Connection Proposal Template Project Title AESO Project Number: Date: Role Click and type date Name Prepared: Reviewed: Approved: Version: Click and type version number Date Signature (Page intentionally blank) R[x] 2 Public R1-2016-05-01 Table of Contents EXECUTIVE SUMMARY SECTION ONE – CONNECTION STUDY SCOPE SECTION TWO – ENGINEERING STUDY REPORT SECTION THREE – FACILITY DESIGN SECTION FOUR – COST ESTIMATES SECTION FIVE – LAND IMPACT ASSESSMENT EXECUTIVE SUMMARY What to include in Executive Summary of a Connection Proposal: Provide the Project description including scheduled In-service date, a Rate STS, a Rate DTS. Describe all alternatives considered in the Stage 1 Connection Study Scope (CSS). Provide rationales what alternatives were initially screened out and was selected to perform studies. Describe the preferred alternative for the Project after studies, and the rationales. Include summary of estimated project cost for the preferred alternative. Include summary of land impact for the preferred alternative. SECTION ONE CONNECTION STUDY SCOPE Stage 1 Connection Study Scope [Insert Customer Name] [Insert Project Name] AESO Project Number: [000] Company Name Engineer Name P.Eng. Date Engineer Signature Date Signature [Studies Consultant] [AESO (Project Planning Engineer)] [TFO] Company Name Name [Insert Customer Name] Document Release [R1] [insert date] Table of Contents 1 PROJECT DESCRIPTION...................... ERROR! BOOKMARK NOT DEFINED. 1.1 Load Component .............................................................................. Error! Bookmark not defined. 1.2 Generation Component .................................................................... Error! Bookmark not defined. 2 STUDY AREA OVERVIEW..................... ERROR! BOOKMARK NOT DEFINED. 2.1 Existing Constraints ......................................................................... Error! Bookmark not defined. 2.2 AESO Long-Term Transmission Plans (LTP) .................................. Error! Bookmark not defined. 3 CONNECTION ALTERNATIVES ............ ERROR! BOOKMARK NOT DEFINED. 3.1 Connection Alternatives Identified ................................................... Error! Bookmark not defined. 3.2 Connection Alternatives Selected for Further Studies ..................... Error! Bookmark not defined. 3.3 Connection Alternatives Not Selected for Further Studies .............. Error! Bookmark not defined. 4 SCOPE OF STUDY ................................ ERROR! BOOKMARK NOT DEFINED. 4.1 Connection Studies to be Performed ............................................... Error! Bookmark not defined. 4.2 Connection Studies to be Excluded ................................................. Error! Bookmark not defined. 5 AESO STUDY REQUIREMENTS, CRITERIA, STANDARDS AND RULES ERROR! BOOKMARK NOT DEFINED. 5.1 Transmission Planning Standards and Reliability Criteria ............... Error! Bookmark not defined. 5.2 AESO Rules ..................................................................................... Error! Bookmark not defined. 5.3 Other Requirements ......................................................................... Error! Bookmark not defined. 6 STUDY ASSUMPTIONS AND MODELING ............. ERROR! BOOKMARK NOT DEFINED. 6.1 Study Scenarios ............................................................................... Error! Bookmark not defined. 6.2 Load Assumptions ............................................................................ Error! Bookmark not defined. 6.3 Generation Assumptions .................................................................. Error! Bookmark not defined. 6.4 Intertie Flow Assumptions ................................................................ Error! Bookmark not defined. 6.5 HVDC Line Flow Assumptions ......................................................... Error! Bookmark not defined. 6.6 Project Assumptions ........................................................................ Error! Bookmark not defined. 6.7 Additional Projects ........................................................................... Error! Bookmark not defined. 6.8 Facility Ratings ................................................................................. Error! Bookmark not defined. 6.9 Protection Fault Clearing Time ........................................................ Error! Bookmark not defined. 6.10 Dynamic Data ................................................................................... Error! Bookmark not defined. 6.11 Voltage Profile Assumption .............................................................. Error! Bookmark not defined. 6.12 Motor Starting Assumptions ............................................................. Error! Bookmark not defined. 6.13 Data Required for Sub-Synchronous Studies .................................. Error! Bookmark not defined. 7 7.1 STUDY METHODOLOGY ...................... ERROR! BOOKMARK NOT DEFINED. Connection Studies Carried Out ...................................................... Error! Bookmark not defined. 7.2 Load Flow Analysis .......................................................................... Error! Bookmark not defined. 7.2.1 Contingencies Studies ................................................................. Error! Bookmark not defined. 7.3 Voltage Stability Analysis ................................................................. Error! Bookmark not defined. 7.3.1 Contingencies Studies ................................................................. Error! Bookmark not defined. 7.4 Transient Stability Analysis .............................................................. Error! Bookmark not defined. 7.4.1 Contingencies Studies ................................................................. Error! Bookmark not defined. 7.5 Short Circuit Analysis ....................................................................... Error! Bookmark not defined. 7.6 Motor Starting Analysis [as required] ............................................... Error! Bookmark not defined. 7.7 Effectiveness Factor Analysis Studies [as required] ........................ Error! Bookmark not defined. 7.8 Sensitivity Studies [as required] ....................................................... Error! Bookmark not defined. 7.9 Sub-Synchronous Studies ............................................................... Error! Bookmark not defined. 7.10 Sub-Synchronous Torsional Interaction Study (SSTI) ..................... Error! Bookmark not defined. 7.11 Sub-Synchronous Resonance (SSR) and Sub-Synchronous Control Interaction (SSCI) Studies Error! Bookmark not defined. 7.12 Mitigation Measures ......................................................................... Error! Bookmark not defined. 8 ENGINEERING REPORT ....................... ERROR! BOOKMARK NOT DEFINED. 9 APPLICABILITY TERM ......................... ERROR! BOOKMARK NOT DEFINED. Page 2 Public R1-2016-05-01 10 KEY ENGINEERS ................................. ERROR! BOOKMARK NOT DEFINED. 11 REVISION HISTORY ............................. ERROR! BOOKMARK NOT DEFINED. Attachment A Transmission Reliability Standards and Criteria .................. Error! Bookmark not defined. Page 3 Public R1-2016-05-01 INSTRUCTIONS FOR USE Template not to be changed, do not add or delete sections o Place ‘N/A’ in sections that are not applicable. PURPOSE The purpose of the Stage 1 Connection Study Scope is to define the boundary of the study parameters. It also identifies the assumptions, basis and criteria to be used in the study and lists the steps to be taken in performing the study. Page 4 Public R1-2016-05-01 1 Project Description This section is compiled by the Market Participant and is to describe the following: • • • • Organization submitting SASR SASR request (load DTS, gen STS, transformer add, breaker add, new POD, …) and why needed (load growth, new load, new generator, DFO reliability – N-1, feeder loading, …) location Requested In-Service date [Market Participant Legal Name (Market Participant Short Name)] has submitted a System Access Service Request (SASR) to the Alberta Electric System Operator (AESO) for [Demand Transmission Service (DTS) and/or Supply Transmission Service (STS)] of [XXX] MW at [Project location, e.g., south of the City of Grande Prairie to serve oilfield loads] (the Project). The requested In-Service Date (ISD) for the Project is [Month, Day, Year of the In-Service date as per the SASR request]. 1.1 Load Component Describe the load component of the project. Include the following: • • • • • State existing Demand Transmission Service (DTS) if applicable. State the requested DTS to be connected along with the anticipated power factor; Describe the type of load; o Motor sizes if applicable o Motor starting methods (Across-the-line vs Variable Frequency Drive) State the magnitude of the potential DTS that the Market Participant intends to apply for; and Comment on possible future expansion plans and anticipated timing for such expansion. Below are two examples of the write up: [1. The requested load addition is 17.9 MW by August 17, 2016. 2. Load Type: Residential, rural, commercial, or light industrial services. 3. DTS contract capacity at South Mayerthorpe 443S to remain at the existing level of 12.5 MW. 4. Currently there is no plan for future expansion. 5. The load will be studied assuming at 0.9 power factor (pf) lagging.] or [Current Demand Transmission Service (DTS) is 14 MW. There would be four (4) 6600 HP motors with three (3) operating. All motors will have dedicated Variable Frequency Drives (VFDs). The requested Demand Transmission Service (DTS) is for 29 MW] 1.2 Generation Component Describe the generation component of the project. Include the following: Page 5 Public R1-2016-05-01 • • • • • • • State size of the generator(s) and estimated Maximum Authorized Real Power (MARP) and Maximum Capability (MC) levels;1 Describe type of generator(s); State estimated reactive power capability of the generator(s) when producing MARP. If this value does not meet the generation interconnection standard specify the intended supplemental strategy. If available, provide maximum capability curve based on pf/temperature. State the potential magnitude of the Supply Transmission Service (STS) that the Market Participant intends to apply for and operate at when connected to the grid; State the seasonal generator capacity (if information available); and State station service load if applicable. Comment on possible future expansion plans and anticipated timing for such expansion; Below is an example of the write up: [Market Participant (MP) plans to install a co-generation facility consisting of a single 85 MW (nominal) natural gas fuelled combustion turbine-generator. With the addition of this generator, the MP has requested an anticipated STS capacity of 85 MW. 1. Generators: Designation Type Model G1 Round Rotor GE 7A6 2. Supply Transmission Service (STS): 85 MW 3. Rated Nameplate Capacity: 93.9 MVA @ 0.85 pf, nominal 4. Maximum Authorized Real Power (MARP): 100 MW 5. Maximum Capability (MC): 85 MW 6. Reactive Power Capability (preliminary): 48 MVar (0.9 pf lagging) / 33 Mvar (0.95 pf leading) at MARP, 7. The customer advised that there is no future expansion planned.] 2 Study Area Overview This section is compiled by the AESO Planning Engineer. Define and describe the Study Area. Include a diagram of the Study Area that clearly shows salient features such as transmission lines, substations, generating assets, and reactive elements in the area. In a Single Line Diagram (the Study Area diagram) show how the Study Area is connected to the rest of the Alberta Interconnected Electric System (AIES). The Project is located in the AESO planning area of [AESO planning area, e.g., Grande Prairie (Area 20)], as part of [The AESO region, e.g., the AESO Northwest (NW) Region]. 1 Maximum Authorized Real Power (MARP) and Maximum Capability (MC) are defined in the Consolidated Authoritative Document Glossary posted on the AESO website: http://www.aeso.ca/downloads/Consolidated_Authoritative_Document_Glossary.pdf Page 6 Public R1-2016-05-01 This section will then describe the Study Area and the ‘Overview of existing system’. Please describe the Key substations/lines in the Project area and intertie connection with neighbouring areas. Below is an example of the write up: [The Study Area for the Project consisted of the Grande Cache (Area 22) and Grande Prairie (Area 20) areas, including the tie lines connecting the two planning areas to the rest of the AIES. All transmission facilities within the two planning areas will be studied and monitored for violations of the Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria). The five 144 kV transmission lines connecting the Grande Cache and Grande Prairie areas to the rest of the AIES (namely transmission lines 7L73, 7L32, 7L45, 7L46 and 7L40) will also be studied and monitored to identify any violations of the Reliability Criteria. The H.R. Milner generation facility, with connection to the H.R. Milner 740S substation, connects to the Alberta Interconnected Electric System (AIES) through two 144 kV transmission lines: one is transmission line 7L20, which connects the HR Milner 740S substation to the Big Mountain 845S substation in the Grande Prairie area; the other is transmission line 7L80, which connects the HR Milner 740S substation to the Simonette 733S substation, which further connects to the Little Smoky 813S substation in the Valleyview planning area (Area 23) via transmission line 7L40. Figure 1-1 shows the existing study area transmission system. Page 7 Public R1-2016-05-01 Figure 2-1: Existing Study Area Transmission System ] Page 8 Public R1-2016-05-01 2.1 Existing Constraints If applicable, describe any known constraint(s) in the Study Area. Explain how the constraint(s) are managed. Discuss any Information Documents (IDs)/Authoritative Documents (ADs) presently applied in the area. Outline relevant existing manual or automatic Remedial Action Schemes (RASs) in the Study Area. Below is an example of the write up: [The existing constraints in [AESO Region where the Project is located, e.g., the NW Region] are managed in accordance with Section 302.1 of the ISO rules, Real Time Transmission Constraint Management (TCM).] 2.2 AESO Long-Term Transmission Plans (LTP) Describe the relevant AESO long-term transmission development plans for the Study Area and its vicinity (either approved NID System Projects or developments identified in the AESO’s most recently published Long Term Plan). List the anticipated in-service dates of those plans. Use a table. Discuss the known impact(s) of any delays in the AESO Long-term Transmission Plans (LTP) for the area on the project. Please specify if the AESO LTP topologies are included in the study scenarios here. Below is an example of the write up: [The AESO Central East sub-region near-term developments are listed in Table 2.2-1. These developments are part of the AESO’s 2015 Long-Term Transmission Plan. These components will not be considered in service unless triggered by the project or study results dictate.] Table 2.2-1: Planned Central East Near-term Developments Description 3 Add voltage reinforcement at Strome substation east of Camrose, Irish Creek substation north of Kitscoty and Whitby Lake substation near Vilna Add new 240/144 kV substation near Vermilion Reconfigure 144 kV lines in vicinity of Vermilion to terminate at new substation Rebuild 144 kV line from Vermilion to Irish Creek to higher capacity Add new 240 kV line from Tinchebray substation northeast of Halkirk to new substation near Vermilion energized at 144 kV Add new 240 kV line from Hansman Lake substation southeast of Hughenden to Edgerton substation energized at 144 kV Connection Alternatives This section is compiled by the Market Participant and Studies Consultant in collaboration with the AESO Planning Engineer. Other alternatives may be identified, considered and evaluated if the connection study results indicate the initially proposed connection alternatives may cause potential adverse impact to the system, violations of the AESO Reliability Criteria remain or where other unanticipated issues (such as connection cost and schedule) arise following the execution of the study. Any such additional connection alternatives to the preliminary set of alternatives described shall be documented in a signed Scope Amendment document. Page 9 Public R1-2016-05-01 3.1 Connection Alternatives Identified Describe each connection alternative separately with associated single-line diagrams. For each alternative, provide single-line diagrams (SLDs) for the proposed facilities. Below is an example of the write up: [Four alternatives were examined in this report. A description of the developments associated with each alternative is provided below. Alternative 1: Add a new point of delivery (POD) substation, and connect the new POD to the existing [Voltage Class, e.g. 138 kV] transmission line [Line name] via an in/out connection configuration. Alternative 2: Add a new point of delivery (POD) substation, and connect the new POD to the existing [Voltage Class, e.g. 138 kV] transmission line [Line name] via a Ttap connection configuration. Alternative 3: Add a new point of delivery (POD) substation, and connect the new POD to the existing [Voltage Class, e.g. 138 kV] transmission line [Line name] via a radial connection configuration to the existing [substation name and number]. Alternative 4: Upgrade the capacity at the existing [Substation Name and number] substation and shift load to neighboring [Substation Name and number] substation. The line length of each alternative will be subject to change after line routing by TFO. ] 3.2 Connection Alternatives Selected for Further Studies Please address which Alternatives are selected for this Project. Below is an example of the write up: [Alternative 1 and Alternative 2 were selected for further study.] 3.3 Connection Alternatives Not Selected for Further Studies Please state the rationale for ruling out the Alternatives. If available, Refer to the DFO’s Distribution Deficiency Report (DDR) Address Market Participant (MP)’s preference (including cost estimates) Specify Transmission Facility Owners (TFOs)’s position on any possible limitation/constraints that would result in ruling out a specific alternative. Below is an example of the write up: [Both Alternative 3 and Alternative 4 would require greater transmission development and were not selected for further studies. Alternative 3: In addition to adding a new POD and converting the existing T-tap connection configuration of Dome Cutbank 810S to an in/out connection configuration, ATCO has advised that Alternative 3 involves reconfiguring or modifying equipment and the 25 kV and 144 kV busses, and mitigation of substation outages. ATCO has also advised that the existing Dome Cutbank 810S substation is constrained on all sides. Therefore, Alternative 3 involves relocating the Dome Cutbank 810S substation to a new greenfield site to accommodate the transmission developments. Page 10 Public R1-2016-05-01 Alternative 4: Alternative 4 involves upgrading the existing Dome Cutbank 810S substation, including either (i) adding two 144 kV breakers and replacing the two existing 144/25 kV 10/13 MVA transformers and one voltage regulator with two 144/25 kV transformers of a higher capacity, or (ii) adding one 144 kV breaker and a 144/25 kV 30/40/50 MVA LTC transformer. ATCO has advised that Alternative 4 also involves reconfiguring or modifying equipment and the 25 kV and 144 kV busses, and mitigation of substation outages. As with Alternative 3, this transmission alternative involves relocating the Dome Cutbank 810S substation to a new greenfield site to accommodate the transmission developments.] 4 Scope of Study This section is compiled by the AESO Planning Engineer. Define the Study Area (i.e. the AESO Planning areas) that will be monitored when performing the connection studies. Describe the scope of engineering studies including the study scenarios the Market Participant intends to complete to produce the connection proposal and the objectives of performing such studies. 4.1 Connection Studies to be Performed Below is an example. Please update or delete the bullets that are not relevant to the Project: [Outline all studies that the Market Participant is required to complete for assessing the connection proposal, such as: Load flow analysis (Category A, Category B, and selected Category C5), pre-Project and post-Project conditions Voltage stability analysis (Category A, Category B, and selected Category C5), postProject conditions Transient stability analysis (Category B, and selected Category C5), post-Project conditions Motor starting analysis, post-Project conditions Short-Circuit fault studies, pre-Project and post-Project conditions In cases where transmission congestion is identified through the connection studies conducted, the AESO will provide further direction on additional studies to identify mitigation measures for congestion management under system normal (N-0) and abnormal conditions (N-1). Other studies deemed necessary to assess transmission system performance such as large motor starting studies, Sub-Synchronous Torsional Interaction2 (SSTI) studies, 2 Thermal Turbine-Generator units, particularly steam driven units, in the vicinity of HVDC Transmission systems can be vulnerable to sub-synchronous (below 60 Hz) torsional oscillations. For this reason, special studies and analysis need to be carried out by an expert in the area of SSTI, to examine if and when undesirable interactions would occur between the HVDC Transmission system and the proposed Turbine-Generating units. Proposed protection and/or operational procedures will accordingly be developed based on study results. Page 11 Public R1-2016-05-01 Sub-Synchronous Resonance3 (SSR) studies when the customer facility might have potential of sub-synchronous interaction. ] 4.2 Connection Studies to be Excluded Outline studies excluded from Section 4.1 See below for an example: [The following studies were not performed in the connection study: 5 Load flow analysis (Category C) Voltage stability analysis (Category C) Transient stability analysis ( Category C)] AESO Study Requirements, Criteria, Standards and Rules This part is compiled by the AESO Planning Engineer. 5.1 Transmission Planning Standards and Reliability Criteria The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria)4 were applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B contingencies (i.e., single element outage) and selected Category C5 contingencies (i.e., double circuit common tower contingency), prior to and following the studied alternatives. Below is a summary of Category A and Category B system conditions as well as a summary of Category C5 system conditions. [NOTE: If Category C5 contingency assessment is not required, remove the reference to Category C5] Category A, often referred to as the N-0 condition, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of service, result in the loss of any single specified system element under specified fault conditions with normal clearing. These elements are a generator, a transmission circuit, a transformer, or a 3 Potential Sub-Synchronous Resonance of the Turbine-Generator shaft system in the vicinity of Series Capacitor Compensated Lines needs to be identified early during the connection planning process. For this reason special studies and analysis, need to be carried out by an expert in the area of SSR, to examine if and when undesirable interactions would occur between the Series Capacitor Compensated lines and the proposed Turbine-Generating units. Proposed protection and operational considerations and/or procedures will accordingly be developed based on study results. Wind farms electrically close to the HVDC terminals or series capacitors will also require sub-synchronous control interaction (SSCI) studies. 4 Please refer to Attachment A Page 12 Public R1-2016-05-01 single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers. Category C5 events [NOTE: Category C wording may need to be adjusted on a project-byproject basis] results in loss of two circuits of a multiple circuit tower. