July 12, 2016 Select Delivery Method Recipient

advertisement
July 12, 2016
Select Delivery Method
Recipient
Company
Address
Address
RE: WORK PROGRESS SCHEDULE – REJECTED
Fin No:
FAP No:
Contract No:
County:
Project Description:
Dear
:
The Work Progress Schedule that was submitted for the above referenced project has been
rejected by Name of Consulting Firm for the following reasons:
List Reasons Here
The above items must be corrected and submitted within fifteen (15) days of this notice.
If you have any questions or concerns, please contact PA's Name at (
)
.
Sincerely,
Name of Senior PE
Senior Project Engineer
cc: Scott Presson, P.E., Construction Services Manager
, Project Manager
, Project Administrator
File
Download