Using Pinch Analysis to Optimize the Heat Exchanger Network of a Regenerative Rankine Cycle for an Existing Modern Nuclear Power Plant by Stephanie Barnes A Project Submitted to the Graduate Faculty of Rensselaer Polytechnic Institute in Partial Fulfillment of the Requirements for the degree of MASTER OF ENGINEERING Major Subject: MECHANICAL ENGINEERING Approved: _________________________________________ Professor Ernesto Gutierrez-Miravete, Project Adviser Rensselaer Polytechnic Institute Hartford, Connecticut December, 2013 i © Copyright 2013 by Stephanie Barnes All Rights Reserved ii CONTENTS LIST OF TABLES ............................................................................................................ vi LIST OF FIGURES ........................................................................................................ viii DEFINITIONS ................................................................................................................. ix ACRONYMS ..................................................................................................................... x NOMENCLATURE ......................................................................................................... xi ACKNOWLEDGMENT ................................................................................................. xii ABSTRACT ................................................................................................................... xiii 1. Introduction.................................................................................................................. 1 1.1 Background ......................................................................................................... 1 1.2 Regenerative Rankine Cycle............................................................................... 1 1.2.1 Millstone III Unit Overview .................................................................. 1 1.3 Pinch Analysis .................................................................................................... 4 1.4 Problem Statement .............................................................................................. 4 1.5 Previous Work .................................................................................................... 4 2. Theory .......................................................................................................................... 6 2.1 Second Law of Thermodynamics ....................................................................... 6 2.2 Conservation of Mass ......................................................................................... 6 2.3 Heat Capacity...................................................................................................... 7 2.4 Problem Table Analysis ...................................................................................... 7 2.5 Composite Curves ............................................................................................... 8 2.5.1 Shifted Composite Curve ....................................................................... 9 2.6 Grand Composite Curve ..................................................................................... 9 2.7 ΔTmin and Trade Offs ........................................................................................ 10 2.8 Design of the Heat Exchanger Network ........................................................... 12 3. Methodology .............................................................................................................. 13 3.1 Overview........................................................................................................... 13 iii 3.2 Assumptions ..................................................................................................... 13 3.3 Data Extraction ................................................................................................. 14 3.4 Problem Table ................................................................................................... 19 3.4.1 Heat Cascades ...................................................................................... 19 3.5 Composite Curves ............................................................................................. 20 3.6 Grid Diagram .................................................................................................... 20 3.7 Effect of the Number of Heat Exchangers on the External Utility Requirements .......................................................................................................................... 22 3.8 Effect of the Minimum Temperature Difference on the Pinch Point and External Utility Requirements.......................................................................... 22 4. Results and Discussion .............................................................................................. 23 4.1 Problem Table ................................................................................................... 23 4.2 Heat Cascade .................................................................................................... 25 4.3 Pinch Points and Utility .................................................................................... 27 4.4 Composite Curves ............................................................................................. 28 4.5 Grand Composite Curve ................................................................................... 29 4.6 Retrofit Heat Exchanger Network .................................................................... 30 4.7 Targeting Improvements to the External Utility Requirements ....................... 31 4.8 4.7.1 Effect of Number of Heat Exchangers on the External Utility Requirements........................................................................................ 31 4.7.2 Effect of Supply and Target Temperatures on the External Utility Requirements........................................................................................ 31 4.7.3 Results .................................................................................................. 32 Effect of the Minimum Temperature Difference on the Pinch Point and External Utility Requirements.......................................................................... 34 5. Conclusion ................................................................................................................. 35 6. References.................................................................................................................. 36 6.1 Works Cited ...................................................................................................... 36 6.2 Additional References Consulted ..................................................................... 37 iv 7. Appendices ................................................................................................................ 38 7.1 Guide to Excel File ........................................................................................... 38 7.2 Millstone Unit III Heat and Mass Balance ....................................................... 39 7.3 Raw Data and Intermediate Steps ..................................................................... 40 7.4 Other Cases Evaluated ...................................................................................... 42 7.4.1 Case 2 ................................................................................................... 42 7.4.2 Case 3 ................................................................................................... 45 7.4.3 Case 4 ................................................................................................... 47 7.4.4 Case 5 ................................................................................................... 50 7.4.5 Case 6 ................................................................................................... 53 7.4.6 Case 7 ................................................................................................... 55 7.4.7 Case 8 ................................................................................................... 57 7.4.8 Case 9 ................................................................................................... 59 7.4.9 Case 10 ................................................................................................. 61 7.4.10 Case 11 ................................................................................................. 64 v LIST OF TABLES Table 1: Millstone Unit III Heat Exchanger Network ..................................................... 15 Table 2: Input Stream Data for Analysis ......................................................................... 18 Table 3: Shifted Temperatures and Heat Capacity Flowrate ........................................... 19 Table 4: Problem Table ................................................................................................... 24 Table 5: Net Heat Capacity Flowrate and Heat Load (Calculated and Software) ........... 25 Table 6: Heat Cascade ..................................................................................................... 26 Table 7: Heat Loads per Interval (Calculated and Software) .......................................... 27 Table 8: External Utilities for Various HEN Designs ..................................................... 32 Table 9: External Utilities for Various Minimum Temperature Differences .................. 34 Table 10: Raw Data from Millstone Unit III Heat and Mass Balance ............................ 40 Table 12: Combined Data for HEN used in Analysis for Case 1 .................................... 41 Table 12: Net Heat Capacity Flowrates ........................................................................... 41 Table 13: Intermediate Calculations for Heat Capacity and Heat Load .......................... 42 Table 14: Input Stream Data for Case 2 .......................................................................... 42 Table 15: Calculated Stream Data for Case 2 .................................................................. 43 Table 16: Problem Table for Case 2 ................................................................................ 43 Table 17: Heat Cascade for Case 2 .................................................................................. 44 Table 18: Input Stream Data for Case 3 .......................................................................... 45 Table 19: Calculated Stream Data for Case 3 .................................................................. 45 Table 20: Problem Table for Case 3 ................................................................................ 