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. For Category C5, the controlled interruption of electric supply to customers (load shedding), the planned removal from service of certain generators, and/or the curtailment of contracted firm (non-recallable reserved) transmission service electric power transfers may be necessary to maintain the overall reliability of the interconnected transmission systems. The Alberta Reliability Standards include the Transmission Planning (TPL) standards that specify the desired system performance under different contingency categories with respect to the Applicable Ratings. The transmission system performance under various system conditions is defined in Appendix 1 of the TPL standards. For the purpose of applying the TPL standards to this study, the Applicable Ratings shall mean: Seasonal continuous thermal rating of the line’s loading limits. Highest specified loading limits for transformers. For Category A conditions: Voltage range under normal operating condition should follow the AESO Information Document ID# 2010-007RS. For the busses not listed in ID#2010-007RS, Table 2-1 in the Reliability Criteria applies. For Category B and Category C5 conditions: The extreme voltage range values per Table 2-1 in the Reliability Criteria. [NOTE: If Category C contingency assessment is not required, remove the reference to Category C5] Desired post-contingency voltage change limits for three defined post event timeframes as provided in Table 5.1-1. Table 5.1-1: Post Contingency Voltage Deviation Guidelines Time Period Parameter and reference point Post Transient (up to 30 sec) Post Auto Control (30 sec to 5 min) Post Manual Control (Steady State) Voltage deviation from steady state at POD low voltage bus. ±10% ±7% ±5% 5.2 AESO Rules The AESO Voltage Control Practice ID # 2010-007RS will be applied to establish precontingency voltage profiles in the Study Area. The Transmission Congestion Management (TCM) Rule will be followed in setting up the study scenarios and assessment of the impact of the Project connection. In addition, due regard will be given to the AESO Customer Connection Study Requirements Document and the Generation and Load Interconnection Standard. Page 13 Public R1-2016-05-01 The Reliability Criteria is the basis for planning the AIES. The transmission system will normally be designed to meet or exceed the Reliability Criteria under credible worst-case loading and generation conditions. 5.3 Other Requirements Other AESO requirements to be applied when performing connection studies are outlined below: if applicable Describe in detail the application of any other AESO requirements, criteria, standards, rules, practices, and guidelines (market or otherwise) when the connection studies were carried out. Use subsection headings that clearly identify the requirement being discussed or add another bullet. 6 Study Assumptions and Modeling This part is compiled by the AESO Planning Engineer. The study will be conducted on the AIES system model using the AESO’s Planning Base Case Suite. The 20XX Summer Light/Peak and Winter Peak study scenarios (for near-term assessment [based on the proposed in service date]) will be studied as required. The 20YY Winter Peak (20YY WP) will be used to determine the future post-project short circuit. The base cases will be provided by AESO. In addition, incremental dispatch IDEVs may be provided by the AESO to adjust the load and generation dispatch in the base cases to a closer starting point for the required studies. Manual adjustments may be required to ensure full alignment with the details outlined in this scope, as described in the process outlined below. The AESO will provide guidance to the Market Participant’s consultant with regard to the setup of the study cases should any questions arise. The expected process for the creation of acceptable study cases is as follows: The consultant will request base cases from AESO. The AESO will provide guidance regarding the appropriate incremental IDEVs to use and any other application information required to the consultant. The consultant will request the appropriate incremental IDEVs (as determined by the AESO) or the AESO will provide alternate IDEVs. Project removal IDEVs, should they be required, will be the responsibility of the consultant. The consultant will apply the identified IDEVs to the cases, and verify the cases are consistent with the assumptions outlined within this scope document including area/region loads, generator dispatch, intertie assumptions and system/customer connection projects. The consultant will make adjustments as required to ensure the cases represent these scoped assumptions correctly. If the IDEVs do not work, or result in cases that do not solve, the AESO will support the consultant in resolving issues including providing corrected IDEV files. Once power flow cases are created to the consultant’s satisfaction, all cases will be forwarded to the AESO for approval. The AESO will provide a list of required corrections, or IDEV scripts, as required, or will give the go-ahead to proceed with power flow analysis Page 14 Public R1-2016-05-01 6.1 Study Scenarios [The 20XX/20YY study cases shall represent the Project conditions as outlined in Table 6.1-1. Load and generation conditions have been chosen as they represent the most reasonable stressed conditions to assess the Project connection. For this study, the Study Area is defined in Section 4 of the Study Scope.] Table 6.1-1: Project Study Cases – Example Condition Project Load (MW) Project Generation (MW) 2016 SP Pre-Project 0 0 2 2016 WP Pre-Project 0 0 3 2016 SP Post-Project 20 0 4 2016 WP Post-Project 20 0 Scenario Year/Season Load 1 System Generation Dispatch Conditions High Wind, High Import High Wind, High Import Outline all scenarios (i.e. system conditions) the Market Participant must consider for the Connection Studies. System conditions may include the following: Low and high loading levels; Low and high generation levels; and If necessary, include major study assumptions for the study cases: transmission system operating levels for major paths such as South of KEG (SOK), Fort McMurray transfer in and out, and other relevant system operating levels. If requires, provide rationales why the conditions are the credible and stressed scenarios for this Project. 6.2 Load Assumptions This section is compiled by the AESO Planning Engineer in collaboration with the AESO Forecasting. This section should be re-confirmed by AESO Forecasting before a Study Scope is signed off. An updated System Access Service Request (SASR) from the MP was provided during the development of study scope (Stage 1), PSAS Planning Engineer should forward the SASR to AESO forecasting. Table 6.2-1 presents the load conditions and assumptions to be used in the connection studies. The coincident load forecast is the AESO 20ZZ Long Term Outlook (LTO) at (Area, Region or AIL) coincident peak. In this study the active power to reactive power ratio in the Base Cases will be maintained when modifying the loads. Table 6.2-1: Forecast Peak/Light Load (MW) - Example Forecast Peak Load (MW) Substation, Area or Region Name and Season 2016 2018 SP Central WP Page 15 Public R1-2016-05-01 Substation, Area or Region Name and Season Forecast Peak Load (MW) 2016 2018 SL SP South* WP SL SP AIL w/o Losses WP SL *Define used Areas/Regions as required. Note: Scaling loads on the region or area should be done with Table 6.2-1. IDEV files contain non-motor loads in zones 34, 36, and 351. These loads are not accounted for in the forecasted peak loads shown above and should not be considered when scaling load. AESO Planning Engineer will provide guidance to load scaling procedures as required. 6.3 Generation Assumptions This section is compiled by the AESO Planning Engineer in collaboration with AESO Forecasting. This section should be re-confirmed by AESO Forecasting before Study Scope is signed off. An updated System Access Service Request (SASR) from the MP was provided during the development of study scope (Stage 1), PSAS Planning Engineer should forward the SASR to AESO forecasting. Describe the generation assumptions (including N-G) and the AESO forecast applied (e.g., 2014LTO). Present existing and future units for consideration in the project studies (local generators) and the dispatch level of each. Describe the notable features of the local generators, as required. Below is an example of the write up: The existing and proposed generators and their dispatch levels in the Study Area are listed in Table 6.3-1, Table 6.3-2, and Table 6.3-3 below (Depending on the study, there may be one, two or three tables). For Wind Aggregated Generating Facility (WAGF) connection studies or where Wind dispatch assumptions are influential to the study (include if required); The wind dispatch level will include all existing and under construction wind generation facilities dispatched as described in Table 6.3-2. Remaining forecast wind growth can be allocated to projects in the Southern or Central Alberta region as identified in Table 6.3-3 to stress the local transmission network. Any remaining wind generation will be distributed proportionally throughout Southern, Central or other region in Alberta based on projects. An incremental dispatch IDEV may be provided by the AESO to adjust the generation dispatch in the Base Case to a closer starting point for the study conditions listed below. However, further adjustments could be required to reach alignment with the details listed in Table 6.3-1 to Table 6.3-3. Guidance on further generation re-dispatch of the Alberta system will be provided if necessary. All the remaining generators will be dispatched based on an economic merit order as in the dispatch IDEV unless otherwise required and described by this scope document. Page 16 Public R1-2016-05-01 Existing/ Future Existing Future Unit Name Table 6.3-1: Summary of Local Non-wind Generation 20xx 20xx 20xx 20yy SL SP WP SL Unit Unit Unit Unit Bus Pmax Area net net net net Number (MW) Gener- Gener- Gener- Generation5 ation ation ation (MW) (MW) (MW) (MW) Gen A … … … Gen B #29 … … … Gen C … … … Gen D … … … Gen E … … … 20yy SP Unit net Gener -ation (MW) 20yy WP Unit net Generation (MW) Total Table 6.3-2: Summary of Existing and Under Construction Wind Farms in Alberta (For Wind Studies or where Wind is important to the study (include if required)) Plant Name Planning Area Bus Number in the Base Cases Unit net Generation Output (MW) 20xx Unit net Generation Output (MW) 20yy Existing Southern Alberta … … Total Under construction South Total Subtotal South Existing central … … Total Under Construction Central Total Subtotal Central Total Alberta 5 Unit net Generation refers to Gross Generating unit MW output less Unit Service Load. Page 17 Public R1-2016-05-01 Table 6.3-3: Southern/Central Alberta future Wind Projects (Past Gate 2) - Example (For Wind Studies or where Wind is important to the study (include if required)) Project Modeling Plant Name No. Alberta Wind Energy Old Man River Wind Farm Pteragen Peace Butte 116 MW Wind Farm 519 513 ISD Area Busses 53 61543 4 2294, 4294 Oct, 2013 Jan, 2014 Dispatch (MW) PMax (MW) 20xx 20yy … Total 6.4 Intertie Flow Assumptions Indicate the assumptions regarding the intertie flow between Alberta and neighbouring jurisdictions. If Intertie flow is not a key assumption in a Connection project, please discard this section. Below are examples of the write up: [Intertie assumptions are included for the B.C., MATL, and Saskatchewan interties. Details on the assumptions can be found in Table 6.4-1.] or [The intertie points are deemed to be too far away to have an effect on the assessment of the proposed connection. The flows in the Study Area are not influenced by the AIES HVDC facilities. As a result, the intertie and HVDC assumptions are kept consistent with that in the AESO planning base cases and not adjusted for this study.] Table 6.4-1: Intertie Assumptions6 Intertie Case No. 1 2 3 4 5 Year / Condition 2016SL (Pre-Project) 2016SP (Pre- Project) 2016WP (Pre- Project) 2016SL (Post- Project) 2016SP (Post-Project) Import (+) /Export (-) to BC Import (+) /Export (-) to Saskatchewan Import (+) /Export (-) to MATL -800 -150 0 480 150 300 480 150 300 -800 -150 0 480 150 300 6 Intertie assumption shall meet the AESO Available Transfer Capability and Transfer Path Management ID#2011-001R Page 18 Public R1-2016-05-01 Intertie Case No. Year / Condition 2016WP (Post-Project) 2018SL (Post-Project) 2018SP (Post- Project) 2018WP (Post- Project) 6 7 8 9 6.5 Import (+) /Export (-) to BC Import (+) /Export (-) to Saskatchewan Import (+) /Export (-) to MATL 480 150 300 -800 -150 0 480 150 300 480 150 300 HVDC Line Flow Assumptions This section is completed by the AESO Planning Engineer. The influence of the HVDC to this study should be identified here. In general, the majority of connections to the AIES will not require adjustment to the planned power flow order levels for the WATL and EATL HVDC links during studies. For major projects and where the scoped study scenarios require adjustments to the pre-set HVDC flow level provided by the AESO in the Base Cases, the AESO Planning Engineer will provide guidance as to the new flow settings and associated VAR adjustments as required. Table 6.5-1: HVDC Power Order by Scenario 6.6 Case No Scenario WATL (MW) EATL (MW) 1 2016SL (Pre- Project) 475 N S Blocked 2 2016SP (Pre- Project) 250 S N 450 S N 3 2016WP (Pre- Project) 475 N S Blocked Project Assumptions This section is compiled by the AESO Planning Engineer. Include any Market Participant and transmission projects that are not already in service but are included in the AESO Base Cases or will be included in the study cases; use a suitable table format with all details shown where possible. Table 6.6-1: Summary of System Project Assumptions for Connection Studies Project Subproject Subproject Name In-Service Date P850 South and West Edmonton 1 Harry Smith Sub 2 New Saunders Lake 240/138kV Substation; re-terminate 910L, 914L, 780L & 858L at Saunders Lake; build lines between Nisku & proposed Saunders Lake; and reconfiguration of September 2017 Page 19 Public R1-2016-05-01 Project Subproject Subproject Name Reinforce ment In-Service Date affected substations. 3 New 138kV Lines from 780L to Cooking Lake & 174L; and reconfiguration of affected substations 4 133L from Wabamun to 234L tap 5 New Capacitor Bank at Leduc 325S All Market Participant projects within the study area and past Gate 2 of the Connection process must be included in the study cases. Table 6.6-2: Summary of Connection Project Assumptions for the Connection Studies (All Market Participant Projects Past Gate 2) Planning Area Queue Position* 53 54 54 19 55 Energize d 55 57 6.7 Planned In-Service Date Jul. 2017 Apr. 2016 Oct. 2014 Feb. 2017 Project Name Project # Gen (MW) Load (MW) Included/Excluded from Studies RESL McLaughlin WAGF 1500 47.0 1.0 Included Lethbridge Chinook NW POD 1260 0 30.0 Included Fortis Spring Coulee Upgrade 1338 0 2.0 Included BowArk Energy Drywood Power Gas Plant 1522 18.6 1.0 Excluded Additional Projects This section is compiled by the AESO Planning Engineer and Market Participant or Studies Consultant. Include all Market Participant planned facilities that are not passed through gate 2 but will be included in the study cases; use a suitable table format with all details shown where possible. The AESO, Market Participant and Studies Consultant may add any projects that have not passed through Gate 2 of the Connection Process to account for project development uncertainty and development of sensitivity study scenarios. Table 6.7-1: Summary of selected projects for inclusion in the study case (Market Participant projects behind Gate 2) Planned InService Date Project Name Project # Gen (MW) Load (MW) Included/Excluded from Studies RESL McLaughlin WAGF 1500 47.0 1.0 Included Lethbridge Chinook NW POD 1260 0 30.0 Included Oct. 2014 Fortis Spring Coulee Upgrade 1338 0 2.0 Included Feb. 2017 BowArk Energy Drywood Power Gas Plant 1522 18.6 1.0 Excluded Jul. 2017 Apr. 2016 Page 20 Public R1-2016-05-01 6.8 Facility Ratings This section is compiled by the AESO Planning Engineer. The TFO will verify the ratings and provide any updates/corrections to the facility ratings as required. Include suitable tables to show facility ratings for relevant equipment at voltage levels of 69 kV and above (existing and new) in the study region. [The Transmission Facility Owner (TFO) provided the ratings of the existing transmission lines (Table 6.8-1), the existing transformers (Table 6.8-2), and the existing shunt elements (Table 6.8-3) in the Study Area.] Table 6.8-1: Summary of Transmission Line Ratings in The Study Area (at 138 kV base) Short-term7 Rating (MVA) Nominal Rating (MVA) Line ID Line Description Voltage Class (kV) Summer Winter Summer Winter 7L84 Flyingshot 749S – Crystal 722S 138 142.8 142.8 180 181 7L03 Flyingshot 749S – Elmworth 731S 138 109.3 139 123.6 150.5 7L68 Clairmont Lake 811S – Rycroft 730S 138 94.9 CT8 94.9 CT 94.9 CT 94.9 CT Table 6.8-2: Summary of Transformer Ratings in The Study Area Substation Name and Number Transformer ID Transformer Voltages (kV) MVA Rating Battle River 757S 912T 240/144 224 Battle River 757S 701T 144/72 75 Nevis 766S 901T 240/144 100 144/72/25 H-M: 33.3 X-M: 33.3 Y-M: 16.6 Nevis 766S 701T Table 6.8-3: Summary of Shunt Elements in The Study Area (at 138 kV base) Capacitors Substation Name and Number Nominal Bus Voltage (kV) Hardisty 377S 138 Tucuman 478S 138 Hill 751S 138 Number of Switched Shunt Blocks 1 x 27 MVAr 1 x 44.9 MVAr 1 x 27.17 MVAr 1 x 20 MVAr Total at Nominal Voltage (MVAr) Reactors Status in Study (on or off) Number of Switched Shunt Blocks 2017S P 2017 WP (MVAr) (MVAr) 71.9 27 (on) 27 (on) - 27.17 (off) (off) 45 45 45 Total at Nominal Voltage (MVAr) Status in Study (on or off) 2017 SP 2017 WP (MVAr) (MVAr) - - - - - - - - - - - 7 When line loading in post Category B contingency is observed to exceed nominal rating and is less than the Short-term rating, it is assumed that AESO and TFO operating practices can manage the constraint within the time requirements of TFO short time rating. 8 The limitation factor for the line rating is due to a current transformer. Page 21 Public R1-2016-05-01 Capacitors Nominal Bus Voltage (kV) Substation Name and Number Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) 1 x 25 MVAr 6.9 Reactors Status in Study (on or off) 2017S P 2017 WP (MVAr) (MVAr) (both on) (both on) Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Status in Study (on or off) 2017 SP 2017 WP (MVAr) (MVAr) Protection Fault Clearing Time This section is compiled by the AESO Planning Engineer. The TFO will verify the ratings and provide any updates/corrections to the facility ratings as required. List the fault clearing times used for the transient stability analysis. Use a table. When providing near-end and far-end fault clearing times, include different directions with the clearing times only when the clearing times are not the same for faults at each end. Indicate if the fault clearing time assumptions have been verified by the Transmission Facility Owner (TFO). Below is an example of the write up: [Fault clearing times for existing facilities are provided by TFO and are listed in Table 6.9-1.] Table 6.9-1: Stated Protection Fault Clearing Times Terminal Location Line 9Lxx Nominal Bus Voltage (kV) 240 Terminal 1 SUB 1S Terminal 2 SUB 2S Total Clearing Time Terminal 3 SUB 3S Faulted Location State if it is calculated (actual) or estimated (generic) Faulted Location Terminal 1 Terminal 2 Terminal 3 SUB 1S 6 7 8 actual SUB 2S 6 7 8 generic SUB 3S 6 7 9 generic 6.10 Dynamic Data This section is compiled by the AESO Planning Engineer. Dynamic data will be referred to Stage 1 PDUP if available. Otherwise, the dynamic data will be specified here. Motor composition information will be specified in this Section. Below is an example of the write up: [Dynamic data for the Project is based on the submitted Stage 1 Project Data Update Package (PDUP-1). Motor composition information is provided in Table 6.10-1.] Table 6.10-1: Transient Stability Analysis Load Representation Planning Areas % of load specified as Large Motors Page 22 % of load specified as Small Motors The Remainder of the Load (excluding Motor loads) Active Power Reactive Power Public R1-2016-05-01 Constant Current Constant Impedance Areas in NW and NE regions 40% 30% 100% 100% Areas in other regions 10% 10% 100% 100% 6.11 Voltage Profile Assumption This section is checked by the AESO Planning Engineer. Please keep the following description unless any change is required. The AESO Planning Engineer will verify the Voltage Profile Assumptions and provide updates/correction corresponding to planned upgrades when required. The AESO Voltage Control Practice ID # 2010-007RS9 is used to establish normal system (i.e., pre-contingency) voltage profiles for key area busses prior to commencing any studies. Table 21 of the Reliability Criteria applies for all the busses not included in the ID 2010-007RS. These voltages will be utilized to set the voltage profile for the study base cases prior to load flow analysis. Table 6.11-1: Summary of voltage at key nodes in the study region Nominal Minimum Desired Maximum Substation Voltage Operating Range Operating (kV) Limit (kV) (kV) Limit (kV) Substation C (xxxS) 240 216 234-252 264 6.12 Motor Starting Assumptions The section is to evaluate the potential impacts of motor starting operation on the surrounding system. The customer must provide details of study assumptions (including how frequent the motor starts and then find the voltage dip percentage for different voltage levels), motor model, and software used to perform the studies. Also the type of motor starting equipment and/or starting methodology that would be implemented must be specified. If motor starting analysis is no longer required, remove the subsection – The example below assumes that VFD will be installed with across the line staring capability as backup. If the Market Participant confirms that the motors in the Project will not start motors across the line, Motor starting analysis is no longer required. Below is an example of the write up for motor starting assumption portion: [The following assumptions were used in conducting motor starting analysis: The transient voltage dip at the 138 kV transmission bus should not exceed 5% when starting a single motor. 9Available at http://www.aeso.ca/downloads/Version_for_posting_June_1_2015_under_blanket_approval.pdf Page 23 Public R1-2016-05-01 The motors will not start simultaneously. Only one motor will be allowed to start in VFD bypass mode while the other motors are running at full load.] 6.13 Data Required for Sub-Synchronous Studies This data will only be required if the initial screening studies identify the need for detailed analyses of sub-synchronous torsional interaction (SSTI) with HVDC facilities or subsynchronous resonance (SSR) with serious capacitor compensated transmission lines. Also control interaction between certain types of Wind Turbines (e.g.Type 3) and series capacitance as well as with HVDC, may require special studies known as Sub-Synchronous Interaction (SSCI). In this case detailed Wind Turbine modes and the associated controls are required. Section 7.9 describes the methodology developed by the AESO and the TFOs to carry out the screening studies as well as the detailed sub-synchronous as required. Table 6.13-1 and Table 6.13-2 list the data required for steam driven turbine-generator(s). Although gas driven generating unit(s) are not as vulnerable to sub-synchronous phenomena as steam driven units, data should also be obtained for these units to ensure that no adverse sub-synchronous interaction/resonance will be overlooked. Table 6.13-1: Required Data for Turbine-Generator Shaft System Basic Requirements Data Number of poles of the Generator Mechanical frequencies as calculated by the manufacturer Table 6.13-2: Torsional Data for the Turbine-Generator Shaft System Mass No. Rotor Steam Moment Stiffness Damping Damping section Fraction S of constants Constant Constant (Min Load) (Max Load) Dmin Dmax [p.u.] Inertia J K [lb.ft²] [lb.ft/rad] [N.m.s/rad] [N.m.s/rad] Or Or Or Or [kg.m²] [N.m/rad] [lb.ft.s/rad] [lb.ft.s/rad] 1 2 i Generator N/A n Page 24 Public R1-2016-05-01 7 Study Methodology This section is compiled by the AESO Planning Engineer in collaboration with the Consultant. The following sections provide additional details on study requirements and methodology. However, they are not meant to provide an exhaustive list. For additional guidance the studies consultant may refer to the AESO Market Participant Connection Study Requirements Document. The studies consultant will consult with the AESO on a regular basis and in particular at key steps in the course of the study. Such key steps may include completion of the study case build-up, contingency analysis file preparation, completion of the existing system studies, and completion of alternative evaluation. The applicable requirement will be based on known system constraints and existing operating limitations in the study region. There might be conditions where system configuration in the long term may impose new operating limits. Adjustments are expected to be made in coordination with the AESO Planning Engineer. In case where transmission congestion is identified through the connection studies, the AESO will provide further direction on additional studies on identifying the mitigation measure for congestion management, under system normal (N-0) and abnormal conditions (N-1). Details of the mitigation measures are covered in Section 7.10. For each type of study explain the study methodology to be used in the following subsections. Describe potential sensitivity tests the Market Participant will have to consider in addition to the given scenarios. Identify if there is any variation of the given scenarios when performing the sensitivity studies. Make sure to state the software that will be utilized to perform each study. 