NGAO System Design Phase Update for NGAO Team

advertisement
NGAO System Design Phase
Update
Peter Wizinowich, Rich Dekany, Don Gavel, Claire Max
for NGAO Team
SSC Meeting
April 3, 2007
Presentation Sequence
•
•
•
•
•
Project Report #2
Science Requirements
Performance Budgets
Trade Studies
Summary
2
Project Report #2
•
2nd report submitted to Directors on Mar. 31
http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning
•
•
Emphasis to date continues to be understanding the major
design drivers through a process of iteratively developing
the science case requirements & the performance budgets
Work also continues on a number of trade studies in
support of the performance budgets & the future design
choices
3
Project Report #2
#
MILESTONE
DATE
DESCRIPTION
1
SD SEMP Approved
10/9/06
2
SD phase contracts in place
10/27/06
Contracts issued to Caltech & UCSC
for the system design phase.
$50k initial contracts
issued on 12/20
3
Science Case Requirements
Summary v1.0 Release
10/27/06
Initial Release as input to trade
studies & performance
budgeting
Complete
4
System Requirements
Document v1.0 Release
12/8/06
Initial release of System
Requirements with emphasis on
science requirements
5
Performance Budgets
Summary v1.0 Release
2/27/07
1st round of all performance budgets
complete & documented
Good progress
6
System Requirements Doc
v2.0 Release
3/22/07
2nd release of System Requirements
Document
Recently started
7
Trade Studies Complete
5/25/07
All trade studies complete (Keck
Adaptive Optics Notes)
Good progress
Approval of this plan by the
Directors. SEMP released to
Directors on 9/29/06.
STATUS
Verbal approval received.
Written approval
requested
Complete
4
Project Report #2
5
Project Report #2
Schedule
•
•
Still behind schedule, but catching up some (need to catch up more)
21% of System Design Phase activities complete through Mar.
Budget
•
•
$772k initially budgeted for FY07. $46k recently added to achieve
SEMP request.
$234k spent through Feb.
–
–
29% of the FY07 budget (versus plan of ~ 40%)
20% of the System Design Phase budget
Replan
•
•
•
Scheduled mid-year replan in process
Will use this to help address schedule slip
Still intend to hold to overall schedule & budget
6
Science Case Requirements
& Science Instruments
Science Case Requirements Document
• Release 1 contains the following:
– JWST and ALMA capabilities
– Future AO capabilities of other observatories
– Key science cases that stress various aspects of AO:
• Multiplicity, size, and shape of minor planets
• Planetary & brown dwarf companions to low mass stars
• General relativistic effects in the Galactic Center
• Assembly and star formation history of high z galaxies
• Release 2 (in progress) will also include
– Solar System: Titan, Io, Jovian planet icy moons
– Galactic astronomy: Protostellar objects, Debris disks
– Extragalactic astronomy: Strong lensing, AGNs, QSO host gals
• Still to come: resolved stellar populations
9
Developments since Release 1:
Complementarity of JWST and NGAO
•
C. Max trip to GSFC to meet with JWST folks
•
Broad-band imaging: limiting mag of JWST ~ 4-5 mags fainter than NGAO
•
JWST not diffraction limited below K band
•
–
PSF FWHM same for 0.6 m < l < 2 m as it is at 2 m: FWHM ~ 0.07 arc sec
–
Spectroscopy:
•
NIRSpec px scale 0.1”
•
Enclosed energy at 1 m = 60-64% within 0.15”
Areas where Keck NGAO would nicely complement JWST
1.
Spectra @ spatial resolution better than 0.1”, l = 0.6 - 2 μm
2.
Imaging @ spatial resolution better than 0.07”, l = 0.6 - 2 μm
3.
Spectral resolution R > 2700
4.
Multi-IFU spectroscopy
10
JWST: Implications for high-z galaxy science case
• One of our key science cases: IFU
spectroscopy of high-z galaxies
• H is redshifted into K band for z =
2 - 2.6
• Yet forl > 2.1 m, NGAO sky
background starts to hurt a lot
• Cooling the AO system can help
– Much more feasible if we use
MEMS (small volume to be cooled)
OAP relay
l/l = 2000
TAO = 277.5 K
11
How cool is cool enough?
• Target goal: AO to contribute
at most 30% of background
• This opens “typical” z~2.6
galaxies within reasonable
observing times ~ 3 hours
• How to achieve this?
