Project Schedule Alignment Document
(DELETE THIS PAGE PRIOR TO DOCUMENT SIGN-OFF)
FOR USE WHEN:

This document must be issued by the Integrated PM following completion of each of the following
three milestones: Connection Proposal, PPS, and P&L.

The purpose of this letter is to re-baseline the Project schedule after completion of each of the three
major milestones listed above. The AESO Project Coordinator will update the AESO Project schedule
upon receipt of the Project Schedule Alignment document.

If this schedule alignment activity results in an In Service Date change, a Change Proposal Form
must be completed.
REQUIRED SIGNATURES/APPROVALS:

The Integrated PM must coordinate sign-off with the AESO, TFO, and the Market Participant.
Transmission Project Delivery
[Insert Date]
Re:
[Insert Project Number] - [Insert Project Name] (the “Project”) –
Project Schedule Alignment
This document completed by the Integrated Project Manager acknowledges that the Project has reached
a significant milestone and a Project schedule alignment is necessary along with updated Project risks
and assumptions.
Select the most recently completed Project milestone reached:
☐Connection Proposal
☐Proposal to Provide Services (PPS)
☐Permit & License Received
Using the Milestones table below, an updated Project schedule has been provided based on completion
of [Conection Proposal, PPS, or Permit & License].
Milestone
Owner
Target Date
Completion Date
Finalize Connection Plan
Finalize Connection Study
Scope
Connection Proposal
Submission
Connection Proposal
Approval
Stage 3/4 Security
Directions & Functional
Specification to TFO
Public
Transmission Project Delivery
1
R1-2015-01-20
PPS Submission
PIP Report Submission
NID Filed
Facility Application Filed
AUC Approvals
Gate 5 Complete (InService Date)
In support of the updated Project schedule a table of updated Project assumptions and risks for the
current stage of the Project has been provided below.
Identified Assumptions for project schedule
(List as required)
Identified Risks to project schedule
(List as required)
Public
Transmission Project Delivery
2
R1-2015-01-20
Upon receipt and sign-off of the Project Schedule Alignment Letter the AESO Project Coordinator will
update the AESO Project schedule.
Company Name
Name
Date
Signature
[Insert Market Participant
Name]
[Insert Studies
Consultant (if applicable)]
[Insert TFO]
[Insert AESO Project
Coordinator]
*Integrated PM will be 1 of 4 parties listed above; if not listed, additional Integrated PM sign-off is required
Should you have any questions or concerns, please contact me directly at [Insert Integrated PM Contact
Information].
Yours truly,
[Insert Integrated Project Manager]
[Insert Integrated Project Manager title]