7.1 Connection Studies Carried Out The studies to be carried out for the connection study area identified in Table 7.1-1. Please delete the rows that are not applicable to the Project. Table 7.1-1: Summary of Studies Performed Project 1234 Scenario and Condition Load (MW) Generation (MW) System Conditions Load Flow10 1 2016 SP Pre-project 0 0 Category A and Category B X 2 2016 WP Pre-Project 0 0 Category A and Category B X 3 2016 SP Post-Project 20 0 Category A and Category B X 4 2016 WP Post-Project 20 0 Category A and Category B X 7.2 Voltage Stability9 Transient Stability9 Motor Starting9 11 X X X Load Flow Analysis The critical generator identified for this study will be [Name N-G unit, e.g., the H.R. Milner unit]. Only Category A - all generators online in the study area. Page 25 11 X Explain the objective of the Load flow studies. Describe the methodology used for the power flow analysis: for example, studies will be performed for pre-connection and post-connection (all alternatives), 10 Shortcircuit Public R1-2016-05-01 X which scenarios will be studied from the list in Section 7, how the studies will be run (such as for 10% voltage deviation the transformer taps and adjustable shunts will be locked), the assumed power factor, and any other relevant information. Include the monitored quantities, such as thermal loading, or voltage magnitude pre and post contingency. State the software that will be utilized to perform the studies. Outline a list of outages to be studied in the power flow and voltage stability analysis for each scenario in a suitable table format where possible. For a very large contingency list, grouping the list is recommended, such as outage of all 138kV and above transmission lines in the study region. All line flows of power flow analysis are reported as percentage loading relative to line rating converted to current (amperes) The transmission lines in the study area whose thermal loading in post contingency, is above 90% of its seasonal continuous ratings, should be reported in the table listing study results of the steady state power flow. The PSSE Powerflow diagrams should be attached in Attachment of Engineering Study Report (ESR) including contingencies of Category A, all the Category B, and selected Category C5 unless otherwise the AESO advises Below is an example of the write up: [Load flow analysis will be completed for all study scenarios to identify any thermal or transmission voltage violations as per the Reliability Criteria. Transformer tap and switched shunt reactive compensation devices such as shunt capacitors and reactors will be locked and continuous shunt devices will be enabled when performing Category B load flow analysis. POD low voltage bus deviations will also be assessed by first locking all tap changers and area capacitors to identify any post-transient voltage deviations above 10%. Tap changers will then be allowed to adjust, while shunt reactive compensating devices remained locked; to determine if any voltage deviations above 7% would occur in the area. Once all taps and shunt reactive compensating devices have been adjusted, voltage deviations above 5% will be reported, for both the pre-Project and post-Project networks.] 7.2.1 Contingencies Studies Below are examples of the write up: [Load flow analysis will be performed for the Category A condition and all Category B contingencies in [the Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios.] Or [All contingencies of lines and transformers in the study area must be simulated based on actual fault isolation points for the equipment whose contingency is under study. Table 7.2-1: Transmission Line Outages (Contingencies) System Condition Outage From Substation To Substation Typical with all elements in service, N-0 Transmission line A Example A 1S Example B 2S N - Generator 1 Transmission line B Example C 3S Example D 4S Page 26 Public R1-2016-05-01 System Condition Outage From Substation To Substation Table 7.2-2: Transmission Equipment Outages (Contingencies) System Condition Outage Substation Typical with all elements in service, N-0 Generator 1 Example A 1S N - Generator 1 Transform er Tx Example A 1S ] 7.3 Voltage Stability Analysis If this analysis is not required, please remove the subsection. The objective of the Power-Voltage (PV) curve is to determine the ability of the network to maintain voltage stability at all the busses in the system under normal and abnormal system conditions. The PV curve is a representation of voltage change as a result of increased power transfer between two systems. The reported incremental transfers will be to the collapse point. As per the AESO requirements, no assessment based upon other criteria such as minimum voltage will be made at the PV minimum transfer. Voltage stability analysis for post-connection scenarios will be performed. For load connection projects, the load level modelled in postconnection scenarios are the same or higher than in pre-connection scenarios. Therefore, voltage stability analysis for pre-connection scenarios will only be performed if post-Project scenarios show voltage stability criteria violations. Voltage stability (PV) analysis will be performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology. The voltage stability criteria states, for load areas, post-transient voltage stability is required for the area modeled at a minimum of 105% of the reference load level for system normal conditions (Category A) and for single contingencies (Category B). For this standard, the reference load level is the maximum established planned load. Typically, voltage stability analysis is carried out assuming the worst case scenarios in terms of loading. The voltage stability analysis was performed by increasing load in [Study Areas, e.g., the Grande Prairie and Grande Cache Areas (AESO planning areas 20 and 22, respectively)], and increasing the corresponding generation in the following AESO Planning Areas: Page 27 Public R1-2016-05-01 [Source area, e.g., the Wabamun planning area (Area 40)] [Source area] [Source area] As per the voltage stability criteria, post transient techniques (all tap changers, all discrete capacitors locked, but SVCs will be allowed to adjust) will used in applying the criteria and this information is reflected in all tables and graphs. Also for this analysis, no limits will be selected for the generation sources, non-negative active power constant MVA loads will be enforced and the existing power factor for the reference will be maintained. 7.3.1 Contingencies Studies Please refer to Section 7.2.1. 7.4 Transient Stability Analysis If this analysis is not required, please remove the subsection. Transient stability analysis will be performed following the post-Project scenarios using [Study scenarios, e.g., the 2017 SL and 2017 SP scenarios]. Stability plots for [State Monitoring quantities , e.g., bus voltage, machine relative angle and active and reactive power outputs.etc] for all available generation units in [Study Area, e.g., the Cold Lake (Area 28) planning area] are provided. [State reference generator, e.g., Genesee #1] will be used as the system reference. 7.4.1 Contingencies Studies Below are examples of the write up: [Transient stability analysis will be performed for the Category A condition and all Category B contingencies in [Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios.] Or Use a suitable table format to outline the selected contingencies and their descriptions for each scenario. [ Table 7.4-1: Contingencies to be studied for Transient Stability Analysis Contingency Fault Location N-1 of 1234L (Sub A to Sub B) Sub A N-1 of 1234L (Sub A to Sub B) Sub B N-1 of 5678L (Sub C to Sub D) Sub C ] Page 28 Public R1-2016-05-01 7.5 Short Circuit Analysis Short-circuit analysis will be performed for [Study scenarios, e.g., the 2016 WP pre Project scenario and 2016 WP and 2025 WP post-Project scenarios] to determine the short-circuit levels in the vicinity of the Project. The short-circuit analysis includes three phase and single line to ground faults. Fault levels are provided in the form of currents in kilo amperes and per unit positive and zero sequence impedances. Highlight the short circuit current levels which are above 90% of equipment rating. Market participants can approach the AESO for advice with respect to long-term anticipated short circuit levels and can collaborate with the AESO on a system-based solution if a more locally-based solution cannot solve it. 7.6 Motor Starting Analysis [as required] If this analysis is not required, please remove the subsection. This section is to describe the study methodology of motor starting analysis. Below is an example of the write up: [Motor starting analysis will be performed for the proposed motors under system normal (Category A) conditions and worst case contingencies identified in the voltage stability and power flow analyses. The analysis considered the starting of one motor, with its Variable Frequency Driver (VFD) out of service, while the other motors will be running at full load.] 7.7 Effectiveness Factor Analysis Studies [as required] Effectiveness factor analysis studies are carried out to determine the generator/load effectiveness factors and identify the most effective generator/load(s) to be curtailed in order to mitigate the thermal violations observed following some Category B contingencies in the Study Area. 7.8 Sensitivity Studies [as required] Describe the methodology used for any other studies carried out. Use a separate heading for each study. The headings should match the headings used in section 6.1. Include the intent, the assumptions, and any relevant discussions regarding the study methodology. Use a table. Page 29 Public R1-2016-05-01 7.9 Sub-Synchronous Studies 7.9.1 Sub-Synchronous Torsional Interaction Study (SSTI)12 This study and analysis will be required when there is a concern of sub-synchronous torsional interaction between turbine-generator units and the nearby HVDC transmission facilities. 7.9.1.1 Preliminary SSTI Screening This section only applies to generation projects near HVDC convertor stations when the AESO or the Consultant identifies potential SSTI. Preliminary screening for potential SSTI for the proposed generating unit(s) does not require detailed models for HVDC, turbine-generators or their controllers. The study should be carried out by calculating the Unit Interaction Factors (UIF) under normal system conditions (N-0) and single contingency (N-1) and credible multiple contingency (N-X) such as Category C and multielement outages. The UIF is calculated as follows: UIFi = {MVAHVDC / MVAi } . {1 - (SCi / SCtot) }2 UIFi : Unit Interaction Factor of the i-th generator MVAHVDC: MVA rating of the HVDC MVAi: MVA rating of the i-th generator SCtot: Short-circuit capability at HVDC commutating bus including all generators (Subtracting AC filters and shunt capacitors) SCi : Short-circuit capability at HVDC commutating bus excluding Generator(i) (Subtracting AC filters and shunt capacitors) An interaction factor close to or higher than 0.1 will require detailed SSTI studies as described in Section 7.9.1.2. The Market Participant in consultation with the AESO should identify any other dispatch combinations that are seen as credible in assessing the potential for SSTI. 7.9.1.2 Detailed SSTI Studies This section will be complied by AESO Planning Engineer and will be carried out by Study Consultant specialized in sub-synchronous oscillation analysis. If the preliminary screening study shows an interaction factor for a generator higher than 0.1, this indicates strong coupling between the particular generator and the HVDC under the studied system condition. Therefore detailed SSTI studies are required to determine if there is a risk of under-damped torsional modes of oscillations of turbine-generator shaft system. If the calculated electrical damping is adequate, in the frequency range of torsional modes of concern, no further studies are required. However, if the damping is not adequate, further studies are required to investigate mitigation/protection measures. Detailed ‘Process for SSTI Studies and Mitigation-protection’ between HVDC and Thermal Turbinegenerators is published in http://www.aeso.ca/connect/files/process_for_SSTI_studies_and_mitigationprotection.docx. Further SSTI studies documents will be published to the AESO website accordingly. 12 Page 30 Public R1-2016-05-01 The detailed SSTI studies should check if under-damped torsional oscillations would be excited during normal system conditions (N-0), single contingency (N-1) and multiple contingency (N-X) events such as Category C and multi-outage conditions. The list of Category C and multielement outage conditions are provided in Table 7.9-1. Table 7.9-1 Conditions to be tested for SSTI Studies Scenario Contingency 201X SP Contingency Category B C5 Multi-element The AESO will provide the necessary support and review to ensure that SSTI study is carried out with credible system conditions and contingencies. The SSTI study report will document the results and identify the scenarios in which torsional interactions may exist and whether mitigation measures are required. The AESO will engage the TFO to work with the vendor to retune the HVDC controls if this has been identified as a viable mitigation measure. 7.9.2 Sub-Synchronous Resonance (SSR) and Sub-Synchronous Control Interaction (SSCI) Studies Studies and analyses will be required when there is a concern of sub-synchronous resonance between turbine-generator units and the nearby serious capacitor compensated AC transmission lines. Studies are also required when there is a potential sub-synchronous control interaction (SSCI) between the wind farms, particularly the DFIG (Type III), and serious capacitor compensated lines or a nearby HVDC terminal. The AESO, TFO or the Consultant will identify the need for SSR or SSCI studies. 7.9.2.1 Preliminary SSR and SSCI Screening Preliminary screening for SSR and SSCI studies are carried out by frequency domain scanning, and it does not require detailed models for turbine-generators or wind turbines or their controllers. The frequency domain scanning for SSR looks for electrical resonance below 60 Hz. In the case of wind turbine the frequency scanning for SSCI will look for sub-synchronous frequency where the external reactance between the wind farm and the system dips by more than 5%. This indicates a potential of unstable control interactions with the series capacitor. If the results indicate potential risk of resonance with torsional modes oscillation or control interaction under normal system conditions (N-0) and single contingency (N-1) and credible multiple contingency (N-X) such as Category C and multi-element outages, then further study will be required. 7.9.2.2 Detailed SSR and SSCI Studies This section will be complied by AESO Planning Engineer and will be carried out by Study Consultant specialized in sub-synchronous oscillation analysis If the preliminary SSR or SSCI screening study shows potential risk of resonance or unstable interaction between the turbine-generator control and the series capacitor(s), detailed SSR or Page 31 Public R1-2016-05-01 SSCI study is required. If risks are identified, further studies are required to investigate mitigation/protection measures. The detailed SSR or SSCI studies should check if under-damped torsional oscillations would be excited during normal system conditions (N-0), single contingency (N-1) and multiple contingency (N-X) events such as Category C and multi-outage conditions. The AESO will provide the necessary support and review to ensure that SSR and SSCI studies are carried out with credible system conditions and contingencies. The SSR or SSCI study report will document the results and identify the scenarios in which potential risks may occur and whether mitigation measures are required. 7.10 Mitigation Measures If study results indicate transmission constraints associated with or exacerbated by the project addition, modification to existing procedures and/or Remedial Action Schemes (RAS) or addition of new procedures and/or RAS may be required. The Studies Consultant must identify those anticipated constraints in a timely manner to the AESO as they arise. The AESO Planning Engineer will guide the Studies Consultant to; - List study results in the constraint table in Attachment N of the part of the ESR Template. - If N-0 overloads are observed in the post connection system, develop generation or load effectiveness factor tables based on identified thermal constraints for N-0 system. - Develop generation or load effectiveness factor13 tables based on identified thermal constraints under Category B contingencies. - Identify the components of the AESO system development plan which will alleviate the identified constraint. Propose adjustments to the original preliminary connection alternatives to avoid proposing permanent RAS for Category B contingencies. Study and propose possible modifications to existing RAS to ensure coordination of proposed protection additions with the existing schemes. Study and propose new temporary RAS required to ensure system reliability until such time the planned system reinforcements are in place. Proper study scenarios with the planned system reinforcements will be studied to reflect removal of the identified constraints and the temporary nature of the RAS. - The AESO Planning Engineer will closely work with the Consultant and guide the development and/or modifications of the proposed RAS to ensure system reliability, security and compliance with AESO system access business practices. 13 Effectiveness factor analysis is carried out to determine the generator/load effectiveness factors which are used to estimate the ability of each generator/load to relieve transmission element constraints. A generator/load’s effectiveness factor is defined as the change in power flow over a specific line following a change in the generator’s output power/ the load. As such, the larger the generator/load effectiveness factor the more helpful it can be in alleviating a thermal violation on the transmission line associated to it. Page 32 Public R1-2016-05-01 8 Engineering Report Study results will be presented to the AESO for review and comment in the form of a draft report using the AESO’s Engineering Study Report (ESR) template: A draft ESR will be provided in MS Word format (electronic format) for the AESO review and comments; Studies Consultant will discuss the followings: - the highlights of the studies as needed during the course of the study to identify any unexpected surprises and resolve them. - the final study results and associated mitigation measures to the AESO Planning Engineer before working on a draft ESR; Study results will be presented using the AESO ESR template; The consultant shall address AESO’s comments and finalize the report by taking into account the comments and suggestions; and Any variation from assumptions laid out in the study scope will be capture in the final ESR. Page 33 Public R1-2016-05-01 9 Applicability Term This section is compiled by the AESO Planning Engineer and the Consultant. State the period the study scope as laid out in this document will be valid for assessing Market Participant connection; include the anticipated timeline that the Market Participant expects to complete the studies. The study scope as laid out in this document will be valid for assessing the Market Participant connection for a period of [state time (ex. six months)] from the date specified on this document unless a material change occurs within this time. This timeline is [based on but not limited to the system constraints, project interdependancies]. This study scope should not be considered valid beyond this period without confirmation from the AESO. The studies must be completed in accordance with the timelines required in the ‘Connection Queue Business Practices’. The approximate timeline for the studies to begin is [state time (ex. first week of February/Year)]. Prior to beginning the studies please check in with the AESO Project Coordinator and Planning Engineer to ensure there are no new developments that might impact the Study Scope. Additional connection assessments including those needed to capture impact of changes in forecast, introduction of new connection alternatives or delays in proposed system developments as described herein shall be captured in a signed Scope Amendment document. The Market Participant anticipates that the studies will be complete [state anticipated timeline (ex. in six months from the date this document is issued)(on Month, Day, Year)]. If study assumptions change due to load forecast or project ISD after the completion of the Connection ESR and Connection Proposal, the AESO will evaluate whether to use the same ESR or create a new ESR for the NID filing. If necessary, further sensitivity study may be required. Remedial Action Schemes (RAS) may be required and will be developed by the AESO as required. Page 34 Public R1-2016-05-01 10 Key Engineers This section is compiled by the Studies Consultant in collaboration with the AESO Planning Engineer. Outline all engineers who will be stamping, performing, supervising, and reviewing the connection studies as stated in this document. Role: [Name], [Title], [Company] Role: [Name], [Title], [Company] Page 35 Public R1-2016-05-01 11 Revision History This section is compiled by the AESO. Rev. Issue Date Author Change Tracking 0 Page 36 Public R1-2016-05-01 Attachment A Transmission Planning Criteria- Basis and Assumptions (Reliability Criteria) Page 37 Public R1-2016-05-01 1 Introduction This document presents the reliability standards, criteria, and assumptions to be used as the basis for planning the Alberta Transmission System. The criteria, standards and assumptions identified in this document supersede those previously established. 2 Transmission Reliability Standards and Criteria14 The AESO applies the following Alberta Reliability Standards to ensure that the transmission system is planned to meet applicable performance requirements under a defined set of system conditions and contingencies. A brief description of each of these standards is given below: 1. TPL-001-AB-0: System Performance Under Normal Conditions Category A represents a normal system condition with all elements in service (N0). All equipment must be within its applicable rating, voltages must be within their applicable ratings and the system must be stable with no cascading outages. Under Category A, electric supply to load cannot be interrupted and generating units cannot be removed from service. 2. TPL-002-AB-0: System Performance Following Loss of a Single BES Element Category B events result in the loss of any single element (N-1) under specified fault conditions with normal clearing. The specified elements are a generating unit, a transmission circuit, a transformer or a single pole of a direct current transmission line. The acceptable impact on the system is the same as Category A with the exception that radial customers or some local network customers, including loads or generating units, are allowed to be disconnected from the system if they are connected through the faulted element. The loss of opportunity load or opportunity interchanges is allowed. No cascading can occur. 3. TPL-003-AB-0: System Performance Following Loss of Two or More BES Elements Category C events result in the loss of two or more bulk electric system elements (sequential, N-1-1 or concurrent, N-2) under specified fault conditions and include both normal and delayed fault clearing. All of the system limits for Category A and B events apply with the exception that planned and controlled loss of firm load, firm transfers and/or generation is acceptable provided there is no cascading. 