46 Table 21: Heat Cascade for Case 3 .................................................................................. 46 Table 22: Input Stream Data for Case 4 .......................................................................... 47 Table 23: Calculated Stream Data for Case 4 .................................................................. 47 Table 24: Problem Table for Case 4 ................................................................................ 48 Table 25: Heat Cascade for Case 4 .................................................................................. 49 Table 26: Input Stream Data for Case 5 .......................................................................... 50 Table 27: Calculated Stream Data for Case 5 .................................................................. 50 Table 28: Problem Table for Case 5 ................................................................................ 51 Table 29: Heat Cascade for Case 5 .................................................................................. 52 Table 30: Input Stream Data for Case 6 .......................................................................... 53 vi Table 31: Calculated Stream Data for Case 6 .................................................................. 53 Table 32: Problem Table for Case 6 ................................................................................ 54 Table 33: Heat Cascade for Case 6 .................................................................................. 54 Table 34: Input Stream Data for Case 7 .......................................................................... 55 Table 35: Calculated Stream Data for Case 7 .................................................................. 55 Table 36: Problem Table for Case 7 ................................................................................ 56 Table 37: Heat Cascade for Case 7 .................................................................................. 56 Table 38: Input Stream Data for Case 8 .......................................................................... 57 Table 39: Calculated Stream Data for Case 8 .................................................................. 58 Table 40: Problem Table for Case 8 ................................................................................ 58 Table 41: Heat Cascade for Case 8 .................................................................................. 58 Table 42: Input Stream Data for Case 9 .......................................................................... 59 Table 43: Calculated Stream Data for Case 9 .................................................................. 59 Table 44: Problem Table for Case 9 ................................................................................ 60 Table 45: Heat Cascade for Case 9 .................................................................................. 60 Table 46: Input Stream Data for Case 10 ........................................................................ 61 Table 47: Calculated Stream Data for Case 10 ................................................................ 61 Table 48: Problem Table for Case 10 .............................................................................. 62 Table 49: Heat Cascade for Case 10 ................................................................................ 63 Table 50: Input Stream Data for Case 11 ........................................................................ 64 Table 51: Calculated Stream Data for Case 11 ................................................................ 64 Table 52: Problem Table for Case 11 .............................................................................. 65 Table 53: Heat Cascade for Case 11 ................................................................................ 65 vii LIST OF FIGURES Figure 1: Millstone Unit III Diagram [2] ........................................................................... 2 Figure 2: Millstone Unit III Power Plant Schematic [2].................................................... 3 Figure 3: Hot and Cold Composite Curves........................................................................ 8 Figure 4: Shifted Composite Curves.................................................................................. 9 Figure 5: Grand Composite Curve Example ................................................................... 10 Figure 6: Utility Use, Heat Exchanger Area, and Cost Variation with Delta Tmin [3] .... 11 Figure 7: Effect of Delta Tmin on Composite Curves ....................................................... 12 Figure 8: Simplified Schematic of the Millstone Unit III HEN ...................................... 14 Figure 9: Hot and Cold Stream Example from the Original Millstone Unit III HEN ..... 16 Figure 10: Hot and Cold Stream Data for the HEN used for Analysis ............................ 16 Figure 11: Hot and Cold Stream Example After Combining Streams ............................ 17 Figure 12: Grid Diagram Example .................................................................................. 21 Figure 13: Grid Diagram with Cross Pinch Heat Transfer Example ............................... 21 Figure 14: Hot and Cold Composite Curves.................................................................... 28 Figure 15: Shifted Hot and Cold Composite Curves ....................................................... 29 Figure 16: Grand Composite Curve ................................................................................. 30 Figure 17: Grid Diagram ................................................................................................. 30 Figure 18: Millstone Unit III Heat Balance ..................................................................... 39 Figure 19: GCC for Case 2 .............................................................................................. 45 Figure 20: GCC for Case 3 .............................................................................................. 47 Figure 21: GCC for Case 4 .............................................................................................. 50 Figure 22: GCC for Case 5 .............................................................................................. 53 Figure 23: GCC for Case 6 .............................................................................................. 55 Figure 24: GCC for Case 7 .............................................................................................. 57 Figure 25: GCC for Case 8 .............................................................................................. 59 Figure 26: GCC for Case 9 .............................................................................................. 61 Figure 27: GCC for Case 10 ............................................................................................ 64 Figure 28: GCC for Case 11 ............................................................................................ 66 viii DEFINITIONS Pinch Point The location of the smallest difference between hot and cold streams in a heat transfer network. Supply Temperature The temperature at the inlet of a heat exchanger. Target Temperature The temperature goal at the outlet of the heat exchanger. Stream Fluid that must be heated or cooled. Heat Capacity Flowrate Mass flowrate multiplied by the enthalpy of the fluid for the given temperature range. Heat Load The maximum amount of heat that could be transferred to or from a stream. Composite Curve Graph of temperature versus enthalpy for the cold and hot stream data. Grand Composite Curve Graph of the combination of the hot and cold composite curves, used to determine external utility requirements. Utility An external source of heating or cooling that does not use energy from the streams in the system. ix ACRONYMS The following is a list of acronyms and abbreviations that are used throughout this paper. Acronym Definition GCC Grand Composite Curve SCC Shifted Composite Curve HEN Heat Exchanger Network SG Stream Generator LP Low Pressure HP High Pressure x NOMENCLATURE The following is a list of nomenclature used throughout this paper: Symbol Description Unit mCp Heat Capacity Flowrate MBtu/hr/F dH Heat Load MBtu/hr Tmin Minimum Temperature Difference Between Hot and Cold F Composite Curves TS Supply Temperature F TT Target Temperature F TSS Shifted Supply Temperature F TTS Shifted Target Temperature F mÝ Mass flow rate lb/hr H Enthalpy Btu/lb TW Supply Temperature of Stream W of Figure 18 F ÝW m Mass flow rate of Stream W of Figure 18 lb/hr ÝTot m Total Mass flow rate of combined streams lb/hr TV Supply Temperature of Stream V of Figure 18 F ÝV m Mass flow rate of Stream V of Figure 18 lb/hr THP1 Output Steam Temperature from High Pressure Turbine F supplied to the First Point Heater of Figure 18 ÝHP1 m Mass flow rate of steam from High Pressure Turbine lb/hr supplied to the First Point Heater of Figure 18 h Change in enthalpy Btu/lb dmcv dt Rate of change of mass within a control volume lb/hr Ýin m Mass flow rate into a control volume lb/hr Ýout m Mass flow rate out of a control volume lb/hr xi ACKNOWLEDGMENT I would like to thank my parents for their continued support and encouragement throughout my college career. I would also like to thank my professors who have helped me learn. I would like to thank Professor Ernesto Gutierrez-Miravete for his support during the duration of this project. xii ABSTRACT This project uses pinch analysis techniques to analyze the heat transfer characteristics and efficiency of a typical Regenerative Rankine cycle, used in the Millstone Unit III nuclear power plant. The heat exchanger network, consisting of six feedwater heaters was evaluated using the data from the Millstone Unit III heat balance. The pinch temperature (shifted) was determined to be 466F. The minimum hot and cold utility requirements are 1,641 MBtu/hr and 370,852 MBtu/hr, respectively, as determined by the software and 1,642 MBtu/hr and 371,225 MBtu/hr as determined by hand calculations. The optimum minimum temperature difference between the hot and cold streams was determined to be 50 F. Additional cases were evaluated to determine the effect of minimum temperature difference, supply and target temperatures, and the number of heat exchangers in the network on the external utility requirements. Case 11 provided the most significant decrease in the cold utility requirement. Deleting the 5th and 6th point heaters decreased the cold utility requirement from 370,852 MBtu/hr to 37,228 MBtu/hr, as determined by the software, while keeping the hot utility at 1,641 MBtu/hr. This would greatly reduce the external energy costs by utilizing the most energy within the system from the turbine exhausts and waste from other components. xiii 1. Introduction 1.1 Background Vapor power systems are commonly used to generate electricity. In nuclear power plants, a controlled nuclear reaction generates heat energy, which is released to a working fluid (i.e. reactor coolant) to transform feedwater into steam, via a steam generator. The steam flows through a secondary plant to power a turbine that generates electricity. The steam leaves the turbine and is sent through a condenser and feedwater is pumped back in the steam generator. The Rankine cycle is an ideal vapor power cycle without irreversibilities that are present in real power plants. Real power plants encounter losses (expansion through the turbine, work input to pumps, frictional losses through pipes, etc.) and modifications to the Rankine cycle are made to improve plant performance. 