Next Generation Adaptive Optics Meeting #2 P. Wizinowich for NGAO Executive Committee

advertisement
Keck Next Generation AO
Next Generation Adaptive Optics
Meeting #2
Caltech
November 14, 2006
P. Wizinowich
for NGAO Executive Committee
Keck NGAO
Welcome - Participants
In-Person Participants
– NGAO Executive Committee: Rich Dekany, Don Gavel,
Claire Max, Peter Wizinowich
– Sean Adkins, Antonin Bouchez, Ian Cameron, Mike
Ireland, Anna Moore, Chris Neyman, Viswa Velur
Telecon Attendees:
– Brian Bauman, Ralf Flicker, Erik Johansson, Franck
Marchis, David Le Mignant, Mike Liu
11/14/06
NGAO Meeting #2
2
Keck NGAO
Goals of Today’s Meeting
Introduce team structure & responsibilities
Review System Requirements document
Review key drivers for NGAO performance
budgets
Review Keck Interferometer requirements
Review instrumentation study strategy
11/14/06
NGAO Meeting #2
3
Keck NGAO
Meeting Agenda
08:30
09:00
09:30
10:30
10:45
12:15
13:00
13:30
14:00
14:30
15:45
16:00
16:30
17:30
11/14/06
Welcome & Introductions
Management Report (Wizinowich)
Science Requirements Document (Max)
Break
Key Performance Drivers (Dekany)
Lunch
LGS Asterism Geometry & Size (Flicker)
Fixed vs Variable LGS Asterism (Velur)
Keck Interferometry Requirements (Neyman)
NGAO Instrument Study Strategy (Adkins, Moore)
Break
Discussion: Upcoming tasks & milestones (Wizinowich)
General Discussion
Adjourn
NGAO Meeting #2
4
Keck Next Generation AO
NGAO System Design Phase
Management Report
P. Wizinowich
for NGAO Executive Committee
Keck NGAO
Presentation Sequence
System Design (SD) Phase Systems Engineering
Management Plan (SEMP)
+ Approval Status
+ Budget
Management Tools
–
–
–
–
–
11/14/06
WBS & tracking
Milestones
Work scope planning & approval
Document management
Science Requirements & Performance Budget Process
NGAO Meeting #2
6
Keck NGAO
Systems Engineering Management Plan
Document describing how the Executive Committee
(EC) plans to manage the SD phase
– http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NG
AO/SystemDesignPhasePlanning
11/14/06
NGAO Meeting #2
7
Keck NGAO
System Design Phase Approval Status
SEMP submitted to the Observatory Directors on
9/29/06 for approval
Official response not yet received (has been
requested)
– Major issue is how many $ can be made available in
FY07
Direction from WMKO management to proceed
while decision is being made
– Contracts (effective 10/1/06) to COO & UCSC need to be
worked out
11/14/06
NGAO Meeting #2
8
Keck NGAO
NGAO SD Phase: Budget
Cost ($k)
WBS
Name
FY07
FY08
Total
1
SD Phase Management
74.4
49.2
123.6
2
System Requirements
118.7
3.2
121.9
3
System Design
559.9
89.8
649.7
4
Systems Engineering Management Plan
4.9
78.8
83.7
Travel/Procure
40.0
20.0
60.0
Contingency (10%)
10.0
93.9
103.9
807.9
334.9
1142.8
Total ($k) =
Work (hours)
Institute
FY07
FY08
Total
COO
2836
702
3589
UCSC
2991
845
3926
WMKO
5355
1852
7360
Students
1850
0
1850
Total =
13032
3399
16725
11/14/06
$163 increase in cost of labor.
Total work same as in proposal.