4. TPL-004-AB-0: System Performance Following Extreme BES Events Category D represents a wide variety of extreme, rare and unpredictable events, which may result in the loss of load and generation in widespread areas. The system may not be able to reach a new stable steady state, which means a blackout is a possible outcome. The AESO needs to evaluate these events, at its discretion, for risks and consequences prior to creating mitigation plans. 14 A complete description of these standards are given in: AESO. Alberta Reliability Standards. Available from http://www.aeso.ca/rulesprocedures/17004.html Page 38 Public R1-2016-05-01 5. FAC-014-AB-2: Establishing and Communicating System Operating Limits The AESO is required to establish system operating limits where a contingency is not mitigated through construction of transmission facilities. 2.1 Thermal Loading Criteria The AESO Thermal Loading Criteria require that the continuous thermal rating of any transmission element is not exceeded under normal and postcontingency operating conditions. Thermal limits are assumed to be 100% of the respective normal summer and winter ratings. Emergency limits are not considered in the planning evaluations. 2.2 Voltage Range and Voltage Stability Criteria The normal minimum and maximum voltage limits as specified in the following table are used to identify Category A system voltage violations, while the extreme minimum and maximum limits are used to identify Category B and C system violations. Table 11.1-1 presents the acceptable steady state and contingency state voltage ranges for the AIES. Table 11.1-2 provides voltage stability criteria used to test the system performance. Table 11.1-1: Acceptable Range of Steady State Voltage (kV) Nominal Voltage Extreme Minimum Normal Minimum Normal Maximum Extreme Maximum 500 475 500 525 550 240 260 (Northeast & Northwest)* 144 138 72 69 216 234 252 264 234 247 266 275 130 124 65 62 137 135 68.5 65.5 151 145 75.5 72.5 155 150 79 76 Table 11.1-2: Voltage Stability Criteria Page 39 Public R1-2016-05-01 Disturbance (1)(2)(3)(4) Performance Initiated by: Level Fault or No fault DC Disturbance A B C D MW Margin (P-V method) (5)(6)(7) MVAr Margin (V-Q method) (6)(7) > 5% Worst Case Scenario(8) > 5% 50% of Margin Requirement in Level A > 2.5% 50% of Margin Requirement in Level A Any element such as: One Generator One Circuit One Transformer One Reactive Power Source One DC Monopole Bus Section Any combination of two elements such as: A Line and a Generator A Line and a Reactive Power Source Two Generators Two Circuits Two Transformers Two Reactive Power Sources DC Bipole Any combination of three or more elements. i.e.: Three or More Circuits on ROW Entire Substation Entire Plant Including Switchyard >0 >0 2.3 Transient Stability Analysis Assumptions Standard fault clearing times as shown in Table 11.1-3 are used for the new facilities or when the actual clearing times are not available for the existing facilities. Double line-to-ground faults are applied for the Category C5 events with normal clearing times. Single line-to-ground faults are applied for Category C6 to C9 events with delayed clearing times as depicted in Table 11.1-4 and Table 11.1-5. Table 11.1-3: Fault Clearing Times Nominal Near Page 40 Far End Public R1-2016-05-01 End kV 500 240 144/138 Cycles 4 5 Cycles 5 6 with telecommunications 6 8 6 30 144/138 without telecommunications Table 11.1-4: Stuck Breaker Clearing Times for Lines Fault Clearing Time (Cycles) 138/144 kV 2nd Ckt (for Near Far C5 End End and C7 Only) 15 24 24 Fault Clearing Time Fault Clearing Time (Cycles) 240 kV (Cycles) 500 kV 2nd Ckt 2nd Ckt Near Far (for C5 End End and C7 Only) Near Far (for C5 End End and C7 Only) 12 6 14 9 5 11 Table 11.1-5: Stuck Breaker Clearing Times for Transformers Fault Clearing Time (Cycles) 240/138 kV Fault on 240 kV Fault on 138 kV Side Side nd 240 138 2 Ckt 138 240 2nd Ckt kV kV kV kV (for (for Sid Sid Breake Sid Sid Breake e e e e r Fail) r Fail) 12 6 14 15 5 24 Fault Clearing Time (Cycles) 500/240 kV Fault on 500 kV Fault on 240 kV Side Side nd 500 240 2 Ckt 240 500 2nd Ckt kV kV kV kV (for (for Sid Sid Breake Sid Sid Breake e e e e r Fail) r Fail) 9 5 11 12 4 14 Page 41 Public R1-2016-05-01 Page 42 Public R1-2016-05-01 SECTION TWO ENGINEERING STUDY REPORT Stage 2 Engineering Study Report Project Title Date: Click and type date Role Name Prepared: Engineer, P. Eng. Reviewed: Engineer, P. Eng. Approved: Engineer, P. Eng. Version: Date Signature Click and type version number Engineering Stamp APEGA Permit to Practice: XXXXXX Page 2 Public R1-2016-05-01 (Page intentionally blank) R[x] 3 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Executive Summary What to include in Executive Summary: The Executive Summary is a high-level summary of the report. Be brief. Make sure the information in the Executive Summary and the information in the Summary and Conclusion are consistent. Instructional statements are italicized with 10 font size. In order to use acronyms/short form, acronyms should be defined in Executive summary. This process will be repeated in the main body of the Engineering Study Report. If referring to a transmission line, please use the following format: 138 kV transmission line 123L (from 345S substation to 678S substation). If referring to a substation, please use the following format: the ABC 345S substation. Project Overview [Market Participant Legal Name (Market Participant Short Name)] has submitted a System Access Service Request (SASR) to the Alberta Electric System Operator for [Demand Transmission Service and/or Supply Transmission Service] of XXXMW at [Project location, e.g., south of the City of Grande Prairie to serve oilfield loads] (the Project). The requested In-Service Date for the Project is [Month, Day, Year of the In-Service date as per the SASR request]. Existing System The Project is located in the AESO planning area of [AESO planning area, e.g., Grande Prairie (Area 20)], as part of [The AESO Region, e.g., the AESO Northwest (NW) Region]. Only if Applicable The existing constraints in [The AESO Region, e.g., the NW Region] are managed in accordance with Section 302.1 of the ISO rules, Real Time Transmission Constraint Management. This section will then describe the ‘overview of existing system’. Please describe the Key substations/lines in the Project area and intertie connection with neighboring areas. Below is an example of the write up: [The H.R. Milner generation facility, with connection to the H.R. Milner 740S substation, connects to the Alberta Interconnected Electric System (AIES) through two 144 kV transmission lines: one is transmission line 7L20, which connects the HR Milner 740S substation to the Big Mountain 845S substation in the Grande Prairie planning area (Area 20); the other is transmission line 7L80, which connects the HR Milner 740S substation to the Simonette 733S substation, which further connects to the Little Smoky 813S substation in the Valleyview planning area (Area 23) via transmission line 7L40.] Study Summary Study Area for the Project The Study Area for the Project consisted of [The AESO Planning areas, e.g., the Grande Cache and Grande Prairie areas], including the tie lines connecting [Specify how many planning areas will be included in the Study Area, e.g., the two] planning areas to the rest of the AIES. All transmission facilities within [Specify how many planning areas will be included in the Study Page 1 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Area, e.g., the two] planning areas were studied and monitored for violations of the Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria). The [Insert the number and voltage rating of the transmission lines connecting the Study Area to the rest of the AIES, e.g., five (5) 144 kV] transmission lines connecting the [The AESO Planning area names, e.g., the Grande Cache and Grande Prairie areas] to the rest of the AIES (namely transmission lines [Insert the designation of the transmission lines connecting the Study Area to the rest of the AIES, e.g. 7L73, 7L32, 7L45, 7L46 and 7L40] were also studied and monitored to identify any violations of the Reliability Criteria. Studies Performed for the Project This section will provide a high level description of the studies performed to assess the impact of connecting the Project to the AIES. Below is an example of the write up: [Load flow analysis was performed for the 2016 summer peak (SP) and winter peak (WP) preProject and post-Project scenarios, with the 2016 AIES topology in the NW Region, to determine the impact of the connection of the Project on the AIES. Voltage stability analysis was performed for the 2016 WP post-Project scenario to identify violations, if any, of the voltage stability criteria. Short-circuit analysis was performed for the 2016 WP pre-Project scenario and for the 2016 WP and 2025 WP post-Project scenarios to determine the short-circuit levels in the vicinity of the Project.] Results of the pre-Project Studies Please follow the structure of the pre-Project study results as follows. Below is an example of the write up: The following is a summary of the results of the pre-Project studies. 201X SP Category A (N-G-0 [for Load Addition Projects] or N-0 [for Generation Addition Projects – Please choose only one depending on the project type]) conditions Please provide summary of the results for the pre-Project Category A scenario. Below is an example of the write up: [Under Category A conditions, no Reliability Criteria violations were observed for any of the preProject scenarios] Category B (N-G-1 [for Load Addition Projects] or N-1 [for Generation Addition Projects – Please choose only one depending on the project type]) conditions Please provide summary of the results for the pre-Project Category B scenario. Below is an example of the write up: [Under Category B conditions, no Reliability Criteria violations were observed for any of the preProject scenarios] Connection alternatives examined for the Project Each Alternative should include details on what neighbouring substations/lines will be involved and what associated equipment will be added for each alternative. Please use the same wording from the Project’s Connection Study Scope to describe each alternative. Below is a new DTS example of the write up: [Distribution Facility Owner] in [The Project area, e.g., south of Grande Prairie], examined and ruled out the use of distribution-based solutions to serve the additional load [Only if Applicable]. This engineering study report will examine the following transmission alternatives to serve [Requested Demand Transmisson Service]. Page 2 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Alternative 1: Add a new point of delivery (POD) substation, and connect the new POD to the existing [Voltage Class, e.g. 138] kV transmission line [Line name] via an in/out connection configuration. Alternative 2: Add a new point of delivery (POD) substation, and connect the new POD to the existing [Voltage Class, e.g. 138] kV transmission line [Line name] via a Ttap connection configuration. Alternative 3: Add a new point of delivery (POD) substation, and connect the new POD to the existing [Voltage Class, e.g. 138] transmission line [Line name] via a radial connection configuration to the existing [substation name and number]. Alternative 4: Upgrade the capacity at the existing [Substation Name and number] substation and shift load to neighboring [Substation Name and number] substation. Connection alternatives selected for further examination Please address which Alternatives are selected for this Project and state the rationale for ruling out the rest of the Alternatives. Refer to the DFO’s Distribution Deficiency Report (DDR) Address Market Participant (MP)’s preference (including cost estimates) Specify Transmission Facility Owners (TFOs)’s position on any possible limitation/constraints that would result in ruling out a specific alternative. Below is an example of the write up: [Alternative 1 and Alternative 2 were selected for further study. Both Alternative 3 and Alternative 4 would require greater transmission development for no incremental benefit and were not selected for further study.] Results of the post-Project studies Please compare study results between selected Alternatives under each study scenario. The following is a summary of the results of the post-Project studies. 201X SP Category A (N-G-0 [for Load Addition Projects] or N-0 [for Generation Addition Projects – Please choose only one depending on the project type]) conditions Please provide summary of the results for the post-Project Cat A scenario. Category B (N-G-1 [for Load Addition Projects] or N-1 [for Generation Addition Projects – Please choose only one depending on the project type]) conditions Please provide summary of the results for the post-Project Category B scenario. Below are examples of the write up: [Marginal thermal violations on the 144 kV line 7L50 from Battle River 757S to Buffalo Creek 726S were observed following the 144 kV line 7L53 contingency from Bonnyville 700S to Irish Creek 706S. This line has clearance issues and continuous flow above the stated ratings cannot be sustained; however, since the line loading is less than 100.8% this will be managed by real time operational practices. or Voltage criteria violations were observed following the loss of the transmission line designated as 7L228. The violations were observed at the Kakwa Ridge 857S, HR Milner 740S, Dome Cutbank 810S and Thornton 2091S substations. To mitigate these violations, it would require a Page 3 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title remedial action scheme (RAS) to trip the new Thornton 2091S substation. Following the 7L228 contingency, the load served by the Thornton 2091S substation would be left unserved. Following the loss of 7L40 (Little Smoky 813S to Simonette 733S) a minor post-transient deviation of 10.5% the Simonette 733S POD bus was noted; this is marginally higher than the 10% guideline. The TFO and DFO have confirmed that such marginal voltage deviation does not impose any operational restriction.] Mitigation Strategy and Sensitivity Analysis [as required] Please describe how to mitigate the identified Reliability Criterial violations in these pre- and post-Project studies. Alternative Selected This section will provide which Alternative is preferred based on performed studies. Please provide how the study results impacted on the Alternative selections. Below is an example of the write up: Alternative [State selected Alternative #, e.g., 2] was selected as the preferred alternative since….. [Provide solid reasons why this Alternative was selected] Recommendation This section will provide the recommendation of this project including selected Alternative, new equipment and mitigation measure (if required). Below is an example of the write up: [The recommended alternative to connect the Facilities is Alternative 2, building the new 144/6.9 kV POD substation Vincent 2019S. The Project will include: Tapping the 144 kV line 7L65 and building 0.15 km of 144 kV line to connect the new Vincent 2019S POD substation. Installing one 20/26.6/33.3 MVA, 144 kV to 6.9 kV LTC transformer, one 144 kV transformer breaker, and associated equipment. The 25 MVAr 144 kV capacitor at Irish Creek 706S, as identified in the 2015 Long-term Transmission Plan (LTP), is required prior to the Project ISD, since the inclusion of this capacitor bank mitigates all criteria violations noted in the pre- and post-connection results.] Page 4 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Contents EXECUTIVE SUMMARY ......................................................................................3 1. INTRODUCTION ...........................................................................................5 1.1. Project .............................................................................................................................................. 5 Project Overview ....................................................................................................................................... 5 1.1.1. Load Component ..................................................................................................................... 5 1.1.2. Generation Component ........................................................................................................... 6 1.2. Study Scope ..................................................................................................................................... 7 1.2.1. Study Objectives...................................................................................................................... 7 1.2.2. Study Area ............................................................................................................................... 7 1.2.3. Studies Performed ................................................................................................................... 8 1.2.4. Studies Excluded ..................................................................................................................... 9 1.3. 2. Report Overview .............................................................................................................................. 9 CRITERIA, SYSTEM DATA, AND STUDY ASSUMPTIONS .............................9 2.1 Criteria, Standards, and Requirements ............................................................................................ 9 2.1.1 Transmission Planning Standards and Reliability Criteria ........................................................... 9 2.1.1 AESO Rules ............................................................................................................................... 11 2.1.1 Other Requirements .................................................................................................................. 11 2.1. Study Scenarios ................................................................................................................................... 11 2.2 Load and Generation Assumptions ................................................................................................ 12 2.2.1 Load Assumptions ..................................................................................................................... 12 2.3.2 Generation Assumptions ........................................................................................................... 12 2.3.2 Intertie Flow Assumptions.......................................................................................................... 13 2.2.2 HVDC Power Order (if applicable) ............................................................................................. 14 2.3 System Projects ............................................................................................................................. 15 2.4 Customer Connection Projects ...................................................................................................... 15 2.5 Facility Ratings and Shunt Elements ............................................................................................. 16 2.6 Dynamic Data and Assumptions .................................................................................................... 17 2.7 Protection Fault Clearing Times ..................................................................................................... 17 2.8 Voltage Profile Assumptions .......................................................................................................... 18 2.9 Motor Starting Assumptions ............................................................. Error! Bookmark not defined. 3 3.1 STUDY METHODOLOGY ............................................................................ 19 Connection Studies Carried Out .................................................................................................... 19 Page 5 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 3.2 Load Flow Analysis ........................................................................................................................ 19 3.2.1 Contingencies Studied ............................................................................................................... 20 3.3 Voltage Stability (PV) Analysis ....................................................................................................... 20 3.3.1 Contingencies Studied ............................................................................................................... 21 3.4 Transient Stability Analysis ............................................................................................................ 21 3.4.1 Contingencies Studied ............................................................................................................... 21 3.5 Short-Circuit Analysis ..................................................................................................................... 21 3.6 Motor Starting Analysis .................................................................................................................. 21 3.7 Sub-Synchronous Studies [as required] ........................................................................................ 22 3.7.1 Sub-Synchronous Torsional Interaction Study (SSTI) ............................................................... 22 3.7.2 Sub-Synchronous Resonance (SSR) and Sub-Synchronous Control Interaction (SSCI) Studies 22 3.8 Effectiveness Factor Analysis Studies [as required] ...................................................................... 22 3.9 Sensitivity Studies [as required] ..................................................................................................... 22 3.10 Mitigation Measures ....................................................................................................................... 22 4 PRE-PROJECT SYSTEM ASSESSMENT...................................................... 23 4.1 Pre-Project Load Flow Analysis ..................................................................................................... 23 4.1.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016 SP) 23 4.2 Pre-Project Voltage Stability Analysis [as required] ....................................................................... 24 4.3 Pre-Project Transient Stability Analysis [as required] .................................................................... 24 5 5.1 CONNECTION ALTERNATIVES .................................................................. 25 Overview ........................................................................................................................................ 25 5.2 Connection Alternatives Identified ................................................................................................. 25 5.2.1 Connection Alternatives Selected for Further Studies ............................................................... 25 5.2.2 Connection Alternatives Not Selected for Further Studies ........................................................ 25 6 TECHNICAL ANALYSIS OF THE CONNECTION ALTERNATIVES ............... 26 6.1 Load Flow ....................................................................................................................................... 27 6.1.1 Alternative 3 ............................................................................................................................... 27 6.1.1.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016SP, Scenario 4) ............................................................................................................................... 27 6.1.1.2 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5).............................................................................................................................. 28 6.1.2 Alternative 4 ............................................................................................................................... 28 6.1.2.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016SP, Scenario 4) ............................................................................................................................... 28 6.1.2.2 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5).............................................................................................................................. 28 Page 6 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 6.1.3 Comparison of Alternatives........................................................................................................ 