1.2 Regenerative Rankine Cycle The Regenerative Rankine cycle has features that improve the thermal efficiency of the power plant when compared with the Rankine cycle. The Regenerative Rankine cycle uses heat available from the output of the turbines to preheat the feedwater from the condenser, before the feedwater enters the steam generator. Modern power plants use open or closed feedwater heaters to increase the average temperature of the feedwater without using an external heat source. Regenerative rankine cycles are common in modern power plants because they increase the thermal efficiency and power generation of the plant, while reducing cost. [1] 1.2.1 Millstone III Unit Overview Figure 1: Millstone Unit III Diagram [2] shows a simplified version of the Millstone III unit nuclear power plant. The unit uses a pressurized water reactor, which prevents boiling in the reactor, to transfer heat to a steam generator in a secondary loop, which produces steam that flows through a high pressure and three low pressure turbines that turn a turbine generator shaft to generate 1290 MW of 1 power. QuickTime™ and a decompressor are needed to see this picture. Figure 1: Millstone Unit III Diagram [2] 2 The secondary loop will be the focus of this project and is shown in Figure 2. The steam exits the high pressure turbine, enters a moisture separator steam reheater that separates moisture from the steam. The steam gets reheated and is dry enough to flow through three low pressure turbines. After exiting each low pressure turbine, the steam enters a condenser below each low pressure turbine that condenses the steam into water. The condensate and feed system transfers the water from the exit of the condenser back to the steam generator. The feedwater is reheated prior to entering the steam generator by six closed feedwater heaters. [2] QuickTime™ and a decompressor are needed to see this picture. Figure 2: Millstone Unit III Power Plant Schematic [2] Excess steam from the turbines is used as a heating element in six closed feedwater heaters. Excess steam from the three low pressure turbines and the high pressure turbine enters four closed feedwater heaters (#3-6) and two closed feedwater heaters (#1-2), respectively. The closed feedwater heaters are used to heat the working fluid (water) before it enters the steam generator, which significantly increases plant efficiency. The closed feedwater heaters contain U-shaped tubes inside a shell and do not allow the steam and water to mix. The temperature of the feedwater is increased after going through each closed feedwater heater. Feedwater pumps operate at high pressure to overcome the pressure that the steam generator operates at. The smaller the temperature 3 difference between the input and output of the steam generator, the less external heating work must be done by the reactor. [2] 1.3 Pinch Analysis Optimizing the thermal efficiency and overall cost of a power plant can be determined by pinch analysis. Linnhoff & Flower developed pinch analysis, at the ETH Zurich & Leeds University, in 1978. Pinch analysis is a means of optimizing a power plant by using the heat energy from the streams, instead of using external heating and cooling methods (heat exchanger, furnace, cooler, etc.), to increase the thermal efficiency of the plant and minimize energy costs. Streams are any flow paths that do not change in chemical composition. Pinch analysis can be used for designing new, or retrofitting existing, power plants. Pinch analysis utilizes energy targets, which “are absolute thermodynamic targets, showing what the process is inherently capable of achieving if the heat recovery, heating and cooling systems are correctly designed.” [3] “The principle is to predict what should be achieved (targeting), and to then set out to achieve it (design).” [4] 1.4 Problem Statement This project will analyze a Regenerative Rankine cycle, based on the Millstone Unit III nuclear power plant, using pinch analysis. The pinch point, or most constrained point in the design, will be determined, as well as the minimum external hot and cold utility requirements to meet the targeted heat exchanges. Modifications to the heat exchanger network will be evaluated and a recommendation for retrofitting the components of the power plant or improvements to increase efficiency and reduce cost will be made. 1.5 Previous Work Pinch analysis has been used to optimize new HENs in power plants as well as retrofit existing HENs. Linnhoff and March wrote papers about the fundamentals of pinch analysis, focusing on retrofitting and new designs. [5] also discusses the PinchExpress 4 software used to perform the analysis. [6] sized and integrated a heat exchanger into an existing HEN at a gas processing plant. Bi and Chang wrote a paper about retrofitting an existing HEN, where cross pinch heat transfer is evaluated [7]. The analysis also includes a cost analysis for the new HEN. [8] discusses the energy pinch, water pinch, and hydrogen pinch. 5 2. Theory 2.1 Second Law of Thermodynamics Pinch analysis is based on the second law of thermodynamics. The second law of thermodynamics describes the spontaneous processes that exist in irreversible (nonideal) cycles. The Clausius Statement of the second law of thermodynamics states: “it is impossible for any system to operate in such a way that the sole result would be an energy transfer by heat from a cooler to a hotter body.” [1] A hot stream cannot be used to heat a cold stream to a temperature hotter than the hot stream. The Kelvin-Planck Statement of the second law states: “it is impossible for any system to operate in a thermodynamic cycle and deliver a new amount of energy by work to its surroundings while receiving energy by heat transfer from a single thermal reservoir.” [1] The hot streams cannot transfer all of their energy to heat the cold stream. There must be some waste heat as a result of the heat transfer process. 2.2 Conservation of Mass In this analysis, each feedwater heater is considered to be a control volume. The law of conservation of mass for a closed system (control volume) is used for each feedwater heater as follows. mÝin mÝout dmcv dt [1} For a steady state system, the mass flow rate entering the control volume is equal to that exiting the control volume. For the control volumes that have multiple hot streams entering the feedwater heaters, the mass flowrates are added together to determine the total inlet flow. The sum of all of the inlet stream flowrates must be equal to the outlet stream flowrate since mass cannot be destroyed. 6 2.3 Heat Capacity Enthalpy is the total energy of a system, which is determined by the sum of the internal energy and the product of pressure and volume. Steam data is plotted on a temperatureenthalpy diagram, called the composite curve. The plot can be shifted, using the shifted temperatures, to determine the pinch point because only the change in enthalpy between the inlet and outlet streams is needed. The heat capacity flowrate and the heat load are used to determine the heat transfer characteristics of the system and the required external utilities. The heat capacity flowrate and the heat load are calculated for all of the temperature intervals, using Equations 2 and 3. The heat capacity flowrate is the mass flowrate multiplied by the enthalpy of the fluid for the given temperature range. Either the actual or shifted temperatures can be used in Equations 2 and 3 because the calculation involves only a temperature difference. A discussion on shifted temperatures is included in section 2.4. The heat load is the difference in enthalpy between the supply and target stream properties and is the maximum amount of heat that could be transferred to or from a stream in a given temperature range. The heat load is important because it determines how much heat transfer is possible between given streams and how much external heating or cooling is required. The conversion factors used in the heat capacity flowrate equation are listed in Appendix 7.2. [1, 3] Ý m h 7936.64144 0.42992261 0.94781742 mCp 1.8 TSS TTS dH mCpTTS TSS [2] [3] 2.4 Problem Table Analysis The problem table method is developed to “allow for the maximum possible amount of heat exchange within each temperature interval.” [3] The method is used for existing 7 systems so that any hot and cold streams can be matched together. There would be little flexibility for improvement of a heat exchanger network if streams that are already matched via the current heat exchanger network were used in the analysis. Shifted temperatures (1/2 ΔTmin below hot stream and 1/2 ΔTmin above cold stream) are used to ensure that Tmin exists between all hot and cold streams to adhere to the Second Law of Thermodynamics. [3, 5] 2.5 Composite Curves The composite curve is a way to incorporate all of the hot and cold streams onto a temperature-enthalpy diagram. Figure 3 shows the change in enthalpy, for the given temperature range, as shown in Equation 3. The maximum amount of heat recovery and hot and cold utilities can be found from the hot and cold composite curves, as shown in Figure 3. The maximum amount of heat recovery, from the excess steam from the turbines and from the cold feedwater, is the area of overlap between the hot and cold composite curves (from the upward arrow at the start of the cold composite to the downward arrow at the end of the hot composite). The gap between the start of the hot and cold composite curves is the minimum cold utility required and the gap between the end of the hot and cold composite curves is the minimum hot utility required. [3, 5] QuickTime™ and a decompressor are needed to see this picture. QuickTime™ and a decompressor are needed to see this picture. Figure 3: Hot and