • Level the plan and tie to people availability Don Gavel: Keck NGAO meeting April 25, 2007 4 Overview of changes in 3.2, 3.3 • WBS 3.2 AO System. • Reshuffling of personnel on four tasks. • Two new tasks: • atmospheric profiler • d-IFU & LOWFS AO & Object Selection (broken out from WBS 3.5) • WBS 3.3 Laser Facility. Reshuffling of personnel on three tasks. Don Gavel: Keck NGAO meeting April 25, 2007 5 Changes to 3.2, 3.3 WBS Current hours New hours Change justification 3.2.2 AO Enclosure 100 40 Enclosure is straightforward engineering. Emissivity vs temperature is covered elsewhere in plan 3.2.3.6.2 Deformable Mirror 140 60 DM specification doesn’t require much design work. Neyman & Bauman instead of Flicker, Dekany, Bauman 3.2.3.10 Atmospheric Profiler - 80 Will likely need profiler for tomography. Matt Britton lead 3.2.3.11 D-IFU & LOWFS Object Selection - 320 Need to explore a number of wide field MOAO pickoff mechanisms. Anna Moore lead 3.3.3 Laser 100 20 Leverage CfAO work in this area. Gavel lead Don Gavel: Keck NGAO meeting April 25, 2007 6 Program Plan Changes – 3.2 Details 3.2.1 AO System Architecture 3.2.2 3.2.3 3.2.3.1 3.2.3.2 3.2.3.3 3.2.3.4 3.2.3.5 3.2.3.5.1 3.2.3.5.2 AO Enclosure Opto-mechanical Field Rotation Optical Relay Optical Switchyard Optical Support Structure Wavefront Sensors High order LGS WFSs High order NGS WFS 3.2.3.5.3 3.2.3.5.4 3.2.3.6 Low Order NGS Wavefront Sensors Calibration Wavefront Sensor Wavefront Correctors 3.2.3.6.2 Deformable Mirror 3.2.3.7 3.2.3.8 3.2.3.9 3.2.3.10 Acquisition Cameras Atmospheric Dispersion Correction Alignment, Diag, Metrology & Monitoring Atmospheric Profiler 3.2.3.11 3.2.4 3.2.4.1 3.2.4.2 d-IFU & LOWFS AO & Object Selection Non-real-time Control Non-RTC Software Non-RTC Electronics 3.2.5.1 3.2.5.2 RTC Architecture Analysis & Design Study RTC Software Module Definition Reduce from 240h total to 40h of DG (just in case any remaining issues). Change predecessor to 3.1.3.2.5 Change predecessor to 3.1.3.2.5. Reduce from 100 to 40h - pulled in end to 9/28 Make predecessor 3.1.3.2.5 Pull in end date to 11/2/07 Pull in end date to 11/2/07 Pull in end date to 11/2/07 Pull in end date to 11/30/07 Pull in end date to 11/16/07 Consider DG suggestion of DG lead + BB Consider DG suggestion of DG lead + BB VV as new lead. 40h of SK to 20h more of VV & 20h of AM CN as new lead. 40h of SK to CN Put CN as lead Reduce BB from 50 to 10h. Replace 40h of RF & 30h of RD with 40h of CN. CN as lead Replace AB hours & lead with CN (familiar w/ MAGIQ) BB replaces 16h of SK. RD lead with 4h Add 20h of DLM. Reduce CN & RF by 10h each New task. MB lead at 50h. 7/23-8/31/07 New task. AM lead at 200h. DG 40h. JM 80h. 5/21-8/6/07 EJ as new lead Remove 30h of Johnson Remove 40h each of JC&MR & add 40h of EJ Remove 20h each of RF& MR. Change start date to 6/18/07 Consider replacing 20h of Reinig with Palmer Don Gavel: Keck NGAO meeting April 25, 2007 7 Program Plan Changes – 3.3 Details 3.3.1 Laser System Architecture 3.3.3 Laser 3.3.4 Laser Launch Facility 3.3.4.1 Laser beam transport 3.3.4.2 Laser pointing & diagnostics 3.3.4.3 Laser launch telescope Change predecessor from 3.1.1.5 to 3.1.1.5.1 Reduce VV from 100 to 20h. DG new lead. DG to perform with CfAO funding Change start & end dates for all subtasks to 7/23 & 8/31, respectively Replace 20h of SK with 16h of VV. Reduce CN from 35 to 30h. Reduce JC from 5 to 4h Replace 30h of AM with 15h of BB. Replace 30h of SK with 15h of CN. Reduce JC from 20 to 10h. Replace 50h of SK with 30h of CN. Reduce JC from 20 to 10h. Reduce VV from 50 to 30h Don Gavel: Keck NGAO meeting April 25, 2007 8 Team Feedback • WBS definitions correct and unambiguous • Objectives feasible in the time allocated • Availability, time commitment Don Gavel: Keck NGAO meeting April 25, 2007 9