28 6.2 Voltage Stability ............................................................................................................................. 29 6.2.1 Alternative 3 ............................................................................................................................... 29 6.2.1.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5).............................................................................................................................. 29 6.2.2 Alternative 4 ............................................................................................................................... 29 6.2.2.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5).............................................................................................................................. 29 6.2.3 Comparison of Alternatives........................................................................................................ 29 6.3 Transient Stability........................................................................................................................... 29 6.3.1 Alternative 3 ............................................................................................................................... 30 6.3.1.1 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016 SP, Scenarios 4) ................................................................................................. 30 6.3.1.2 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016 WP, Scenarios 5) ................................................................................................... 30 6.3.2 Alternative 4 ............................................................................................................................... 30 6.3.2.1 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016 SP, Scenarios 4) ................................................................................................. 30 6.3.2.2 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016 WP, Scenarios 5) ................................................................................................... 30 6.3.3 Comparison of Alternatives........................................................................................................ 30 6.4 Motor Starting Analysis [as required] ............................................................................................. 30 6.4.1 Motor Starting Results for Alternative 1 ..................................................................................... 32 6.5 Sub-Synchronous Studies Analysis ............................................................................................... 33 6.6 Sensitivity Studies [as required] ..................................................................................................... 33 6.7 Effectiveness Factor Analysis [as required] ................................................................................... 33 7 MITIGATION MEASURES ........................................................................... 34 8 SHORT-CIRCUIT ANALYSIS ....................................................................... 34 8.1 Pre-Project ..................................................................................................................................... 35 8.2 Post-Project .................................................................................................................................... 35 9 PROJECT INTERDEPENDENCIES .............................................................. 36 10 SUMMARY AND CONCLUSION .................................................................. 37 Page 7 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachments Attachment A Attachment B Attachment C Attachment D Attachment E Attachment F Attachment G Attachment H Attachment I Attachment J Attachment K Attachment L Attachment M Attachment N Dynamic Data and Assumptions of All Equipment Proposed for Connection Pre-Project Load Flow Diagrams (Scenarios 1 to XX) Pre-Project Voltage Stability Diagrams (Scenarios 1 to XX) Pre-Project Transient Stability Diagrams (Scenarios 1 to XX) Alternative 1: Load Flow Diagrams (Scenarios 1 to XX) Alternative XX: Load Flow Diagrams (Scenarios 1 to XX) Alternative 1: Voltage Stability Diagrams (Scenarios 1 to XX) Alternative XX: Voltage Stability Diagrams (Scenarios 1 to XX) Alternative 1: Transient Stability Diagrams (Scenarios 1 to XX) Alternative XX: Transient Stability Diagrams (Scenarios 1 to XX) Motor Starting Analysis and Diagrams Category B Loading and Voltage Performance Generation/Load Effectiveness Factor (if necessary) Power Flow Diagrams after Mitigation Measures Figures Figure 6.4-1: Equivalent Circuit of Induction Motor ......................................................................... 32 Tables Table 1.2-1: Summary of System Projects ........................................................................................ 8 Table 2.1-1: Post Contingency Voltage Deviation Guidelines ......................................................... 10 Table 2.2-1: List of the Connection Study Scenarios ...................................................................... 11 Table 2.3-1: Forecast Area Load (201X LTO at AIL Peak) ............................................................. 12 Table 2.3-2: Local Generation (MW) in the Study Cases ................................................................ 13 Table 2.3-3: Intertie Assumptions – Example .................................................................................. 13 Table 2.3-4: HVDC Power Order by Scenario ................................................................................. 14 Table 2.4-1: Summary of System Projects Included in the Study Cases ........................................ 15 Table 2.5-1: Summary of Customer Connection Assumptions ........................................................ 15 Table 2.6-1: Summary of Transmission Line Ratings in the Study Area (MVA on 138 kV Bases) .. 16 Table 2.6-2: Summary of Transformer Ratings in the Study Area ................................................... 16 Table 2.6-3: Summary of Shunt Elements in the Study Area .......................................................... 17 Table 2.8-1: Summary of Protection Fault Clearing Times .............................................................. 17 Table 3.1-1: Summary of Studies Performed* ................................................................................. 19 Table 4.1-1: Summary of System Performance (Element Loading) [2017SP Pre-Project N-G-1 Line Loading Above Rate A] ............................................................................................................................................ 24 Table 6.1-1: Summary of System Performance (Element Loading) [Scenario 4- 2017 SP Post-Project N-G-1 Line Loading Above Rate A] ................................................................................................................... 28 Table 6.1-2: Summary of System Performance (Voltage Range) ................................................... 28 Table 6.1-3: Summary of System Performance (Voltage Deviation) ............................................... 28 Table 6.2-1: Scenario 4: 2016 WP– Voltage stability analysis results (Minimum transfer = 22.5 MW)29 Table 6.3-1: Summary of Transient Instability ................................................................................. 30 Table 6.4-1: Motor Nameplate and Calculated Data ....................................................................... 31 Table 6.4-2: Equivalent Circuit Data................................................................................................ 32 Table 6.4-3: Motor Starting Performance for Alternative 1 .............................................................. 32 Table 8.1-1: Summary of Short-Circuit Current Levels – Pre-Project (Year 20XX) ......................... 35 Page 8 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Table 8.1-2: Summary of Short-Circuit Current Levels – Pre-Project (Year 20XX [Year of Proposed Connection + 10 Years]) ............................................................................................................................................ 35 Table 8.2-1: Summary of Short-Circuit Current Levels – Post-Project (Year 20XX)........................ 35 Table 8.2-2: Summary of Short-Circuit Current Levels – Post-Project (Year 20XX [Year of Proposed Connection + 10 Years]) ............................................................................................................................................ 35 Page 9 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 1. Introduction Present a brief overview of the project using the headings provided. Note If a subsection heading is not relevant to the project write "Not Applicable" under the heading in the first draft of the report submitted for AESO review. Such headings must be removed before submission of the final report.) Acronym should be defined in the main body of the Engineering Study Report. This Customer Connection Engineering Study Report (ESR) presents the results of the study conducted to analyze the recommended connection alternative of [Project Name] (the Project) to the Alberta Interconnected Electrical System (AIES). 1.1. Project 1.1.1. Project Overview This section is to describe the following: • • • • Organization submitting SASR SASR request (load DTS, gen STS, transformer add, breaker add, new POD, …) and why needed (load growth, new load, new generator, DFO reliability – N-1, feeder loading, …) location Requested In-Service date [Market Participant Legal Name (Market Participant Short Name)] has submitted a System Access Service Request (SASR) to the Alberta Electric System Operator (AESO) for [Demand Transmission Service (DTS) and/or Supply Transmission Service (STS)] of [XXX] MW at [Project location, e.g., south of the City of Grande Prairie to serve oilfield loads] (the Project). The requested In-Service Date (ISD) for the Project is [Month, Day, Year of the In-Service date as per the SASR request]. 1.1.2. Load Component Describe the load component of the project. Include the following: • • • • • State existing Demand Transmission Service (DTS) if applicable. State the requested DTS along with the anticipated power factor; Describe the type of load either Residential, Rural, Commercial, Industrial, and/or Oil Sands(these are the sectors identified in the LTO); o Motor sizes if applicable o Motor starting methods (Across-the-line vs Variable Frequency Drive) State the magnitude of the potential DTS that the Market Participant intends to apply for; and Comment on possible future expansion plans and anticipated timing for such expansion. Below are two examples of the write up: Page 5 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title [1. The requested load addition is 17.9 MW by August 17, 2016. 2. Load Type: Residential, rural, commercial, or light industrial services. 3. DTS contract capacity at South Mayerthorpe 443S to remain at the existing level of 12.5 MW. 4. Currently there is no plan for future expansion. 5. The load will be studied assuming at 0.9 power factor (pf) lagging.] or [Current DTS is 14 MW. There will be an addition four 6600 HP motors with three in operation at any one time. All motors will have dedicated Variable Frequency Drives (VFDs). The requested DTS increase is for an additional 25 MW for a total DTS 29 MW.] 1.1.3. Generation Component Describe the generation component of the project. Include the following: • • • • • • • State size of the generator(s) and estimated Maximum Authorized Real Power (MARP) and Maximum Capability (MC) levels;15 Describe type of generator(s); State estimated reactive power capability of the generator(s) when producing MARP. If this value does not meet the generation interconnection standard specify the intended supplemental strategy. If available, provide maximum capability curve based on pf/temperature. State the potential magnitude of the Supply Transmission Service (STS) that the Market Participant intends to apply for and operate at when connected to the grid; State the seasonal generator capacity (if information available); State station service load if applicable; and Comment on possible future expansion plans and anticipated timing for such expansion; Below is an example of the write up: [Market Participant Short Name plans to install a co-generation facility consisting of a single 85 MW (nominal) natural gas fuelled combustion turbine-generator. With the addition of this generator, Market Participant Short Name has requested an anticipated STS capacity of 85 MW. 1. Generators: Designation Type Model G1 Round Rotor GE 7A6 2. Supply Transmission Service (STS): 85 MW 3. Rated Nameplate Capacity: 93.9 MVA @ 0.85 pf, nominal 4. Maximum Authorized Real Power (MARP): 100 MW 5. Maximum Capability (MC): 85 MW 15 Maximum Authorized Real Power (MARP) and Maximum Capability (MC) are defined in the Consolidated Authoritative Document Glossary posted on the AESO website: http://www.aeso.ca/downloads/Consolidated_Authoritative_Document_Glossary.pdf Page 6 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 6. Reactive Power Capability (preliminary): 48 MVar (0.9 pf lagging) / 33 Mvar (0.95 pf leading) at MARP, 7. The customer advised that there is no future expansion planned.] 1.2. Study Scope 1.2.1. Study Objectives The objective of the study is as follows: 1. Assess the impact of the Project connection on the AIES. 2. Evaluate the Project connection alternatives based on technical performance. 3. Recommend the Project connection alternative and any mitigation measures to address system performance concerns, if any, to enable the reliable integration of the Project into the AIES. 1.2.2. Study Area 1.2.2.1. Study Area Description Define and describe the Study Area. Include a diagram of the Study Area that clearly shows salient features such as transmission lines, substations, generating assets, and reactive elements in the area and indicates their voltage classes. In the Single Line Diagram (the Study Area diagram) show how the Study Area is connected to the rest of the Alberta Interconnected Electric System (AIES). The Project is located in the AESO planning area of [AESO planning area, e.g., Grande Prairie (Area 20)], as part of [The AESO region, e.g., the AESO Northwest (NW) Region]. This section will then describe the Study Area and the ‘Overview of existing system’. Please describe the Key substations/lines in the Project area and intertie connection with neighbouring areas. Below is an example of the write up: [The Study Area for the Project consisted of the Grande Cache (Area 22) and Grande Prairie (Area 20) areas, including the tie lines connecting the two planning areas to the rest of the AIES. All transmission facilities within the two planning areas will be studied and monitored for violations of the Reliability Criteria (defined in Section 2.1.1). The five 144 kV transmission lines connecting the Grande Cache and Grande Prairie areas to the rest of the AIES (namely transmission lines 7L73, 7L32, 7L45, 7L46 and 7L40) will also be studied and monitored to identify any violations of the Reliability Criteria. The H.R. Milner generation facility, with connection to the H.R. Milner 740S substation, connects to the Alberta Interconnected Electric System (AIES) through two 144 kV transmission lines: one is transmission line 7L20, which connects the HR Milner 740S substation to the Big Mountain 845S substation in the Grande Prairie area; the other is transmission line 7L80, which connects the HR Milner 740S substation to the Simonette 733S substation, which further connects to the Little Smoky 813S substation in the Valleyview planning area (Area 23) via the 144 kV transmission line 7L40. Figure 1-1 shows the existing study area transmission system. Page 7 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Figure 1-1: Existing Study Area Transmission System Please add SLD here 1.2.2.2. Existing Constraints If applicable, describe any known constraint(s) in the Study Area. Explain how the constraint(s) are managed. Discuss any Information Documents (IDs)/Authoritative Documents (ADs) presently applied in the area. Outline relevant existing manual or automatic Remedial Action Schemes (RASs) in the Study Area. Below is an example of the write up: [The existing constraints in [AESO Region where the Project is located, e.g., the Northwest Region] are managed in accordance with Section 302.1 of the ISO Rules, Real Time Transmission Constraint Management (TCM).] 1.2.2.3. AESO Long-Term Transmission Plans (LTP) Describe the relevant AESO long-term transmission development plans for the Study Area and its vicinity (either approved NID System Projects or developments identified in the AESO’s most recently published Long Term Plan). List the anticipated in-service dates of those plans. Use a table. Discuss the known impact(s) of any delays in the AESO Long-term Transmission Plans (LTP) for the area on the project. Please specify if the AESO LTP topologies are included in the study scenarios here. Below is an example of the write up: [The AESO Central East sub-region near-term developments are listed in Table 1.2-1. These developments are part of the AESO’s 2015 Long-Term Transmission Plan. These components will not be considered in service unless triggered by the project or study results dictate.] Table 1.2-1: Planned Central East Near-term Developments Description Add voltage reinforcement at Strome substation east of Camrose, Irish Creek substation north of Kitscoty and Whitby Lake substation near Vilna Add new 240/144 kV substation near Vermilion Reconfigure 144 kV lines in vicinity of Vermilion to terminate at new substation Rebuild 144 kV line from Vermilion to Irish Creek to higher capacity Add new 240 kV line from Tinchebray substation northeast of Halkirk to new substation near Vermilion energized at 144 kV Add new 240 kV line from Hansman Lake substation southeast of Hughenden to Edgerton substation energized at 144 kV 1.2.3. Studies Performed Provide a high-level summary of the system conditions (20XX WP for example) and the studies performed, such as analysis of the existing system before the connection and analysis of the system performance after the connection. Include the contingency categories applicable to the project. Below is an example. Please delete the bullets that are not relevant to the project: The following studies were performed in the connection study: Page 8 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title • Load flow analysis (Category A, Category B, and selected Category C5), pre-Project and post-Project conditions Voltage stability analysis (Category A, Category B, and selected Category C5), post-Project conditions Transient stability analysis (Category B, and selected Category C5), post-Project conditions Motor starting analysis, post-Project conditions Short-Circuit fault studies, pre-Project and post-Project conditions In cases where transmission congestion is identified through the connection studies conducted, the AESO will provide further direction on additional studies to identify mitigation measures for congestion management under system normal (N-0) and abnormal conditions (N-1). • • • • • 1.2.4. Studies Excluded Provide a high-level summary of the studies excluded. See below for an example: [The following studies were not performed in the connection study: • Load flow analysis (Category C) Voltage stability analysis (Category C) Transient stability analysis ( Category C)] • • 1.3. Report Overview The Executive Summary provides a high-level summary of the study and its conclusions. Section 1 introduces this engineering study report. Section 2 describes the reliability criteria, system data, and other study assumptions used in this study. Section 3 describes the methodology used for this study. Section 4 discusses the pre-Project assessment of the system. Section 4 presents all the connection alternatives contemplated. Section 6 provides a technical analysis of the connection alternatives considered for further study. Section 8 provides the results of the short-circuit analysis. Section 9 identifies any interdependencies this project may have. Section 10 presents the summary and conclusions of this study. 2. Criteria, System Data, and Study Assumptions 2.1 Criteria, Standards, and Requirements 2.1.1 Transmission Planning Standards and Reliability Criteria The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria)16 were applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B contingencies (i.e., single element 16 Please refer to Attachment A Page 9 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title outage) and selected Category C5 contingencies (i.e., double circuit common tower contingency), prior to and following the studied alternatives. Below is a summary of Category A and Category B system conditions as well as a summary of Category C5 system conditions. [NOTE: If Category C5 contingency assessment is not required, remove the reference to Category C5] Category A, often referred to as the N-0 condition, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of service, result in the loss of any single specified system element under specified fault conditions with normal clearing. These elements are a generator, a transmission circuit, a transformer, or a single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers. Category C5 events [NOTE: Category C wording may need to be adjusted on a project-by-project basis] results in loss of two circuits of a multiple circuit tower. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. For Category C5, the controlled interruption of electric supply to customers (load shedding), the planned removal from service of certain generators, and/or the curtailment of contracted firm (non-recallable reserved) transmission service electric power transfers may be necessary to maintain the overall reliability of the interconnected transmission systems. The Alberta Reliability Standards include the Transmission Planning (TPL) standards that specify the desired system performance under different contingency categories with respect to the Applicable Ratings. The transmission system performance under various system conditions is defined in Appendix 1 of the TPL standards. For the purpose of applying the TPL standards to this study, the Applicable Ratings shall mean: Seasonal continuous thermal rating of the line’s loading limits. Highest specified loading limits for transformers. For Category A conditions: Voltage range under normal operating condition should follow the AESO Information Document ID# 2010-007RS. For the busses not listed in ID#2010-007RS, Table 2-1 in the Reliability Criteria applies. For Category B and Category C5 conditions: The extreme voltage range values per Table 2-1 in the Reliability Criteria. Desired post-contingency voltage change limits for three defined post event timeframes as provided in Table 5.1-1. Table 2.1-1: Post Contingency Voltage Deviation Guidelines Time Period Parameter and reference point Page 10 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Voltage deviation from steady state at POD low voltage bus. Post Transient (up to 30 sec) Post Auto Control (30 sec to 5 min) Post Manual Control (Steady State) ±10% ±7% ±5% 2.1.2 AESO Rules The AESO Voltage Control Practice ID # 2010-007RS will be applied to establish precontingency voltage profiles in the Study Area. The Section 302.1 of the ISO Rules, Real Time Transmission Constraint Management (TCM) will be followed in setting up the study scenarios and assessment of the impact of the Project connection. In addition, due regard will be given to the AESO’s Connection Study Requirements and the AESO’s Generation and Load Interconnection Standard. The Reliability Criteria is the basis for planning the AIES. The transmission system will normally be designed to meet or exceed the Reliability Criteria under credible worst-case loading and generation conditions. 2.1.3 Other Requirements Other AESO requirements to be applied when performing connection studies are outlined below: if applicable Describe in detail the application of any other AESO requirements, criteria, standards, rules, practices, and guidelines (market or otherwise) when the connection studies were carried out. Use subsection headings that clearly identify the requirement being discussed or add another bullet. 