Cold Composite Curves 8 2.5.1 Shifted Composite Curve The composite curves are also plotted using the shifted temperatures, as shown in Figure 4. The shifted composite curves touch at the pinch point. The problem is divided on either side of the pinch point. Above the pinch point, the cold flow is greater than the hot flow and the hot utilities must be supplied to make up the difference. As shown in Figure 4, the cold composite extends farther along the x-axis (heat flow) than the hot composite, therefore requiring a heating duty. Below the pinch point, the hot flow is greater than the cold flow and cold utilities must be supplied. As shown in Figure 4, the cold composite curve trails the hot composite, requiring an external cooling duty. Using shifted temperatures does not affect the values of the heat recovery, cooling duty or heating duty, as seen by comparing Figure 3 and Figure 4, because the hot composite is being shifted down and the cold composite is being shifted up by the same value. QuickTime™ and a decompressor are needed to see this picture. QuickTime™ and a decompressor are needed to see this picture. Figure 4: Shifted Composite Curves 2.6 Grand Composite Curve The grand composite curve, shown in Figure 5, is a graph of the net heat flow (utility requirement) versus the shifted temperature. The GCC is used for “setting multiple utility targets.” [5] The shifted composite curves ensure that ΔTmin is maintained (by 9 using ΔTmin /2 less than hot temperatures & ΔTmin /2 greater than cold temperaturs) at all points. The x-axis of the GCC shows the utility heating or cooling required. QuickTime™ and a decompressor are needed to see this picture. Figure 5: Grand Composite Curve Example The pinch point is the location where the net heat flow is zero. The net heat flow values at the two endpoints of the graph are the external heating and cooling duties that are required for optimum heat transfer within the HEN. The curve also shows the temperatures at which heating and cooling are required. When the pinch occurs at one end of the curve, it is referred to as a threshold problem. 2.7 ΔTmin and Trade Offs The minimum temperature difference between the hot and cold composite curves affects the pinch temperature, the required external utilities, and the size of the heat exchangers. However, only the heat exchangers that exist at the pinch point need to operate at ΔTmin because this is the most constrained area of the HEN. 10 As shown in Figure 6, the heat exchanger area is roughly inversely proportional to the temperature difference. However, low values of ΔTmin can result in large and costly heat exchangers. The hot utility required increases as the heat exchanger area decreases. While there are cost savings involved with decreasing the physical area of the heat exchanger, there are high energy costs associated with an increase in hot utilities. The optimum ΔTmin must be selected for the best cost savings. The optimum ΔTmin can be selected by matching the capital cost and the energy cost to determine the minimum cost for new designs. The point at which the energy cost and the heat exchanger cost (surface area) are equal identifies the optimal ΔTmin [8]. QuickTime™ and a decompressor are needed to see this picture. Figure 6: Utility Use, Heat Exchanger Area, and Cost Variation with Delta T min [3] As ΔTmin is increased, the difference between the hot and cold composite curves increases, which increases the heat required by external utilities, as shown in Figure 7. The heating and cooling duties increase as the hot and cold composite curves are separated by a larger ΔTmin. 11 QuickTime™ and a decompressor are needed to see this picture. Figure 7: Effect of Delta Tmin on Composite Curves 2.8 Design of the Heat Exchanger Network Many variables exist when performing a retrofit pinch analysis. The pinch point is determined and cross-pinch heat transfer in the existing network is identified. To improve the network design, cross-pinch heat transfer should not exist. Correcting this problem involves using new heat exchangers, of different areas, in the network. In some cases it is best to combine two existing heat exchangers and design a new heat exchanger to handle the mass flowrates and heat exchange requirements of multiple streams. Other times it is best to add an additional heat exchanger in the network. Additional heat exchangers and redesigned heat exchangers are costly for existing power plants, depending on the area of the heat exchanger. However, it is worthwhile when the cost from energy savings exceeds the one time cost of the new heat exchanger(s). 12 3. Methodology 3.1 Overview The pinch analysis performed for this project is divided into three major steps: (1) extraction of stream data (temperature, flow, and heat capacity data) from the Millstone Unit III heat and mass balance, (2) selection of Tmin and calculation of the pinch point and minimum utility requirements, (3) determining areas of cross-pinch heat transfer and modifying the heat exchanger network. An excel spreadsheet template, provided with [3] was used for the first two steps of the analysis. The user enters Tmin, the supply and target temperatures, the mass flow rates, and the change in enthalpy. Typical ΔTmin values for different types of plants can be found in various texts. ΔTmin for chemical plants ranges from 10-20 C. [3, 5, 8] The program calculates the heat load, whether the stream is hot or cold, and the shifted temperatures based on the supplied Tmin. The problem was evaluated as two systems, one above the pinch and one below the pinch. The analysis was also verified by hand calculations. 3.2 Assumptions A simplified Millstone Unit III HEN consisting of six feedwater heaters, as shown in Figure 8, was evaluated. In the analysis, it is assumed that the flow from the condenser is that which enters the 6th point heater. The main condenser is considered a permanent utility because of the cooling water from the Long Island Sound and was therefore, not included in the analysis. Weighted average supply and target temperatures, enthalpy, and flowrates are used when streams are combined. The weighted average is based on the mass flowrates of the individual streams, and will be discussed in section 3.3. 13 QuickTime™ and a decompressor are needed to see this picture. Figure 8: Simplified Schematic of the Millstone Unit III HEN 3.3 Data Extraction Data is extracted from the heat and mass balance in Appendix 7.2 for all areas of the plant that need heating or cooling. In this analysis, the HEN consisting of six feedwater heaters, shown in Figure 8, was evaluated for simplicity. A ΔTmin of 50 F was used for this analysis. In the input stage, the heating and cooling demands of the streams are included without any reference to the existing heat exchangers. [5] Typically, the analysis does not match specific hot and cold streams so the analysis is not constrained. However, the analysis performed was simplified with only one cold stream that feeds through all of the feedwater heaters. Therefore, it is apparent that one cold stream is heated by, and cools, all of the hot streams. For an existing plant, the heat exchangers and the plant layout should not be used at first. Utility streams (cooling water, steam, etc.) are not to be included in the data extraction phase unless they cannot be replaced. [3] The original heat exchanger network design parameters, extracted from Figure 18: Millstone Unit III Heat Balance , are presented in Table 1. 14 Table 1: Millstone Unit III Heat Exchanger Network Hot Stream Heat Exchanger Cold Stream Number Ts (F) Tt (F) Ts (F) Tt (F) 1st Point 491 380 369 442.8 2nd Point 379 334 326.7 365.6 3rd Point 346 292 282 297.9 4th Point 297 266 222.9 288.1 5th Point 231 174 158.3 222.9 6th Point 163 158 101 158.3 Figure 9 is an example of the streams associated with the 1st point heater (of Table 1) from the Millstone Unit III HEN, shown in Figure 18: Millstone Unit III Heat Balance . The figure shows a control volume of the hot and cold streams entering and exiting. The weighted average supply and target temperatures are those listed in Table 1. The figure can also be used to describe the 2nd through 6th point heaters with their original temperatures from Table 1. Treating each heater as its own control volume would significantly constrain the analysis. Therefore, the six cold streams for each of the heat exchangers listed in Table 1 were combined into one stream for this analysis, using only the supply temperature for the 6th point heater and the target temperature for the 1st point heater. The HEN with supply and target temperatures used for the analysis is shown in Figure 10 and Table 2. The analysis was done using one cold stream (from the condenser to the SG (Stream 1 of Table 2)) and six hot streams (one stream for each closed feedwater heater (Streams 2 through 7 of Table 2)). 15 QuickTime™ and a decompressor are needed to see this picture. Figure 9: Hot and Cold Stream Example from the Original Millstone Unit III HEN QuickTime™ and a decompressor are needed to see this picture. Figure 10: Hot and Cold Stream Data for the HEN used for Analysis The 1st through 4th point heaters have a combination of streams that flow through the heat exchanger to heat the feedwater stream, as shown in Figure 18: Millstone Unit III Heat Balance . For example, the 1st point heater from the Millstone Unit III heat balance has three hot stream supplies (W, V, and HP 1) that combine in the heater into one target stream, as shown in Figure 9. The input streams are combined to simplify the analysis, as shown in Figure 10 and Figure 11. 