NGAO Meeting #2
9
Keck NGAO
SD Phase - Work Breakdown Structure
Each major WBS produces one of the 4 major deliverables of
the SD Phase:
1 System Design Phase Management
 System Design Report
2 System Requirements
 System Requirements Document
3 System Design Approach
 System Design Manual
4 Systems Engineering Management Plan
 Systems Engineering Management Plan
WBS dictionary defines each element in WBS
11/14/06
NGAO Meeting #2
10
Keck NGAO
WBS 1 SD Phase Management
1.1 Planning & Contracting
1.2 Meetings
1.3 Tracking & Reporting
1.4 Proposals & Fundraising
1.5 System Design Report & Review
11/14/06
NGAO Meeting #2
11
Keck NGAO
WBS 2 System Requirements
2.1 Science Requirements
2.2 Observatory Requirements
2.3 System Requirements Document
11/14/06
NGAO Meeting #2
12
Keck NGAO
WBS 3 System Design Approach
3.1 Systems Engineering
3.2 AO System
3.3 Laser Facility
3.4 Operations Tools
3.5 Science Instruments
3.6 System Design Manual
11/14/06
NGAO Meeting #2
13
Keck NGAO
WBS 4 System Engineering Management Plan
4.1 Project Plan
4.2 Risk Assessment & Management Plan
4.3 Preliminary Design Phase Plan
4.4 Integration & Test Plans
4.5 Configuration Management Plan
4.6 Project Management Plan
4.7 Systems Engineering Management Plan
11/14/06
NGAO Meeting #2
14
Keck NGAO
System Design Phase Tracking
Tracked version of the plan posted at
http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Kec
k/NGAO/SystemDesignPhasePlanning
11/14/06
NGAO Meeting #2
15
Keck NGAO
NGAO SD Phase
Milestones
11/14/06
MILESTONE
DATE
DESCRIPTION
SD SEMP Approved
10/9/06
Approval of this plan by the Directors. Initial
SEMP version released to Directors for
comment on 9/12 & final version on 9/29/06.
SD phase contracts in place
10/27/06
Contracts issued to Caltech & UCSC for the
system design phase.
Science Requirements Summary v1.0
Release
10/27/06
Initial Release of the Science Requirements as
input to trade studies and performance
budgeting
System Requirements Document
(SRD) v1.0 Release
12/8/06
Initial release of System Requirements with
emphasis on the science requirements
Performance Budgets Summary v1.0
Release
2/27/07
First round of all performance budgets complete
& documented
SRD v2.0 Release
3/22/07
Second release of System Requirements Doc
Trade Studies Complete
5/25/07
All trade studies complete & documented (as a
series of Keck Adaptive Optics Notes)
SRD v3.0 Release
7/12/07
Third release of System Requirements
System Design Manual (SDM) v1.0
Release
8/31/07
First release of System Design Manual
Technical Risk Analysis v1.0 Release
11/13/07
First round of project risk analysis complete &
documented
Cost Review Complete
11/30/07
Project cost estimates complete, documented &
internally reviewed
SDM v2.0 Release
1/8/07
Second release of System Design Manual
System Design Review Package
Distributed
3/4/08
SDR documents sent to reviewers
System Design Review
3/31/08
SDR meeting
SDR Report NGAO
& Project
Planning
Meeting
#2
Presentation at SSC meeting
4/14/08
Final SD phase report including results of SDR
16
& project plans
Keck NGAO
Team Meeting Calendar
Date
#
Venue
14-Sep-06
1
UCI
14-Nov-06
2
Major Meeting Goal
Kickoff
Sci. Case I
Science/Management
Milestone
NGAO SD Plan
CIT Performance Drivers
Systems Engineering
Milestone
3
Video Various TS's
22-Jan-07
4
Keck Performance Budgets Continuous Sci. Field Photometric Budget
18-Apr-07
6
UCSC Various TS's
30-May-07
7
9-Jul-07
8
UCSC 5-day Retreat
22-Aug-07
9
Video Cost Review I
11-Sep-07
10
CIT Infrastructure I
5-Nov-07
11
Video Software Review II
12-Dec-07
Video Software Review I
12 Keck 3-day Meeting
Cost Review II
9-Jan-08
31-Mar-08
13
Video SDR Preparation
Prelim. Design Prop.