2.2 Study Scenarios Outline the scenarios (system conditions) studied and the study years. These scenarios should represent a range of potential system conditions, assumed loading conditions, and assumed generation dispatches sufficient to allow an analysis of the transmission system performance in the Study Area. The scenarios may include the following: • • • • Low and high loading levels Low and high generation levels Interchange conditions (for example, high, medium, or low export from Alberta to British Columbia or high, medium, or low import from British Columbia to Alberta) Transmission flow variations, such as South of Keephills/Ellerslie/Genesee (SOK), Fort McMurray transfer in and out, HVDC power order and other relevant area transfers [Table 2.2-1 provides a list of the study scenarios. Scenarios 1 and 2 are the pre-Project scenarios for 2016 SP and WP. Scenarios 3 and 4 are the post-Project scenarios for 2016 SP and WP with the requested DTS 20 MW addition at the Thornton 2091S. A power factor of 0.9 lagging was used for the new Project load] Table 2.2-1: List of the Connection Study Scenarios Page 11 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Condition Project Load (MW) Project Generation (MW) 2016 SP Pre-Project 0 0 2 2016 WP Pre-Project 0 0 3 2016 SP Post-Project 20 0 4 2016 WP Post-Project 20 0 Scenario Year/Season Load 1 System Generation Dispatch Conditions High Wind, High Import High Wind, High Import 2.3 Load and Generation Assumptions 2.3.1 Load Assumptions The Study Area and Region load forecasts used for this connection study is shown in Table 2.3-1 and is from [The AESO Forecast specified in the Study Scope, e.g., the AESO 2014 Long-term Outlook (2014 LTO)]. In this study the active power to reactive power ratio in the base case scenarios was maintained when modifying the planning area loads. Table 2.3-1: Forecast Area Load (201X LTO at AIL Peak) Forecast Peak Load (MW) Area or Region Name and Season 2016 Area 37 (Provost) Central Region 2018 SP WP SL SP WP SL SP South Region WP SL SP AIL w/o Losses WP SL 2.3.2 Generation Assumptions Describe the generation assumptions (including N-G) and the AESO forecast applied (e.g., 2014LTO). Present existing and future units for consideration in the project studies (local generators) and the dispatch level of each. Describe the notable features of the local generators, as required. Below is an example of the write up: Page 12 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title [The generation conditions for this connection study are described in Table 2.3-2. The study identified the HR Milner Generator at H.R. Milner 740S substation as the critical generator and it is turned off to represent the N-G study condition in the Grand Cache area for all analysis except for the short circuit analysis] Table 2.3-2: Local Generation (MW) in the Study Cases 20xx 20xx 20xx 20yy SL SP WP SL Unit Unit Unit Unit Bus Pmax Area Net Net Net Net Number (MW) Gener- Gener- Gener- Generation17 ation ation ation (MW) (MW) (MW) (MW) Existing/ Future Unit Name Existing Gen A … … … Gen B #29 … … … Gen C … … … Gen D … … … Gen E … … … Future 20yy SP Unit Net Gener -ation (MW) 20yy WP Unit Net Generation (MW) Total 2.3.3 Intertie Flow Assumptions Indicate the assumptions regarding the intertie flow between Alberta and neighbouring jurisdictions. If Intertie flow is not a key assumption in a Connection project, please discard this section. Below are examples of the write up: [Intertie assumptions are included for the B.C., MATL, and Saskatchewan interties. Details on the assumptions can be found in Table 2.3-3.] or [The intertie points are deemed to be too far away to have an effect on the assessment of the proposed connection. The flows in the Study Area are not influenced by the AIES HVDC facilities. As a result, the intertie and HVDC assumptions are kept consistent with that in the AESO planning base cases and not adjusted for this study.] Table 2.3-3: Intertie Assumptions – Example18 Intertie Case No. Year / Condition 1 2016 SL (Pre-Project) Import (+) /Export (-) to BC Import (+) /Export (-) to Saskatchewan Import (+) /Export (-) to MATL -1000 -150 0 17 Unit Net Generation refers to Gross Generating unit MW output less Unit Service Load. Intertie assumption shall meet the AESO Available Transfer Capability and Transfer Path Management ID#2011-001R 18 Page 13 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Intertie Case No. Year / Condition 2016 SP (Pre- Project) 2016 WP (Pre- Project) 2016 SL (Post- Project) 2016 SP (Post-Project) 2016 WP (Post-Project) 2018 SL (Post-Project) 2018 SP (Post- Project) 2018 WP (Post- Project) 2 3 4 5 6 7 8 9 Import (+) /Export (-) to BC Import (+) /Export (-) to Saskatchewan Import (+) /Export (-) to MATL 800 150 300 800 150 300 -1000 -150 0 800 150 300 480 150 300 -800 -150 0 480 150 300 480 150 300 2.3.4 HVDC Power Order (if applicable) In general, the majority of connections to the AIES will not require adjustment to the planned load flow order levels for the WATL and EATL HVDC links during studies. For major projects and where the scoped study scenarios require adjustments to the pre-set HVDC flow level provided by the AESO in the Base Cases, the AESO Planning Engineer will provide guidance as to the new flow settings and associated VAR adjustments as required. In these cases, below are examples of wording: [The power orders shown in Table 2.3-4 were assumed in this Study. HVDC dispatch aligns with the AESO’s planned HVDC operating procedures. Under some scenarios, EATL was dispatched to a higher power order in a South-to-North direction to reduce congestion on the Central East 138/144 kV existing transmission system. The pre-Project and post-Project dispatches were the same for each alternative.] or [The HVDC power orders will be set based on the minimum loss per the assumptions in pre- and post-Project study scenarios.] Table 2.3-4: HVDC Power Order by Scenario Case No Scenario WATL19 (MW) EATL20 (MW) 1 2016 SL (Pre-Project) 475 N S21 Blocked 2 2016 SP (Pre- Project) 250 S N 450 S N 3 2016 WP (Pre- Project) 475 N S Blocked 19 Western Alberta Transmission Line (the west HVDC line) Eastern Alberta Transmission Line (the east HVDC line) 21 N S: HVDC flow direction is North to South S N: HVDC flow direction is South to North 20 Page 14 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Case No Scenario WATL19 (MW) EATL20 (MW) 4 2018 WP (Post- Project) 250 S N 800 S N 2.4 System Projects List the relevant transmission facilities that are not in service but were included in the study cases. Use a table. Briefly discuss any relevant information regarding system projects, such as developments proposed for each project. Below is an example of the write up: [Table 2.4-1 lists the system reinforcement subprojects that are part of CETD and that have been included in this study.] Table 2.4-1: Summary of System Projects Included in the Study Cases Project Subproject 1 P850 South and West Edmonton Reinforce ment Subproject Name In-Service Date Harry Smith Sub New Saunders Lake 240/138kV Substation; re-terminate 910L, 914L, 780L & 858L at Saunders Lake; build lines between Nisku & proposed Saunders Lake; and reconfiguration of affected substations. New 138kV Lines from 780L to Cooking Lake & 174L; and reconfiguration of affected substations 2 3 4 133L from Wabamun to 234L tap 5 New Capacitor Bank at Leduc 325S September 2017 2.5 Customer Connection Projects List the relevant customer connection facilities that are not in the existing system but were included in the study cases. Use a table. Include relevant information such as size of the load and/or generation for each project. Below is an example of the write up: [The list of the customer projects included in the study is shown in Table 2.5-1] Table 2.5-1: Summary of Customer Connection Assumptions Planning Area Queue Position* Planned In-Service Date Project Name Project # Gen (MW) Load (MW) Included/Excluded from Studies 53 54 Jul. 2017 RESL McLaughlin WAGF 1500 47.0 1.0 Included 54 19 Apr. 2016 Lethbridge Chinook NW POD 1260 0 30.0 Included 55 Energize d Oct. 2014 Fortis Spring Coulee Upgrade 1338 0 2.0 Included Page 15 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Planning Area Queue Position* Planned In-Service Date Project Name Project # Gen (MW) Load (MW) Included/Excluded from Studies 55 57 Feb. 2017 BowArk Energy Drywood Power Gas Plant 1522 18.6 1.0 Excluded * Per the AESO Connection Queue posted in December 2015. Provide any other relevant information for each project, such as whether it has already been approved by the Alberta Utilities Commission (AUC). 2.6 Facility Ratings and Shunt Elements Include tables that show the facility ratings for key existing and proposed equipment rated XX kV and above and any other relevant equipment ratings. Show only the most important equipment. Below is an example of the write up: [The Transmission Facility Owner (TFO) provided the ratings of the existing transmission lines (Table 2.6-1) and the existing transformers ( Table 2.6-2) in the Study Area.] Table 2.6-1: Summary of Transmission Line Ratings in the Study Area (MVA on 138 kV Base) Line ID Line Description Nominal Rating (MVA) Short-term22 Rating (MVA) Voltage Class (kV) Summer Winter Summer Winter 7L84 Flyingshot 749S – Crystal 722S 138 142.8 142.8 180 181 7L03 Flyingshot 749S – Elmworth 731S 138 109.3 139 123.6 150.5 7L68 Clairmont Lake 811S – Rycroft 730S 138 94.9 CT23 94.9 CT 94.9 CT 94.9 CT Table 2.6-2: Summary of Transformer Ratings in the Study Area Substation Name and Number Transformer ID Transformer Voltages (kV) MVA Rating Battle River 757S 912T 240/144 224 Battle River 757S 701T 144/72 75 Nevis 766S 901T 240/144 100 Nevis 766S 701T 144/72/25 H-M: 33.3 X-M: 33.3 Y-M: 16.6 22 When line loading in post Category B contingency is observed to exceed nominal rating and is less than the Short-term (emergency) rating, it is assumed that AESO and TFO operating practices can manage the constraint within the time requirements of TFO short time (emergency) rating. 23 The limitation factor for the line rating is due to a current transformer. Page 16 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title List the shunt elements in the Study Area, including shunt element size and status. Use a table. Present all assumptions made regarding the shunt elements, such as whether they were switched on or off in the studies. Below is an example of the write up: [The details of shunt elements in the Study Area are given in Table 2.6-3.] Table 2.6-3: Summary of Shunt Elements in the Study Area (MVAr on 138 kV Base) Capacitors Substation Name and Number Voltage Class (kV) Hardisty 377S 138 Tucuman 478S 138 Hill 751S 138 Number of Switched Shunt Blocks 1 x 27 MVAr 1 x 44.9 MVAr 1 x 27.17 MVAr Total at Nominal Voltage (MVAr) Reactors Status in Study (on or off) Number of Switched Shunt Blocks 2017S P 2017 WP (MVAr) (MVAr) 71.9 27 (on) 27 (on) - 27.17 (off) (off) 45 45 (both on) 45 (both on) 1 x 20 MVAr 1 x 25 MVAr Total at Nominal Voltage (MVAr) Status in Study (on or off) 2017 SP 2017 WP (MVAr) (MVAr) - - - - - - - - - - - 2.7 Dynamic Data and Assumptions Dynamic data and Assumption including motor composition information will be a part of Attachment section. Below is an example of the write up: [Dynamic data and assumptions including motor composition information are provided in Attachment A. Dynamic data for the Project is based on the submitted stage 2 Project Data Update Package (PDUP-2). 2.8 Protection Fault Clearing Times List the fault clearing times used for the transient stability analysis. Use a table. When providing near-end and far-end fault clearing times, include different directions with the clearing times only when the clearing times are not the same for faults at each end. Indicate if the fault clearing time assumptions have been verified by the Transmission Facility Owner (TFO). Below is an example of the write up: [Fault clearing times for existing facilities were provided by TFO and are listed in Table 2.8-1.] Table 2.8-1: Summary of Protection Fault Clearing Times Terminal Location Line 9Lxx Nominal Bus Voltage (kV) 240 Terminal 1 SUB 1S Terminal 2 SUB 2S Total Clearing Time Terminal 3 SUB 3S Faulted Location State if it is calculated (actual) or estimated (generic) Faulted Location Terminal 1 Terminal 2 Terminal 3 SUB 1S 6 7 8 actual SUB 2S 6 7 8 generic SUB 3S 6 7 9 generic Page 17 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 2.9 Voltage Profile Assumptions Please keep the following description unless any change is required. The AESO Voltage Control Practice ID # 2010-007RS is used to establish normal system (i.e. pre-contingency) voltage profiles for key area busses prior to commencing any studies. Table 21 of the Reliability Criteria applies for all the busses not included in the ID 2010-007RS. These voltages were utilized to set the voltage profile for the study base cases prior to load flow analysis. 2.10 Motor Starting Assumptions The section is to evaluate the potential impacts of motor starting operation on the surrounding system. The customer must provide details of study assumptions (including how frequent the motor starts and then find the voltage dip percentage for different voltage levels), motor model, and software used to perform the studies. Also the type of motor starting equipment and/or starting methodology that would be implemented must be specified. If Motor starting analysis is no longer required, remove the subsection – The example below assumes that VFD will be installed with across the line staring capability as backup. If the Market Participant confirms that the motors in the Project will not start motors across the line, Motor starting analysis is no longer required. Below is an example of the write up for motor starting assumption portion: [The following assumptions were used in conducting motor starting analysis: The transient voltage dip at the 138 kV transmission bus should not exceed 5% when starting a single motor. The motors will not start simultaneously. Only one motor will be allowed to start in VFD bypass mode while the other motors are running at full load.] Page 18 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 3 Study Methodology 3.1 Connection Studies Carried Out The studies to be carried out for this connection study were identified in Table 7.1-1: Please delete the rows that are not applicable to the Project. Table 3.1-1: Summary of Studies Performed* Project 1234 Scenario and Condition Load (MW) Generation (MW) System Conditions Load Flow24 1 2016 SP Pre-project 0 0 Category A and Category B X 2 2016 WP Pre-Project 0 0 Category A and Category B X 3 2016 SP Post-Project 20 0 Category A and Category B X 4 2016 WP Post-Project 20 0 Category A and Category B X 3.2 Voltage Stability9 Transient Stability9 Motor Starting9 X X X Load Flow Analysis [Load flow analysis will be completed for all study scenarios to identify any thermal or transmission voltage violations as per the Reliability Criteria. Transformer tap and switched shunt reactive compensation devices such as shunt capacitors and reactors will be locked and continuous shunt devices will be enabled when performing Category B load flow analysis. POD low voltage bus deviations will also be assessed by first locking all tap changers and area capacitors to identify any post-transient voltage deviations above 10%. Tap changers will then be allowed to adjust, while shunt reactive compensating devices remained locked; to determine if any voltage deviations above 7% would occur in the area. Once all taps and shunt reactive compensating devices have been adjusted, voltage deviations above 5% will be reported, for both the pre-Project and post-Project networks.] 25 The critical generator identified for this study was [Name N-G unit, e.g., the H.R. Milner unit]. Only Category A with all generators on. Page 19 25 X Each project has different loadflow analysis methodology based on Study Area characteristics and study assumptions. Please describe the methodology used in the loadflow analysis in this section. If any abnormal thermal loadings (above 100% thermal loading) are observed, perform Category B load flow analysis on the identified contingencies by stepping Transformer tap adjustment. The identified abnormal thermal loadings are still observed, it should be addressed in the load flow results. Below is an example of the write up: 24 Shortcircuit Public R1-2016-05-01 X Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 3.2.1 Contingencies Studied Load flow analysis was performed for the Category A condition and all Category B contingencies in [the Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios. 3.3 Voltage Stability (PV) Analysis If this analysis is not required, please remove the subsection. The objective of the Power-Voltage (PV) curve is to determine the ability of the network to maintain voltage stability at all the busses in the system under normal and abnormal system conditions. The PV curve is a representation of voltage change as a result of increased power transfer between two systems. The reported incremental transfers will be to the collapse point. As per the AESO requirements, no assessment based upon other criteria such as minimum voltage will be made at the PV minimum transfer. Voltage stability analysis for post-connection scenarios will be performed. For load connection projects, the load level modelled in postconnection scenarios are the same or higher than in pre-connection scenarios. Therefore, voltage stability analysis for pre-connection scenarios will only be performed if post-Project scenarios show voltage stability criteria violations. Voltage stability (PV) analysis will be performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology. The voltage stability criteria states, for load areas, post-transient voltage stability is required for the area modeled at a minimum of 105% of the reference load level for system normal conditions (Category A) and for single contingencies (Category B). For this standard, the reference load level is the maximum established planned load. Typically, voltage stability analysis is carried out assuming the worst case scenarios in terms of loading. The voltage stability analysis was performed by increasing load in [Study Areas, e.g., the Grande Prairie and Grande Cache Areas (AESO planning areas 20 and 22, respectively)], and increasing the corresponding generation in the following AESO Planning Areas: [Source area, e.g., the Wabamun planning area (Area 40)] [Source area] [Source area] As per the voltage stability criteria, post transient techniques (all tap changers, all discrete capacitors locked, but SVCs will be allowed to adjust) will used in applying the criteria and this information is reflected in all tables and graphs. Also for this analysis, no limits will be selected for the generation sources, non-negative active power constant MVA loads will be enforced and the existing power factor for the reference will be maintained. Page 20 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 3.3.1 Contingencies Studied Voltage stability analysis was performed for the Category A condition and all Category B contingencies in [Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios. 3.4 Transient Stability Analysis If this analysis is not required, please remove the subsection. Transient stability analysis will be performed following the post-Project scenarios using [Study scenarios, e.g., the 2017 SL and 2017 SP scenarios]. Stability plots for [State Monitoring quantities , e.g., bus voltage, machine relative angle and active and reactive power outputs.etc] for all available generation units in [Study Area, e.g., the Cold Lake (Area 28) planning area] are provided. [State reference generator, e.g., Genesee #1] will be used as the system reference. 3.4.1 Contingencies Studied Transient stability analysis was performed for the Category A condition and all Category B contingencies in [Study Area, e.g., the Grande Cache (Area 22) and Grande Prairie (Area 20) planning areas], including ties to surrounding areas for all pre- and post-Project scenarios. 3.5 Short-Circuit Analysis Short-circuit analysis was performed for [Study scenarios, e.g., the 2016 WP pre Project scenario and 2016 WP and 2025 WP post-Project scenarios] to determine the short-circuit levels in the vicinity of the Project. The short-circuit analysis includes three phase and single line to ground faults. Fault levels are provided in the form of currents in kilo amperes and per unit positive and zero sequence impedances. 3.6 Motor Starting Analysis If this analysis is not required, please remove the subsection. This section is to describe the study methodology of motor starting analysis. Below is an example of the write up: [Motor starting analysis will be performed for the proposed motors under system normal (Category A) conditions and worst case contingencies identified in the voltage stability and power flow analyses. The analysis considered the starting of one motor, with its Variable Frequency Driver (VFD) out of service, while the other motors will be running at full load.] Page 21 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 3.7 Sub-Synchronous Studies [as required] 3.7.1 Sub-Synchronous Torsional Interaction Study (SSTI) 26 This study and analysis will be required when there is a concern of sub-synchronous torsional interaction between turbine-generator units and the nearby HVDC. 3.7.2 Sub-Synchronous Resonance (SSR) and Sub-Synchronous Control Interaction (SSCI) Studies Studies and analyses will be required when there is a concern of sub-synchronous resonance between turbine-generator units and the nearby serious capacitor compensated AC transmission lines. Studies are also required when there is a potential sub-synchronous control interaction (SSCI) between the wind farms, particularly the DFIG (Type III), and series capacitor compensated lines or a nearby HVDC terminal. The AESO, TFO or the Consultant will identify the need for SSR or SSCI studies. 3.8 Effectiveness Factor Analysis Studies [as required] Effectiveness factor analysis studies are carried out to determine the generator/load effectiveness factors and identify the most effective generator/load(s) to be curtailed in order to mitigate the thermal violations observed following some Category B contingencies in the Study Area. 3.9 Sensitivity Studies [as required] Describe the methodology used for any other studies carried out. Use a separate heading for each study. The headings should match the headings used in section 2.2. Include the intent, the assumptions, and any relevant discussions regarding the study methodology. Use a table. 3.10 Mitigation Measures If study results indicate transmission constraints associated with or exacerbated by the project addition, modification to existing procedures and/or Remedial Action Schemes (RAS) or addition of new procedures and/or RAS may be required. The Studies Consultant must identify those anticipated constraints in a timely manner to the AESO as they arise. The AESO Planning Engineer will guide the Studies Consultant to; - List study results in the constraint table in Attachment N. - If N-0 overloads are observed in the post connection system, develop generation or load effectiveness factor tables based on identified thermal constraints for N-0 system. Detailed ‘Process for SSTI Studies and Mitigation-protection’ between HVDC and Thermal Turbinegenerators is published in http://www.aeso.ca/connect/files/process_for_SSTI_studies_and_mitigationprotection.docx. Further SSTI studies documents will be published to the AESO website accordingly. 26 Page 22 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title - Develop generation or load effectiveness factor27 tables based on identified thermal constraints under Category B contingencies. - Identify the components of the AESO system development plan which will alleviate the identified constraint. Propose adjustments to the original preliminary connection alternatives to avoid proposing permanent RAS for Category B contingencies. Study and propose possible modifications to existing RAS to ensure coordination of proposed protection additions with the existing schemes. Study and propose new temporary RAS required to ensure system reliability until such time the planned system reinforcements are in place. Proper study scenarios with the planned system reinforcements will be studied to reflect removal of the identified constraints and the temporary nature of the RAS. - The AESO Planning Engineer will closely work with the Consultant and guide the development and/or modifications of the proposed RAS to ensure system reliability, security and compliance with AESO system access business practices. 