– 65% thruput, cool to -18C
– 75% thruput, cool to -12 C
–
We have to assess how much it’s
worth investing to cool NGAO at
K band, in view of JWST’s great
advantage in sensitivity
12
Astrometry: goal 0.1 mas for Galactic Center
• Ghez et al. are studying what is
limiting astrometric accuracy for
current LGS AO system
• Can achieve average positional
uncertainty close to 0.1 mas for
bright stars (K < 14).
• But what is causing the broad
spread?
• Under active investigation: PSF
changes due to
–
–
–
–
Anisoplanatism
Differential atmospheric refraction
Wind shake
.....
13
NGAO Instruments Working Group
• Focused on interactions with Science team
• Developing more complete instrument requirements
– Requirements for deployable IFU are converging
– Further work needed to refine imager requirements
– Further work needed to refine visible wavelength instrumentation
• Membership:
Sean Adkins (chair), Steve Eikenberry, Claire Max,
David Le Mignant, Anna Moore
(and later, James Larkin)
• Regular telecons & planning future in person workshop sessions
14
Current Instrumentation Thoughts
• Visible and near-IR
– Natural configuration breakpoints based on wavelength coverage
– Trying to balance performance, features, cost and risk
• Imagers
– Simple, Nyquist or Nyquist/2 spatial sampling
– Coronagraph
– Deployable imagers?
• Spectrographs
– Single object IFU
– Deployable IFU
• Specialized instruments?
– R ~100 IFU
– High contrast imaging
15
NGAO Performance Budget Development
Developing Science-based Performance Budgets
• Systems engineering considers all of the following:
–
–
–
–
–
–
–
–
–
–
Model assumptions
Model/tool validation
Wavefront error vs. sky coverage
for 5-7 science cases
Photometric precision in crowded and sparse stellar fields
Astrometric accuracy
at the GC and in sparse fields
High-contrast for diffuse debris disks and compact companions
Polarimetric precision
for high-contrast observations
Transmission/background/SNR
for several science cases
Observing efficiency
Observing uptime
17
Photometric Precision with NGAO
• Technical report completed
(see Britton, et al., at http://eraserhead.caltech.edu/keck/ngao/photometry/drafts/)
– Considered r0 variations, stellar crowding (K. Olsen), scintillation, & techniques of PSF estimation
• Conclusions
– Photometric precision intimately tied to knowledge of the PSF
• On-axis PSF can sometimes be estimated from direct imaging
• In principle, on-axis PSF can be estimated from AO telemetry (but this has not
been tackled for Shack-Hartmann WFS)
• Off-axis PSF can be estimated using Cn2(h) information
– Single conjugate AO & MOAO relative photometric precision better than 1% should
be achievable with NGAO over 30” FoV, assuming appropriate auxiliary systems
• This meets all of the NGAO science case goals developed so far
– The photometric precision performance of MCAO cannot be easily estimated (due to
both space & time variability)
• No obvious precision advantage over MOAO
• We will have to await ESO’s MAD & Gemini S MCAO to evaluate the performance w.r.t.
single conjugate AO & MOAO
18
Photometric Precision IPT Recommendations
•
Active, concurrent Cn2(h) measurements on minute time scales are essential to
precision photometry with NGAO
– Provides significant benefit for estimation of off-axis PSF’s
– Allows additional optimization of NGAO performance (e.g. tomography algorithms)
•
NGAO should provide an auxiliary PSF imaging capability for all instruments &
observing modes
– This camera should be Nyquist sampled and deployable over sufficient field of regard to
ensure acquisition of an appropriate PSF stars (for narrow field science instruments.)