Var/Fixed LGS Ast
LGS Ast Geom & Sz
Tel Wavefr Errors
Interfer. Requirements
Instr. Study Strategy
LOWFS Num & Type
HOWFS Num & Type
Astrometric Budget
High-contrast Budget
Polarimetric Budget
Throughput Budget
K- & L-band Science SRD II
GLAO for non-AO
Subsys Funct Req I
AM2
Optical Relay
d-IFU Opt Sampling
Risk Analysis I
Field Rotat. Strategy
Encl/Relay Temp.
Operations Tools I
Laser Enclosure
Sci Path Opt Des I
Mech Structure I
SRD III
Cost Estimate I
Instrument/Observatory
Milestone
Sci. Instr Reuse
Instrument Balance
Subsystem Test Plans
SDM I
Science Verification
NGAO vs Upgrades
Interfer. Support
Focus Compens.
DM Stroke Req
Dichroics
Laser Pulse Format
Software Architecture
Slow WFS
Centroid Anisoplan
Free/Fiber BTO
DM RfI
Obs. Interfaces I
Instrument Interfaces
Non-real-time Softwr I
HOWFS I
LOWFS II
Laser RfI
Calibr. Stimulus I
Electronics I
Real-time Control I
LGS Delivery I
Obs. Interfaces II
Sci Path Opt Des II
Mech Structure II
Operations Tools II
SDM II
Non-real-time Softwr II
Risk Analysis II
Cost Estimate II
Integr. & Test Plan I
Subsys Funct Req I
Electronics II
HO WFS II
LO WFS II
SDR Prep
SDR Prep
SRD IV
SDR Prep
SDR Prep
SDR Prep
14 Keck SDR
11/14/06
Laser/DM
Milestone
Obs. Effic. Budget
Rayleigh Rejection
Site Monitoring Update Tip/Tilt Stage v. DM
MCAO/MOAO
Operations Arch. I
Video SRD II
Various TS's
WFS/WFP
Milestone
Model/Tool Validation
13-Dec-06
5
Electronics/Software
Milestone
Identify Perf. Drivers
SRD I
SRD I
7-Mar-07
Optics/Mechanics
Milestone
Instrument #1 I
SDR Prep
SDR Prep
SDR
NGAO Meeting #2
17
Keck NGAO
Work Scope Planning & Approval
Template posted at
http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Kec
k/NGAO/WebHome under “Systems Engineering”
To be prepared by WBS element lead & approved
prior to performing significant work on a WBS
element
– In general these should be submitted at least 1 week
prior to the MS Project start date
Approvals & document control by Dekany &
Wizinowich
– We will endeavor to provide approvals within 5 working
days of submittal
11/14/06
NGAO Meeting #2
18
Keck NGAO
Document Control
All materials to be posted on Twiki site
All significant items should be made Keck Adaptive
Optics Notes & will also be archived on Keck’s
docushare site (Wizinowich to provide KAON
numbers)
– Simple documents can use “Work Scope” template with
“Keck Adaptive Optics Note XXX” at top of title block
– SD phase deliverable documents should use SEMP
document as a template
11/14/06
NGAO Meeting #2
19
Keck NGAO
NGAO SD Phase:
Science Requirements
& Performance Budget
Process
11/14/06
NGAO Meeting #2
20
Keck Next Generation AO
NGAO System Design Phase
Upcoming Tasks & Milestones
P. Wizinowich
for NGAO Executive Committee
Keck NGAO
Upcoming Tasks
Work Scope planning sheets
– These should be submitted for all WBS elements that
need to start in CY06 by 12/8
– These include WBS elements under:
2.1 Science cases
2.2 Observatory requirements
2.3 System requirements
3.1.1 Performance budgets
3.1.2 Trade Studies
3.5 Science Instruments
Work on the scheduled WBS elements for CY06
11/14/06
NGAO Meeting #2
22
Keck NGAO
Upcoming Meetings & Milestones
Meeting #3 is a Dec. 13 telecon
– http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NG
AO/061213_Remote_NGAO_Meeting_3
- Will need % complete for WBS elements prior to meeting
Milestones:
– SD phase contracts in place was due 10/27
– Science requirements summary v1.0 was due 10/27
– System Requirements document v1.0 due 12/8
11/14/06
NGAO Meeting #2
23
Download