16 QuickTime™ and a decompressor are needed to see this picture. Figure 11: Hot and Cold Stream Example After Combining Streams The supply temperatures for the 1st through 4th point heaters, in this analysis, are weighted averages based on the mass flow rates. For example, the supply temperature for the 1st point heater (Stream 2 of Table 2) was determined by multiplying the temperature of each hot supply stream by the mass flowrate, divided by the total combined mass flowrate, and taking the sum of this result for all of the supply streams to the heater, as shown in equation 4. The total mass flowrates for streams 2 through 5 of Table 2 are a combined sum of the individual stream flowrates that enter the feedwater heater, as described above for the 1st point heater (See Table 11 of Appendix 7.3 for intermediate steps and details). The average supply and target temperatures used in the analysis are shown in Table 2, along with the mass flowrate for each stream and enthalpy change. m m m Ý Ý Ý Ts TW W TV V THP1 HP1 ÝTot ÝTot ÝTot m m m [4] 73,748lbm /hr 1,540,778lb /hr 1,247,218lb /hr Ts 525F 525F 448F 491F 2,861,744lbm /hr 2,861,744lb /hr 2,861,744lb /hr The same procedure was followed to determine the supply enthalpy for the heaters that have multiple supply streams. The combined supply enthalpy for the 1st point heater is calculated as follows: 17 m m m Ý Ý Ý Hs HW W HV V H HP1 HP1 ÝTot ÝTot ÝTot m m m [5] 73,748lbm /hr 1,540,778lb /hr 1,247,218lb /hr Hs 1,198Btu /lb 518Btu /lb 1,146Btu /lb 809Btu /lb 2,861,744lbm /hr 2,861,744lb /hr 2,861,744lb /hr Table 2: Input Stream Data for Analysis Stream Name Supply Target Temperature Temperature dT Min / 2 Mass Flowrate Enthalpy Change °F °F °F lb/hr Btu(IT)/lb 1 98 442.8 25 10085320.000 202 2 491 380 25 2861744.000 455 3 379 334 25 3444389.000 173 4 346 292 25 3983700.000 171 5 297 266 25 4566511.000 146 6 231 174 25 675020.000 968 7 163 158 25 571554.000 928 The shifted temperatures are then calculated by subtracting half of Tmin from the hot stream supply and target temperatures. The shifted supply temperature for stream 2 of Table 2 is calculated as follows. TSS Hot TS Tmin 50F 491F 466F 2 2 [6] The supply shift temperature for the cold stream (Stream 1 of Table 2) is calculated by adding half of Tmin to the supply temperature as follows. TSSCold TS Tmin 50F 98F 123F 2 2 [7] Table 3 shows the shifted temperatures for the hot and cold streams, along with the net heat capacity flowrates, which will be addressed in section 3.4. 18 Table 3: Shifted Temperatures and Heat Capacity Flowrate Stream Supply Shift (°F) Target Shift (°F) mcp net (MBtu/hr/°F) 1 123 467.8 -912 2 466 355 1810 3 354 309 2055 4 407 267 1947 5 272 241 3319 6 206 149 1769 7 138 133 16370 3.4 Problem Table To make the problem table, the shifted temperatures are ranked in decreasing order, starting from the highest temperature, as shown in Table 4 of section 4.1. The heat capacity flowrate and the heat load are calculated for all of the temperature intervals, using equations 1 and 2. The calculations for the first interval (between shifted temperatures 467.8 °F and 466 °F) are provided below. The net heat capacity flowrates are shown in Table 3. The intermediate calculations for the problem table and heat loads can be found in Table 13 of Appendix 7.3. [7] 10085320lb /hr 202Btu /lb 7936.64144 0.42992261 0.94781742 mCp 911.7986MBtu /hr /F 1.8 123F 467.8F dH 911.7986MBtu /hr /F 467.8 466 1641.2375MBtu /hr 3.4.1 Heat Cascades The heat cascade uses the surplus heat from one hot utility and moves it into the next interval so that the heat from the system is not wasted. The minimum utility requirements are determined from the heat cascade diagram. Starting from a zero heat input at the highest temperature in the Problem Table, the net heat change (dH) is added to each temperature interval to form a heat cascade. The heat 19 cascade was evaluated and determined to be infeasible because the cascade contains negative heat flows. The minimum heat flow (largest negative value) from the infeasible heat cascade is now added to the hot utility in a new cascade. This causes the net heat flows in the new cascade to increase by the largest negative value from the infeasible cascade, making the minimum value in the new cascade equal to zero. The minimum value (should be zero) is the pinch point. The heat added to the first interval is the hot utility requirement and the heat removed from the final interval is the cold utility target. [3] The intermediate steps to construct the heat cascade are provided in Table 13 of Appendix 7.3. The results of the heat cascade will be provided and discussed in section 4.2. 3.5 Composite Curves The composite curve is a graph of temperature versus heat flow. The shifted composite curve is then made using the shifted temperatures for both the hot and cold streams. To generate the GCC, the net heat flow (right side of the feasible heat cascade) is plotted on the horizontal axis and the shifted temperature is plotted on the vertical axis. The composite curves generated for this analysis can be found in sections 4.4 and 4.5 of the results section. 3.6 Grid Diagram The grid diagram is another way to visualize the streams in the analysis. The grid diagram “represents the countercurrent nature of the heat exchange.” [3] The grid diagram is a useful visual tool to apply the rules of pinch analysis. Some of the rules for a successful pinch analysis are: do not transfer heat across the pinch, do not use cold utilities above the pinch, and do not use hot utilities below the pinch. [3, 5, 8] If one were to transfer heat across the pinch, one would have to “replace this cross-pinch heat with an equivalent amount of hot utility above the pinch, and we would increase our consumption of cold utility below the pinch (air, cooling water, etc.) by the same amount.” [8] 20 As shown in Figure 12, streams 1 and 2 (boxes) are hot streams and streams 3 and 4 are cold streams. The circles represent current heat exchangers between two streams. QuickTime™ and a decompressor are needed to see this picture. Figure 12: Grid Diagram Example For a retrofit analysis, the current streams and heat exchangers are depicted on the grid diagram. The location of the pinch is drawn, as shown in Figure 13. If there is a current heat exchanger that transfers heat across the pinch, the heat exchanger is split into two (one above the pinch and one below the pinch as shown by circles “1” and “1a” in Figure 13). QuickTime™ and a decompressor are needed to see this picture. Figure 13: Grid Diagram with Cross Pinch Heat Transfer Example 21 The heat exchangers that were split are then combined with another heat exchanger on the same side of the pinch or a new heat exchanger is created. 3.7 Effect of the Number of Heat Exchangers on the External Utility Requirements Multiple cases were analyzed to determine the effect of the number of heat exchangers and the temperatures of the streams. The results will be addressed in section 4.7. The base case of the six feedwater heaters and the one cold stream, from Figure 10 was the foundation for each case. 3.8 Effect of the Minimum Temperature Difference on the Pinch Point and External Utility Requirements The effect of the minimum temperature difference was analyzed using the pinch analysis software and will be addressed further in section 4.8. Minimum temperature differences of 10 F, 30 F, 40 F, 48 F, 50 F, and 70 F were evaluated. 22 4. Results and Discussion 4.1 Problem Table The problem table is provided in Table 4 and was constructed based on the method described in section 3.4. The heat capacity flowrate and the heat load are calculated for each interval, using Equations 2 and 3. The heat capacity flowrates of all the streams that exist within the given temperature interval are added together to determine the net heat capacity flowrate, shown in column four of Table 4. For example, in interval 2 of Table 4, the shifted temperature range is from 466 F to 355 F. Streams 1 and 2, of Table 2, exist within the temperature interval, so the net heat capacity flowrate is the sum of the heat capacity flowrates for streams 1 and 2. Table 12 in Appendix 7.3 shows the heat capacity flowrates for each stream. Table 13 in Appendix 7.3 shows the intermediate calculations for the heat capacity flowrates and heat loads for each interval in Table 4. Table 5 shows the net heat capacity flowrates and heat loads for each interval and compares them to the values obtained using the software. 23 Table 4: Problem Table Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 1.8 -912 -1641 demand 2 111 898 99731 surplus 3 1 -912 -912 demand 4 33 1132 37346 surplus 5 12 3078 36941 surplus 6 37 1035 38294 surplus 7 5 4354 21770 surplus 8 26 2407 62586 surplus 9 35 -912 -31913 demand 10 57 857 48864 surplus 11 11 -912 -10030 demand 12 5 15459 77293 surplus 13 10 -912 -9118 demand 466 355 354 321 309 272 267 241 206 149 138 133 123 24 Table 5: Net Heat Capacity Flowrate and Heat Load (Calculated and Software) Interval 1 2 3 4 5 6 7 8 9 10 11 12 13 Temperature (F) 467.8 to 466 466 to 355 355 to 354 354 to 321 321 to 309 309 to 272 272 to 267 267 to 241 241 to 206 206 to 149 149 to 138 138 to 133 133 to 123 Temperature Difference (F) 2 111 1 33 12 37 5 26 35 57 11 5 10 mcp net (Mbtu/hr/ F) -912 898 -912 1143 3090 1035 4353 2407 -912 857 -912 15458 -912 mcp net (Mbtu/hr/F) from software -912 898 -912 1132 3078 1035 4354 2407 -912 857 -912 15459 -912 dH (Mbtu/hr) -1642 99680 -912 37720 37077 38277 21767 62574 -31928 48838 -10035 77290 -9122 dH (Mbtu/hr) from software -1641 99731 -912 37346 36941 38294 21770 62586 -31913 48864 -10030 77293 -9118 The theoretical calculations for the heat capacity flowrates and the heat load, shown in Table 5, were calculated using Equations 2 and 3 and are very close to those determined from the software. The slight error could be due to differences in conversion factors and rounding (number of decimal places). Overall, the results from the software are considered valid based on the hand calculations. 4.2 Heat Cascade The heat cascade is drawn from the problem table. The heat loads (of Table 4) are in the boxes of Table 6 and the heat load for each interval is added to that of the previous interval. Table 6 shows the heat cascade calculated by the software program. [3] The heat cascade on the left hand side of Table 6 is infeasible because there is a negative net heat load. The minimum heat flow (largest negative value) from the infeasible heat cascade is now added to the hot utility in a new cascade. The feasible heat cascade does not include any negative heat flows. The temperature at which there is no heat flow is the pinch point. 25 Table 6: Heat Cascade QuickTime™ and a decompressor are needed to see this picture. Table 7 compares the heat loads for the infeasible and feasible heat cascades from the software and those calculated by hand. The error between the hand calculations and the software is a carryover of the error from the heat load calculations in Table 5 and rounding differences. 