4 Pre-Project System Assessment 4.1 Pre-Project Load Flow Analysis For each scenario, report and discuss the load flow analysis results. If any violation appears, please include tables that summarize the results with respect to thermal overloads, voltage violation and deviations. Describe the results of the contingency categories that were analyzed. Present the results for each scenario separately. In the appropriate attachments, include load flow diagrams that provide a general representation of the overall Study Area. 4.1.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016 SP) Provide the results for all system conditions and contingencies considered, as outlined in Section 3 (Category A, Category B, and Category C5 analysis). Summarize the thermal overload results based on a 100% seasonal static thermal rating (specify the season). Use a table as the example tables below. In the appropriate attachment sections, include load flow diagrams that encompass a general representation of the overall Study Area. For each scenario, include a diagram that shows generator output, the switched shunts, and the SVCs, as appropriate, in the attachment to this section. Below is an example of the write up for load flow analysis portion: [No criteria violations for the Category A condition were found. No thermal or voltage violations for the selected Category C5 contingencies were found. 27 Effectiveness factor analysis is carried out to determine the generator/load effectiveness factors which are used to estimate the ability of each generator/load to relieve transmission element constraints. A generator/load’s effectiveness factor is defined as the change in power flow over a specific line following a change in the generator’s output power/ the load. As such, the larger the generator/load effectiveness factor the more helpful it can be in alleviating a thermal violation on the transmission line associated to it. Page 23 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title No transmission voltage criteria violations for the Category B contingencies were found. Transmission line flows above the short-term summer rating (Rate A) were identified for the Category B contingency as shown in Table 4.1-1. 749L contingency leaves 7L130 to radially feed the area load which causes a slight overload on this line. Please refer to Attachment B for pre-Project load flow diagram.] Table 4.1-1: Summary of System Performance28 (Element Loading) [2017SP Pre-Project N-G-1 Line Loading Above Rate A] Contingency 749L (Metiskow 267S – Edgerton 899S) 4.2 Limiting Branch Continuous Line Rating (MVA) Short-term Rating (MVA) 72 72 7L130 (Vermilion 710SKitscoty 705S) Pre-Project Load Flow29 (MVA) % Loading30 72.1 100.1 Pre-Project Voltage Stability Analysis [as required] Use Power Voltage (PV) curves and tables to show the critical steady state voltage stability analysis results. For each scenario, provide complete information regarding any Category A, Category B, and selected Category C5 analyses carried out and the outcomes of each. Present the results for each scenario separately. If any constraints are identified, AESO will advise the study consultant if these constraint(s) has previously been identified in other studies done by or for the AESO. If so, specify how the constraints are currently managed. In the appropriate attachment sections, include voltage stability diagrams. 4.3 Pre-Project Transient Stability Analysis [as required] Discuss the main study outcomes of the transient stability analysis. The complete transient stability diagrams should be included in an attachment. This section, please use tables to show summarize results of all Category A, Category B and Category C5 contingencies examined. If any constraints are identified, AESO will advise the study consultant if these constraint(s) has previously been identified in other studies done by or for the AESO. If so, specify how the constraints are currently managed. In the appropriate attachment sections, include transient stability diagrams. 28 All line flows of load flow analysis are reported as percentage loading relative to normal line rating as shown in Table 2.6-1. Load flow (MVA) is current expressed as MVA (ie. S =√3 x Vbase x Iactual) 30 % loading is current expressed as MVA (ie. S =√3 x V base x Iactual) 29 Page 24 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 5 Connection Alternatives 5.1 Overview Section 5 is to list all the conceptual connection alternatives considered. Please refer to the alternative section in the signed study scope. If any additional alternatives were added during the studies, please include the additional alternatives and explain why the alternatives were proposed. Below is an example of the write up: [The DFO examined and ruled out the use of distribution-based solutions to serve the load additions31. This engineering study report examined four transmission alternatives to serve the Project, as detailed in Section 5.2.] 5.2 Connection Alternatives Identified Describe each connection alternative separately. For each alternative, include a connection diagram that shows the main transmission network in the Study Area post-connection. Provide single-line diagrams (SLDs) for the proposed facilities. The connection diagrams and proposed facilities SLDs can be presented in the appropriate attachment. Below is an example of the write up: [Four alternatives were examined in this report. A description of the developments associated with each alternative is provided below. Alternative 1: Add a new point of delivery (POD) substation, and connect the new POD to the existing transmission line [Line name] via an in/out connection configuration. Alternative 2: Add a new point of delivery (POD) substation, and connect the new POD to the existing transmission line [Line name] via a T-tap connection configuration. Alternative 3: Add a new point of delivery (POD) substation, and connect the new POD to the existing transmission line [Line name] via a radial connection configuration to the existing [substation name and number]. Alternative 4: Upgrade the capacity at the existing [Substation Name and number] substation and shift load to neighboring [Substation Name and number] substation. The line length of each alternative will be subject to change after line routing by TFO. ] 5.2.1 Connection Alternatives Selected for Further Studies Please address which Alternatives are selected for this Project. [Alternative 1 and Alternative 2 were selected for further study.] 5.2.2 Connection Alternatives Not Selected for Further Studies Please state the rationale for ruling out the Alternatives. If available, 31 The DFO’s report detailing this analysis is included in section [YY] of the [DFO Legal Name] Distribution Deficiency Report, [DDR Report Title], which is filed under a separate cover. Page 25 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Refer to the DFO’s Distribution Deficiency Report (DDR) Address Market Participant (MP)’s preference (including cost estimates) Specify Transmission Facility Owners (TFOs)’s position on any possible limitation/constraints that would result in ruling out a specific alternative. Below is an example of the write up: [Both Alternative 3 and Alternative 4 would require greater transmission development and were not selected for further studies. Alternative 3: In addition to adding a new POD and converting the existing T-tap connection configuration of Dome Cutbank 810S to an in/out connection configuration, ATCO has advised that Alternative 3 involves reconfiguring or modifying equipment and the 25 kV and 144 kV busses, and mitigation of substation outages. ATCO has also advised that the existing Dome Cutbank 810S substation is constrained on all sides. Therefore, Alternative 3 involves relocating the Dome Cutbank 810S substation to a new greenfield site to accommodate the transmission developments. Alternative 4: Alternative 4 involves upgrading the existing Dome Cutbank 810S substation, including either (i) adding two 144 kV breakers and replacing the two existing 144/25 kV 10/13 MVA transformers and one voltage regulator with two 144/25 kV transformers of a higher capacity, or (ii) adding one 144 kV breaker and a 144/25 kV 30/40/50 MVA LTC transformer. ATCO has advised that Alternative 4 also involves reconfiguring or modifying equipment and the 25 kV and 144 kV busses, and mitigation of substation outages. As with Alternative 3, this transmission alternative involves relocating the Dome Cutbank 810S substation to a new greenfield site to accommodate the transmission developments.] 6 Technical Analysis of the Connection Alternatives Using the structure below, detail the results of the studies carried out for each connection alternative. Exclude any subsection that does not apply to the connection studies. If criteria violations were observed based on the study results for Alternatives, investigate and propose the needed mitigation method(s) -in consultation with AESO- to alleviate or manage the condition(s). System performance issues may include, for example, the following: • • • • • • Thermal loading violations of transformers based on 100% static seasonal thermal rating Thermal loading of lines exceeding 100% nominal seasonal thermal rating and less than TFO declared short-term seasonal rating which would require real time operation adjustments. Thermal loading of lines exceeding TFO declared short-term seasonal rating which would be managed by the remedial action scheme or by procedure in curtailing load or generation in pre contingency or by re-configuration. Voltage levels and deviations beyond the allowed levels indicated in the AESO Transmission Reliability Criteria. Inadequate Voltage stability margin. Transient instability Page 26 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 6.1 Load Flow For each scenario, report and discuss the load flow analysis results by comparing Alternatives. If any violation(s) are observed, please include tables that summarize the results with respect to thermal overloads, voltage violations, and deviations. Describe the results of the contingency categories that were analyzed. Present the results for each scenario separately. In the appropriate attachments, include load flow diagrams that provide a general representation of the overall Study Area. 6.1.1 Alternative 3 Below is an example of the write up: [The following is a summary of the Alternative 3 load flow analysis.] 6.1.1.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016SP, Scenario 4) Provide the results for all system conditions and contingencies considered, as outlined in Section 3 (Category A, Category B, and Category C5 analysis). Summarize any observed thermal overload results based on a 100% seasonal static thermal rating (specify the season). Use a table as the example tables below. In the appropriate attachment sections, include load flow diagrams that encompass a general representation of the overall Study Area. For each scenario, include a diagram that shows generator output, the switched shunts, and the SVCs, as appropriate, in the attachment to this section. Below is an example of the write up: [Category A: No criteria violations for the Category A condition were found in this scenario. Category B: Marginal thermal violations on the 138 kV line 174L between Bardo 197S to North Holden 395S were observed following the loss of the 912L/9L912 from Red Deer 63S to Nevis 766S in Table 6.1-1. The 174L thermal loading under the loss of the 912L/9L912 was only identified in the 2016 SP post-Project scenario Table 6.1-2 for the Category B voltage criteria violations identified. Voltage criteria violations were observed following the loss of the transmission line designated as 7L228. The violations were observed at the H.R Milner 740S substation. Following the loss of 7L40 (Little Smoky 813S to Simonette 733S) a minor post-transient deviation of 10.5% at the Simonette 733S POD bus in Table 6.1-3; this is marginally higher than the 10% guideline. The TFO and DFO have confirmed that such marginal voltage deviation does not impose any operational restriction. The load flow diagrams are shown in Attachment E and F. The possible mitigation measures to alleviate theses loadings are provided in Attachment L and the associated Generation/Load Effectiveness factor tables under thermal constraint lines under Category B contingencies are provided in Attachment M. The load flow diagrams after mitigation measures’ actions are provided in Attachment N.] Page 27 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Table 6.1-1: Summary of System Performance32 (Element Loading) [Scenario 4- 2017 SP Post-Project N-G-1 Line Loading Above Rate A] Contingency Limiting Branch 912L\9L912 (Red 63S Deer to Nevis 766S) 174L (Bardo 197S to North Holden 395S) Continuous Line Rating (MVA) Shortterm Rating (MVA) 85.0 94.0 Pre- Project % Loading Difference Post- Project Load Flow 33 (MVA) % Loading34 Load Flow (MVA) % Loading Post-Pre 57.0 67.0 89.1 104.8 37.8 Table 6.1-2: Summary of System Performance (Voltage Range) Contingency Substation Name and Number Bus No. Nominal kV Emergency Minimum Voltage (kV) Emergency Maximum Voltage (kV) Initial Voltage (kV) Steady State (kV) 7L228 (Big Mountain 845S to Thornton 2091S) H.R Milner 740S 1147 144 130 155 143.4 112.7 Table 6.1-3: Summary of System Performance (Voltage Deviation) Contingency 7L40 (Little Smoky 813S to Simonette 733S) Substation Name and Number Bus No. Nominal kV Initial Voltage (kV) Simonette 733S 19170 25 25.9 Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) % Change Post Manual (kV) % Change 23.3 10.5 -- -- -- -- 6.1.1.2 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5) 6.1.2 Alternative 4 6.1.2.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016SP, Scenario 4) 6.1.2.2 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5) 6.1.3 Comparison of Alternatives Compare the load flow results amoung selected Alternatives. 32 All line flows of load flow analysis are reported as percentage loading relative to normal line rating as shown in Table 2.6-1. Load flow (MVA) is current expressed as MVA (ie. S =√3 x Vbase x Iactual) 34 % loading is current expressed as MVA (ie. S =√3 x V base x Iactual) 33 Page 28 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 6.2 Voltage Stability Present the critical voltage stability results using tables. Provide the complete study results regarding the Category A, Category B, and Category C5 events studied. Present the voltage stability analysis results for each scenario separately. Discuss the study results in this section and include the corresponding PV curves diagrams in the appropriate attachment. 6.2.1 Alternative 3 6.2.1.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5) Provide explanation to clarify the study results and conclusions, as appropriate. Include any var support devices required to alleviate voltage instability or voltage collapse. Below is an example of the write up for voltage stability analysis portion: [Voltage stability analysis was performed for the 2016 WP scenario. The reference load level for the Grande Prairie area and Grande Cache area (AESO Planning Areas 20 and 22) is 449.1 MW. MW. The minimum incremental load transfer for the Category B contingencies is 5.0% of the reference load or 22.5 MW to meet the voltage stability criteria (0.05 x 449.1 MW = 22.5 MW). Table 6.2-1 summarizes the voltage stability results for Category A and the worst contingencies for voltage stability transfer margins. The voltage stability diagrams are shown in Attachment G and H] Table 6.2-1: Scenario 4: 2016 WP– Voltage stability analysis results (Minimum transfer = 22.5 MW) Contingency From N-G To System Normal Maximum incremental transfer (MW) Meets 105% transfer criteria? 73.8 Yes 7L46 Little Smoky 813S Big Mountain 845S 30.6 Yes 7L73 Rycroft 730S Friedenstal 800S 38.1 Yes 6.2.2 Alternative 4 6.2.2.1 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016WP, Scenario 5) 6.2.3 Comparison of Alternatives Compare Voltage Stability results amoung selected Alternatives. 6.3 Transient Stability Present the transient stability analysis results for each scenario separately and include the corresponding transient stability result diagrams in the appropriate attachment. Below is an example of the write up for transient stability analysis portion: Page 29 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 6.3.1 Alternative 3 6.3.1.1 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016 SP, Scenarios 4) [Transient stability analysis shows well damped responses with no stability concerns. Table 6.3-1 shows all the contingencies that were studied. The transient stability results are provided in Attachment I and J. Transient Stability analysis was not conducted for the pre-Project study scenarios because transient stability analysis results for the post-Project scenarios demonstrated system stability without any stability concerns.] Table 6.3-1: Summary of Transient Instability System Condition Contingency Fault Description (fault location) Category B (N-1) 1001L (sub A to sub B) Fault Location (ex Sub A) Figure # 6.3.1.2 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016 WP, Scenarios 5) 6.3.2 Alternative 4 6.3.2.1 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Summer Peak – 2016 SP, Scenarios 4) 6.3.2.2 Stability Results 20XX Season [Summer/Winter] Load Condition [Peak/Light] (e.g., 2016 Winter Peak – 2016 WP, Scenarios 5) 6.3.3 Comparison of Alternatives Compare the transient stability results amoung selected Alternatives. 6.4 Motor Starting Analysis [as required] If the MP has confirmed that the motors will not start with VFD, then motor starting analysis will not be required. Present the motor starting analysis results by using “across-the-line” starting of the motors at the proposed substation. Please list the nameplate data of the proposed motors in a table. Specify equivalent circuit diagram and corresponding data (parameter). Below is an example of the write up for motor starting analysis portion: Page 30 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title [Motor starting analysis was performed to assess the feasibility of the “across-the-line” starting of the 7,000 HP motors at the proposed Battle Sands 594S substation. Although Enbridge has indicated that Variable Frequency Drivers (VFDs) will be used to start the motors, the analysis assesses the voltage dip at the transmission busses in the case of a VFD failure (VFD by-pass condition) and to determine if starting restrictions would be imposed. Motor starting analysis was conducted for the start-up of a single motor with all other motors in the station already running at full load. All four motors were supplied by one 138/6.9 kV, 25/33 MVA transformer. The 2017 WP post-Project scenario was used in the analysis. The analysis was based on the dynamic analysis method in PSS/E 33. ] Table 6.4-1 shows the nameplate data of the 7,000 HP induction motors. Table 6.4-1: Motor Nameplate and Calculated Data Motor Rating Value Rated power 7,000 HP Rated voltage 6,600 V Rated current 516 A Rated speed 1780 rpm Rated torque 20,676 lb-ft Nominal power factor 0.92 Nominal efficiency 0.964 Moment of inertia (motor) 4667 lb-ft2 Moment of inertia (Driven Machine) 400 lb-ft2 Locked-rotor torque 75.7% Breakdown torque 196.2% Locked-rotor current 650% MVA base 5.889 MVA Rated motor speed pu 0.9889 Driven machine torque pu @ n=ns 0.8 H (combined motor and driven machine) 0.6297 Page 31 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Figure 6.4-1 shows the equivalent circuit that was used to model the motors. Figure 6.4-1: Equivalent Circuit of Induction Motor Ra La L1 L2 R1 S Lm R2 S Table 6.4-2 lists the equivalent circuit parameters. Table 6.4-2: Equivalent Circuit Data Equivalent Circuit Parameter Value in Per Unit Ra 0.037 La 0.071 Lm 3.4 R1 0.025 L1 0.07 R2 0.0195 L2 0.024 6.4.1 Motor Starting Results for Alternative 1 Please provide the motor starting results in a table. Below is an example of the write up for motor starting results portion: [Motor starting analysis was conducted for the 2017 WP post-Project Alternative 1 configuration. The analysis was conducted under system normal Category A and critical contingency conditions extracted from the power flow analysis. Table 6.4-3 shows the summary for Alternative 1. Table 6.4-3: Motor Starting Performance for Alternative 1 Contingencies Substation Substation A Nominal Bus Voltage (kV) Category A (N-0) Category B (N-1) 681L (From Hardisty 377S to Tucuman 478S) Category C5 (N-2) 679L and 680L (From Nilrem 574S to Tucuman 478S) 138 138 138 Page 32 … … Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Before Motor Start (kV) 142.83 129.38 129.38 After Motor Start (kV) 139.66 123.86 123.86 Voltage Dip (kV) 3.17 5.52 5.52 % Voltage Dip 2.22 4.27 4.27 Nominal Bus Voltage (kV) … .. .. Before Motor Start (kV) Substation B After Motor Start (kV) Voltage Dip (kV) % Voltage Dip The motor starting results show that the voltage dip caused by “across-the-line” motor starting at Substation A and B 138 kV busses are below 5% under both system normal and contingency conditions. The simulation results suggest that the impact on the voltage due to “across-the-line” starting of one motor is acceptable. The induction motor curves and the voltages at Substation A and B busses are provided in Attachment K.] 6.5 Sub-Synchronous Studies Analysis The AESO will provide detailed guidance if sub-synchronous studies are required. 6.6 Sensitivity Studies [as required] Discuss the results obtained from all sensitivity tests carried out to determine the robustness of the study conclusions. 6.7 Effectiveness Factor Analysis [as required] Describe the analysis carried out to determine the generator/load effectiveness factors which are used to estimate the ability of each generator/load to relieve transmission element constraints. The effectiveness factor is defined as the proportional change in MW over a specific line as a result of a change in the Page 33 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title generator’s output power or the load to be supplied. As such, the larger the generator/load effectiveness factor the more helpful it can be in alleviating a thermal violation on the transmission line associated with that particular effectiveness factor. The results of the effectiveness factor analysis are presented in detail in Attachment M. 7 Mitigation Measures This section summarizes the mitigation measures identified in Section 6. If any constraints are identified, AESO will advise the study consultant if any constraints are identified. Please make sure to check and answer the following questions. 1. Is it the existing constraint and captured in pre-Project scenarios? If so, please describe how the addition of the Project worsen or improve a pre-existing condition? Also specify how the existing constraints are currently managed. 2. If this is not a previously identified constraint in the Study Area, will AESO and the consultant identify solutions for mitigating the identified constraints? Demonstrate the generation/load effectiveness (depending on the Project) of the proposed mitigation methods using the study results. Use tables and figures where possible. Include any explanations required to clarify the study outcome and conclusions. Below is an example of the write up: [The steady state analysis showed N-1 thermal violations for the studied 2017 scenarios. Operational measures will be utilized to alleviate line loadings above continuous loading limit and below emergency rating. Loadings beyond emergency rating will be mitigated by the existing RAS already in service, RASs specified for the other projects connections, and proposed new connection RASs. The application of these RASs in alleviating the thermal violations is demonstrated in Attachment L and the associated power flow diagrams after mitigation measures are shown in Attachment N. The corresponding Generation/Load Effectiveness factor tables under thermal constraint lines under Category B contingencies are provided in Attachment M. AESO will specify new RASs in the Functional Specifications for the EON and Mainstream Wainwright WAGFs to include the additional needed functionality and equipment. Several thermal violations were observed for double circuit Category C5 contingencies. These existing violations will be mitigated by the real-time measures.] 