Build to Cost Directions & Guidelines Peter Wizinowich SSC Meeting November 3, 2008 Presentation Sequence • • • • New Directions & Guidelines Implications Build to Cost Concept Review Conclusion 2 New Directions & Guidelines • $60M cost cap in then-year dollars – – – – From start of system design through completion Includes science instruments Must include realistic contingency Cap of $17.1M in Federal + Observatory funds ($4.7M committed) • Reviews – NFIRAOS cost comparison report at Nov/08 SSC meeting • To better understand the fidelity of the SDR costing – Internal review of build to cost concept – Report on internal review no later than Apr/09 SSC meeting 3 Implications of New Directions & Guidelines – 1 • Work required to reduce costs to fit in $60M cap – NGAO estimate at SDR, plus SD phase, ~ $53M (then-year $) – Science instrument estimate at proposal ~ $27M (then-year $) – Need to provide a major breakthrough in science capability for $ • Need Science Advisory Team to help insure this • Work required on science instruments as part of NGAO project – Cost cap requires NGAO project to integrate all costs & planning including instruments • During PD phase, instrument program management will continue for instruments, but as part of NGAO project – Need to develop at least system designs, preferably preliminary designs, & costs during the NGAO PD – Need to identify funds & people for this (none in WMKO FY09 plan) & determine impact on NGAO PD plan 4 Implications of New Directions & Guidelines – 2 • Report/Reviews – NFIRAOS cost comparison already planned – Phased implementation & descopes review no longer required • May need something for PDR, but not for build to cost concept review – Need success criteria, & plan to prepare, for build to cost review 5 Build to Cost Concept Review – 1 • Proposed Success Criteria – The revised science cases & requirements continue to provide a compelling case for building NGAO – We have a credible technical approach to producing an NGAO facility within the cost cap – We have reserved contingency consistent with the level of programmatic & technical risk • Proposed Deliverables for the review – A summary of the: • • • • • Revisions to the science cases & requirements, & the scientific impact Major design changes Major cost changes (cost book updated for design changes) Major schedule changes Contingency changes 6 Build to Cost Concept Review – 2 • Proposed Deliverables from the review – A summary of the reviewer findings (not by the team) – A team response to the reviewer report – A report of the results to the SSC (not by the team) • Proposed assumptions – Starting point will be the SD cost estimate with the addition of the science instruments & refined by the NFIRAOS cost comparison • Better cost estimates will be produced for the PDR – No phased implementation options will be provided • Some may be for the PDR to respond to the reviewer concerns – Major documents will only be updated for the PDR • SCRD, SRD, FRD, SDM, SEMP – This is an internal review. Directors will identify reviewers in consultation with NGAO team. – Take into account the Keck Strategic Planning 2008 results 7 Build to Cost Actions to Date • Evaluated implications & requested some clarifications • Build to Cost team meeting (Sept. 11/12 at UCSC) – Reviewed/discussed core science requirements, performance cost drivers & a range of cost savings ideas – Made some modest cost reduction decisions – Identified a number of potential cost savings areas that we are currently investigating • Identified success criteria for NFIRAOS cost comparison & build to cost concept review • Reworking NGAO PD phase plan – Working with instrument program manager to incorporate NGAO instruments 8 Conclusion • • • • We understand the need for a build to cost cap & accept the Director/SSC wisdom that this is what is needed to ensure NGAO’s future Our emphasis will be on maximizing the science return within the cost cap The short-term impact has been a delay in the planned NGAO preliminary design work To successfully prepare for the build to cost concept review we need: – Active participation from the NGAO Science Advisory Team – Agreement on the success criteria – Creative & focused work from the NGAO team 9