• Details of wavelength coverage & other requirements will depend on NGAO architecture
•
As a step toward understand the requirements of the PSF imager, near-term
experiments with OSIRIS &/or NIRC2 & the T6 MASS/DIMM should be undertaken
– Open issues of access to Keck engineering time & funding for this investigation
•
NGAO should consider incorporating a facility deconvolution pipeline as a program
deliverable
– This would likely improve consistency & uniformity of photometric & astrometric results
19
Companion Sensitivity
NGAO high-contrast science goals and drivers:
• Direct imaging & spectroscopy of 1) Planets around low-mass stars &
brown dwarfs, 2) Resolved debris disks and proto-stellar envelopes
• LGS tomography
– Fainter host stars: larger sky coverage & relaxed contrast requirements
– Multi-band studies: optical & near-IR
Status (1st draft of report posted)
• Contrast budget spreadsheet tool (1st order approximation)
– No coronagraph model; no dynamic telescope aberrations
• Numerical AO simulations partly done (more accurate modeling)
– Band-limited Lyot coronagraph; static & dynamic telescope errors
20
NGAO Trade Studies
Trade Studies
• The following studies have been completed since the last meeting:
– Keck AO upgrade
– GLAO for non-NGAO instruments
– Low order wavefront sensor type & number
• Additional design studies nearing completion include:
–
–
–
–
–
–
–
MOAO vs MCAO
Keck Interferometer support
Science instrument re-use
Telescope wavefront errors
Observing model
Rayleigh rejection
LGS wavefront sensor number and type
22
Keck AO Upgrade
•
•
•
Anchored NGAO tool to
measured Keck AO
performance
Upgrades part 1 (NGWFC, K1
LGS, CCID-56, 2x DM, new
science instrument, simplified
tomography, vibration
reduction, 50W laser)
Upgrades 2 would need
multiple LGS & multiple IR
tip/tilt sensors
Companion Sensitivity
•
Performance improvement
with Strehl
Case
NGS
LGS
LGS
Rmag
8
10
18
Current Upgrade 1
258
149
378
229
557
419
NGAO
148
155
158
Contrast versus Radius
K1 LGS (1.0um)
K1 LGS (1.25um)
-2.00
K1 LGS (1.65um)
-3.00
K1 LGS (2.2 um)
-4.00
Contrast (magnitudes)
Wavefront error budget
Upgrade (1.0um)
-5.00
Upgrade (1.25um)
-6.00
Upgrade(1.65um)
Upgrade 2.2um)
-7.00
NGAO (1.0um)
-8.00
NGAO (1.25um)
-9.00
NGAO (1.65um)
NGAO (2.2um)
-10.00
-11.00
-12.00
-13.00
0
0.1
0.2
0.3
0.4
0.5
Radius (arcsec)
0.6
0.7
0.8
0.9
23
Keck AO Upgrade
• Pros & cons
– Potentially lower cost, but likely lower performance
– Interferometer needs addressed
• Would allow for an incremental approach
• Conclusion:
– Keck AO upgrade worth further consideration, especially as a reduced
funding/scope option.
24
GLAO for non-NGAO Instruments
GLAO = ground-layer adaptive optics
• NGAO provides multiple LGS; adaptive secondary mirror assumed
• GLAO then “only” requires additional WFS, RTC & software to be
employed with non-NGAO Keck instruments
• GLAO produces a modest, but dependable improvement in FWHM & EE
over wide fields of view (several arc minutes)
– Increase angular resolution, sensitivity &
observing efficiency
– Recover bad seeing nights to science
grade observing
– Large sky coverage (>50% at b=30°)
From GLAO TS report (KAON 472 - see document for explanation of figures)
25
Low Order Wavefront Sensor
• IR WFS (J+H bands) preferable to visible WFS
• Multiple NGS WFS significantly improve tip/tilt estimate over science field
• Measuring focus with one tilt sensors also helps tip/tilt estimate
J=17.1
J=16.4
J=17.4
Field Galaxies
science case:
Latitude=30 deg
J=16.6
J=19.0
J=18.7
26
Keck Interferometer Trade Study
•
•
•
Consider the relative performance, cost, risk, & schedule of feeding
KI with NGAO or a repackaged version of the current AO system
Decoupling of NGAO from interferometer support may simplify &
improve performance of NGAO
The feasibility of maintaining a version of the two current AO
systems for KI use should be evaluated
27
Keck Interferometer Preliminary Options
• Swapping Keck I/II AO with NGAO
• Matching NGAO to Keck I/II AO
• Two AO systems + NGAO
– AO secondary on each telescope
• GLAO trade study
Move Large
Instruments
– MEMs AO for each IF arm
LAO/UCSC
Challenging with current IF
28
Telescope Dynamic & Static Wavefront Errors
Goal: Improve/document understanding of telescope wavefront errors
• Telescope tip/tilt errors could dominate tip/tilt error budget
– “Encircled Energy Science” might be impacted less
– Consider correction or mitigation on current system
• Segment motion
– Acceptable error, comparable to NGAO proposal
• Segment figures
– Acceptable error, already included in NGAO proposal
• Segment phasing
– Small, interaction with figure errors needs testing
Correcting for segment figure errors
29
Summary
• Management:
–
–
–
–
System design phase efforts continue to be behind schedule
Now at reasonable staffing levels versus plan
Scheduled mid-year replan in process
Intention continues to be to deliver the system design within
budget & schedule
• Technical:
– Good progress being made on requirements, performance
budgets & trade studies
30
Download