8 Short-Circuit Analysis For load and generator connection, all the generators in the Study Area should be on-line. Include the short-circuit analysis for the preferred alternative amoung the listed alternatives in Section 5.2. If connection alternatives will impact short-circuit current, provide the results, include the short-circuit analysis for the studied alternative. Explain if the short-circuit current levels35 would not be materially changed or not. 35 Short-circuit current studies were based on modeling information provided to the AESO by third parties. The authenticity of the modeling information has not been validated. Fault levels could change as a result of system developments, new customer connections, or additional generation in the area. It is recommended that these Page 34 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Highlight the short circuit current levels which are above 90% of equipment rating. Market participants can approach the AESO for advice with respect to long-term anticipated short circuit levels and can collaborate with the AESO on a system-based solution if a more locally-based solution cannot solve it. 8.1 Pre-Project Provide pre-Project short-circuit current levels for the studied alternative. Use a table. Table 8.1-1: Summary of Short-Circuit Current Levels – Pre-Project (Year 20XX) Substation Name and Number Base Voltage (kV) PreFault Voltage (kV) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Table 8.1-2: Summary of Short-Circuit Current Levels – Pre-Project (Year 20XX [Year of Proposed Connection + 10 Years]) Substation Name and Number 8.2 Base Voltage (kV) PreFault Voltage (kV) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Post-Project Provide post-Project short-circuit current levels for the preferred alternative. Use a table. Table 8.2-1: Summary of Short-Circuit Current Levels – Post-Project (Year 20XX) Substation Name and Number Base Voltage (kV) PreFault Voltage (kV) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Table 8.2-2: Summary of Short-Circuit Current Levels – Post-Project (Year 20XX [Year of Proposed Connection + 10 Years]) changes be monitored and fault levels reviewed to ensure that the fault levels are within equipment operating limits. The information provided in this study should not be used as the sole source of information for electrical equipment specifications or for the design of safety-grounding systems. Page 35 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Substation Name and Number 9 Base Voltage (kV) PreFault Voltage (kV) 3-Φ Fault (kA) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Project Interdependencies Discuss if there are any interdependencies between this project and other system projects and customer connection projects. Indicate the impact of such interdependencies between the projects. Below are some examples of the write up: Example for no project independency [The Projects are not dependent on the future developments of the AESO Long Term Plan for the region.] Examples for project dependency [Transmission voltage criteria violations identified both pre- and post-Projects indicate the need for the Irish Creek 706S capacitor addition, as identified in the 2015LTP, prior to the 2017WP.] Another example [The Project is dependent on line 7L44 relay tele-communication upgrade to mitigate instability of Lowe Lake (NPP1) generator on a fault on line 7L44. The existing relay upgrade at Flyingshot 749S and Big Mountain 847S substation is scheduled for completion in the first quarter of 2016 (ATCO capital maintenance project). This upgrade will incorporate tele-communication functionality, i.e. communications assisted tripping, and will allow for reduced fault clearing times of 8 cycles for a remote fault on line 7L44. Upon the completion of this capital maintenance project, the NPP1 request to increase its STS contract from 93 MW to 105 MW can be realized.] Page 36 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 10 Summary and Conclusion Copy and paste the executive summary here in its entirety. Page 37 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment A Dynamic Data and Assumptions of All Equipment Proposed for Connection Page 38 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Study Area load representation assumed for the transient studies is in Table A-1 Table A-1: Transient Stability Analysis Load Representation Planning Areas % of load specified as Large Motors % of load specified as Small Motors Areas in NW and NE regions 40% Areas in other regions 10% The Remainder of the Load (excluding Motor loads) Active Power Constant Current Reactive Power Constant Impedance 30% 100% 100% 10% 100% 100% In Attachment A, list the dynamic data of all equipment proposed for connection to the grid, such as generators, excitation systems and their limiters, power system stabilizers (PSSs), turbine governors, wind turbines, static VAR compensators (SVCs), large motors, as well as all other relevant dynamic representations of the proposed facilities. Use a table. If it is not possible to present the information in a table, attach the detailed dynamic data in a comprehensive format or attach it directly as a dyr file. Table A-2: Generator Dynamic (Example) Generator Dynamic Data (GENROU model) T’do T"do S(1.0) S(1.2) T’qo T"qo H D Xd Xq X’d X’q X"d Xl Table A-3: Exciter Dynamic Data (Example) Exciter Dynamic Data (EXAC2 model) TR TR TR TR TR TR TR TR TR TR TR TR KH KH KH KH KH KH KH KH KH KH KH KH Table A-4: Stabilizer Dynamic Data (Example) Stabilizer Dynamic Data (PSS2B model) Tw1 Tw2 T6 Tw3 Tw4 T7 KS2 KS3 T8 T9 KS1 T1 T2 T3 T4 T10 T11 VSI1M AX VSI2MI N VSI1M AX VSI2MI N VSTM AX VSTMI N ICS1 Page 39 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Stabilizer Dynamic Data (PSS2B model) REMBUS 1 ICS2 REMBU S2 M N Table A-5: Governor Dynamic Data (Example) Governor Dynamic Data (GGOV1 model) R Tpelec Maxerr Minerr Kpgov Kigov Kdgov Tdgov Vmax Vmin Tact Kturb Wfnl Tb Tc Teng Tfload Kploa d kiload Ldref Dm Ropen Rclose Kimw Aact Ka Ta Trate db Tsa Tsb Rup Rdown Rsele ct Flag Provide a high-level summary of the modelling assumptions made for all other generators, such as the dynamic data provided by AESO used, the generator test reports used (where such test reports were available), and/or the standard generator data used (where such test reports were not available). Page 40 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment B Pre-Project Load Flow Diagrams (Scenarios 1 to XX) Page 41 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment C Pre-Project Voltage Stability Diagrams (Scenarios 1 to XX) Page 42 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Table C-1: Summary of Voltage Stability Outages; Initial Load Level for Area XX is YY MW Incremental Area Available Voltage System Condition Worst Case Outage Load Increase before Stability Margin Collapse Point (MW) (%) All figures must be easy to read and have proper labels for both the x axis and the y axis. See Figure C-1 for an example. The table headings must identify the initial amount of static load in the study region or the initial transfer level, whichever is applicable. Figure C-1: Overview of Voltage Stability Outages (Example) Figure C-1: Overview of Voltage Stability Outages (Example) System Condition: N-FNG, Area Capacitor banks utilized to prepare for next outage, RB Area Load = ~140 MW including losses, Examined: N-FNG-RL1 Rainbow Lake 791S 144kV Bus 155 Voltage (kV) t 150 145 140 135 130 135 140 145 150 155 160 165 Rainbow Area Total Load (MW) N-FNG N-FNG-RL1+LS1 N-FNG-RL1+LS2 Page 43 N-FNG-RL1+LS3 N-FNG-RL1+LS4 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment D Pre-Project Transient Stability Diagrams (Scenarios 1 to XX) Page 44 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Use figures to illustrate the system dynamic responses following Category A, Category B, and Category C5 contingencies. The figures must be easy to read and properly labelled. The figure numbers should be noted in the Summary of Transient Stability table and in the attachment. Include figures for system voltages at key nodes in the Study Area, relevant generator angles with respect to the reference generator, the power output of the relevant generators in the area, and any other relevant information. Figure D-1 and Figure D-2 are examples of figures that show system response. Figure D-1: Three-Phase Fault near Example 1S Substation on 1001L (Example) Bus Voltage (kV) 160 155 150 145 140 Example 135 130 125 120 0 5 Blumenort 10 15 Ft.Nelson 20 High Level 25 Hotchkiss 30 Keg River 35 Rainbow Lake Figure D-2: Transient System Response following Loss of Example Generator (Example) NW generators angle: N-FNG 0 Example -10 -20 -30 -40 -50 -60 0 5 RB2 10 RL1 15 RB5 20 Bear Creek (Gas) Page 45 25 Bear Creek (Steam) 30 35 H.R.Milner Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment E Alternative 1: Load Flow Diagrams (Scenarios 1 to XX) Page 46 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Page 47 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment F Alternative XX: Load Flow Diagrams (Scenarios 1 to XX) Page 48 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Page 49 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment G Alternative 1: Voltage Stability Diagrams (Scenarios 1 to XX) Page 50 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Page 51 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment H Alternative XX: Voltage Stability Diagrams (Scenarios 1 to XX) Page 52 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Page 53 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment I Alternative 1: Transient Stability Diagrams (Scenarios 1 to XX) Page 54 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Page 55 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment J Alternative XX: Transient Stability Diagrams (Scenarios 1 to XX) Page 56 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment K Motor Starting Analysis and Diagrams Page 57 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment L Category B Loading and Voltage Performance (Scenarios 1 to XX) Page 58 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Table L-1: Remedial Action Scheme RAS Number RAS Name 134 174L-395S North Holden overload mitigation scheme Table L-2: Performance Violations and Potential Mitigation Options Mitigation Approach6 Triggering Events (Element out of Service) Type of System Constraint (Nature of constraint) (ex. thermal violation, instability, voltage range violation) Details of Constraint36 (ex. %I of MVA loading of nominal rating, nominal and short-term emergency rating, and direction of flow, or what type of instability, or voltage level) Voltage (SteadyState) Thermal Nomin al rating (MVA) Shortterm rating (MVA ) Load Flow (MVA ) Assumed System Conditions %I of MVA continuou s ratings (ex. Summer peak, year, and other critical project assumptions) Stability Location Voltage (RAS or Procedure, also include post-RAS system performance, ex. %I of MVA loading of nominal rating) Automat ic (RAS) OR Real Time Operati ng Practice Post RAS Action Action 1 % of MVA continuo us Rating Action 2 % of MVA continuo us Rating Tempo rary or Perma nent Mitigat ion Measu re Propose d LongTerm Planning Solution 201xLTP xxxL (xxx xxxS to xxx xxxS 36 Thermal Violation xxxL (xxx xxxS to xxx xxxS) 85 94 89.0 104.7 20xx Summer Peak Scenario 1 (List other critical project assumption) May include sub-columns for details Page 59 Public R1-2016-05-01 Tempo rary (Please specify on what portion of LTP will remove the temporary mitigation measure) Page 60 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment M Generation/Load Effectiveness Factor (if necessary) Page 61 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Regarding Generation Effectiveness Factor analysis, please address generator types in the Study Area and created effectiveness analysis table for N-0 and N-1 contingencies. Table M-0: Generator Types Plant xxx xxx xxx xxx xxx xxx xxx xxx xxx xxx Type Wind Wind Wind Gas Gas Hydro Hydro Coal Coal Coal Table M-1: 20xxSL (Post-Project), Generators Effectiveness Factors under Normal Condition (N-0) Plant xxx xxx xxx Xxx xxx xxx xxx xxx xxx xxx Line Table M-2: 20xxSL (Post- Project), Generators Effectiveness Factors under Normal Condition (N-1) Plant xxx xxx xxx Xxx xxx xxx xxx xxx xxx xxx Line Page 62 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Attachment N Load Flow Diagrams after RAS Action (Scenarios 1 to XX) Page 63 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title SECTION THREE FACILITY DESIGN Page 64 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Facility Design Template AESO Project Number: # Date: Click and type date Company Name Version: Name Signature Date Click and type version number Engineering Stamp APEGA Permit to Practice: XXXXXX Page 65 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title (Page intentionally blank) Page 66 Public R1-2016-05-01 Connection Proposal Template Table of Contents SECTION THREE- FACILITY DESIGN TEMPLATE....... ERROR! BOOKMARK NOT DEFINED. 1 PROPOSED FACILITY ADDITION/UPGRADES ............................................ 68 2 SCOPE OF WORK ....................................................................................... 68 2.1 STANDARD COMPLIANCE ............................................................ Error! Bookmark not defined. 2.2 SUBSTATION EQUIPMENT SPECIFICATIONS .......................................................................... 68 2.2.1 MAXIMUM FAULT LEVEL ......................................................................................................... 69 2.2.2 MAXIMUM AND MINIMUM CONTINUOUS VOLTAGE RATINGS (kV) ................................... 69 2.2.3 MINIMUM CONTINUOUS CURRENT RATINGS (A) ................................................................ 69 2.2.4 INSULATION LEVEL ................................................................................................................. 69 2.3 FACILITIES AND EQUIPMENT DETAILS FOR THE PREFERRED ALTERNATIVE ................. 70 2.3.1 Preferred Alternative .................................................................... Error! Bookmark not defined. 3 TRANSMISSION SYSTEM OPERATING REQUIREMENTS .......................... 71 3.1 SHORT CIRCUIT CURRENT LEVELS ......................................................................................... 71 3.2 OPERATIONAL CONSTRAINTS .................................................................................................. 71 3.2.1 Remedial Action Schemes (RAS) .............................................................................................. 71 3.2.2 Generator Synchronization ........................................................................................................ 71 3.2.3 Sync-Check or Anti-Islanding .................................................................................................... 71 4 REVISION HISTORY ................................................................................... 72 APPENDIX AA. PREFERRED ALTERNATIVE ..................................................... 73 A.1 CUSTOMER CONNECTION – PREFERRED ALTERNATIVE....................................................... 73 A.1.1 SLD – ###S SUBSTATION – PREFERRED ALTERNATIVE ..................................................... 73 A.1.2. TELE-COMMUNICATION CONNECTION – PREFERRED ALTERNATIVE ............................ 73 Page 67 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 1 Proposed Facility Addition/Upgrades This section is compiled by the Market Participant and is to describe the following: • • • • Organization submitting SASR SASR request (load DTS, gen STS, transformer add, breaker add, new POD, …) and why needed (load growth, new load, new generator, DFO reliability – N-1, feeder loading, …) location Requested In-Service date The Engineering Study Report (ESR) evaluated multiple alternates. The AESO or TFO or Studies Consultant proposes to implement the preferred alternate which requires the following facilities (list the facilities herein): • • • • • • • Line nominal voltage, minimum capacity, and approximate length Transformer voltage (high/low voltage), minimum capacity and the type of tap changer (on-load or offload) Salvage of any existing transmission facilities Bus arrangement and breakers (25 kV or higher voltage) Tele-protection requirement to meet the ESR (stability) and AESO (protection rule) fault clearing requirements Remedial Action Schemes (RAS), if needed, for the preferred alternate Anything else (incl. SVC or other voltage control devices, etc.) Please include a relevant single line diagrams for the existing transmission system in the project area. 2 Scope of Work 2.1 Standard Compliance All work undertaken by TFOs or customers must be designed, constructed, and operated to meet the standards, guidelines, codes and regulations governing such installations including, but not limited to those listed below. All AESO documentation can be found on the AESO website (http://www.aeso.ca/rulesprocedures/8778.html). List only the applicable standards related to the facilities listed in Section 1. 2.2 Substation Equipment Specifications All proposed new transmission equipment must meet the minimum specifications provided below or in the following subsections: Page 68 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Any exceptions from the Alberta Reliability Standards (e.g., there may be different temperature rating for the north region vs. the south region, exceptions to line and tower design, exceptions to protection requirements, etc.) Maximum Fault Level as indicated in Section 2.2.1. Equipment maximum and minimum voltage ratings as indicated in Section 2.2.2. Minimum continuous equipment current ratings as indicated in Section 2.2.3. 2.3 Maximum Fault Level Provide the maximum fault level for the nominal voltage. The Alberta standard fault duty levels are: 31.5 kA for 138/144 kV, and 40 kA for 240 kV. These values may need to be changed, depending on the short circuit study results. 2.4 Maximum and Minimum Continuous Voltage Ratings (kV) Provide appropriate nominal voltages in Table 3 based on the connection area and modify the column headers accordingly. Table 3: Equipment Maximum and Minimum Continuous Voltage Ratings (kV) Area 25 kV 69/72 kV 138/144 kV 240 kV 500 kV Minimum Maximum 2.5 Minimum Continuous Current Ratings (A) Provide appropriate values in Table 4 based on the connection area and modify the column headers accordingly. Table 4: Equipment Minimum Continuous Current Ratings (A) Component 25 kV 69/72 kV 138/144 kV 240 kV 500 kV Main Bus Cross Bus Feeder Provide Single Line Diagrams (SLD) of the proposed facilities showing substation ampacities and other information, detailed as follows. 2.6 Insulation Level Table 5: Basic Insulation Level (kV) Nominal Voltage Classification (kV rms) 25 kV 69/72 kV 138/144 kV 240 kV 500 kV Station Post Insulators and Airbreaks Page 69 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Nominal Voltage Classification (kV rms) 25 kV 69/72 kV 138/144 kV 240 kV 500 kV Circuit Breakers Current and Potential Transformers Transformer Windings 2.7 Facilities and Equipment Details for the Preferred Alternative Describe preferred alternative as the outcome of Stage 2 Engineering Study Report (ESR). Include the pre- and post-Project diagrams. 2.8 Transmission lines Specify number of circuits, the approximate length of the new line(s) to be constructed and the minimum capacity (summer/winter) requirement. 2.9 Substations Itemize all major equipment as follows. Bus arrangement Transformer size and type of tap changer Number of breakers at ≥25 kV Number of motor operated disconnect (MOD) switches at 138 kV or higher voltage Cap banks (if any and if at or higher than 25 kV voltage) Transformer neutral reactor/resistor 2.10 Protection, Control Requirements The protection and control will be designed to meet ISO Rules. 2.11 SCADA All SCADA requirements will be designed as per ISO Rules. 2.12 Telecommunication All Telecommunication requirements will be designed as per ISO Rules. Page 70 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 2.13 Revenue Metering The Revenue metering will be designed to meet the current AESO’s Measurement System Standard 37. 3 Transmission System Operating Requirements In the following sections provide brief description to outline the need for mitigation measures to connect commission and operate the new connection as per the electrical environment in which the facilities outlined in this document will operate. 3.1 Short Circuit Current Levels Summarize the short circuit current levels from the Stage 2 Engineering Study Report, pre- and postProject, and 10 years into the future. Highlight the short circuit current levels which are above 90% of equipment rating. Market participants can approach the AESO for advice with respect to long-term anticipated short circuit levels and can collaborate with the AESO on a system-based solution if a more locally-based solution cannot solve it. 3.2 Operational Constraints The following sections identify the need for new or potential changes to existing mitigation measures to successfully commission and operate the new connection to meet AESO reliability standards in operations domain. 3.2.1 Remedial Action Schemes (RAS) Provide brief description of the identified constraints as identified in the Stage 2 Engineering Study Report. Briefly describe new RAS requirement, or the necessary changes to existing RAS schemes or procedures for the project or in the project area. 3.2.2 Generator Synchronization Refer to the AESO’s Generation and Load Interconnection Standard38 related to synchronization requirements. Provide detailed information of any synchronization plan which deviates from the standard. 3.2.3 Sync-Check or Anti-Islanding If there is an existing anti-islanding scheme in the project area, specify the modifications needed. If no existing scheme, provide suggested options to address anti-islanding requirements. 37 38 http://www.aeso.ca/downloads/AESO_Measurement_System_Standard(1).pdf http://www.aeso.ca/downloads/Generation_and_Load_Standard_Rev1.pdf Page 71 Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title 4 Revision History Revision Issue Date Author Page 72 Change Tracking Public R1-2016-05-01 Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Appendix A. Preferred Alternative A.1 Customer connection – Preferred Alternative Provide a drawing showing the proposed area transmission system including the development described in the Specification. A.1.1 SLD39 – ###S Substation – Preferred Alternative Provide a drawing showing the proposed configuration of each substation that will be affected by the development described in the Specification. Each drawing should clearly indicate the following as a minimum: Station layout and bus configuration Switches at 138 kV or higher voltage Interrupting devices at 25 kV or higher voltage Voltage control equipment (e.g. capacitors and reactors) Transformers complete with configuration, tap changing and grounding Proposed additions/changes/salvages clearly indicated Current ratings of bus sections (only if bus upgrades are required) Delineation of ownership Provide information of other subsections as necessary. A.1.2. Tele-communication Connection – Preferred Alternative Provide a drawing(s) showing the proposed area tele-communication system including the development described in this Functional Specification. Each drawing should clearly indicate the following as a minimum: Proposed connection and upgrades to existing tele-communication system. Proposed type (microwave, fiber, and etc.) of new and upgraded tele-communication systems. Specify for all new and upgraded tele-communication systems what (if any) TPR or protection applications will be carried. Note – that RAS requirements determined at a later date may modify the tele-communication requirement 39 SLD in Microsoft Visio format to the AESO is required Page 73 Public R1-2016-05-01 SECTION FOUR COST ESTIMATES Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Refer to the AESO website40 for Cost Estimates Template. 40 Refer to the ‘Templates’ section in http://www.aeso.ca/connect/files/aeso_cost_estimate_template.xlsx SECTION FIVE LAND IMPACT ASSESSMENT Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title Land Impact Assessment AESO Project Number: # Date: Click and type date Company Name Version: Name Click and type version number Signature Date Connection Proposal Template Stage 2 Connection Engineering Study Report for AUC Application: Project Title (Page intentionally blank) 1 Land Impact Assessment To meet the AUC Rule 007 requirements, a land impact assessment may be needed depending on the scope of development being proposed to connect the Market Participant project. Provide a summary of the land assessment for the technically feasible connection alternatives as advised by AESO. Page 79 Public R1-2016-05-01