Information Management and Technology - Programme Management Office Launch Checklist – Handover from Project to Live Project Title IMT Ref. No. Owner / Sponsor Dept/End Users Project Manager Technical Development by E.g.: Applications, Systems, Telecoms etc. Estimated Project Internal Launch Date Click here to enter a date. Project External Launch Date Click here to enter a date. Key dates project cannot Go Live/ Launch on Project Manager to inform all key stakeholders of planned launch and SMT & Team Managers to review. Note: The project/ product/ service is almost ready for service/ launch/ go live and that you are ready to support this and have communicated this to your teams. To be completed by Project Manager or Project Sponsor/ Owner Service Brief Description New Service or enhancement to existing? Expected outcomes & benefits Keys users Contact details and location RFC submitted and approved by CAB? Attendance at CAB should be four weeks before go live date. Cut over / transition plan (if required) Insert file Data migration plan (if required) Insert file Vendor support in place? Who owns relationship with Vendor? IT Service Definition Template available here IT Service Architecture Diagram Template available here DR plan & test complete? Template available here Insert file Insert file Insert IT Service Technical Recovery Plan Highlight any known issues/ criteria that were not met during testing Insert file – or add to knowledge base? UAT / users feedback Insert file Document1 12 July 2016 Page 1 of 3 Information Management and Technology - Programme Management Office Escalation path for support Complete info for Service Catalogue: Service Catalogue information required Service Catalogue Information.xlsx Other Note: Each ‘owner’ is responsible for making sure their teams are ready for the launch. Each owner can define the deliverables they are checking against – below is just an example. Department Database/ Applications teams (Specify) Security Training Network, Infrastructure, Systems, Telecoms Communications Customer Services Deliverable (below are examples only) All operating, application, database software and configurations, licensing, patches required for support document and securely stored Permissions set Staff trained and capable, and assigned Owner Date Reviewed John Harris Documentation completed PCI-DSS Security levels checked and approved Documentation completed Training needs identified Training designed/developed/sourced Piloting, testing and revising Agree evaluation metric and timescale with sponsor Sign off and handover of training to sponsor Systems - Tested and checked Staff trained and ready Launch date and process communicated Documentation completed Support process in place Online Public LSE website – pages updated and checked FAQ’s updated and checked Service Notification sent to communicate change to relevant stakeholders BLOG LSE Newsletter Intranet & Internal comms Communication approved and ready Promotional activity Brief approved Tested and checked Service Catalogue – item added? Staff trained and ready – key contacts Launch date and process communicated Systems guides and manuals stored and available Jethro Perkins Steve Bond Chris Roberts Jessica Reid Floriana Molone Document1 12 July 2016 Page 2 of 3 Information Management and Technology - Programme Management Office FAQs and User guides entered into knowledge base IMT Service Catalogue IMT Admin (HR, Finance & Billing) For IMT Service Catalogue changes. Billing of service set up Staff trained and ready Recurring costs accepted Nicos Kyriacou James Harvey IMT Director sign off FINAL APPROVAL FOR LAUNCH Nick Deyes Customer sign off FINAL APPROVAL FOR LAUNCH Sponsor/Owner Document1 12 July 2016 Page 3 of 3