26 Table 7: Heat Loads per Interval (Calculated and Software) Shift Temperature (F) 467.8 466 355 354 321 309 272 267 241 206 149 138 133 123 Infeasible cascade (MBtu/hr) 0 -1642 98038 97126 134846 171923 210200 231967 294541 262612 311450 301415 378706 369583 Infeasible cascade (software) (MBtu/hr) 0 -1641 98090 97178 134523 171465 209759 231528 294114 262201 311065 301035 378328 369210 Feasible Cascade (MBtu/hr) 1642 0 99680 98768 136488 173565 211842 233609 296183 264254 313092 303057 380348 371225 Feasible Cascade (software) (MBtu/hr) 1641 0 99731 98819 136165 173106 211400 233169 295755 263842 312706 302676 379970 370852 4.3 Pinch Points and Utility The pinch temperature (shifted) is 466F and is highlighted in yellow in Table 4 and Table 7. The hot pinch is 491F and the cold pinch is 441F and are calculated using Equations 6 and 7. The minimum hot and cold utility requirements are 1,641 MBtu/hr and 370,852 MBtu/hr, respectively, as determined by the software and 1,642 MBtu/hr and 371,225 MBtu/hr, respectively as determined by hand calculations. The hot utility is fairly low because there are six hot streams heating up the one cold stream. The cold utility is relatively high because the base case analysis, using Figure 10, was done with the exact supply and target temperatures from Figure 18. However, the target temperatures of the hot streams do not need to be fixed because they are not used to heat up any other streams. The cold stream is the only stream in the analysis that has a fixed target temperature. Changes to the hot stream target temperatures are evaluated and discussed in Section 4.7. 27 4.4 Composite Curves The pinch point is also determined graphically by using the shifted composite curve. The hot and cold composite curves are shown in Figure 14. Hot and Cold Composite Curves 600 Actual Temperature (ЎF) 500 400 300 200 100 0 0 100000 200000 300000 400000 500000 600000 700000 800000 Heat Flow (Mbtu(IT)/hr) QuickTime™ and a decompressor are needed to see this picture. Figure 14: Hot and Cold Composite Curves The shifted hot and cold composite curves are shown in Figure 15. The point where the hot and cold shifted composite curves touch is the pinch point. ΔTmin is redistributed in the shifted composite curves by subtracting 1/2 ΔTmin from the hot stream temperatures and adding1/2 ΔTmin to the cold stream temperatures. This allows the hot and cold composite curves to shift and touch at the pinch point for easier visual interpretation of the results. 28 Shifted Hot and Cold Composite Curves 500 450 Shifted Temperature (ЎF) 400 350 300 250 200 150 100 50 0 0 100000 200000 300000 400000 500000 600000 700000 800000 Heat Flow (Mbtu(IT)/hr) QuickTime™ and a decompressor are needed to see this picture. Figure 15: Shifted Hot and Cold Composite Curves 4.5 Grand Composite Curve The grand composite curve is shown in Figure 16. The utility requirements can also be obtained from the grand composite curve. 29 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 50000 100000 150000 200000 250000 300000 350000 400000 Net Heat Flow (Mbtu(IT)/hr) Figure 16: Grand Composite Curve 4.6 Retrofit Heat Exchanger Network The grid diagram is shown in Figure 17. The current heat exchangers, with their corresponding cold and hot streams, are depicted by black circles with arrows between the streams. There are no streams that cross through the pinch point. QuickTime™ and a decompressor are needed to see this picture. Figure 17: Grid Diagram 30 4.7 Targeting Improvements to the External Utility Requirements Multiple cases were analyzed to determine the effect of the number of heat exchangers and the supply and target temperatures of the streams on the external utility requirements. 4.7.1 Effect of Number of Heat Exchangers on the External Utility Requirements The following cases were selected for evaluation to determine the effect of the number of heat exchangers on the external utility requirements. The purpose of reducing the number of heat exchangers is to determine if improvements could be made to the current HEN to reduce the cold utility requirement. As discussed in section 4.3, the hot and cold utility requirements were determined to be 1,641 MBtu/hr and 370,852 MBtu/hr, respectively using the HEN of Figure 10. The thought was that reducing the number of heat exchangers would decrease the cold utility required to cool the hot streams for the heat exchangers that are removed. In case 2, the 6th point heater was deleted and the hot stream 7 was combined with the hot stream 6. In case 3, the 5th and 6th point heaters were deleted and streams 5, 6, and 7 were combined to go through the 4th point heat exchanger. Case 4 deleted the 1st point heat exchanger, closest to the pinch point and combined streams 2 and 3 through the 2nd point heat exchanger. Case 5 deleted the 1st point heat exchanger and the 6th point heat exchanger and combined streams 2 and 3 and 6 and 7, respectively. Case 7, combined the 1st & 2nd point and 3rd, 4th, 5th, and 6th point heaters, into two heat exchangers. In this case, all of the output from the high pressure turbine entered the combined 1st and 2nd heaters and all of the output from the three low pressure turbines entered one heater. Case 11 deleted the 5th & 6th point heaters entirely, with the thought of possibly redirecting the heat & flow through the condenser or elsewhere. 4.7.2 Effect of Supply and Target Temperatures on the External Utility Requirements The following cases were selected for evaluation to determine the effect of supply and target temperatures on the external utility requirements. The purpose of changing the 31 target temperatures of the hot streams was to require less heat transfer from the cold stream to the hot streams (i.e. requiring a smaller temperature difference between hot supply and target streams). The exit temperature of the hot stream is not the driving factor for the HEN. The cold stream must be heated to its target temperature to maintain the plant efficiency to enter the SG. Cases 6, 8, and 9 increased the supply temperatures for the hot streams of Figure 10 because with a larger temperature difference between the hot and cold streams, more heat could be transferred to the cold stream. Case 10, changed the target temperatures of the hot streams (made supply & target temperatures as close as possible for all the hot streams), so that the cold stream wouldn’t have to transfer that much heat to the hot stream to cool it. 4.7.3 Results The results for the cases presented above are shown in Table 8. The full analysis for each case can be found in Appendix 7.4. Table 8: External Utilities for Various HEN Designs Case Pinch Minimum Temperature (F) Utility (MBtu/hr) Utility (MBtu/hr) 2 466 1,641 370,917 3 466 1,641 370,548 4 447 18,965 366,897 5 447 18,965 366,962 6 447 18,965 366,592 7 447 18,965 366,252 8 465 2,553 349,840 9 467 729 348,016 10 466 1,641 320,096 11 466 1,641 37,228 32 Hot Minimum Cold The target temperatures for the base case were directly input from Figure 10. However, the target temperatures for the hot streams are flexible. The main goal is to heat the cold stream to 442.8 F before entering the steam generator. The hot streams that heat the one cold stream have fixed supply temperatures, from the output of the turbines, but the target temperatures can change. Some of the supply temperatures are dependent on the target (output) temperatures of the hot streams because the output streams are combined for a supply stream of another heat exchanger. The results of cases 2 through 5, and 7, did not improve the cold utility requirements significantly because the analysis was done to maintain the conservation of mass and redistribute the hot streams from the heat exchangers that were removed to other heat exchangers in the network. After realizing why this method was unsuccessful, case 11 was performed to determine how removing two heat exchangers and not redirecting their hot supply streams to other heat exchangers would affect the utility requirements. This action decreased the hot streams by two, which significantly decreased the cold utility required. The results were as expected; the cold utility requirement decreased significantly due to the one cold stream not needing to cool two hot streams. The minimum cold utility requirement does not change much between cases 2 through 9 because the target temperatures for the hot streams were not changed. The analysis assumes that the hot streams must be cooled to the specified target temperature. However, this is not necessary because the cold stream is the only stream that must be heated to a specified temperature. The target temperatures for the hot streams were changed in Case 10 to be close to the supply temperatures. Enthalpy values were changed as the temperatures were adjusted. The cold utility still did not change significantly in this case. The hot utility increases in Cases 4, 5, and 7 as expected because the heating capacity of the heat exchangers was removed. 33 4.8 Effect of the Minimum Temperature Difference on the Pinch Point and External Utility Requirements The minimum temperature difference is important to optimize the efficiency and cost of the HEN. “A zero temperature difference would require an infinitely large heat exchanger.” [3] The ideal minimum temperature difference for the base case (Figure 10) was found to be 50 F. As shown in Table 9, the minimum temperature difference is the driving variable for the pinch point. In this analysis, the hot and cold utilities do not change with a temperature difference less than 50 F. Decreasing ΔTmin can greatly increase the heat exchanger cost. Since the minimum utility requirements do not change up until a ΔTmin of 50 F, it is not worth the extra cost to use heat exchangers capable of a smaller minimum temperature difference between streams. The utility requirements significantly increased as ΔTmin was increased above 50 F, which would cost less for the heat exchanger, but more for the energy associated with the utilities. Therefore, the optimal minimum temperature difference for the base case is 50 F. Table 9: External Utilities for Various Minimum Temperature Differences ΔTmin Pinch Minimum Hot Utility Minimum (F) Temperature (F) (MBtu/hr) Utility (MBtu/hr) 10 486 0 369,210 30 476 0 369,210 40 471 0 369,210 48 467 0 369,210 50 466 1,641 370,852 70 456 19,877 389,088 34 Cold 5. Conclusion In conclusion, pinch analysis techniques were used to evaluate the external utility requirements for the Millstone Unit III heat exchanger network, consisting of six feedwater heaters. The problem table, heat cascades, shifted composite curve, and the grand composite curves were constructed to determine the pinch temperature and the utility requirements. The pinch temperature (shifted) was determined to be 466F. The minimum hot and cold utility requirements are 1,641 MBtu/hr and 370,852 MBtu/hr, respectively, as determined by the software and 1,642 MBtu/hr and 371,225 MBtu/hr as determined by hand calculations. The optimum minimum temperature difference between the hot and cold streams was determined to be 50 F for the base case of Figure 10. Ten additional cases were analyzed to determine the effect of the number of heat exchangers and the supply and target temperatures of the streams on the utility requirements. The utility requirements contribute to the efficiency and cost optimization of the power plant. The larger the utility requirements, the more expensive the cost due to energy costs. Case 11 provided the most significant decrease in the cold utility requirement. Deleting the 5th and 6th point heaters decreased the cold utility requirement from 370,852 MBtu/hr to 37,228 MBtu/hr, as determined by the software, while keeping the hot utility at 1,641 MBtu/hr. To provide adequate cost savings, it is recommended that the 5th and 6th point heaters be deleted and the exhaust from the turbines that enters the 5th and 6th point heaters be directed elsewhere, such as the main condenser. This would also increase the temperature of the fluid leaving the condenser (entering the first feedwater heater), which would decrease the hot utility required to heat the fluid to 442.8 F when entering the SG. 35 6. References 6.1 Works Cited [1] Moran, Michael J., and Howard N. Shapiro. Fundamentals of Engineering Thermodynamics. New York: Wiley, 2008. Print. [2] Dominion. Nuclear Media Guide, Information on Millstone Power Station. Waterford: Dominion, 2012. Dominion, 2012. Web. 19 Aug. 2013. [3] Kemp, Ian E. Pinch Analysis and Process Integration - A User Guide on Process Integration for the Efficient Use of Energy. 2nd ed. Oxford: Elsevier, 2007. Print. [4] Tjoe, T. N., and Bodo Linnhoff. "Using Pinch Technology for Process Retrofit." Chemical Engineering 28 (1986): 47-60. Web. [5] March, Linnhoff. Introduction to Pinch Technology. 1998. Targeting House Gadbrook Park, England. [6] Singh, Kamel, and Raymond Crosbie. "Use of Pinch Analysis in Sizing and Integrating a Heat Exchanger into an Existing Exchanger Network at a Gas Processing Plant." The Journal of the Association of Professional Engineers of Trinidad and Tobago 40.2 (2011): 43-48. Print. [7] Bi, Bao-Hong, and Chuei-Tin Chang. "Retrofitting Heat Exchanger Networks Based on Simple Pinch Analysis." Ind. Eng. Chem. Res. 49 (2010): 3967-971. Web. [8] Pinch Analysis: For the Efficient Use of Energy, Water, and Hydrogen. N.p.: Canada, 2003. Print. 36 6.2 Additional References Consulted Bakhtiari, Bahador, and Serge Bedard. "Retrofitting Heat Exchanger Networks Using a Modified Network Pinch Approach." Applied Thermal Engineering 51 (2012): 973-979. Science Direct. Web. 17 Aug. 2013. Linnhoff, B., and E. Hindmarsh. "The Pinch Design Method for Heat Exchanger Networks." Chemical Engineering Science 38.5 (1983): 745-63. Print. Rossiter, Alan P. Using Spreadsheets for Pinch Analysis. Tech. no. 96D. N.p.: Unpublished, 2004. Print. Zebian, Hussam, and Alexander Mitsos. "A Double-pinch Criterion for Regenerative Rankine Cycles." Energy 40.2 (2012): 258-70. Print. 37 7. Appendices 7.1 Guide to Excel File The following are the tabs in the excel file: INDEX – Table of Contents INPUT – Input Stream Data for the Heat Exchanger Network PT – Problem Table and Heat Cascade CC – Hot and cold composite curves SCC – Shifted composite curves GCC – Grand composite curves GRID – Network grid diagram, shifted temperatures AS – Stream data plot, actual temperatures AT – Interval tables (heat loads and temperatures), actual temperatures SS – Stream data plot, shifted temperatures ST – Interval tables (heat loads and temperatures), shifted temperatures DTMIN – Variation of hot and cold utility targets and pinch temperature with ∆Тmin. A1 – Intermediate calculations A2 – Plot raw data 38 7.2 Millstone Unit III Heat and Mass Balance QuickTime™ and a decompressor are needed to see this picture. Figure 18: Millstone Unit III Heat Balance 39 7.3 Raw Data and Intermediate Steps Table 10: Raw Data from Millstone Unit III Heat and Mass Balance Stream Description from LP 1 from LP 2 from LP 3 from LP 4 HP 1 HP 2 W to 1st pt V to 1st pt A to 2nd pt waste from 1st pt waste from 2nd pt waste from 3rd pt waste from 5th pt waste from 6th pt Input H (Btu/lb) 1241 1200 1110 1054 1146 1089 1198 518 1192 Output H (Btu/lb( 261 235 142 126 354 305 354 354 305 Change H (Btu/lb) 980 965 968 928 792 784 844 164 887 Supply Temp (F) 426 335 231 163 448 373 525 525 538 Target Temp (F) 292 266 174 158 380 334 380 380 334 Flow (lb/hr) 539308 582815 675020 571554 1247218 570935 73748 1540778 11711 354 305 49 380 334 2861743 305 261 44 334 292 3444392 261 235 26 292 266 3983696 142 56 86 174 98 675021 126 56 70 158 98 785742 40 Table 11: Combined Data for HEN used in Analysis for Case 1 Stream Description Condenser to SG 1 Total W+V+HP1 flow 2 Total A + 2nd pt + waste from 1st pt Total 3rd pt (LP1)+ 2nd pt waste 3 4 Total waste from 3rd pt + LP2 5 From LP 3 6 7 From LP 4 Output H (Btu/lb ) Change H (Btu/lb) 56 258.1 809 Supply Temp (F) Target Temp (F) 202.1 98 442.8 354 455 491 380 479 305 174 379 432 261 171 381 235 1110 1054 Input H (Btu/lb) Supply Shift (F) Target Shift (F) Cold 123 467.8 2861744 Hot 466 355 334 3444389 Hot 354 309 346 292 3983700 Hot 407 267 146 297 266 4566511 Hot 272 241 142 968 231 174 675020 Hot 206 149 126 928 163 158 571554 Hot 138 133 Flow (lb/hr) Stream Type 10085320 Table 12: Net Heat Capacity Flowrates Stream mcp net (Mbtu/hr/F) 1 Supply Shift (F) 123 Target Shift (F) 467.8 2 466 355 1810 3 354 309 2055 4 407 267 1947 5 272 241 3319 6 206 149 1769 7 138 133 16370 41 -912 Table 13: Intermediate Calculations for Heat Capacity and Heat Load Temperature Temperature (F) Interval 1 467.8 to 466 2 466 to 355 3 355 to 354 4 354 to 321 5 321 to 309 6 309 to 272 7 272 to 267 8 267 to 241 9 241 to 206 10 206 to 149 11 149 to 138 12 138 to 133 13 133 to 123 mcp net (Mbtu/hr/F) dH (Mbtu/hr) -912 -912 * 2 -912 + 1810 898 * 111 -912 -912 * 1 -912 + 2055 1143 * 33 -912 + 2055 + 1947 -912 + 1947 3090 * 12 4353 * 5 26 -912 + 3319 + 1947 -912 + 3319 35 -912 -912 * 35 57 -912 + 1769 857 * 57 11 -912 -912 * 11 -912 + 16370 15458 * 5 -912 -912 * 10 Difference (F) 2 111 1 33 12 37 5 5 10 1035 * 37 2407 * 26 Conversion Factors for heat capacity flowrate calculations (from [1]) 1 kJ/kg = 0.42992261 Btu/lb 1 kJ = 0.94781742 Btu T(R) = 1.8T(K) 1 kg/s = 7936.64144 lb/hr 7.4 Other Cases Evaluated 7.4.1 Case 2 Table 14: Input Stream Data for Case 2 Stream Name Supply Temperature Target Temperature dT Min / 2 Mass Flowrate 1 2 3 4 5 6 °F 98 491 379 346 297 200 °F 442.8 380 334 292 266 167 °F 25 25 25 25 25 25 lb/h 10085320.000 2861744.000 3444389.000 3983700.000 4566511.000 1246574.000 42 Enthalpy Change Btu(IT)/lb 202 455 173 171 146 950 Table 15: Calculated Stream Data for Case 2 Stream Name Heat Flow 1 2 3 4 5 6 MBtu(IT)/hr 314388.1611 200940.4215 91956.7107 105125.4499 102887.4717 182753.9621 Stream Type Supply Shift Target Shift COLD HOT HOT HOT HOT HOT °F 123.0 466.0 354.0 321.0 272.0 175.0 °F 467.8 355.0 309.0 267.0 241.0 142.0 Table 16: Problem Table for Case 2 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 1.8 -911.7986 -1641.2375 demand 2 111 898.4755 99730.7757 surplus 3 1 -911.7986 -911.7986 demand 4 33 1131.6838 37345.567 surplus 5 12 3078.4514 36941.4173 surplus 6 37 1034.969 38293.8522 surplus 7 5 4353.9197 21769.5984 surplus 8 26 2407.1521 62585.9543 surplus 9 66 -911.7986 -60178.7083 demand 10 33 4626.2002 152664.6079 surplus 11 19 -911.7986 -17324.1736 demand 466 355 354 321 309 272 267 241 175 142 123 43 Table 17: Heat Cascade for Case 2 Infeasible Cascade ▼ PINCH -1641.2375 ▼ 99730.7757 ▼ -911.798611 ▼ 37345.56701 ▼ 36941.41727 ▼ 38293.85224 ▼ 21769.5984 ▼ 62585.95432 ▼ 60178.70833 ▼ 152664.6079 ▼ 17324.17361 ▼ Feasible Cascade ▼ 0 -1641.2375 98089.5382 97177.73959 134523.3066 171464.7239 209758.5761 231528.1745 294114.1288 233935.4205 386600.0284 369275.8548 44 -1641.2375 ▼ 99730.7757 ▼ -911.798611 ▼ 37345.56701 ▼ 36941.41727 ▼ 38293.85224 ▼ 21769.5984 ▼ 62585.95432 ▼ 60178.70833 ▼ 152664.6079 ▼ 17324.17361 ▼ 1641.2375 0 99730.7757 98818.97709 136164.5441 173105.9614 211399.8136 233169.412 295755.3663 235576.658 388241.2659 370917.0923 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 50000 100000 150000 200000 250000 300000 350000 400000 450000 Net Heat Flow (Mbtu(IT)/hr) Figure 19: GCC for Case 2 7.4.2 Case 3 Table 18: Input Stream Data for Case 3 Stream Name Supply Temperature Target Temperature dT Min / 2 Mass Flowrate 1 2 3 4 5 °F 98 491 379 346 277 °F 442.8 380 334 292 245 °F 25 25 25 25 25 lb/h 10085320.000 2861744.000 3444389.000 3983700.000 5813085.000 Table 19: Calculated Stream Data for Case 3 Stream Name Heat Flow 1 2 3 4 5 MBtu(IT)/hr 314388.1611 200940.4215 91956.7107 105125.4499 285271.854 Stream Type Supply Shift Target Shift COLD HOT HOT HOT HOT °F 123.0 466.0 354.0 321.0 252.0 °F 467.8 355.0 309.0 267.0 220.0 45 Enthalpy Change Btu(IT)/lb 202 455 173 171 318 Table 20: Problem Table for Case 3 Shift Temperature °F 467.8 T(i+1)Ti °F mCpnet dH MBtu(IT)/hr/°F MBtu(IT)/hr 1 1.8 -912 -1641 demand 2 111 898 99731 surplus 3 1 -912 -912 demand 4 33 1132 37346 surplus 5 12 3078 36941 surplus 6 42 1035 43469 surplus 7 15 -912 -13677 demand 8 32 8003 256094 surplus 9 97 -912 -88444 demand Interval 466 355 354 321 309 267 252 220 123 Table 21: Heat Cascade for Case 3 Infeasible Cascade Feasible Cascade 9 30.7757 0 PINCH -1641.2375 ▼ 99730.7757 ▼ -911.798611 ▼ 37345.56701 ▼ 36941.41727 ▼ 43468.69714 ▼ 13676.97917 ▼ 256094.2985 -1641.2375 ▼ 99730.7757 ▼ -1641.2375 98089.5382 -911.798611 ▼ 37345.56701 ▼ 36941.41727 ▼ 43468.69714 ▼ 13676.97917 ▼ 256094.2985 97177.73959 134523.3066 171464.7239 214933.421 201256.4419 46 0 99730.7757 98818.97709 136164.5441 173105.9614 216574.6585 202897.6794 ▼ 88444.46527 ▼ ▼ 88444.46527 ▼ 457350.7403 368906.2751 458991.9778 370547.5126 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 100000 200000 300000 400000 500000 Net Heat Flow (Mbtu(IT)/hr) Figure 20: GCC for Case 3 7.4.3 Case 4 Table 22: Input Stream Data for Case 4 Stream Name Supply Temperature Target Temperature dT Min / 2 Mass Flowrate 1 2 3 4 5 6 °F 98 472 346 297 231 163 °F 442.8 372 292 266 174 158 °F 25 25 25 25 25 25 lb/h 10085320.000 3444390.000 3983700.000 4566511.000 675020.000 571554.000 Table 23: Calculated Stream Data for Case 4 Stream Name Heat Flow 1 2 MBtu(IT)/hr 314388.1611 271617.8775 Stream Type Supply Shift Target Shift COLD HOT °F 123.0 447.0 °F 467.8 347.0 47 Enthalpy Change Btu(IT)/lb 202 511 171 146 968 928 3 4 5 6 105125.4499 102887.4717 100836.3529 81852.2036 HOT HOT HOT HOT 321.0 272.0 206.0 138.0 267.0 241.0 149.0 133.0 Table 24: Problem Table for Case 4 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 20.8 -912 -18965 demand 2 100 1804 180438 surplus 3 26 -912 -23707 demand 4 49 1035 50713 surplus 5 5 4354 21770 surplus 6 26 2407 62586 surplus 7 35 -912 -31913 demand 8 57 857 48864 surplus 9 11 -912 -10030 demand 10 5 15459 77293 surplus 11 10 -912 -9118 demand 447 347 321 272 267 241 206 149 138 133 123 48 Table 25: Heat Cascade for Case 4 Infeasible Cascade ▼ 18965.41111 PINCH ▼ 180438.0164 ▼ 23706.76389 ▼ 50713.48 ▼ 21769.5984 ▼ 62585.95432 ▼ 31912.95139 ▼ 48863.83203 ▼ 10029.78472 ▼ 77293.21059 ▼ -9117.98611 ▼ Feasible Cascade ▼ 18965.41111 18965.41111 0 357049.1806 ▼ 180438.0164 ▼ 23706.76389 ▼ 50713.48 ▼ 21769.5984 ▼ 62585.95432 ▼ 31912.95139 ▼ 48863.83203 ▼ 10029.78472 ▼ 77293.21059 ▼ 347931.1945 -9117.98611 ▼ 0 18965.41111 161472.6053 137765.8414 188479.3214 210248.9198 272834.8741 240921.9227 289785.7548 279755.97 49 180438.0164 156731.2525 207444.7325 229214.3309 291800.2852 259887.3338 308751.1659 298721.3812 376014.5917 366896.6056 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 50000 100000 150000 200000 250000 300000 350000 400000 Net Heat Flow (Mbtu(IT)/hr) Figure 21: GCC for Case 4 7.4.4 Case 5 Table 26: Input Stream Data for Case 5 Stream Name Supply Temperature Target Temperature dT Min / 2 Mass Flowrate 1 2 3 4 5 °F 98 472 346 297 200 °F 442.8 372 292 266 167 °F 25 25 25 25 25 lb/h 10085320.000 3444390.000 3983700.000 4566511.000 1246574.000 Table 27: Calculated Stream Data for Case 5 Stream Name Heat Flow 1 2 3 4 5 MBtu(IT)/hr 314388.1611 271617.8775 105125.4499 102887.4717 182753.9621 Stream Type Supply Shift Target Shift COLD HOT HOT HOT HOT °F 123.0 447.0 321.0 272.0 175.0 °F 467.8 347.0 267.0 241.0 142.0 50 Enthalpy Change Btu(IT)/lb 202 511 171 146 950 Table 28: Problem Table for Case 5 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 20.8 -912 -18965 demand 2 100 1804 180438 surplus 3 26 -912 -23707 demand 4 49 1035 50713 surplus 5 5 4354 21770 surplus 6 26 2407 62586 surplus 7 66 -912 -60179 demand 8 33 4626 152665 surplus 9 19 -912 -17324 demand 447 347 321 272 267 241 175 142 123 51 Table 29: Heat Cascade for Case 5 Infeasible Cascade ▼ 18965.41111 PINCH ▼ 180438.0164 ▼ 23706.76389 ▼ 50713.48 ▼ 21769.5984 ▼ 62585.95432 ▼ 60178.70833 ▼ 152664.6079 ▼ 17324.17361 ▼ Feasible Cascade ▼ 18965.41111 0 18965.41111 161472.6053 137765.8414 188479.3214 210248.9198 272834.8741 212656.1658 365320.7737 347996.6001 52 ▼ 180438.0164 ▼ 23706.76389 ▼ 50713.48 ▼ 21769.5984 ▼ 62585.95432 ▼ 60178.70833 ▼ 152664.6079 ▼ 17324.17361 ▼ 18965.41111 0 180438.0164 156731.2525 207444.7325 229214.3309 291800.2852 231621.5769 384286.1848 366962.0112 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 50000 100000 150000 200000 250000 300000 350000 400000 450000 Net Heat Flow (Mbtu(IT)/hr) Figure 22: GCC for Case 5 7.4.5 Case 6 Table 30: Input Stream Data for Case 6 Stream Name Supply Temperature Target Temperature dT Min Contrib Mass Flowrate 1 2 3 4 °F 98 472 346 277 °F 442.8 372 292 245 °F 25 25 25 25 lb/h 10085320.000 3444390.000 3983700.000 5813085.000 Table 31: Calculated Stream Data for Case 6 Stream Name Heat Flow 1 2 3 4 MBtu(IT)/hr 314388.1611 271617.8775 105125.4499 285271.854 Stream Type Supply Shift Target Shift COLD HOT HOT HOT °F 123.0 447.0 321.0 252.0 °F 467.8 347.0 267.0 220.0 53 Enthalpy Change Btu(IT)/lb 202 511 171 318 Table 32: Problem Table for Case 6 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 20.8 -911.7986 -18965.4111 demand 2 100 1804.3802 180438.0164 surplus 3 26 -911.7986 -23706.7639 demand 4 54 1034.969 55888.3249 surplus 5 15 -911.7986 -13676.9792 demand 6 32 8002.9468 256094.2985 surplus 7 97 -911.7986 -88444.4653 demand 447 347 321 267 252 220 123 Table 33: Heat Cascade for Case 6 Infeasible Cascade ▼ 18965.41111 PINCH ▼ 180438.0164 ▼ 23706.76389 ▼ 55888.32489 ▼ 13676.97917 ▼ 256094.2985 ▼ 88444.46527 ▼ Feasible Cascade 0 18965.41111 161472.6053 137765.8414 193654.1663 179977.1871 436071.4856 347627.0204 54 ▼ 18965.41111 18965.41111 ▼ 180438.0164 ▼ 23706.76389 ▼ 55888.32489 ▼ 13676.97917 ▼ 256094.2985 ▼ 88444.46527 ▼ 0 180438.0164 156731.2525 212619.5774 198942.5982 455036.8967 366592.4315 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 100000 200000 300000 400000 500000 Net Heat Flow (Mbtu(IT)/hr) Figure 23: GCC for Case 6 7.4.6 Case 7 Table 34: Input Stream Data for Case 7 Stream Name Supply Temperature Target Temperature dT Min Contrib Mass Flowrate 1 2 3 4 °F 98 472 346 277 °F 442.8 372 292 245 °F 25 25 25 25 lb/h 10085320.000 3444390.000 3983700.000 5813085.000 Table 35: Calculated Stream Data for Case 7 Stream Name Heat Flow 1 2 3 4 MBtu(IT)/hr 314388.1611 271617.8775 105125.4499 285271.854 Stream Type Supply Shift Target Shift COLD HOT HOT HOT °F 123.0 447.0 321.0 252.0 °F 467.8 347.0 267.0 220.0 55 Enthalpy Change Btu(IT)/lb 202 511 171 318 Table 36: Problem Table for Case 7 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 20.8 -911.7986 -18965.4111 demand 2 100 1804.3802 180438.0164 surplus 3 26 -911.7986 -23706.7639 demand 4 54 1034.969 55888.3249 surplus 5 15 -911.7986 -13676.9792 demand 6 32 8002.9468 256094.2985 surplus 7 97 -911.7986 -88444.4653 demand 447 347 321 267 252 220 123 Table 37: Heat Cascade for Case 7 Infeasible Cascade Feasible Cascade 1 0438.0164 .6053 .0164 ▼ 180 -237 76389 -23706.763 23706.76389 .76389 56 6 8 0164 ▼ 23706.76389 ▼ 55888.32489 ▼ 13676.97917 ▼ 256094.2985 ▼ 88444.46527 ▼ ▼ 23706.76389 ▼ 55888.32489 ▼ 13676.97917 ▼ 256094.2985 ▼ 88444.46527 ▼ 161472.6053 137765.8414 193654.1663 179977.1871 436071.4856 347627.0204 180438.0164 156731.2525 212619.5774 198942.5982 455036.8967 366592.4315 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 100000 200000 300000 400000 500000 Net Heat Flow (Mbtu(IT)/hr) Figure 24: GCC for Case 7 7.4.7 Case 8 Table 38: Input Stream Data for Case 8 Stream Name Supply Temperature Target Temperature dT Min Contrib Mass Flowrate 1 2 °F 98 490 °F 442.8 372 °F 25 25 lb/h 10085320.000 3444390.000 57 Enthalpy Change Btu(IT)/lb 202 511 3 400 264 25 9796785.000 258 Table 39: Calculated Stream Data for Case 8 Stream Name Heat Flow 1 2 3 MBtu(IT)/hr 314388.1611 271617.8775 390057.3038 Stream Type Supply Shift Target Shift COLD HOT HOT °F 123.0 465.0 375.0 °F 467.8 347.0 239.0 Table 40: Problem Table for Case 8 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 2.8 -911.7986 -2553.0361 demand 2 90 1390.0478 125104.3028 surplus 3 28 4258.1162 119227.2541 surplus 4 108 1956.2698 211277.1383 surplus 5 116 -911.7986 -105768.6389 demand 465 375 347 239 123 Table 41: Heat Cascade for Case 8 Infeasible Cascade ▼ 2553.036111 PINCH ▼ 125104.3028 ▼ 119227.2541 ▼ 211277.1383 ▼ Feasible Cascade 0 2553.036111 122551.2667 241778.5208 453055.6591 58 ▼ 2553.036111 2553.036111 ▼ 125104.3028 ▼ 119227.2541 ▼ 211277.1383 ▼ 0 125104.3028 244331.5569 455608.6952 105768.6389 ▼ 105768.6389 ▼ 347287.0202 349840.0564 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 100000 200000 300000 400000 500000 Net Heat Flow (Mbtu(IT)/hr) Figure 25: GCC for Case 8 7.4.8 Case 9 Table 42: Input Stream Data for Case 9 Stream Name Supply Temperature Target Temperature dT Min Contrib Mass Flowrate 1 2 3 °F 98 492 372 °F 442.8 372 264 °F 25 25 25 lb/h 10085320.000 3444390.000 9796785.000 Table 43: Calculated Stream Data for Case 9 Stream Name Heat Flow 1 2 3 MBtu(IT)/hr 314388.1611 271617.8775 390057.3038 Stream Type Supply Shift Target Shift COLD HOT HOT °F 123.0 467.0 347.0 °F 467.8 347.0 239.0 59 Enthalpy Change Btu(IT)/lb 202 511 258 Table 44: Problem Table for Case 9 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 0.8 -911.7986 -729.4389 demand 2 120 1351.6837 162202.0442 surplus 3 108 2699.8431 291583.0538 surplus 4 116 -911.7986 -105768.6389 demand 467 347 239 123 Table 45: Heat Cascade for Case 9 Infeasible Cascade ▼ 729.4388888 PINCH ▼ 162202.0442 ▼ 291583.0538 ▼ 105768.6389 ▼ Feasible Cascade ▼ 729.4388888 0 729.4388888 161472.6053 453055.6591 347287.0202 60 ▼ 162202.0442 ▼ 291583.0538 ▼ 105768.6389 ▼ 729.4388888 0 162202.0442 453785.098 348016.4591 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 100000 200000 300000 400000 500000 Net Heat Flow (Mbtu(IT)/hr) Figure 26: GCC for Case 9 7.4.9 Case 10 Table 46: Input Stream Data for Case 10 Stream Name Supply Temperature Target Temperature dT Min Contrib Mass Flowrate 1 2 3 4 5 6 7 °F 98 491 462 447 418 231 163 °F 442.8 480 450 430 410 200 158 °F 25 25 25 25 25 25 25 lb/h 10085320.000 2861744.000 3444389.000 3983700.000 4566511.000 675020.000 571554.000 Table 47: Calculated Stream Data for Case 10 Stream Name Heat Flow 1 2 3 4 5 6 7 MBtu(IT)/hr 314388.1611 152361.4185 92488.2524 105125.4499 102887.4717 98127.9384 81852.2036 Stream Type Supply Shift Target Shift COLD HOT HOT HOT HOT HOT HOT °F 123.0 466.0 437.0 422.0 393.0 206.0 138.0 °F 467.8 455.0 425.0 405.0 385.0 175.0 133.0 61 Enthalpy Change Btu(IT)/lb 202 345 174 171 146 942 928 Table 48: Problem Table for Case 10 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 1.8 -912 -1641 demand 2 11 12939 142332 surplus 3 18 -912 -16412 demand 4 12 6796 81547 surplus 5 3 -912 -2735 demand 6 17 5272 89625 surplus 7 12 -912 -10942 demand 8 8 11949 95593 surplus 9 179 -912 -163212 demand 10 31 2254 69862 surplus 11 37 -912 -33737 demand 12 5 15459 77293 surplus 13 10 -912 -9118 demand 466 455 437 425 422 405 393 385 206 175 138 133 123 62 Table 49: Heat Cascade for Case 10 Infeasible Cascade ▼ PINCH -1641 ▼ 142332 ▼ -16412 ▼ 81547 ▼ -2735 ▼ 89625 ▼ -10942 ▼ 95593 ▼ -163212 ▼ 69862 ▼ -33737 ▼ 77293 ▼ -9118 ▼ Feasible Cascade ▼ 0 -1641 140690 124278 205825 203089 292714 281773 377366 214154 284016 -1641 ▼ 142332 ▼ -16412 ▼ 81547 ▼ -2735 ▼ 89625 ▼ -10942 ▼ 95593 ▼ -163212 ▼ 69862 ▼ 327573 -33737 ▼ 77293 ▼ 318455 -9118 ▼ 250279 63 1641 0 142332 125919 207466 204731 294355 283414 379007 215795 285657 251921 329214 320096 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 50000 100000 150000 200000 250000 300000 350000 400000 Net Heat Flow (Mbtu(IT)/hr) Figure 27: GCC for Case 10 7.4.10 Case 11 Table 50: Input Stream Data for Case 11 Stream Name Supply Temperature Target Temperature dT Min Contrib Mass Flowrate 1 2 3 4 °F 98 491 462 446 °F 442.8 480 450 430 °F 25 25 25 25 lb/h 10085320.000 2861744.000 3444389.000 3983700.000 Table 51: Calculated Stream Data for Case 11 Stream Name Heat Flow 1 2 3 4 MBtu(IT)/hr 314388.1611 152361.4185 92488.2524 105125.4499 Stream Type Supply Shift Target Shift COLD HOT HOT HOT °F 123.0 466.0 437.0 421.0 °F 467.8 455.0 425.0 405.0 64 Enthalpy Change Btu(IT)/lb 202 345 174 171 Table 52: Problem Table for Case 11 Shift Temperature °F 467.8 Interval T(i+1)-Ti mCpnet dH °F MBtu(IT)/hr/°F MBtu(IT)/hr 1 1.8 -912 -1641 demand 2 11 12939 142332 surplus 3 18 -912 -16412 demand 4 12 6796 81547 surplus 5 4 -912 -3647 demand 6 16 5659 90537 surplus 7 282 -912 -257127 demand 466 455 437 425 421 405 123 Table 53: Heat Cascade for Case 11 Infeasible Cascade ▼ PINCH -1641 ▼ 142332 ▼ -16412 ▼ 81547 ▼ -3647 ▼ 90537 ▼ -257127 ▼ Feasible Cascade ▼ 0 -1641 140690 124278 205825 -1641 ▼ 142332 ▼ -16412 ▼ 81547 ▼ 292714 -3647 ▼ 90537 ▼ 35587 -257127 ▼ 202177 65 1641 0 142332 125919 207466 203819 294355 37228 Grand Composite 500 450 400 Shifted Temperature (ЎF) 350 300 250 200 150 100 50 0 0 50000 100000 150000 200000 250000 Net Heat Flow (Mbtu(IT)/hr) Figure 28: GCC for Case 11 66 300000 350000